LAPORAN INSPEKSI PEMENUHAN INDIKATOR KINERJA JALAN

Kontrak Nomor : PW 0401-Bb4/P2JN/PPKPW/262 Tanggal Inspeksi


Ruas Jalan : Bts. Tanjabbar - Sp. Betara Segmen Jalan
Provinsi : Jambi Lingkup Pekerjaan
Total Panjang Jalan : 16,600 Km
Kategori Pemenuhan Indikator Kinerja Jalan
No. Sta - Sta LR
1a 1b 1c 2a 2b 2c 3a 3b 4a 4b 4c 5a 5b 5c 5d 6a 6b
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 00 + 000 s/d 00 + 500 L/R V V V - - - V - - - - - - - V V V
2 00 + 500 s/d 01 + 000 L/R V V V - - - V - - - - - - - V V V
3 01 + 000 s/d 01 + 500 L/R V V V - - - V - - - - - - - V V V
4 01 + 500 s/d 02 + 000 L/R V V V - - - V - - - - - - - V V V
5 02 + 000 s/d 02 + 500 L/R V V V - - - V - - - - - - - V V V
6 02 + 500 s/d 03 + 000 L/R V V V - - - V - - - - - - - V V V
7 03 + 000 s/d 03 + 500 L/R X X V - - - V - - - - - - - V V V
8 03 + 500 s/d 04 + 000 L/R X X V - - - V - - - - - - - V V V
9 04 + 000 s/d 04 + 500 L/R V V V - - - V - - - - - - - V V V
10 04 + 500 s/d 05 + 000 L/R X X V - - - V - - - - - - - V V V
11 05 + 000 s/d 05 + 500 L/R V V V - - - V - - - - - - - V V V
12 05 + 500 s/d 06 + 000 L/R V V V - - - V - - - - - - - V V V
13 06 + 000 s/d 06 + 500 L/R V V V - - - V - - - - - - - V V V
14 06 + 500 s/d 07 + 000 L/R V V V - - - V - - - - - - - V V V
15 07 + 000 s/d 07 + 500 L/R V V V - - - V - - - - - - - V V V
Catatan 00 + 000
1. Pada Kolom 4 s/d Kolom 20 beri tanda : 3. Kode Kategori Indikator Kinerja Jalan sesuai SSKK yaitu:
V = Memenuhi Indikator Kinerja - Perkerasan Jalan : 1a. Lubang ; 1b. Retak ; 1c. Amblas
X = Tidak Memenuhi Indikator Kinerja - Bahu Jalan : 2a. Lubang ; 2b. Amblas
2. Pada Kolom 21 diisi tanggal sesuai target waktu tanggap perbaikan - Drainase : 3a. Tidak rusak & ada penyumbatan ; 3b. Erosi / Deformasi lereng
- Perlengkapan Jalan : 4a. Rambu ; 4b. Median/Trotoar ; Guardrail/Rel pengama
- Bangunan Pelengkap : 5a. Oprit ; 5b. Diding penahan tanah ; 5c. Expansiont Jo
- Pengendalian Tanaman : 6a. Bebas dari tanaman ; 6b. Ketinggian tanaman terk

