ANALISA BIAYA PERALATAN

DAFTAR ALAT TAHUN ANGGARAN 2001

UMUR DAN KAPASITAS ALAT TOTAL BIAYA MODAL TOTAL BIAYA


KODE #REF!
URAIAN UNIT INSTALASI DAN ALAT BERAT TOTAL BIAYA MODAL THN 2001 MODAL TAHUN
ALAT Total Umur Pakai Tenaga
Jam/Tahun (Rp.7.000/$) 1998/1999
Tahun Jam Kuda
BULLDOZER 125 HP E 001 Rp 1,452,000,000 8 9,600 1,200 125 Rp 1,452,000,000 $132,000
BULLDOZER 65 HP E 003 Rp 939,400,000 8 9,600 1,200 65 Rp 939,400,000 $85,400
MOTOR GRADER 125 HP E 010 Rp 1,113,200,000 8 12,000 1,500 125 Rp 1,113,200,000 $101,200
HYDRAULIC EXCAVATOR 1m³ 90 HP E 020 Rp 665,500,000 8 12,000 1,500 90 Rp 665,500,000 $60,500
STONE CRUSHER ( 30 t / h ) 140 HP E 031 Rp 1,320,000,000 10 15,000 1,500 140 Rp 1,320,000,000 $120,000
STONE CRUSHER ( 20 t / h ) 95 HP E 032 Rp 1,018,600,000 10 15,000 1,500 95 Rp 1,018,600,000 $92,600
STONE CRUSHER ( 10 t / h ) 15 HP E 033 Rp 555,500,000 8 12,000 1,500 15 Rp 555,500,000 $50,500
SCREENING PLANT 80 HP E 040 Rp 463,100,000 8 12,000 1,500 80 Rp 463,100,000 $42,100
LOADER TRACKED 135 HP E 051 Rp 1,061,500,000 8 12,000 1,500 135 Rp 1,061,500,000 $96,500
LOADER WHEELED 115 HP E 052 Rp 556,600,000 8 12,000 1,500 115 Rp 556,600,000 $50,600
TRACTOR WHEELED 60 HP E 053 Rp 206,250,000 10 15,000 1,500 60 Rp 206,250,000 $18,750
ROLLER 3 WHEELED ( 6 - 8 t ) 51 HP E 080 Rp 129,250,000 10 15,000 1,500 51 Rp 129,250,000 $11,750
TANDEM ROLLER ( 8 - 10 t ) 40 HP E 081 Rp 193,600,000 10 15,000 1,500 40 Rp 193,600,000 $17,600
SELF VIBRATOR ROLLER ( 10 t ) 35 HP E 082 Rp 214,500,000 8 12,000 1,500 35 Rp 214,500,000 $19,500
TOWED VIBRATOR ROLLER ( 4 t ) 6 HP E 083 Rp 363,000,000 8 12,000 1,500 6 Rp 363,000,000 $33,000
PNEUMATIC TIRE ROLLER ( 8 - 12 t ) 95 HP E 084 Rp 1,325,786,000 10 15,000 1,500 95 Rp 1,325,786,000 $120,526
VIBRATOR ROLLER 600 kg 7 HP E 087 Rp 107,800,000 6 7,200 1,200 7 Rp 107,800,000 $9,800
TAMPER (VIBRATOR PLATE) 4 HP E 088 Rp 30,800,000 6 4,500 750 4 Rp 30,800,000 $2,800
CONCRETE VIBRATOR 4 HP E 089 Rp 7,986,000 5 3,000 600 4 Rp 7,986,000 $726
CHIP SPREADER 3 tonne HP E 130 Rp 9,515,000 6 3,600 600 0 Rp 9,515,000 $865
SPRAYER SELFPROP 4.000 liter 38 HP E 152 Rp 90,750,000 6 7,200 1,200 38 Rp 90,750,000 $8,250
ASPHALT SPRAYER TOWED 200 liter 7 HP E 154 Rp 27,500,000 6 4,500 750 7 Rp 27,500,000 $2,500
ASPHALT MIXING PLANT ( 50 t / h ) 125 HP E 155 Rp 2,200,000,000 10 12,000 1,200 125 Rp 2,200,000,000 $200,000
