Professional Documents
Culture Documents
Project Delivery
Systems:
How They Impact Efficiency and Profitability
in the Buildings Sector
Contributing Partner:
■ Design and Construction Intelligence
SmartMarket Report
T
he need to improve efficiency, These findings and others across the 11
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR
Harvey M. Bernstein, the Civil Engineering Research from Loyola College, an M.S. starting this position in 2008,
F.ASCE, LEED AP, has been a Foundation. He has written in engineering from Princeton she worked for nearly 20 years
leader in the engineering and hundreds of papers covering University and a B.S. in civil with MHC’s Dodge division,
construction industry for over innovation and sustainability and engineering from the New Jersey where she gained insight into
30 years. Currently, he has lead currently serves as a member of Institute of Technology. the construction news industry.
responsibilities for MHC’s market the Princeton University Civil From 2005–2008, she served as
research group, including MHC’s and Environmental Engineering Donna Laquidara-Carr, Ph.D., Editorial Training and Policy
thought leadership initiatives in Advisory Council and the LEED AP, currently provides Manager, responsible for
areas such as commercial and National Building Museum Board editorial direction, analysis and educating over 250 reporters
residential green building, BIM, of Trustees. He is a visiting content to MHC’s SmartMarket on key trends in the industry.
information mobility, innovation professor with the University of Reports, examining critical Laquidara-Carr has a Ph.D. from
and global construction markets. Reading’s School of Construction construction industry trends Tulane University, an M.A. from
Prior to joining MHC, Bernstein Management and Engineering in including BIM, risk management Boston University and a B.A.
served as President and CEO of England. Bernstein has an M.B.A. and green building. Prior to from Middlebury College.
TABLE OF
CONTENTS
4 Executive Summary
4 Executive Summary
6 Player Perspectives: Delivery System Benefits, Drivers and Obstacles, According to Owners, Architects
and Contractors
10 Data
10 Introduction
Case Studies
38 Slimming the Project Schedule Using Design-Build Delivery:
Chobani New Greek Yogurt Facility, Twin Falls, Idaho
48 Multidisciplinary Collaboration Yields Unique Results for a Construction Management At Risk Project:
Perot Museum of Nature and Science, Dallas, Texas
56 Team Win: How an Integrated Approach Completed a New Denver Law Building Ahead of Schedule:
Ralph L. Carr Colorado Judicial Center, Denver, Colorado
63 Glossary
64 Methodology
65 Resources
Given these differences, the top findings for benefits, Improved communication between the project team:
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR
drivers and obstacles are discussed by player, with the 59% of architects and 39% of contractors
owner findings discussed on page 6, architect findings on ■ Increased process efficiency: 48% of architects and
A
s the findings of this research demonstrate, systems, is essential to gain the full benefit of employing
owners, architects and contractors experience specific delivery systems in the buildings sector.
the benefits associated with delivery systems To capture all the implications of these findings, the
very differently. In addition, they have following section is divided into three parts: owner,
different perspectives on what will drive growth in the architect and contractor perspectives. Each section looks
use of these systems in the future. at the perception of the benefits of the three established
These different perspectives are critical to understand. delivery systems and the drivers and obstacles that will
Owners set the contractual terms on a project, but the influence their use in the buildings sector over the next
ways in which architects and contractors participate in three years. In addition, among those familiar with IPD
specific delivery systems influences the profitability, or those with experience in IPD, specific perceptions on
efficiency and even the quality of the projects with benefits, drivers and obstacles are also summarized.
which they are involved. Therefore, understanding the Familiarity with DBO/M was too low for it to be included
perspective of the owners, who are the decision-makers, in this summary.
and the architects and contractors, who work in these
Design-Build: Maximizing the budget is the top driver, CM-at-Risk: The highest percentage of owners (43%)
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR
■ ■
followed by concerns about risk and liability and agree that lack of familiarity with CM-at-risk, too
reducing project schedule. few checks and balances and additional costs due to
■ CM-at-Risk: Improving project quality is the top driver, project length are all influential obstacles to further use
followed by maximizing the budget and reducing of this project delivery system.
project cost.
INTEGRATED PROJECT DELIVERY BENEFITS
Companies in the buildings sector need to take note AND DRIVERS
that reliability and achieving budget are more important While more than three-quarters of the owners included
drivers for owners than cost or schedule reductions. The in the survey have not used IPD, those who have used
strong cost performance of all three delivery systems IPD see a variety of benefits. 80% or more of the
may help explain why the shift from design-bid-build to owners who have used IPD have experienced the
other delivery systems has been gradual. following benefits:
The most influential obstacles that owners say ■ Increased Process Efficiency (88%)
prevents use of delivery systems focus on three issues: ■ Reduced Risk of Litigation (84%)
costs, familiarity with the systems and concerns about ■ Improved Construction Quality (80%)
■ Design-Bid-Build: Highest concern is about the issue ■ Reduced Construction Costs (80%)
DRIVERS AND OBSTACLES OF ESTABLISHED Top Drivers for Increased Use of Delivery
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR
Lack of owner familiarity is the most common obstacle ■ Increased Process Efficiency: 32%
reported about the three delivery systems by contractors, ■ Improved Productivity: 32%
Best Delivery System for Achieving Benefits Top Drivers for Increased Use of Delivery
(According to Contractors) Systems
Source: McGraw Hill Construction, 2014 (According to Contractors)
Best Delivery System According to 30% or More Source: McGraw Hill Construction, 2014
4_10_Benefits_Contrs_#01
I
n the last few years, McGraw Hill Construction has
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
researched several trends that focus on improving Note About the Data
efficiency, productivity and profitability in the The data in this report are based on two
construction industry. SmartMarket Reports have surveys conducted from March to May 2014.