Inspeksi Oleh :
Diketahui oleh : Mengetahui : Konsultan Supervisi
Pelaksana Pengawas Lapangan PU Inspector
LAPORAN INSPEKSI PEMENUHAN INDIKATOR KINERJA JALAN
Kontrak Nomor : PW 0401-Bb4/P2JN/PPKPW/262 Tanggal Inspeksi
Ruas Jalan : Bts. Tanjabbar - Sp. Betara Segmen Jalan
Provinsi : Jambi Lingkup Pekerjaan
Total Panjang Jalan : 16,600 Km
Kategori Pemenuhan Indikator Kinerja Jalan
No. Sta - Sta LR
1a 1b 1c 2a 2b 2c 3a 3b 4a 4b 4c 5a 5b 5c 5d 6a 6b
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
16 07 + 500 s/d 08 + 000 L/R V V V - - - V - - - - - - - V X X
17 08 + 000 s/d 08 + 500 L/R V V V - - - V - - - - - - - V X X
18 08 + 500 s/d 09 + 000 L/R V V V - - - V - - - - - - - V X X
19 09 + 000 s/d 09 + 500 L/R V V V - - - V - - - - - - - V X X
20 09 + 500 s/d 10 + 000 L/R V V V - - - V - - - - - - - V X X
21 10 + 000 s/d 10 + 500 L/R V V V - - - V - - - - - - - V V V
22 10 + 500 s/d 11 + 000 L/R V V V - - - V - - - - - - - V V V
23 11 + 000 s/d 11 + 500 L/R V V V - - - V - - - - - - - V V V
24 11 + 500 s/d 12 + 000 L/R V V V - - - V - - - - - - - V V V
25 12 + 000 s/d 12 + 500 L/R V V V - - - V - - - - - - - V V V
26 12 + 500 s/d 13 + 000 L/R X X X - - - V - - - - - - - V V V
27 13 + 000 s/d 13 + 500 L/R X X X - - - V - - - - - - - V V V
28 13 + 500 s/d 14 + 000 L/R V V V - - - V - - - - - - - V V V
29 14 + 000 s/d 14 + 500 L/R V V V - - - V - - - - - - - V V V
30 14 + 500 s/d 15 + 000 L/R V V V - - - V - - - - - - - V V V
Catatan :
1. Pada Kolom 4 s/d Kolom 20 beri tanda : 3. Kode Kategori Indikator Kinerja Jalan sesuai SSKK yaitu:
V = Memenuhi Indikator Kinerja - Perkerasan Jalan : 1a. Lubang ; 1b. Retak ; 1c. Amblas
X = Tidak Memenuhi Indikator Kinerja - Bahu Jalan : 2a. Lubang ; 2b. Amblas
2. Pada Kolom 21 diisi tanggal sesuai target waktu tanggap perbaikan - Drainase : 3a. Tidak rusak & ada penyumbatan ; 3b. Erosi / Deformasi lereng
- Perlengkapan Jalan : 4a. Rambu ; 4b. Median/Trotoar ; Guardrail/Rel pengama
- Bangunan Pelengkap : 5a. Oprit ; 5b. Diding penahan tanah ; 5c. Expansiont Jo
- Pengendalian Tanaman : 6a. Bebas dari tanaman ; 6b. Ketinggian tanaman terk

Inspeksi Oleh :
Diketahui oleh : Mengetahui : Konsultan Supervisi
Pelaksana Pengawas Lapangan PU Inspector
LAPORAN INSPEKSI PEMENUHAN INDIKATOR KINERJA JALAN
Kontrak Nomor : PW 0401-Bb4/P2JN/PPKPW/262 Tanggal Inspeksi
Ruas Jalan : Bts. Tanjabbar - Sp. Betara Segmen Jalan
Provinsi : Jambi Lingkup Pekerjaan
Total Panjang Jalan : 16,600 Km
Kategori Pemenuhan Indikator Kinerja Jalan
No. Sta - Sta LR
1a 1b 1c 2a 2b 2c 3a 3b 4a 4b 4c 5a 5b 5c 5d 6a 6b
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
31 15 + 000 s/d 15 + 500 L/R V V V - - - V - - - - - - - V V V
32 15 + 500 s/d 16 + 000 L/R V V V - - - V - - - - - - - V V V
33 16 + 000 s/d 16 + 500 L/R V V V - - - V - - - - - - - V V V
34 16 + 500 s/d 16 + 600 L/R V V V - - - V - - - - - - - V V V

Catatan :
1. Pada Kolom 4 s/d Kolom 20 beri tanda : 3. Kode Kategori Indikator Kinerja Jalan sesuai SSKK yaitu:
V = Memenuhi Indikator Kinerja - Perkerasan Jalan : 1a. Lubang ; 1b. Retak ; 1c. Amblas
X = Tidak Memenuhi Indikator Kinerja - Bahu Jalan : 2a. Lubang ; 2b. Amblas
2. Pada Kolom 21 diisi tanggal sesuai target waktu tanggap perbaikan - Drainase : 3a. Tidak rusak & ada penyumbatan ; 3b. Erosi / Deformasi lereng
- Perlengkapan Jalan : 4a. Rambu ; 4b. Median/Trotoar ; Guardrail/Rel pengama
- Bangunan Pelengkap : 5a. Oprit ; 5b. Diding penahan tanah ; 5c. Expansiont Jo
- Pengendalian Tanaman : 6a. Bebas dari tanaman ; 6b. Ketinggian tanaman terk

