1. A reduction in truck movements to/from the port that may prolong the time until road
capacity is reached and reduce the number of containers that are caught up in road
congestion.
2. To reduce import container dwell periods, as import containers can be transferred
directly to an on-dock rail facility from the quayside. This avoids them having to be
stacked in the main yard. In this scenario, additional yard equipment may be required to
ensure yard equipment can match STSC productivity.
This section focusses on the benefits a rail facility provides to yard capacity through reduction in
dwell period.
Figure 32 illustrates how the MIRT transfer options benefit container dwell periods and container
transits through the terminal.
2 3
5.
Figure 32 – Yard – MIRT container transfer options
The capacity enhancement analysis has considered the following rail terminal throughput
scenarios.
Four scenarios are adopted to align with an envisaged development in rail network capacity up
to a future maximum of 1.6 M TEU. The capacity steps align with the initial network capacity
findings outlined in Section 8.6. The rail throughput scenarios include:
a. 400,000 TEU
b. 800,000 TEU
GHD | Report for GHD - Victoria Second Container Terminal Port Advice , 31/34508/ | 89
c. 1,200,000 TEU
d. 1,600,000 TEU
Table 44 shows the estimated dwell time reductions that would result from use of an on-dock
rail terminal for the four rail throughput volume scenarios.
The results suggest dwell time reductions of around 0.5 days could be achieved with the use of
the envisaged capacity MIS shuttles (800,000 TEU), and up to 1 day, if the network capacity
was increased to 1.6 m TEU.
Table 44 Effective dwell time reductions for each of the on-dock rail volume
throughput scenarios at Swanson Dock
Rail terminal SDW – Avg SDW - Dwell SDE – Avg dwell SDE - Dwell
TEU volume dwell (days) reduction (days) (days) reduction (days)
As is 2.9 - 2.9 -
Table 45 shows the capacity enhancement that is estimated for ‘0.5 day’ and ‘1.0 dwell ‘time
reduction scenarios against the previous yard capacity enhancement scenarios.
As a reminder, the following five yard capacity enhancement scenarios considered are:
a. The implications of the basin widening considered in the berth capacity scenarios.
b. The expansion of the current yard system (straddle carriers) to the full leased area.
c. The use of a Rubber Tyred Gantry (RTG) based system on the existing yard areas of
both SDE and SDW. RTG systems can offer storage density increases over straddle
systems of in excess of 20%.
d. The use of existing yard areas for an RTG based system on SDW and an ASC based
system on SDE. An ASC system has marginal storage density improvements over RTG
systems with the added benefit of automation.
90 | GHD | Report for GHD - Victoria Second Container Terminal Port Advice , 31/34508/