included investigations on topics like prefabrication and ■ An online survey of 125 architects and
modularization, increasing information mobility, the 115 contractors
emergence of Lean construction approaches and a series ■ A telephone survey of 100 owners
effective by a broad swath of the industry, especially industry. Because all findings on the benefits
architects. However, when it comes to achieving specific of delivery systems are reported only by those
benefits, like a reduced schedule and costs, improved that have worked with those delivery systems
productivity and improved client satisfaction, each delivery in both studies, no DBO/M benefits can be
system is perceived differently by the individual players. reported, even as trending data, for owners.
Understanding these unique perspectives is critical to help
players take advantage of the benefits of specific delivery For a more complete description of the study,
systems and reveals the need for more industry consensus see the full methodology on page 64.
about the best ways to employ these systems in the future.
Most contractors and architects in the buildings sector Familiarity With Project Delivery Systems
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
are familiar with the established forms of project (According to Architects and Contractors)
delivery: design-bid-build, design-build and construction Source: McGraw Hill Construction, 2014
Design-bid-build is by far the delivery system that With Project Delivery Systems
architects and contractors participated in most frequently (According to Architects and Contractors)
in the past three years. 60% of architects report doing Source: McGraw Hill Construction, 2014
DBO/M projects.
2_5_USE_Use_B1b_#02
Professional Services:
Becoming More Critical in a Hyper-Competitive Marketplace
R
ecent years have Why Are Professional sees PM becoming an important
witnessed an increase in Services Gaining factor for such large projects. He
the popularity and visibility Popularity Now? points to Hill’s many PM projects for
of professional-services Most owners, even the most airports in Phoenix, Los Angeles,
firms. Program management knowledgeable ones, have neither San Francisco and Salt Lake City,
(PM) companies typically provide the staff nor the expertise to manage and, most notably, for the Muscat
support for multiple related effectively every phase of the International and Salalah airports
projects, often where specialized project. Many of these owners have in Oman.
expertise is essential. Construction limited hands-on experience with Even firms that have completed
management for-fee firms (also the intricacies of the procurement large projects in the past may
known as CM-for-fee, agency process, in evaluating change orders confront new quality-control
construction management, or dealing with permitting issues. standards. It is difficult for any single
construction management for hire, This may be particularly true for individual or team to have all the
agency CM or CM agency) usually some public-works departments requisite knowledge, experience
provide expertise on a particular when technical expertise is spread and skills to capably design and
project, augmenting the project staff. too thinly within the bureaucracy. monitor project execution. Moreover,
According to Engineering News With regard to use of a CM, Bruce as Rich Diggs, president of Heery
Record (ENR), revenue for the top D’Agostino, president and CEO of International, points out, “There is an
100 CM-for-fee and PM firms rose to CMAA, notes that the use is typically enormous amount of waste in what
$19.41 billion in 2013, an increase of a reflection of the complexity of the we do, perhaps as much as 20 to 30
1% from the previous year. project and the sophistication of percent. Having a CM or PM on board
The CM or PM often serves as the owner. “The biggest advantage can go a long way to eliminating
an extension of the owner’s staff [of CM-for-fee] is having someone much of this waste.”
and acts in the owner’s interest to look out for the interests of the
throughout every phase of the project, the needs of the owner. The Does Use of a
project. They typically do not only downside to this is if the CM Professional-Services
contract directly with subcontractors is brought into the project too late. Firm Align With a
but offer advice and staff to the Ideally, the CM should be involved Particular Project
owner. In most cases, these from the very beginning.” Delivery Strategy?