ASPHALT MIXING PLANT ( 10 t / h ) 50 HP E 156 Rp 1,650,000,000 10 12,000 1,200 50 Rp 1,650,000,000 $150,000
ASPHALT FINISHER 6 tonne 30 HP E 157 Rp 1,610,620,000 7 8,400 1,200 30 Rp 1,610,620,000 $146,420
FUEL TANK TRUCK 115 HP E 172 Rp - 8 5,600 700 115 Rp -
WATER TANK TRUCK 115 HP E 182 Rp 187,726,000 8 5,600 700 115 Rp 187,726,000 $17,066
TRAILER TOWED 1 tonne 1 tonne E 191 Rp 30,800,000 12 9,000 750 1 Rp 30,800,000 $2,800
LOW LOADER + TRACTOR 175 HP E 192 Rp - 10 7,500 750 175 Rp -
DUMP TRUCK 3,5 tonne 106 HP E 211 Rp 272,250,000 6 7,800 1,300 106 Rp 272,250,000 $24,750
DUMP TRUCK 5 tonne 145 HP E 212 Rp 379,500,000 6 7,800 1,300 145 Rp 379,500,000 $34,500
DUMP TRUCK 8 tonne 175 HP E 213 Rp - 6 9,000 1,500 175 Rp -
FLATBED TRUCK 4 tonne 80 HP E 221 Rp 330,000,000 6 7,800 1,300 80 Rp 330,000,000 $30,000
PICK UP TRUCK 61 HP E 222 Rp - 6 9,000 1,500 61 Rp -
JEEP 4 WD 49 HP E 223 Rp - 6 9,000 1,500 49 Rp -
FLATBED TRUCK 5 tonne 110 HP E 224 Rp - 6 7,800 1,300 110 Rp -
FLATBED TRUCK WITH CRANE 110 HP E 225 Rp - 6 9,000 1,500 110 Rp -
MOTOR CYCLE 125cc 14 HP E 226 Rp - 5 6,000 1,200 14 Rp -
MOBILE WORKSHOP 5 tonne 80 HP E 231 Rp - 6 9,600 1,600 80 Rp -
LUBE TRUCK 5 tonne 82 HP E 232 Rp - 6 9,600 1,600 82 Rp -
CONCRETE MIXER ( 0,125 m³ ) 6 HP E 251 Rp - 4 6,000 1,500 6 Rp -
CONCRETE MIXER ( 0,250 m³ ) 10 HP E 252 Rp 55,000,000 5 7,500 1,500 10 Rp 55,000,000 $5,000
CONCRETE MIXER ( 0,500 m³ ) 20 HP E 253 Rp - 5 7,500 1,500 20 Rp -
AIR COMPRESSOR (125 CFM) 20 HP E 301 Rp 90,750,000 8 6,000 750 20 Rp 90,750,000 $8,250
GENERATOR ( 3 - 5 KVA ) 10 HP E 311 Rp - 8 4,800 600 10 Rp -
WATER PUMP 5cm ( 30m³ / h ) 8 HP E 341 Rp 7,700,000 4 3,000 750 8 Rp 7,700,000 $700
WATER PUMP 10cm ( 40m³ / h ) 10 HP E 342 Rp 9,350,000 4 3,000 750 10 Rp 9,350,000 $850
JACKHAMMER EQUIPMENT etc E 351 Rp 11,000,000 5 3,750 750 0 Rp 11,000,000 $1,000
TRACTOR EQUIPMENT etc E 401 Rp 90,750,000 5 3,000 600 0 Rp 90,750,000 $8,250
Rp -
Rp - 2
Rp -
Umur 1 Tahun 1.10000 0.12500 0.15000
Umur 2 Tahun 0.57619 0.59559 0.61512
Umur 3 Tahun 0.40211 0.41993 0.43798
Umur 4 Tahun 0.31547 0.33271 0.35027
Umur 5 Tahun 0.26300 0.28085 0.29832
Umur 6 Tahun 0.22961 0.24668 0.26424
Umur 7 Tahun 0.20541 0.22260 0.24036
Umur 8 Tahun 0.18744 0.20483 0.22285
Umur 9 Tahun 0.17364 0.19126 0.20957
Umur 10 Tahun 0.16275 0.18062 0.19925
Umur 11 Tahun 0.15396 0.17211 0.19107
Umur 12 Tahun 0.14676 0.16519 0.18448
FAKTOR BIAYA PENGEMBALIAN MODAL
NILAI UMUR PEMAKAIAN 10.00% 12.50% 15.00%