Inspeksi Oleh :
Diketahui oleh : Mengetahui : Konsultan Supervisi
Pelaksana Pengawas Lapangan PU Inspector
LAPORAN INSPEKSI PEMENUHAN INDIKATOR KINERJA JALAN
Kontrak Nomor : PW 0401-Bb4/P2JN/PPKPW/262 Tanggal Inspeksi
Ruas Jalan : Bts. Tanjabtim - Tanjabbar Segmen Jalan
Provinsi : Jambi Lingkup Pekerjaan
Total Panjang Jalan : 20,100 Km
Kategori Pemenuhan Indikator Kinerja Jalan
No. Sta - Sta LR
1a 1b 1c 2a 2b 2c 3a 3b 4a 4b 4c 5a 5b 5c 5d 6a 6b
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 00 + 000 s/d 00 + 500 L/R V V V - - - V - - - - - - - V V V
2 00 + 500 s/d 01 + 000 L/R V V V - - - V - - - - - - - V V V
3 01 + 000 s/d 01 + 500 L/R V V V - - - V - - - - - - - V V V
4 01 + 500 s/d 02 + 000 L/R V V V - - - V - - - - - - - V V V
5 02 + 000 s/d 02 + 500 L/R V V V - - - V - - - - - - - V V V
6 02 + 500 s/d 03 + 000 L/R X X X - - - V - - - - - - - V V V
7 03 + 000 s/d 03 + 500 L/R X X X - - - V - - - - - - - V V V
8 03 + 500 s/d 04 + 000 L/R X X X - - - V - - - - - - - V V V
9 04 + 000 s/d 04 + 500 L/R V V V - - - V - - - - - - - V V V
10 04 + 500 s/d 05 + 000 L/R V V V - - - V - - - - - - - V V V
11 05 + 000 s/d 05 + 500 L/R V V V - - - V - - - - - - - V V V
12 05 + 500 s/d 06 + 000 L/R V V V - - - V - - - - - - - V V V
13 06 + 000 s/d 06 + 500 L/R V V V - - - V - - - - - - - V X X
14 06 + 500 s/d 07 + 000 L/R V V V - - - V - - - - - - - V X X
15 07 + 000 s/d 07 + 500 L/R V V V - - - V - - - - - - - V V V
Catatan :
1. Pada Kolom 4 s/d Kolom 20 beri tanda : 3. Kode Kategori Indikator Kinerja Jalan sesuai SSKK yaitu:
V = Memenuhi Indikator Kinerja - Perkerasan Jalan : 1a. Lubang ; 1b. Retak ; 1c. Amblas
X = Tidak Memenuhi Indikator Kinerja - Bahu Jalan : 2a. Lubang ; 2b. Amblas
2. Pada Kolom 21 diisi tanggal sesuai target waktu tanggap perbaikan - Drainase : 3a. Tidak rusak & ada penyumbatan ; 3b. Erosi / Deformasi lereng
- Perlengkapan Jalan : 4a. Rambu ; 4b. Median/Trotoar ; Guardrail/Rel pengama
- Bangunan Pelengkap : 5a. Oprit ; 5b. Diding penahan tanah ; 5c. Expansiont Jo
- Pengendalian Tanaman : 6a. Bebas dari tanaman ; 6b. Ketinggian tanaman terk

Inspeksi Oleh :
Diketahui oleh : Mengetahui : Konsultan Supervisi
Pelaksana Pengawas Lapangan PU Inspector
LAPORAN INSPEKSI PEMENUHAN INDIKATOR KINERJA JALAN
Kontrak Nomor : PW 0401-Bb4/P2JN/PPKPW/262 Tanggal Inspeksi
Ruas Jalan : Bts. Tanjabtim - Tanjabbar Segmen Jalan
Provinsi : Jambi Lingkup Pekerjaan
Total Panjang Jalan : 20,100 Km
Kategori Pemenuhan Indikator Kinerja Jalan
No. Sta - Sta LR
1a 1b 1c 2a 2b 2c 3a 3b 4a 4b 4c 5a 5b 5c 5d 6a 6b
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
07 + 500 s/d 08 + 000 L/R V V V - - - V - - - - - - - V V V
08 + 000 s/d 08 + 500 L/R V V V - - - V - - - - - - - V V V
08 + 500 s/d 09 + 000 L/R V V V - - - V - - - - - - - V V V
09 + 000 s/d 09 + 500 L/R V V V - - - V - - - - - - - V V V
09 + 500 s/d 10 + 000 L/R V V V - - - V - - - - - - - V V V
10 + 000 s/d 10 + 500 L/R X X X - - - V - - - - - - - V X X
10 + 500 s/d 11 + 000 L/R X X X - - - V - - - - - - - V X X
11 + 000 s/d 11 + 500 L/R X X X - - - V - - - - - - - V X X
11 + 500 s/d 12 + 000 L/R V V V - - - V - - - - - - - V V V
12 + 000 s/d 12 + 500 L/R V V V - - - V - - - - - - - V V V
12 + 500 s/d 13 + 000 L/R V V V - - - V - - - - - - - V V V
13 + 000 s/d 13 + 500 L/R V V V - - - V - - - - - - - V V V
13 + 500 s/d 14 + 000 L/R V V V - - - V - - - - - - - V X X
14 + 000 s/d 14 + 500 L/R V V V - - - V - - - - - - - V X X
14 + 500 s/d 15 + 000 L/R V V V - - - V - - - - - - - V V V
Catatan :
1. Pada Kolom 4 s/d Kolom 20 beri tanda : 3. Kode Kategori Indikator Kinerja Jalan sesuai SSKK yaitu:
V = Memenuhi Indikator Kinerja - Perkerasan Jalan : 1a. Lubang ; 1b. Retak ; 1c. Amblas
X = Tidak Memenuhi Indikator Kinerja - Bahu Jalan : 2a. Lubang ; 2b. Amblas
2. Pada Kolom 21 diisi tanggal sesuai target waktu tanggap perbaikan - Drainase : 3a. Tidak rusak & ada penyumbatan ; 3b. Erosi / Deformasi lereng
- Perlengkapan Jalan : 4a. Rambu ; 4b. Median/Trotoar ; Guardrail/Rel pengama
- Bangunan Pelengkap : 5a. Oprit ; 5b. Diding penahan tanah ; 5c. Expansiont Jo
- Pengendalian Tanaman : 6a. Bebas dari tanaman ; 6b. Ketinggian tanaman terk