services may go well beyond basic Many owners who use One frequently asked question is
construction tasks and include many professional services, such as whether use of professional-services
preconstruction services, such as CM-for-fee or PM, choose to firms is especially amenable to one
feasibility studies, constructability supplement their staff because of the type of project delivery strategy
reviews, estimating, lifecycle costing, enormous complexity of the project. over another. Charles Kluenker, vice
value engineering, safety, scheduling Such projects may be large enough president of Vanir Construction
and sustainability analysis. These financially to create significant risks Management, says that the key to
services can be provided regardless for the owner if not conceived and being a successful CM-for-fee or PM
of what type of project delivery executed properly. David Richter, is being able to offer a “very flexible
system is used. president of Hill International, as menu of services.” The CM or PM
quoted in a 2014 feature story in ENR, works directly with the owner to plan
and manage the project, regardless Does Using a $1.6 billion. One of the key elements
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR
The decision to be involved in projects using one Experience With Delivery Systems For
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
particular delivery system over another may reflect past Commercial Projects
experience with that delivery system, as well as specific (According to Architects and Contractors)
project concerns for quality, speed of construction, Source: McGraw Hill Construction, 2014
K–12 Schools: Close to half of all architects and Experience With Delivery Systems for
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
■
projects were much less common than those using Architects Contractors
CM-at-risk, with only 25% of contractors and just 13% of Public Buildings
architects reporting involvement in this delivery system Design-Bid-Build
for schools. While design-build is often considered a 86%
62%
delivery system that can accelerate project schedule, this
advantage may have been less salient during the past few Design-Build
18%
years of economic downturn, with limited funds available 31%
for public-school construction. CM-at-Risk
■ College/University Projects: While CM-at-risk is the 44%
44%
second most frequently used delivery system for
college/university projects, the gap between CM-at-risk K–12 Schools
and design-build is narrower as compared with other Design-Bid-Build
institutional projects. The relatively high level of design- 86%
build participation (39% of contractors, 29% of architects) 59%
may reflect the recent increased emphasis on community- Design-Build
13%
college growth and the need for rapid project completion. 25%
■ Healthcare Projects: While design-bid-build is the
CM-at-Risk
most frequently used delivery system for healthcare 45%
projects, the gap between it and other established 44%
project delivery strategies is narrower than with other
College/University
institutional projects.
Design-Bid-Build
• Approximately one-third of both architects and contractors 80%
engaged in design-build projects, while over half of 51%
contractors (53%) and over a third of architects (36%) Design-Build
were involved in CM-at-risk projects. 29%
39%
• IPD was used more often for healthcare projects than
CM-at-Risk
for any other project type, although still far less than 39%
by the three established approaches. IPD is cited by 64%
7% of contractors and 5% of architects.
Healthcare
The robust use of a variety of project delivery systems Design-Bid-Build
reflects the explosion of healthcare construction in recent 66%
49%
years as the “boomer” population matures. Owners need
Design-Build
to get the work completed quickly and with high quality, so 32%
more delivery options are on the table. 36%
CM-at-Risk
Variation by Firm Size 36%
53%
■ Architects from large firms doing office, retail and
Integrated Project Delivery
college/university projects were significantly more likely
5%
than architects from smaller firms to be involved in a 7%
CM-at-risk project.
■ Contractors in large firms doing office and public building
projects were significantly more likely to participate in These trends may be a result of large firms dealing with a
CM-at-risk or design-build projects than their colleagues broader range of projects, unlike smaller firms that may
2_12_USE_Institutional_B2_#03
in smaller firms. specialize in one or two project delivery systems.
Most owners, architects and contractors anticipate Expected Change in Use of Established
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
increases in the buildings sector’s use of design-build Delivery Systems in the Buildings Sector
and CM-at-risk delivery systems over the next three by 2017 (According to Owners, Architects and
years. Architects and contractors were asked to gauge Contractors)
the growth in the use of delivery systems by sector, while Source: McGraw Hill Construction, 2014
Predictions about the future use of particular project Delivery Systems Expected to Increase in
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
delivery systems across the buildings sector as a whole are Use With Commercial Projects
often a reflection of respondents’ specific experiences with (According to Architects and Contractors)
those delivery systems.They may have had substantial Source: McGraw Hill Construction, 2014
experience with a given project delivery system or feel that Architects Contractors
certain delivery systems lend themselves better to specific Increase Decrease Increase Decrease
types of projects.Top findings include:
■ There is no consensus across all building types. Office
■ Frequently, architects and contractors predict that the Design-Bid-Build 17% 17% 7% 20%
delivery systems will remain essentially the same.
■ Where there are changes, respondents anticipate Design-Build 42% 8% 41% 4%
decline in the use of design-bid-build and increases in
CM-at-Risk 20% 5% 27% 15%
the use of design-build and CM-at-risk.
Retail
Commercial Projects: Office and Retail Design-Bid-Build 15% 15% 13% 13%
For both office and retail projects, more respondents
anticipate an increase in design-build project delivery Design-Build 43% 11% 36% 8%
than any other established project delivery system. Both
architects and contractors feel that CM-at-risk use will CM-at-Risk 18% 9% 26% 4%
also increase, though fewer respondents expect this to be
true compared with those that expected increases in the Public Buildings
use of design-build. Design-Bid-Build 6% 18% 18% 27%
One possible reason for why both architects and
contractors expect higher involvement in design-build Design-Build 42% 15% 53% 5%
projects over CM-at-risk projects is the nature of these
two commercial building types. Both office and retail CM-at-Risk 69% 0% 48% 0%
projects are not subject to any public statutes that may
prevent or limit the use of design-build. Accordingly, K–12 Schools
both contractors and architects probably have had more Design-Bid-Build 6% 11% 9% 18%
opportunities to gain experience with design-build in
these two sectors. Design-Build 26% 11% 63% 5%
A strong majority of architects (62%) and contractors (59%) A large majority of contractors expect increases in
expect to see greater use of CM-at-risk project delivery for the use of design-build (71%) and CM-at-risk (68%) for
K–12 projects.This preference for CM-at-risk appears to healthcare projects. But only 38% of architects expect
mirror that for public building projects. Satisfaction with the increases for CM-at-risk, with a quarter anticipating
two separate contract structures of both design-bid-build increases for design-build.