TABEL FAKTOR BIAYA PENGEMBALIAN MODAL (CRF)


ANALISA BIAYA PERALATAN
#REF!
DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 001
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = BULLDOZER


TENAGA = 100 HP
HARGA = Rp 1,452,000,000.00
UMUR KERJA = 8 Tahun = 9,600 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 4 Jam Kerja
FAKTOR CRF = 0.20483 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 1,452,000,000.00 x 0.20483 = Rp 223,059.87
Jam/Tahun 1,200

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 1,452,000,000.00 = Rp 39,930.00
Jam/Tahun 1,200

Sub Total A = Rp 262,989.87

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 100 x Rp 3,208.92 = Rp 51,342.72


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 100 x Rp 23,264.67 = Rp 13,958.80

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 223,059.87 = ------------------------------------ = Rp 178,447.90

Sub Total B = Rp 243,749.42

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 262,989.87 + Rp 243,749.42 = Rp 506,739.29

Pembulatan = Rp 506,739 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 010
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = MOTOR GRADER


TENAGA = 115 HP
HARGA = Rp 1,113,200,000.00
UMUR KERJA = 8 Tahun = 12,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.20483 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 1,113,200,000.00 x 0.20483 = Rp 136,810.05
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 1,113,200,000.00 = Rp 24,490.40
Jam/Tahun 1,500

Sub Total A = Rp 161,300.45

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 115 x Rp 3,208.92 = Rp 59,044.13


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 115 x Rp 23,264.67 = Rp 16,052.62

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 136,810.05 = ------------------------------------ = Rp 109,448.04

Sub Total B = Rp 184,544.79

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 161,300.45 + Rp 184,544.79 = Rp 345,845.25

Pembulatan = Rp 345,845 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 020
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = HYDRAULIC EXCAVATOR


TENAGA = 90 HP
HARGA = Rp 665,500,000.00
UMUR KERJA = 8 Tahun = 12,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.20483 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 665,500,000.00 x 0.20483 = Rp 81,788.62
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 665,500,000.00 = Rp 14,641.00
Jam/Tahun 1,500

Sub Total A = Rp 96,429.62

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 90 x Rp 3,208.92 = Rp 46,208.45


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 90 x Rp 23,264.67 = Rp 12,562.92

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 81,788.62 = ------------------------------------ = Rp 65,430.90

Sub Total B = Rp 124,202.27

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 96,429.62 + Rp 124,202.27 = Rp 220,631.88

Pembulatan = Rp 220,631 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 031
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = STONE CRUSHER 30 TONNE/HOUR


TENAGA = 140 HP
HARGA = Rp 1,320,000,000.00
UMUR KERJA = 10 Tahun = 15,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.18062 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 1,320,000,000.00 x 0.18062 = Rp 143,051.04
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 1,320,000,000.00 = Rp 29,040.00
Jam/Tahun 1,500

Sub Total A = Rp 172,091.04

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 140 x Rp 3,208.92 = Rp 71,879.81


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 140 x Rp 23,264.67 = Rp 19,542.32

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 143,051.04 = ------------------------------------ = Rp 114,440.83

Sub Total B = Rp 205,862.96

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 172,091.04 + Rp 205,862.96 = Rp 377,954.00

Pembulatan = Rp 377,954 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 032
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = STONE CRUSHER 20 TONNE/HOUR


TENAGA = 95 HP
HARGA = Rp 1,018,600,000.00
UMUR KERJA = 10 Tahun = 15,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.18062 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 1,018,600,000.00 x 0.18062 = Rp 110,387.72
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 1,018,600,000.00 = Rp 22,409.20
Jam/Tahun 1,500

Sub Total A = Rp 132,796.92

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 95 x Rp 3,208.92 = Rp 48,775.58


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 95 x Rp 23,264.67 = Rp 13,260.86

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 110,387.72 = ------------------------------------ = Rp 88,310.18

Sub Total B = Rp 150,346.62

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 132,796.92 + Rp 150,346.62 = Rp 283,143.54

Pembulatan = Rp 283,143 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 033
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = STONE CRUSHER 10 TONNE/HOUR


TENAGA = 75 HP
HARGA = Rp 555,500,000.00
UMUR KERJA = 8 Tahun = 12,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.20483 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 555,500,000.00 x 0.20483 = Rp 68,269.84
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 555,500,000.00 = Rp 12,221.00
Jam/Tahun 1,500

Sub Total A = Rp 80,490.84

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 75 x Rp 3,208.92 = Rp 38,507.04


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 75 x Rp 23,264.67 = Rp 10,469.10

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 68,269.84 = ------------------------------------ = Rp 54,615.87

Sub Total B = Rp 103,592.01

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 80,490.84 + Rp 103,592.01 = Rp 184,082.85

Pembulatan = Rp 184,082 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 040
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = SCREENING PLANT


TENAGA = 80 HP
HARGA = Rp 463,100,000.00
UMUR KERJA = 8 Tahun = 12,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.20483 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 463,100,000.00 x 0.20483 = Rp 56,914.06
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 463,100,000.00 = Rp 10,188.20
Jam/Tahun 1,500

Sub Total A = Rp 67,102.26

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 80 x Rp 3,208.92 = Rp 41,074.18


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 80 x Rp 23,264.67 = Rp 11,167.04

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 56,914.06 = ------------------------------------ = Rp 45,531.25

Sub Total B = Rp 97,772.47

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 67,102.26 + Rp 97,772.47 = Rp 164,874.73

Pembulatan = Rp 164,874 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 052
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = WHEEL LOADER


TENAGA = 115 HP
HARGA = Rp 556,600,000.00
UMUR KERJA = 8 Tahun = 12,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.20483 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 556,600,000.00 x 0.20483 = Rp 68,405.03
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 556,600,000.00 = Rp 12,245.20
Jam/Tahun 1,500

Sub Total A = Rp 80,650.23

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 115 x Rp 3,208.92 = Rp 59,044.13


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 115 x Rp 23,264.67 = Rp 16,052.62

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 68,405.03 = ------------------------------------ = Rp 54,724.02