Inspeksi Oleh :
Diketahui oleh : Mengetahui : Konsultan Supervisi
Pelaksana Pengawas Lapangan PU Inspector
LAPORAN INSPEKSI PEMENUHAN INDIKATOR KINERJA JALAN
Kontrak Nomor : PW 0401-Bb4/P2JN/PPKPW/262 Tanggal Inspeksi
Ruas Jalan : Bts. Tanjabtim - Tanjabbar Segmen Jalan
Provinsi : Jambi Lingkup Pekerjaan
Total Panjang Jalan : 20,100 Km
Kategori Pemenuhan Indikator Kinerja Jalan
No. Sta - Sta LR
1a 1b 1c 2a 2b 2c 3a 3b 4a 4b 4c 5a 5b 5c 5d 6a 6b
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
15 + 000 s/d 15 + 500 L/R V V V - - - V - - - - - - - V V V
15 + 500 s/d 16 + 000 L/R V V V - - - V - - - - - - - V V V
16 + 000 s/d 16 + 500 L/R V V V - - - V - - - - - - - V V V
p[;p;\0p 16 + 500 s/d 17 + 000 L/R X X X - - - V - - - - - - - V V V
17 + 000 s/d 17 + 500 L/R X X X - - - V - - - - - - - V V V
17 + 500 s/d 18 + 000 L/R X X X - - - V - - - - - - - V V V
18 + 000 s/d 18 + 500 L/R X X X - - - V - - - - - - - V V V
18 + 500 s/d 19 + 000 L/R V V V - - - V - - - - - - - V V V
19 + 000 s/d 19 + 500 L/R V V V - - - V - - - - - - - V V V
19 + 500 s/d 20 + 000 L/R V V V - - - V - - - - - - - V V V
20 + 000 s/d 20 + 100 L/R V V V - - - V - - - - - - - V V V

Catatan :
1. Pada Kolom 4 s/d Kolom 20 beri tanda : 3. Kode Kategori Indikator Kinerja Jalan sesuai SSKK yaitu:
V = Memenuhi Indikator Kinerja - Perkerasan Jalan : 1a. Lubang ; 1b. Retak ; 1c. Amblas
X = Tidak Memenuhi Indikator Kinerja - Bahu Jalan : 2a. Lubang ; 2b. Amblas
2. Pada Kolom 21 diisi tanggal sesuai target waktu tanggap perbaikan - Drainase : 3a. Tidak rusak & ada penyumbatan ; 3b. Erosi / Deformasi lereng
- Perlengkapan Jalan : 4a. Rambu ; 4b. Median/Trotoar ; Guardrail/Rel pengama
- Bangunan Pelengkap : 5a. Oprit ; 5b. Diding penahan tanah ; 5c. Expansiont Jo
- Pengendalian Tanaman : 6a. Bebas dari tanaman ; 6b. Ketinggian tanaman terk