and CM-at-risk options may drive this expectation. One possible explanation for the difference in opinion
Predictions about the use of design-build are split. is that, compared with all other building types, the gap
A majority of contractors (63%) anticipate greater use between use of design-bid-build and the use of other
of design-build, but only a quarter (26%) of architects established and emerging delivery systems in healthcare
believe that will occur. The reason for this split among projects has been the narrowest in recent years (see page
K–12 practitioners is not clear, beyond possibly the 16). Because of the need to complete a large amount of
generally greater comfort level that contractors have with healthcare building construction quickly and efficiently,
design-build. owners have worked with different delivery systems
Most architects (78%) believe that design-bid-build use more than for any other building type.
will remain the same, but just 55% of contractors expect
that to happen. Nearly a fifth of contractors (18%) expect Variation by Firm Size
design-bid-build use to decline for these projects. Architects working in large firms were significantly more
likely than their colleagues in smaller firms to predict
College/University Projects decreases in the use of design-bid-build and increases
Over half (53%) of architects and 25% of contractors in DBO/M. Contractors in large firms were more likely to
anticipate the use of design-bid-build will decrease for anticipate increases in the use of IPD and DBO/M. This
these projects. There is consensus among contractors likely reflects the fact that larger firms have more
that owners’ use of both design-build (81%) and CM-at- experience in using a variety of delivery systems,
risk (76%) will increase. Architects are not as certain, with including emerging ones such as DBO/M and IPD.
a small plurality expecting increase rather than inertia for Smaller firms may have much more limited experience
CM-at-risk, and a comparable plurality expecting design- with such approaches.
build to remain about the same rather than increase.
As discussed earlier (see page 16), a possible driver
for college/university projects is the recent focus on
community-college development and the need for
rapid project completion. Design-bid-build is seen by
many observers as a slower option compared to other
delivery systems.
Project Delivery:
How Infrastructure Differs From Building Delivery
While integrated project delivery (IPD) is rapidly changing how buildings are
designed and constructed, other delivery systems are used for infrastructure
projects both to control costs and ensure that design standards are met.
This data section (pages 22–30) includes a detailed Top Drivers Influencing Adoption of
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
analysis of the triggers, drivers and obstacles for each Established Project Delivery Systems
delivery system. The chart at right shows an overview (According to Owners, Architects and
of the most critical drivers and obstacles for each of the Contractors)
three established project delivery systems, as reported Source: McGraw Hill Construction, 2014
4_1_Drivers_Intro_#03
Architects and contractors that have worked with one of Top Triggers Influencing Selection of the
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
design-bid-build saves money on projects. However, Ranked 1st—Architects Ranked 2nd or 3rd—Architects
only 22% of contractors say that design-bid-build is the 1_4_DRIV_Triggers_DBBFirst_C1_#02
Ranked 1st—Contractors Ranked 2nd or 3rd—Contractors
most effective delivery method for reducing construction Need for Fixed Construction Budget/
cost (see page 35), suggesting that they perceive a gap Guaranteed Maximum Price (GMP) on Project
between the reasons triggering the selection of a delivery 24% 46% 70%
17% 43% 60%
method and the actual results of those projects.
Concerns About Cost
17% 42% 59%
Design-Build 14% 32% 46%
Unlike the owners’ choice of design-bid-build, which is Owner Mandate/Contract
largely motivated by a few key factors, the architects and 39% 15% 54%
29% 5% 34%
contractors surveyed find that the selection of design-
Concerns About Schedule/Phasing
build is triggered by a range of factors. 15% 31% 46%
■ Need for Fixed Construction Budget/GMP: The highest 17% 23% 40%
percentage of architects and contractors rank this among Distribution of Risk/Liability Among Project Team Members
the top three triggers. This general agreement shows 17% 17%
9% 8% 17%
that design-build is widely regarded in the buildings 0%
sector as a way to have a fixed price on a project. Increased Quality
■ Concerns About Cost: The second highest percentage of 17% 17%
6% 23% 29%
architects and contractors rank this among the top three 0%
triggers. This finding demonstrates that both architects Flexibility to Pursue Innovative Approaches
and contractors agree that there is a perception that 9% 9%
design-build has a positive impact on project cost. 3% 37% 40%
0%
Owner Mandate/Contract: In addition to this trigger’s Top Triggers Influcencing Selection of the
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
■
strong performance among the top three, the highest CM-at-Risk Delivery System
percentage of architects and contractors rank this first (According to Architects and Contractors)
among all triggers. This finding is not surprising since Source: McGraw Hill Construction, 2014
the owner ultimately mandates the selection of each Ranked 1st—Architects Ranked 2nd or 3rd—Architects