Sub Total B = Rp 129,820.77

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 80,650.23 + Rp 129,820.77 = Rp 210,471.00

Pembulatan = Rp 210,470 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 053
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = TRACTOR WHEELED


TENAGA = 60 HP
HARGA = Rp 206,250,000.00
UMUR KERJA = 10 Tahun = 15,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.18062 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 206,250,000.00 x 0.18062 = Rp 22,351.73
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 206,250,000.00 = Rp 4,537.50
Jam/Tahun 1,500

Sub Total A = Rp 26,889.23

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 60 x Rp 3,208.92 = Rp 30,805.63


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 60 x Rp 23,264.67 = Rp 8,375.28

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 22,351.73 = ------------------------------------ = Rp 17,881.38

Sub Total B = Rp 57,062.29

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 26,889.23 + Rp 57,062.29 = Rp 83,951.52

Pembulatan = Rp 83,951 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 080
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = ROLLER 3 WHEEL 8-10 TONNE


TENAGA = 51 HP
HARGA = Rp 129,250,000.00
UMUR KERJA = 10 Tahun = 15,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.18062 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 129,250,000.00 x 0.18062 = Rp 14,007.08
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 129,250,000.00 = Rp 2,843.50
Jam/Tahun 1,500

Sub Total A = Rp 16,850.58

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 51 x Rp 3,208.92 = Rp 26,184.79


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 51 x Rp 23,264.67 = Rp 7,118.99

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 14,007.08 = ------------------------------------ = Rp 11,205.66

Sub Total B = Rp 44,509.44

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 16,850.58 + Rp 44,509.44 = Rp 61,360.02

Pembulatan = Rp 61,360 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 081
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = TANDEM ROLLER 8-10 TONNE


TENAGA = 40 HP
HARGA = Rp 193,600,000.00
UMUR KERJA = 10 Tahun = 15,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.18062 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 193,600,000.00 x 0.18062 = Rp 20,980.82
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 193,600,000.00 = Rp 4,259.20
Jam/Tahun 1,500

Sub Total A = Rp 25,240.02

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 40 x Rp 3,208.92 = Rp 20,537.09


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 40 x Rp 23,264.67 = Rp 5,583.52

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 20,980.82 = ------------------------------------ = Rp 16,784.66

Sub Total B = Rp 42,905.26

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 25,240.02 + Rp 42,905.26 = Rp 68,145.28

Pembulatan = Rp 68,145 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 082
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = SELF VIBRATOR ROLLER 10 TONNE


TENAGA = 35 HP
HARGA = Rp 214,500,000.00
UMUR KERJA = 8 Tahun = 12,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.20483 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 214,500,000.00 x 0.20483 = Rp 26,361.62
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 214,500,000.00 = Rp 4,719.00
Jam/Tahun 1,500

Sub Total A = Rp 31,080.62

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 35 x Rp 3,208.92 = Rp 17,969.95


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 35 x Rp 23,264.67 = Rp 4,885.58

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 26,361.62 = ------------------------------------ = Rp 21,089.30

Sub Total B = Rp 43,944.83

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 31,080.62 + Rp 43,944.83 = Rp 75,025.45

Pembulatan = Rp 75,025 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 083
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = TOWED VIBRATOR ROLLER 4 TONNE


TENAGA = 6 HP
HARGA = Rp 363,000,000.00
UMUR KERJA = 8 Tahun = 12,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.20483 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 363,000,000.00 x 0.20483 = Rp 44,611.97
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 363,000,000.00 = Rp 7,986.00
Jam/Tahun 1,500

Sub Total A = Rp 52,597.97

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 6 x Rp 3,208.92 = Rp 3,080.56


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 6 x Rp 23,264.67 = Rp 837.53

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 44,611.97 = ------------------------------------ = Rp 35,689.58

Sub Total B = Rp 39,607.67

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 52,597.97 + Rp 39,607.67 = Rp 92,205.64

Pembulatan = Rp 92,205 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 084
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = PNEUMATIC TIRE ROLLER 8-12 TONNE


TENAGA = 95 HP
HARGA = Rp 1,325,786,000.00
UMUR KERJA = 10 Tahun = 15,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.18062 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 1,325,786,000.00 x 0.18062 = Rp 143,678.08
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 1,325,786,000.00 = Rp 29,167.29
Jam/Tahun 1,500

Sub Total A = Rp 172,845.37

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 95 x Rp 3,208.92 = Rp 48,775.58


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 95 x Rp 23,264.67 = Rp 13,260.86

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 143,678.08 = ------------------------------------ = Rp 114,942.46

Sub Total B = Rp 176,978.91

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 172,845.37 + Rp 176,978.91 = Rp 349,824.28

Pembulatan = Rp 349,824 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 087
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = VIBRATOR ROLLER 600 KG


