Height of Excavation (height of 2 floor + 4.2 + 4.2 + 1 = 9.4 m
pcc layer)
Particular of Items No Area Height or Dept Quantity
h Excavation 1 9500sqm 4.2 + 4.2 = 8.4m 90720 cu m
Lime or lean conc. In foundati 1 9500sqm 1m 10800 cu m
on According to the table by DAR- Excavation cost of the Substructure-
Area x Height x rate of amount = Total Excavation cost
9500sqm x 9.4m x 155.6rs = Rs 1,38,95,080
2) PLAIN CEMENT CONCRETE
According to the table by DAR- PCC cost of the Substructure-
Area x Height x rate of amount = Total PCC bed in substructure cost
Total Area of PCC ( w/o footing) – area of footing x no. of columns = Area of PCC 9500 -1026= 8474sqM 8474 x 0.15m x 5719rs = Rs 72,70,000 ( w/o footing area )
3) FOUNDATIONS, FOOTINGS, BASES OF COLUMNS
Length of one column – 600mm
Length of one footing - 0.6 x 5 = 3m Area of one footing - 3m x 3m = 9sqm Height of the footing - 1m No. of columns - 114 Volume x no. of columns x rate = Total rate 9 x 114 x 196.5 = Rs 2,01,600 4) POURING OF 1:2:4 CEMENT CONCRETE FOR FOUNDATION
Area of one footing - 3m x 3m = 9sqm
Height of the footing - 1m No. of columns - 114 Volume x no. of columns x rate = Total rate 9 x 114 x 196.5 = Rs 2,01,600 5) Shuttering of Columns
Area of the column – 0.6 x 0.6 = 0.36sqm
Height of the column – 8.4m No. of columns - 114 Volume x Rate = rate of the shuttering column 3.024 x 453 = RS 1,56,165 6) Retaining Wall
According to the table by DAR-
Retaining wall in Basement cost of the Substructure-
Length of Retaining Wall - 435 M
Ht of Retaining wall - 8.4 M ( Excluding Footing ) Thickness of Wall - 0.3m