Inspeksi Oleh :
Diketahui oleh : Mengetahui : Konsultan Supervisi
Pelaksana Pengawas Lapangan PU Inspector
LAPORAN INSPEKSI PEMENUHAN INDIKATOR KINERJA JALAN
Kontrak Nomor : PW 0401-Bb4/P2JN/PPKPW/262 Tanggal Inspeksi
Ruas Jalan : Sp. Betara/Gas Plant - Ka.Tungkal (SKPD - TP) Segmen Jalan
Provinsi : Jambi Lingkup Pekerjaan
Total Panjang Jalan 10,00 Km
Kategori Pemenuhan Indikator Kinerja Jalan
No. Sta - Sta LR
1a 1b 1c 2a 2b 2c 3a 3b 4a 4b 4c 5a 5b 5c 5d 6a 6b
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
00 + 000 s/d 00 + 500 L/R V V V - - - V - - - - - - - V V V
00 + 500 s/d 01 + 000 L/R V V V - - - V - - - - - - - V V V
01 + 000 s/d 01 + 500 L/R V V V - - - V - - - - - - - V V V
01 + 500 s/d 02 + 000 L/R V V V - - - V - - - - - - - V V V
02 + 000 s/d 02 + 500 L/R V V V - - - V - - - - - - - V V V
02 + 500 s/d 03 + 000 L/R V V V - - - V - - - - - - - V V V
03 + 000 s/d 03 + 400 L/R V V V - - - V - - - - - - - V V V
03 + 400 s/d 04 + 600 L/R LOKASI HOLDING TREATMENT (SKPD)
04 + 600 s/d 05 + 150 L/R LOKASI REHAB MAYOR SEGMEN I (SKPD)
05 + 150 s/d 06 + 800 L/R LOKASI HOLDING TREATMENT (SKPD)
06 + 800 s/d 09 + 350 L/R LOKASI REHAB MAYOR SEGMEN II (SKPD)
09 + 350 s/d 09 + 600 L/R LOKASI HOLDING TREATMENT (SKPD)
09 + 600 s/d 10 + 000 L/R LOKASI REHAB MAYOR SEGMEN III (SKPD)

Catatan :
1. Pada Kolom 4 s/d Kolom 20 beri tanda : 3. Kode Kategori Indikator Kinerja Jalan sesuai SSKK yaitu:
V = Memenuhi Indikator Kinerja - Perkerasan Jalan : 1a. Lubang ; 1b. Retak ; 1c. Amblas
X = Tidak Memenuhi Indikator Kinerja - Bahu Jalan : 2a. Lubang ; 2b. Amblas
2. Pada Kolom 21 diisi tanggal sesuai target waktu tanggap perbaikan - Drainase : 3a. Tidak rusak & ada penyumbatan ; 3b. Erosi / Deformasi lereng
- Perlengkapan Jalan : 4a. Rambu ; 4b. Median/Trotoar ; Guardrail/Rel pengama
- Bangunan Pelengkap : 5a. Oprit ; 5b. Diding penahan tanah ; 5c. Expansiont Jo
- Pengendalian Tanaman : 6a. Bebas dari tanaman ; 6b. Ketinggian tanaman terk

Inspeksi Oleh :
Diketahui oleh : Mengetahui : Konsultan Supervisi
Pelaksana Pengawas Lapangan PU Inspector
EMENUHAN INDIKATOR KINERJA JALAN
: 01 April 2019
: Sta 00+000 s/d 16+600
: Rutin Jalan

Pemenuhan Tgl Batas Tanggap


Indikator Perbaikan
21 22
V
V
V
V
V
V
X 08 April 2019
X 08 April 2019
V
X 08 April 2019
V
V
V
V
V

- Drainase : 3a. Tidak rusak & ada penyumbatan ; 3b. Erosi / Deformasi lereng
- Perlengkapan Jalan : 4a. Rambu ; 4b. Median/Trotoar ; Guardrail/Rel pengaman
- Bangunan Pelengkap : 5a. Oprit ; 5b. Diding penahan tanah ; 5c. Expansiont Joint ; 5d. Pagar jembatan
- Pengendalian Tanaman : 6a. Bebas dari tanaman ; 6b. Ketinggian tanaman terkendali

Inspeksi Oleh :
Konsultan Supervisi
Inspector
EMENUHAN INDIKATOR KINERJA JALAN
: 08 April 2019
: Sta 00+000 s/d 16+600
: Rutin Jalan

Pemenuhan Tgl Batas Tanggap


Indikator Perbaikan
21 22
X 15 April 2019
X 15 April 2019
X 15 April 2019
X 15 April 2019
V
V
V
V
V
V
X 15 April 2019
X 15 April 2019
V
V
V