TENAGA = 7 HP
HARGA = Rp 107,800,000.00
UMUR KERJA = 6 Tahun = 7,200 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 4 Jam Kerja
FAKTOR CRF = 0.24668 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 107,800,000.00 x 0.24668 = Rp 19,944.08
Jam/Tahun 1,200

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 107,800,000.00 = Rp 2,964.50
Jam/Tahun 1,200

Sub Total A = Rp 22,908.58

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 7 x Rp 3,208.92 = Rp 3,593.99


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 7 x Rp 23,264.67 = Rp 977.12

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 19,944.08 = ------------------------------------ = Rp 15,955.26

Sub Total B = Rp 20,526.37

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 22,908.58 + Rp 20,526.37 = Rp 43,434.95

Pembulatan = Rp 43,434 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 088
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = PLATE VIBRATOR TAMPER


TENAGA = 4 HP
HARGA = Rp 30,800,000.00
UMUR KERJA = 6 Tahun = 4,500 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 3 Jam Kerja
FAKTOR CRF = 0.24668 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 30,800,000.00 x 0.24668 = Rp 9,117.29
Jam/Tahun 750

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 30,800,000.00 = Rp 1,355.20
Jam/Tahun 750

Sub Total A = Rp 10,472.49

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 4 x Rp 3,208.92 = Rp 2,053.71


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 4 x Rp 23,264.67 = Rp 558.35

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 9,117.29 = ------------------------------------ = Rp 7,293.83

Sub Total B = Rp 9,905.90

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 10,472.49 + Rp 9,905.90 = Rp 20,378.39

Pembulatan = Rp 20,378 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 089
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = CONCRETE VIBRATOR


TENAGA = 4 HP
HARGA = Rp 7,986,000.00
UMUR KERJA = 5 Tahun = 3,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 2 Jam Kerja
FAKTOR CRF = 0.28085 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 7,986,000.00 x 0.28085 = Rp 3,364.30
Jam/Tahun 600

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 7,986,000.00 = Rp 439.23
Jam/Tahun 600

Sub Total A = Rp 3,803.53

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 4 x Rp 3,208.92 = Rp 2,053.71


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 4 x Rp 23,264.67 = Rp 558.35

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 3,364.30 = ------------------------------------ = Rp 2,691.44

Sub Total B = Rp 5,303.50

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 3,803.53 + Rp 5,303.50 = Rp 9,107.03

Pembulatan = Rp 9,107 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 130
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = CHIPSPREADER


TENAGA = HP
HARGA = Rp 9,515,000.00
UMUR KERJA = 6 Tahun = 3,600 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 2 Jam Kerja
FAKTOR CRF = 0.24668 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 9,515,000.00 x 0.24668 = Rp 3,520.74
Jam/Tahun 600

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 9,515,000.00 = Rp 523.33
Jam/Tahun 600

Sub Total A = Rp 4,044.07

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 0 x Rp 3,208.92 = Rp -


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 0 x Rp 23,264.67 = Rp -

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 3,520.74 = ------------------------------------ = Rp 2,816.59

Sub Total B = Rp 2,816.59

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 4,044.07 + Rp 2,816.59 = Rp 6,860.66

Pembulatan = Rp 6,860 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 152
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = SPRAYER, SELFPROPELLED


TENAGA = 38 HP
HARGA = Rp 90,750,000.00
UMUR KERJA = 6 Tahun = 7,200 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 4 Jam Kerja
FAKTOR CRF = 0.24668 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 90,750,000.00 x 0.24668 = Rp 16,789.66
Jam/Tahun 1,200

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 90,750,000.00 = Rp 2,495.63
Jam/Tahun 1,200

Sub Total A = Rp 19,285.28

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 38 x Rp 3,208.92 = Rp 19,510.23


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 38 x Rp 23,264.67 = Rp 5,304.34

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 16,789.66 = ------------------------------------ = Rp 13,431.73

Sub Total B = Rp 38,246.30

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 19,285.28 + Rp 38,246.30 = Rp 57,531.59

Pembulatan = Rp 57,531 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 154
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = ASPHALT SPRAYER TOWED 200 LITRE


TENAGA = 7 HP
HARGA = Rp 27,500,000.00
UMUR KERJA = 6 Tahun = 4,500 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 3 Jam Kerja
FAKTOR CRF = 0.24668 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 27,500,000.00 x 0.24668 = Rp 8,140.44
Jam/Tahun 750

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 27,500,000.00 = Rp 1,210.00
Jam/Tahun 750

Sub Total A = Rp 9,350.44

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 7 x Rp 3,208.92 = Rp 3,593.99


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 7 x Rp 23,264.67 = Rp 977.12

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 8,140.44 = ------------------------------------ = Rp 6,512.35

Sub Total B = Rp 11,083.46

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 9,350.44 + Rp 11,083.46 = Rp 20,433.90

Pembulatan = Rp 20,433 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 155
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = ASPHALT MIXING PLANT 50 TONNE/HOUR