delivery system. However, the percentage who select Ranked 1st—Contractors Ranked 2nd or 3rd—Contractors
this trigger among the top three is notably lower than Need for Fixed Construction Budget/
the percentage selecting design-bid-build, suggesting Guaranteed Maximum Price (GMP) on Project
18% 46% 64%
that firms using design-build are more cognizant of 21% 46% 67%
factors driving owners to mandate it for their projects. Concerns About Schedule/Phasing
■ Concerns About Schedule/Phasing: There is close 18% 32% 50%
agreement on this trigger between architects 10% 30% 40%
(46%) and contractors (40%). One advantage of Owner Mandate/Contract
29% 17% 46%
design-build according to its proponents is its ability 36% 7% 43%
to reduce coordination issues and positively impact
Increased Quality
project schedules. 7% 25% 32%
■ Flexibility to Pursue Innovative Approaches: A higher 5% 21% 26%
percentage of contractors (40%) select this among Concerns About Cost
7% 25% 32%
the top three triggers compared with architects (14%). 12% 19% 31%
Contractors are typically the lead on design-build
Concerns About Project Complexity
projects, and it is not surprising that they would consider 4% 25% 29%
participation in design-build projects to enhance their 5% 12% 17%
ability to innovate more than architects would. Flexibility to Pursue Innovative Approaches
14% 11% 25%
It is also notable that more contractors than architects 21% 21%
0%
find that design-build projects are selected to enhance
Distribution of Risk/Liability Among Project Team Members
quality, given the fact that the contractor typically has the 4% 10% 14%
lead role on such projects. 10% 19% 29%
Owners were asked to consider the relative impact of Drivers Influencing Increased Use of
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
a variety of factors that will drive the increased use of Delivery Systems
different project delivery systems in the buildings sector (By Percentage of Owners Using Each Delivery
over the next three years, focusing specifically on a System Who Find The Drivers Influential)
delivery system that they have used previously and that Source: McGraw Hill Construction, 2014
Improved Quality
Established Project Delivery Systems 71%
DESIGN-BID-BUILD Reduce Construction Schedule
The need to maximize the project budget (100% of
57%
owners) and to reduce project cost (86%) are seen by
owners as the primary drivers that will increase use of
Design-Build
design-bid-build over the next three years. The prospect
Maximize Budget
of improved quality is the third most highly ranked
89%
driver for using design-bid- build. Controlling costs has
frequently been perceived as a strength of design-bid- Reduce Project Cost
build, although that may have as much to do with the 63%
comfort and experience levels of its users, rather than any
intrinsic advantage of this delivery approach. Concerns about Risk/ Liability
Architects and contractors also rank reducing project 79%
cost as the primary driver increasing the use of design- Improved Quality
bid-build (see chart on page 25), with more than one half
47%
of architects ranking this as the primary driver and just
over a third of contractors doing so. Maximizing the value Reduce Construction Schedule
of work put in place is the second most discussed driver. 68%
It is not surprising that both architects and contractors
point to reducing project cost as the top factor that will CM at-Risk
drive increased use of design-bid-build. The fact that Maximize Budget
this driver resonates more forcefully with architects than 73%
contractors, however, may reflect architects’ general
satisfaction with their role in making design decisions Reduce Project Cost
under design-bid-build. 73%
importance of risk/liability. Design-build advocates often 80% of owners feel that improved quality is the most
claim that the single-responsibility aspect is one of the important driver that will cause increased use of CM-at-
delivery system’s greatest strengths; apparently, many risk. Maximizing the budget and reducing project
owners agree. cost are also important drivers, ranked nearly as high.
Architects and contractors have somewhat different Adherents of CM-at-risk frequently argue that improved
perceptions of the key drivers that will produce increased quality accrues from having contractors participate
use of design-build. in preconstruction decisions while maintaining two
■ Architects: Reducing project cost is key (40%), followed separate design and construction contracts with the
by reducing project schedule. owner. The study findings may support that contention.
■ Contractors rank reducing construction schedule Both architects and contractors identify reducing
as the most important driver (47%), with a smaller construction schedule and maximizing the value of
percentage pointing to reducing project cost. work put in place for the project budget as the main
drivers for CM-at-risk. Combined with the architects’
Dissatisfaction with project scheduling and other time
and contractors’ comments on design-build above, this
constraints under design-bid-build is apparently an issue
finding reaffirms one of the perceived weaknesses of
for many contractors that will encourage broader use of
design-bid-build: inadequate schedule control. Both sets
design-build.
of respondents believe that reducing the construction
schedule is an important driver for increased use of both
design-build and CM-at-risk.