- Drainase : 3a. Tidak rusak & ada penyumbatan ; 3b. Erosi / Deformasi lereng
- Perlengkapan Jalan : 4a. Rambu ; 4b. Median/Trotoar ; Guardrail/Rel pengaman
- Bangunan Pelengkap : 5a. Oprit ; 5b. Diding penahan tanah ; 5c. Expansiont Joint ; 5d. Pagar jembatan
- Pengendalian Tanaman : 6a. Bebas dari tanaman ; 6b. Ketinggian tanaman terkendali

Inspeksi Oleh :
Konsultan Supervisi
Inspector
EMENUHAN INDIKATOR KINERJA JALAN
: 15 April 2019
: Sta 00+000 s/d 16+600
: Rutin Jalan

Pemenuhan Tgl Batas Tanggap


Indikator Perbaikan
21 22
V
V
V
V

- Drainase : 3a. Tidak rusak & ada penyumbatan ; 3b. Erosi / Deformasi lereng
- Perlengkapan Jalan : 4a. Rambu ; 4b. Median/Trotoar ; Guardrail/Rel pengaman
- Bangunan Pelengkap : 5a. Oprit ; 5b. Diding penahan tanah ; 5c. Expansiont Joint ; 5d. Pagar jembatan
- Pengendalian Tanaman : 6a. Bebas dari tanaman ; 6b. Ketinggian tanaman terkendali

Inspeksi Oleh :
Konsultan Supervisi
Inspector
EMENUHAN INDIKATOR KINERJA JALAN
: 15 April 2019
: Sta 00+000 s/d 20+100
: Rutin Jalan

Pemenuhan Tgl Batas Tanggap


Indikator Perbaikan
21 22
V
V
V
V
V
X 22 April 2019
X 22 April 2019
X 22 April 2019
V
V
V
V
X 22 April 2019
X 22 April 2019
V

- Drainase : 3a. Tidak rusak & ada penyumbatan ; 3b. Erosi / Deformasi lereng
- Perlengkapan Jalan : 4a. Rambu ; 4b. Median/Trotoar ; Guardrail/Rel pengaman
- Bangunan Pelengkap : 5a. Oprit ; 5b. Diding penahan tanah ; 5c. Expansiont Joint ; 5d. Pagar jembatan
- Pengendalian Tanaman : 6a. Bebas dari tanaman ; 6b. Ketinggian tanaman terkendali

Inspeksi Oleh :
Konsultan Supervisi
Inspector
EMENUHAN INDIKATOR KINERJA JALAN
: 22 Maret 2019
: Sta 00+000 s/d 20+100
: Rutin Jalan

Pemenuhan Tgl Batas Tanggap


Indikator Perbaikan
21 22
V
V
V
V
V
X 29 April 2019
X 29 April 2019
X 29 April 2019
V
V
V
V
X 29 April 2019
X 29 April 2019
V

- Drainase : 3a. Tidak rusak & ada penyumbatan ; 3b. Erosi / Deformasi lereng
- Perlengkapan Jalan : 4a. Rambu ; 4b. Median/Trotoar ; Guardrail/Rel pengaman
- Bangunan Pelengkap : 5a. Oprit ; 5b. Diding penahan tanah ; 5c. Expansiont Joint ; 5d. Pagar jembatan
- Pengendalian Tanaman : 6a. Bebas dari tanaman ; 6b. Ketinggian tanaman terkendali

Inspeksi Oleh :
Konsultan Supervisi
Inspector
EMENUHAN INDIKATOR KINERJA JALAN
: 22 April 2019
: Sta 00+000 s/d 20+100
: Rutin Jalan

Pemenuhan Tgl Batas Tanggap


Indikator Perbaikan
21 22
V
V
V
X 29 April 2019
X 29 April 2019
X 29 April 2019
X 29 April 2019
V
V
V
V

- Drainase : 3a. Tidak rusak & ada penyumbatan ; 3b. Erosi / Deformasi lereng
- Perlengkapan Jalan : 4a. Rambu ; 4b. Median/Trotoar ; Guardrail/Rel pengaman
- Bangunan Pelengkap : 5a. Oprit ; 5b. Diding penahan tanah ; 5c. Expansiont Joint ; 5d. Pagar jembatan
- Pengendalian Tanaman : 6a. Bebas dari tanaman ; 6b. Ketinggian tanaman terkendali

Inspeksi Oleh :
Konsultan Supervisi
Inspector
EMENUHAN INDIKATOR KINERJA JALAN
: 22 April 2019
: Sta 00+000 s/d 10+000
: Rutin Jalan