TENAGA = 125 HP
HARGA = Rp 2,200,000,000.00
UMUR KERJA = 10 Tahun = 12,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 4 Jam Kerja
FAKTOR CRF = 0.18062 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 2,200,000,000.00 x 0.18062 = Rp 298,023.00
Jam/Tahun 1,200

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 2,200,000,000.00 = Rp 60,500.00
Jam/Tahun 1,200

Sub Total A = Rp 358,523.00

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 125 x Rp 3,208.92 = Rp 64,178.40


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 125 x Rp 23,264.67 = Rp 17,448.50

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 298,023.00 = ------------------------------------ = Rp 238,418.40

Sub Total B = Rp 320,045.30

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 358,523.00 + Rp 320,045.30 = Rp 678,568.30

Pembulatan = Rp 678,568 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 156
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = ASPHALT MIXING PLANT 10 TONNE/HOUR


TENAGA = 50 HP
HARGA = Rp 1,650,000,000.00
UMUR KERJA = 10 Tahun = 12,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 4 Jam Kerja
FAKTOR CRF = 0.18062 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 1,650,000,000.00 x 0.18062 = Rp 223,517.25
Jam/Tahun 1,200

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 1,650,000,000.00 = Rp 45,375.00
Jam/Tahun 1,200

Sub Total A = Rp 268,892.25

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 50 x Rp 3,208.92 = Rp 25,671.36


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 50 x Rp 23,264.67 = Rp 6,979.40

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 223,517.25 = ------------------------------------ = Rp 178,813.80

Sub Total B = Rp 211,464.56

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 268,892.25 + Rp 211,464.56 = Rp 480,356.81

Pembulatan = Rp 480,356 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 157
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = ASPHALT FINISHER 6 TONNE


TENAGA = 30 HP
HARGA = Rp 1,610,620,000.00
UMUR KERJA = 7 Tahun = 8,400 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 4 Jam Kerja
FAKTOR CRF = 0.22260 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 1,610,620,000.00 x 0.2226 = Rp 268,893.01
Jam/Tahun 1,200

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 1,610,620,000.00 = Rp 44,292.05
Jam/Tahun 1,200

Sub Total A = Rp 313,185.06

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 30 x Rp 3,208.92 = Rp 15,402.82


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 30 x Rp 23,264.67 = Rp 4,187.64

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 268,893.01 = ------------------------------------ = Rp 215,114.41

Sub Total B = Rp 234,704.86

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 313,185.06 + Rp 234,704.86 = Rp 547,889.92

Pembulatan = Rp 547,889 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 172
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = FUEL TANK TRUCK


TENAGA = 115 HP
HARGA = Rp -
UMUR KERJA = 6 Tahun = 7,200 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 4 Jam Kerja
FAKTOR CRF = 0.24668 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp - x 0.24668 = Rp -
Jam/Tahun 1,200

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp - = Rp -
Jam/Tahun 1,200

Sub Total A = Rp -

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 115 x Rp 3,208.92 = Rp 59,044.13


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 115 x Rp 23,264.67 = Rp 16,052.62

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp - = ------------------------------------ = Rp -

Sub Total B = Rp 75,096.75

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp - + Rp 75,096.75 = Rp 75,096.75

Pembulatan = Rp 75,096 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 182
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = WATER TANK TRUCK


TENAGA = 115 HP
HARGA = Rp 187,726,000.00
UMUR KERJA = 6 Tahun = 9,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.24668 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 187,726,000.00 x 0.24668 = Rp 27,784.95
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 187,726,000.00 = Rp 4,129.97
Jam/Tahun 1,500

Sub Total A = Rp 31,914.92

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 115 x Rp 3,208.92 = Rp 59,044.13


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 115 x Rp 23,264.67 = Rp 16,052.62

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 27,784.95 = ------------------------------------ = Rp 22,227.96

Sub Total B = Rp 97,324.71

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 31,914.92 + Rp 97,324.71 = Rp 129,239.63

Pembulatan = Rp 129,239 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 191
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = TRAILER TOWED


TENAGA = HP
HARGA = Rp 30,800,000.00
UMUR KERJA = 12 Tahun = 9,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 3 Jam Kerja
FAKTOR CRF = 0.16519 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 30,800,000.00 x 0.16519 = Rp 6,105.42
Jam/Tahun 750

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 30,800,000.00 = Rp 1,355.20
Jam/Tahun 750

Sub Total A = Rp 7,460.62

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 0 x Rp 3,208.92 = Rp -


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 0 x Rp 23,264.67 = Rp -

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 6,105.42 = ------------------------------------ = Rp 4,884.34

Sub Total B = Rp 4,884.34

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 7,460.62 + Rp 4,884.34 = Rp 12,344.96

Pembulatan = Rp 12,344 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 211
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = DUMP TRUCK 3,5 TONNE


TENAGA = 106 HP
HARGA = Rp 272,250,000.00
UMUR KERJA = 6 Tahun = 9,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.24668 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 272,250,000.00 x 0.24668 = Rp 40,295.18
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 272,250,000.00 = Rp 5,989.50
Jam/Tahun 1,500