Top Drivers in Increased Use of Established Delivery Systems in the Next Three Years
(According to Architects and Contractors)
Source: McGraw Hill Construction, 2014
Architects Contractors
Design-Bid-Build Design-Build CM-at-Risk
Reduce Project Cost Reduce Project Cost Reduce Construction Schedule
50% 40% 31%
37% 27% 18%
Maximize the Value of Work Reduce Construction Schedule Maximize the Value of Work
Put in Place for the Budget Put in Place for the Budget
30%
25% 27%
47%
26% 27%
Maximize the Value of Work
Reduce Construction Schedule Put in Place for the Budget Reduce Project Cost
17% 10% 19%
16% 20% 9%
For the three established delivery systems, architects Positive Influences on the Use of Specific
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
and contractors that use them agree that construction- Project Delivery Systems
industry firms are the most influential factor (According to Architects and Contractors)
encouraging the use of each delivery system, more so Source: McGraw Hill Construction, 2014
Design-Build
In sharp contrast to design-bid-build, contractors who CM-at-Risk
have used design-build find many other factors beyond Construction Professional Green Policy Legal
Industry Associations Building Profession
industry firms driving its use, far more than architects do. Firms Practices
• More than 40% of contractors find that green building
practices (49%), professional associations (46%) and
Architects 82% 50% 46% 18% 11%
policy (43%) all encourage wider use of design-build.
• There is nearly a 20-point differential between the
responses of architects and contractors about green
building practices (26% of architects), professional Contractors 93% 50% 26% 19% 21%
associations (28%) and policy (26%).
Owners were asked about obstacles in a different manner Obstacles Considered Highly Impactful on
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
from the architects and contractors. Owners were asked Wider Use of Design-Bid-Build
to determine the degree of impact of each obstacle on (According to Owners Using Design-Bid-Build)
preventing wider adoption of specific delivery systems, Source: McGraw Hill Construction, 2014
while architects and contractors were asked to rank their Too Few Checks and Balances
top three obstacles.
29%
1_8_DRIV_DBBObstacles_C4_#02
SmartMarket Report McGraw Hill Construction 28 www.construction.com
Drivers and Obstacles
Obstacles Preventing Wider Adoption of Delivery Systems CONTINUED
obstacle, very high in comparison with most of the Ranked 1st—Architects Ranked 2nd or 3rd—Architects
other obstacles ranked for any of the three established Ranked 1st—Contractors Ranked 2nd or 3rd—Contractors
delivery systems. Clearly contractors consider owners Too Few Checks and Balances
the major stumbling block to wider use of design-build. 20% 37% 57%
11% 15% 26%
1_9_DRIV_DBObstacles_C4_#02
The best way to mitigate risk through a project delivery system is to select
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR
the delivery system that fits the particulars of the project. That means
identifying the project’s sensitivities and identifying which delivery system
allocates risks to the parties that are best able to control for them.
F
rom the owner’s perspective, 50% to 90% complete and may even delivery system that takes risk off an
project delivery systems assume the risk of design errors owner, there will be a contingency to
generally form a spectrum discovered during construction. parties who accept that risk instead—
of risk that correlates The most common difficulty which may or may not be justifiable
with the owner’s level of control, with CM-at-risk centers on the in the context of a given project.
according to a comparison published construction manager’s shift from “What it comes down to is having
by the Construction Management in-house adviser during design to a fundamental understanding of
Association of America. CMR during construction, a shift the pros and cons of each delivery
that risks a deterioration in project method,” says Blake Peck, president
A Spectrum of Risk team relationships. and chief operating officer of MBP,
Design-bid-build, the delivery a firm of construction management
system most commonly used in Collaborate to Mitigate consultants. “And, if you’re going
North America, occupies the risk At the low end of the risk spectrum, to try something new, you’ve got to
spectrum’s mid zone. Offering the enhanced collaboration in train people so they know what their
owners a high degree of control delivery systems such as design- roles and responsibilities are, and
over the design and reliable costing build and integrated project delivery make sure they know if they’ve got
information before construction (IPD) can significantly reduce an that ball or not.”
starts, the system is well understood owner’s risk. “It can be amazing what Ultimately, it is the human factors
in the industry, with the roles of each kind of impact collaboration has on that will determine a project’s
party clearly defined. the bottom line,” says John Manning, success, regardless of delivery
Design-bid-build’s clear distinction principal at Krauss-Manning, a system. “A bad team will overcome
of phases carries certain risks, firm of project management and [the benefits of] any delivery method
however: Developing the design construction consultants. you have. A good team that works
in the absence of reliable costing But that does not make these well together will figure out how to
information can result in a project that systems panaceas, notes Manning. A get [the project] built,” says Peck.
is more expensive than necessary; formal commitment to collaboration “The bottom line is what we’ve
the horizontal timeline of design-bid- is all to the good, but an integrated all known for a long time in this
build can make it a poor choice for a partnership may achieve only limited industry: It’s a people business.” n
schedule-sensitive project; and the success if partnership behaviors
compartmentalization of parties and aren’t rewarded in the project’s
functions can generate an adversarial, contract structure.
rather than collaborative, culture. Design-build’s loss of owner
Construction management at and stakeholder involvement may
risk (CM-at-risk) can increase an pose a risk of its own: for example,
owner’s control of the project reducing the ability of owners to
schedule and/or reduce overall costs determine whether they are getting
by allowing for the potential for a the best value for their money or
fast-track process. The construction compromising building performance
manager at risk (CMR) will often on specialized projects, which
provide a fixed or guaranteed will then face increased operating
maximum price when the design is costs for years to come. And in any
This data section (pages 33–51) includes a detailed Architects view CM-at-risk as the best system to
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
analysis of the benefits that different players associate provide improved communication and construction
with different project delivery systems. As an overview, quality benefits, while contractors emphasize it as a
the chart at right contains the major benefits reported delivery system that offers productivity and reduced
in this section of the report for the established delivery project cost benefits.
systems—design-bid-build, design-build and CM-at- ■ Design-bid-build is seen as reducing project costs—
risk—and provides a summary of the benefits that are with both architects and contractors listing it as the
associated with each system by different players. best delivery system to provide this benefit.