Pemenuhan Tgl Batas Tanggap


Indikator Perbaikan
21 22
V
V
V
V
V
V
V
LOKASI HOLDING TREATMENT (SKPD)
LOKASI REHAB MAYOR SEGMEN I (SKPD)
LOKASI HOLDING TREATMENT (SKPD)
LOKASI REHAB MAYOR SEGMEN II (SKPD)
LOKASI HOLDING TREATMENT (SKPD)
LOKASI REHAB MAYOR SEGMEN III (SKPD)

- Drainase : 3a. Tidak rusak & ada penyumbatan ; 3b. Erosi / Deformasi lereng
- Perlengkapan Jalan : 4a. Rambu ; 4b. Median/Trotoar ; Guardrail/Rel pengaman
- Bangunan Pelengkap : 5a. Oprit ; 5b. Diding penahan tanah ; 5c. Expansiont Joint ; 5d. Pagar jembatan
- Pengendalian Tanaman : 6a. Bebas dari tanaman ; 6b. Ketinggian tanaman terkendali

Inspeksi Oleh :
Konsultan Supervisi
Inspector
LAPORAN INSPEKSI ULANG PEMENUHAN INDIKATOR KINERJA JALAN
Kontrak Nomor : PW 0401-Bb4/P2JN/PPKPW/262 Tanggal Inspeksi
Ruas Jalan : Tanjabbar - Sp.Betara Segmen Jalan
Provinsi : Jambi Lingkup Pekerjaan
Total Panjang Jalan : 16,600 Km
Ketidak Sesuaian Indikator Kinerja Jalan Kode Kategori Tanggal Perbaikan Masa Denda
No.
Sta - Sta LR Tgl. Penemuan Indikator Kerja Target Realisasi (Hari)
1 2 3 4 5 6 7 8
1 03 + 000 s/d 03 + 500 L/R 01 April 2019 1a,1b 08 April 2019 08 April 2019 -
2 03 + 500 s/d 04 + 000 L/R 01 April 2019 1a,1b 08 April 2019 08 April 2019 -
3 04 + 500 s/d 05 + 000 L/R 2 April 2019 1a,1b,6a,6b 08 April 2019 08 April 2019 -

Catatan :
1. Kolom 4 diisi tanggal penemuan ketidak sesuaian pada saat inspeksi 3. Kolom 6 diisi tanggal target perbaikan sesuai spesifikasi khusu

2. Kolom 5 diisi kode memenuhi indikator kerja 4. Kolom 7 diisi tanggal realisasi perbaikan

5. Kolom 8 diisi jumlah hari masa denda = (kolom 7) - (kolom 6)

Diketahui oleh : Penyedia Jasa :


Pengawas Lapangan PU Pelaksana Kontraktor
LAPORAN INSPEKSI ULANG PEMENUHAN INDIKATOR KINERJA JALAN
Kontrak Nomor : PW 0401-Bb4/P2JN/PPKPW/262 Tanggal Inspeksi
Ruas Jalan : Tanjabbar - Sp.Betara Segmen Jalan
Provinsi : Jambi Lingkup Pekerjaan
Total Panjang Jalan : 16,600 Km
Ketidak Sesuaian Indikator Kinerja Jalan Kode Kategori Tanggal Perbaikan Masa Denda
No.
Sta - Sta LR Tgl. Penemuan Indikator Kerja Target Realisasi (Hari)
1 2 3 4 5 6 7 8
1 07 + 500 s/d 08 + 000 L/R 08 April 2019 6a,6b 15 April 2019 15 April 2019 -
2 08 + 000 s/d 08 + 500 L/R 08 April 2019 6a,6b 15 April 2019 15 April 2019 -
3 08 + 500 s/d 09 + 000 L/R 08 April 2019 6a,6b 15 April 2019 15 April 2019 -
4 09 + 000 s/d 09 + 500 L/R 08 April 2019 6a,6b 15 April 2019 15 April 2019 -
5 12 + 500 s/d 13 + 000 L/R 08 April 2019 1a,1b,1c 15 April 2019 15 April 2019 -
6 13 + 000 s/d 13 + 500 L/R 08 April 2019 1a,1b,1c 15 April 2019 15 April 2019 -

Catatan :
1. Kolom 4 diisi tanggal penemuan ketidak sesuaian pada saat inspeksi 3. Kolom 6 diisi tanggal target perbaikan sesuai spesifikasi khusu

2. Kolom 5 diisi kode memenuhi indikator kerja 4. Kolom 7 diisi tanggal realisasi perbaikan

5. Kolom 8 diisi jumlah hari masa denda = (kolom 7) - (kolom 6)

Diketahui oleh : Penyedia Jasa :