Sub Total A = Rp 46,284.68

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 106 x Rp 3,208.92 = Rp 54,423.28


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 106 x Rp 23,264.67 = Rp 14,796.33

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 40,295.18 = ------------------------------------ = Rp 32,236.14

Sub Total B = Rp 101,455.76

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 46,284.68 + Rp 101,455.76 = Rp 147,740.43

Pembulatan = Rp 147,740 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 212
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = DUMP TRUCK 5 TONNE


TENAGA = 145 HP
HARGA = Rp 379,500,000.00
UMUR KERJA = 6 Tahun = 9,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.24668 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 379,500,000.00 x 0.24668 = Rp 56,169.04
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 379,500,000.00 = Rp 8,349.00
Jam/Tahun 1,500

Sub Total A = Rp 64,518.04

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 145 x Rp 3,208.92 = Rp 74,446.94


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 145 x Rp 23,264.67 = Rp 20,240.26

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 56,169.04 = ------------------------------------ = Rp 44,935.23

Sub Total B = Rp 139,622.44

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 64,518.04 + Rp 139,622.44 = Rp 204,140.47

Pembulatan = Rp 204,140 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 221
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = FLAT BED TRUCK 4 TONNE


TENAGA = 80 HP
HARGA = Rp 330,000,000.00
UMUR KERJA = 6 Tahun = 9,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.24668 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 330,000,000.00 x 0.24668 = Rp 48,842.64
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 330,000,000.00 = Rp 7,260.00
Jam/Tahun 1,500

Sub Total A = Rp 56,102.64

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 80 x Rp 3,208.92 = Rp 41,074.18


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 80 x Rp 23,264.67 = Rp 11,167.04

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 48,842.64 = ------------------------------------ = Rp 39,074.11

Sub Total B = Rp 91,315.33

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 56,102.64 + Rp 91,315.33 = Rp 147,417.97

Pembulatan = Rp 147,417 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 251
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = CONCRETE MIXER 0,125 m³


TENAGA = 6 HP
HARGA = Rp -
UMUR KERJA = 4 Tahun = 6,000 Jam
1 Tahun = 1,500 Jam Kerja
atau 1 Hari = 6 Jam Kerja
FAKTOR CRF = 0.33271 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp - x 0.33271 = Rp -
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp - = Rp -
Jam/Tahun 1,500

Sub Total A = Rp -

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 6 x Rp 3,208.92 = Rp 3,080.56


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 6 x Rp 23,264.67 = Rp 837.53

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp - = ------------------------------------ = Rp -

Sub Total B = Rp 3,918.09

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp - + Rp 3,918.09 = Rp 3,918.09

Pembulatan = Rp 3,918 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 252
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = CONCRETE MIXER 0,25 m³


TENAGA = 10 HP
HARGA = Rp 55,000,000.00
UMUR KERJA = 5 Tahun = 7,500 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.28085 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 55,000,000.00 x 0.28085 = Rp 9,268.05
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 55,000,000.00 = Rp 1,210.00
Jam/Tahun 1,500

Sub Total A = Rp 10,478.05

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 10 x Rp 3,208.92 = Rp 5,134.27


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 10 x Rp 23,264.67 = Rp 1,395.88

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 9,268.05 = ------------------------------------ = Rp 7,414.44

Sub Total B = Rp 13,944.59

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 10,478.05 + Rp 13,944.59 = Rp 24,422.64

Pembulatan = Rp 24,422 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 253
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = CONCRETE MIXER 0,5 m³


TENAGA = 20 HP
HARGA = Rp -
UMUR KERJA = 5 Tahun = 7,500 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 5 Jam Kerja
FAKTOR CRF = 0.28085 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp - x 0.28085 = Rp -
Jam/Tahun 1,500

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp - = Rp -
Jam/Tahun 1,500

Sub Total A = Rp -

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 20 x Rp 3,208.92 = Rp 10,268.54


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 20 x Rp 23,264.67 = Rp 2,791.76

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp - = ------------------------------------ = Rp -

Sub Total B = Rp 13,060.30

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp - + Rp 13,060.30 = Rp 13,060.30

Pembulatan = Rp 13,060 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 301
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = AIR COMPRESSOR 125 CFM


TENAGA = 20 HP
HARGA = Rp 90,750,000.00
UMUR KERJA = 8 Tahun = 6,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 3 Jam Kerja
FAKTOR CRF = 0.20483 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 90,750,000.00 x 0.20483 = Rp 22,305.99
Jam/Tahun 750

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 90,750,000.00 = Rp 3,993.00
Jam/Tahun 750

Sub Total A = Rp 26,298.99

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 20 x Rp 3,208.92 = Rp 10,268.54


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 20 x Rp 23,264.67 = Rp 2,791.76

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 22,305.99 = ------------------------------------ = Rp 17,844.79