Looking at these data results in aggregate, a few key
findings emerge:
■ While there are some differences, owners report strong
Delivery Systems With the Best Performance for Achieving Project and Process Benefits
(According to Owners, Architects and Contractors)
Source: McGraw Hill Construction, 2014
4_7_Benefits_Intro_#02
Benefits of Delivery Systems
82% of architects and 91% of contractors report using Delivery Systems That Offer the Best Value
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
more than one delivery system in the last three years. for Owners
These respondents were asked, among the delivery (According to Architects and Contractors Who
systems that they have used, which provides the best Have Used These Delivery Systems)
value for the owner. Source: McGraw Hill Construction, 2014
Architects
Design-Bid-Build Contractors
The highest percentage of architects using more than
one delivery system (34%) select design-bid-build as the Design-Bid-Build
delivery system that provides the most value to owners, 34%
which is a far higher percentage than the contractors 14%
using more than one system (14%).
While there is a higher percentage overall of architects Design-Build
in the study that report using this delivery system than 18%
there are contractors—95% of architects versus 87% of 55%
contractors—that differential is not enough to account
CM-at-Risk
for the number of architects who feel it has the highest
31%
value to owners of any delivery system. This finding
corresponds with the architects’ concern about checks 24%
and balances and may even suggest some resistance
to the value of more collaborative engagement by
contractors during design, which may occur with the
other delivery systems.
1_14_BEN_ValueforOwners_B5_#01
and 24% of contractors find this system to have the
VARIATION BY SIZE OF FIRM
greatest value. The collaborative aspects of this
30% of small contractors (those with less than 50
system may be balanced against the risks of a high
employees) report that design-bid-build has the best
contingency being built into the guaranteed maximum
value for building owners, compared with 5% of larger
price (GMP) offered.
firms. There may be larger challenges faced by small
firms seeking to use less common delivery systems. VARIATION BY TYPE OF WORK
43% of architects whose firms largely do public work (more
Design-Build than 40% of their projects) believe that CM-at-risk offers
By far, the highest percentage of contractors using more the greatest value to owners, compared with 23% of those
than one delivery system select design-build as the doing fewer public projects.This finding is in contrast to
delivery system providing the most value to owners, at the fact that fewer firms doing public work are familiar
55% compared with just 18% of architects. with this delivery system (see page 11). It demonstrates the
In this case, a higher percentage of contractors use, value placed on this delivery system by those that have
and therefore were asked about, design-build than actually been involved in a CM-at-risk project.
architects do—90% of contractors, compared with 78%
of architects—but again, the disparity in the value placed Emerging Delivery Systems
on design-build is much larger than this difference in use The emerging delivery systems, IPD and DBO/M, were
could account for. Contractor-led design-build can allow for included in this question, but the findings are minimal
the most direct input by contractors throughout the design given the low number of architects and contractors
process, and a high percentage of contractors using this currently using these systems. However, it may be worth
approach believe the owners benefit as a result. noting that even though only 22% of architects report
using IPD at all, 12% of the architects using more than one
CM-at-Risk delivery system identify it as having the greatest value
Architects and contractors are much closer to agreement for owners.This demonstrates that a high percentage of
on the value of CM-at-risk for owners; 31% of architects architects using this system believe in its value for owners.
Owners were asked about the cost performance of a Budgets (According to Owners)
specific project that uses design-bid-build, design-build Source: McGraw Hill Construction, 2014
or CM-at-risk as its delivery system.
Under Budget On Budget Over Budget
Performance in terms of cost of these projects was
relatively equivalent across all three delivery systems, Design-Bid-Build
with about two-thirds of the projects finishing on budget.
The only notable difference is that a slightly higher 7%
percentage of CM-at-risk projects (33%) finished under 27%
budget, compared to 27% of design-bid-build and 23% of
design-build projects. However, the similarity in overall
performance is more striking than any differences.
In addition, owners who indicated that they had 67%
experience with IPD were asked about this benefit for
their IPD projects in general, and 80% reported that the
use of IPD reduced construction costs.