Pengawas Lapangan PU Pelaksana Kontraktor
LAPORAN INSPEKSI ULANG PEMENUHAN INDIKATOR KINERJA JALAN
Kontrak Nomor : PW 0401-Bb4/P2JN/PPKPW/262 Tanggal Inspeksi
Ruas Jalan : Bts. Tanjabtim - Tanjabbar Segmen Jalan
Provinsi : Jambi Lingkup Pekerjaan
Total Panjang Jalan : 20,100 Km
Ketidak Sesuaian Indikator Kinerja Jalan Kode Kategori Tanggal Perbaikan Masa Denda
No.
Sta - Sta LR Tgl. Penemuan Indikator Kerja Target Realisasi (Hari)
1 2 3 4 5 6 7 8
1 02 + 500 s/d 03 + 000 L/R 15 April 2019 1a,1b,1c 22 April 2019 22 April 2019 -
2 03 + 000 s/d 03 + 500 L/R 15 April 2019 1a,1b,1c 22 April 2019 22 April 2019 -
3 03 + 500 s/d 04 + 000 L/R 15 April 2019 1a,1b,1c 22 April 2019 22 April 2019 -
4 06 + 000 s/d 06 + 500 L/R 15 April 2019 6a,6b 22 April 2019 22 April 2019 -
5 06 + 500 s/d 07 + 000 L/R 15 April 2019 6a,6b 22 April 2019 22 April 2019 -
6 10 + 000 s/d 10 + 500 L/R 22 April 2019 1a,1b,1c,6a,6b 29 April 2019 29 April 2019 -
7 10 + 500 s/d 11 + 000 L/R 22 April 2019 1a,1b,1c,6a,6b 29 April 2019 29 April 2019 -
8 11 + 000 s/d 11 + 500 L/R 22 April 2019 1a,1b,1c,6a,6b 29 April 2019 29 April 2019 -
9 13 + 500 s/d 14 + 000 L/R 22 April 2019 6a,6b 29 April 2019 29 April 2019 -
10 14 + 000 s/d 14 + 500 L/R 22 April 2019 6a,6b 29 April 2019 29 April 2019 -
11 16 + 500 s/d 17 + 000 L/R 22 April 2019 1a,1b,1c 29 April 2019 29 April 2019 -
12 17 + 000 s/d 17 + 500 L/R 22 April 2019 1a,1b,1c 29 April 2019 29 April 2019 -
13 17 + 500 s/d 18 + 000 L/R 22 April 2019 1a,1b,1c 29 April 2019 29 April 2019 -
14 18 + 000 s/d 18 + 500 L/R 22 April 2019 1a,1b,1c 29 April 2019 29 April 2019 -

Catatan :
1. Kolom 4 diisi tanggal penemuan ketidak sesuaian pada saat inspeksi 3. Kolom 6 diisi tanggal target perbaikan sesuai spesifikasi khusu

2. Kolom 5 diisi kode memenuhi indikator kerja 4. Kolom 7 diisi tanggal realisasi perbaikan

5. Kolom 8 diisi jumlah hari masa denda = (kolom 7) - (kolom 6)

Diketahui oleh : Penyedia Jasa :


Pengawas Lapangan PU Pelaksana Kontraktor
G PEMENUHAN INDIKATOR KINERJA JALAN
: 08 April 2019
: Sta 00+000 s/d 16+600
: Rutin Jalan

Keterangan

Kolom 6 diisi tanggal target perbaikan sesuai spesifikasi khusus

Kolom 8 diisi jumlah hari masa denda = (kolom 7) - (kolom 6)

Inspeksi Oleh :
Konsultan Supervisi
Inspector
G PEMENUHAN INDIKATOR KINERJA JALAN
: 15 April 2019
: Sta 00+000 s/d 16+600
: Rutin Jalan

Keterangan

Kolom 6 diisi tanggal target perbaikan sesuai spesifikasi khusus

Kolom 8 diisi jumlah hari masa denda = (kolom 7) - (kolom 6)

Inspeksi Oleh :
Konsultan Supervisi
Inspector
G PEMENUHAN INDIKATOR KINERJA JALAN
: 22-29 April 2019
: Sta 00+000 s/d 20+100
: Rutin Jalan

Keterangan

Kolom 6 diisi tanggal target perbaikan sesuai spesifikasi khusus

Kolom 8 diisi jumlah hari masa denda = (kolom 7) - (kolom 6)

Inspeksi Oleh :
Konsultan Supervisi
Inspector