Sub Total B = Rp 30,905.09

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 26,298.99 + Rp 30,905.09 = Rp 57,204.08

Pembulatan = Rp 57,204 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 311
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = GENERATOR 3-5 KVA


TENAGA = 10 HP
HARGA = Rp -
UMUR KERJA = 8 Tahun = 4,800 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 2 Jam Kerja
FAKTOR CRF = 0.20483 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp - x 0.20483 = Rp -
Jam/Tahun 600

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp - = Rp -
Jam/Tahun 600

Sub Total A = Rp -

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 10 x Rp 3,208.92 = Rp 5,134.27


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 10 x Rp 23,264.67 = Rp 1,395.88

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp - = ------------------------------------ = Rp -

Sub Total B = Rp 6,530.15

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp - + Rp 6,530.15 = Rp 6,530.15

Pembulatan = Rp 6,530 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 341
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = WATER PUMP ø5cm


TENAGA = 8 HP
HARGA = Rp 7,700,000.00
UMUR KERJA = 4 Tahun = 3,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 3 Jam Kerja
FAKTOR CRF = 0.33271 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 7,700,000.00 x 0.33271 = Rp 3,074.24
Jam/Tahun 750

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 7,700,000.00 = Rp 338.80
Jam/Tahun 750

Sub Total A = Rp 3,413.04

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 8 x Rp 3,208.92 = Rp 4,107.42


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 8 x Rp 23,264.67 = Rp 1,116.70

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 3,074.24 = ------------------------------------ = Rp 2,459.39

Sub Total B = Rp 7,683.51

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 3,413.04 + Rp 7,683.51 = Rp 11,096.55

Pembulatan = Rp 11,096 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 342
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = WATER PUMP ø10cm


TENAGA = 10 HP
HARGA = Rp 9,350,000.00
UMUR KERJA = 4 Tahun = 3,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 3 Jam Kerja
FAKTOR CRF = 0.33271 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 9,350,000.00 x 0.33271 = Rp 3,733.01
Jam/Tahun 750

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 9,350,000.00 = Rp 411.40
Jam/Tahun 750

Sub Total A = Rp 4,144.41

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 10 x Rp 3,208.92 = Rp 5,134.27


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 10 x Rp 23,264.67 = Rp 1,395.88

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 3,733.01 = ------------------------------------ = Rp 2,986.40

Sub Total B = Rp 9,516.56

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 4,144.41 + Rp 9,516.56 = Rp 13,660.96

Pembulatan = Rp 13,660 per Jam


DIREKTORAT JENDERAL BINA MARGA
KODE
DIREKTORAT BINA PROGRAM JALAN
ANALISA BIAYA PERALATAN
SUB.DIT.PERENCANAAN

JALAN LOKAL DAN KABUPATEN


E 401
PROPINSI KALIMANTAN TENGAH KABUPATEN BARITO UTARA DINAS PEKERJAAN UMUM #REF!

JENIS ALAT = TRACTOR EQUIPMENT


TENAGA = HP
HARGA = Rp 90,750,000.00
UMUR KERJA = 5 Tahun = 3,000 Jam
1 Tahun = 300 Hari Kerja
atau 1 Hari = 2 Jam Kerja
FAKTOR CRF = 0.28085 pada 12,50%

A. BIAYA PEMILIKAN (OWNER COSTS)


1. Depresiasi ;
90% x Harga Alat x CRF x 1 = 90% x Rp 90,750,000.00 x 0.28085 = Rp 38,230.71
Jam/Tahun 600

2. Lain-lain ;
Asuransi 3% per Tahun + PPN 10% x Harga Alat = 3.30% x Rp 90,750,000.00 = Rp 4,991.25
Jam/Tahun 600

Sub Total A = Rp 43,221.96

B. BIAYA OPERASI (OPERATION COSTS)


1. Kebutuhan Bahan Bakar dan Pelumas tiap HP
Koefisien Bahan Bakar dan Pelumas
- Solar (Diesel) = 0.160
- Bensin = 0.170
- Pelumas = 0.006

Harga Bahan Bakar dan Pelumas


- Solar (Diesel) = Rp 3,208.92 Liter / HP / Jam
- Bensin = Rp 3,208.92 Liter / HP / Jam
- Pelumas = Rp 23,264.67 Liter / HP / Jam

- Solar (Diesel) = 0.160 x 0 x Rp 3,208.92 = Rp -


- Bensin = 0.170 x 0 x Rp 3,208.92 = Rp -
- Pelumas = 0.006 x 0 x Rp 23,264.67 = Rp -

2. Perbaikan & Spareparts


80% x Depresiasi = 80% x Rp 38,230.71 = ------------------------------------ = Rp 30,584.57

Sub Total B = Rp 30,584.57

Total Biaya Pemilikan & Biaya Operasi Alat = A + B = Rp 43,221.96 + Rp 30,584.57 = Rp 73,806.52

Pembulatan = Rp 73,806 per Jam