Design-Build
Architects and Contractors
Unlike owners, architects and contractors were asked to
select the best delivery system for reducing construction 10%
costs out of any they have worked with in the past. 23%
■ While roughly the same percentage of contractors find Best Project Delivery System for Reducing
CM-at-risk (23%) to be the best for lowering construction Construction Costs
costs as do those that select design-bid-build (22%), only (According to Architects and Contractors Who
15% of architects agree. This is a notable contrast to the Have Worked With These Delivery Systems)
percentage of architects versus that of contractors who Source: McGraw Hill Construction, 2014
Construction Schedules:
Impact of the Use of Specific Delivery Systems
Owners were asked about the schedule performance of Schedules (According to Owners)
specific projects that they have conducted using design- Source: McGraw Hill Construction, 2014
of design-build to improve schedules than the efficacy Best Project Delivery System for Reducing
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
of any specific delivery system for most of the other Project Schedules
benefits. Again, though, the type of procurement for the (According to Architects and Contractors Who
design-build project is important. Have Worked With These Delivery Systems)
Among those that report seeing construction Source: McGraw Hill Construction, 2014
20% 27%
33% 30%
33%
36%
S
peed to market is essential new products and packaging that times during the project. The team
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR
CONTINUED
TI
N
CO
st
at
people. Shift work for key trades accommodate those changes.” and Figures
s
was implemented to mitigate Although these owner-driven
Design-Builder
congestion, reducing risks to changes increased the total project
Shambaugh & Son
productivity and safety. budget, the team was able to remain
on schedule. Type of Project
Manufacturing Facility
Dynamic Development To help accommodate changes
Because Chobani continued to and delays, Shambaugh devised a Size
1 million sq. ft.
develop its needs throughout the plan that allowed workers to shift
project, the design and construction their attention from one portion of Foundations
planning processes were very the project to another, as necessary. January 2012
dynamic. Early on, Shambaugh The team started in the utility wing Completed
developed an “owner wants versus prior to working on the process wing November 2012
owner needs” list to segregate of the facility.
cost options proactively. The team The project also included a large Project Highlights
developed a value-engineering warehouse, which Hegger said was
■ Compressed project schedule
list of more that 100 items totaling “simple by comparison” to other from 24 months to 10 months
$50 million, of which not all were aspects of the project. “That was
■ Construction commencement
accepted. During construction available for us to work on when we
while project development and
and near completion of final had to go back to design decisions or design was still underway
design, Chobani revealed a new deal with delays,” he says.
Shambaugh says that although ■ Single point of responsibility
product launch and changes in
filling and packaging that had to be the team had to “keep the pedal to ■ $50 million of cost-savings
incorporated into the design. the metal and never let up,” the team options from value engineering
Hegger says that major changes did not sacrifice safety.The project Two million manhours without
Photos by Bill Nichols
■
included the addition of two new logged more than 2 million manhours a lost-time accident
floors and new air-handling systems. without a lost-time accident.
Most architects and contractors find that the type of Best Project Delivery System for Improving
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
delivery system can impact project costs and schedules Specific Project Outcomes
(see pages 35 and 37), but fewer find that delivery (According to Architects and Contractors Who
systems impact green/sustainable building performance Have Worked With These Delivery Systems)
or construction quality. Source: McGraw Hill Construction, 2014
These findings reflect the role that each player has in the
Improved Construction Quality
early phases of a project in terms of the delivery system
that they value most. Design-Bid-Build
• Architects determine the fundamental approach to 20%
green and the elements that contribute to the quality of 10%
the building in a design-bid-build project.
Design-Build
• Contractors are typically far more engaged and have
greater authority in design-build projects. 12%
• With a CM-at-risk project, the architect still may be 35%
engaged more in early design, but by the construction CM-at-Risk
documents phase, the construction team plays a
21%
greater role than it does in design-bid-build projects.
22%
■ 44% of small contractors (annual project values of less 80% of owners with IPD experience report that IPD
than $50 million) think that no system is better for has improved sustainable building performance and
achieving sustainable building performance, compared construction quality on their projects.
with 21% of large contractors. Some trends emerge from the responses of architects
■ 33% of small contractors think that no system is better and contractors that have done IPD or DBO/M projects.
for improving construction quality, compared with 17% • Nearly half of the architects and over one fifth of the
of large contractors. contractors who have worked on an IPD project find
that it contributes to project sustainability.
While many factors could contribute to the different
• Almost one quarter of the architects and one third of
responses, one possible influence may be the relatively
the contractors who have worked on an IPD project
low number of projects on which to base any comparisons.
also find that it improves quality, findings roughly
Construction projects are each quite individual in terms
comparable with the established delivery systems.
of their benefits and challenges, and a smaller sample of
• Few respondents with experience in DBO/M regard it
projects is less likely to reveal differences.
as the best system for either of these outcomes.
1_23_BEN_Communication_E4a_#01
Benefits of Delivery Systems
Owner Satisfaction:
Impact of the Use of Specific Delivery Systems
Owners were asked about the level of satisfaction that Specific Delivery Systems
they had with a specific project that employed one of the Source: McGraw Hill Construction, 2014
Architects are much more evenly split between the This further supports the conclusion that contractors are
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
■
three established delivery systems, with only a divide more directly impacted by client satisfaction associated
of three percentage points between them. with delivery-system selection than are architects.
■ When asked about the degree to which customer
• Design-Build: 43% of contractors report clients are an IPD project said that IPD is the best delivery system
much more satisfied, compared with 10% of architects. for increasing client satisfaction. However, only a few of
• CM-at-Risk: 44% of contractors report clients are much the contractors that have used IPD believe this.
more satisfied, compared with 19% of architects. ■ Few architects or contractors that have worked on
Improved Productivity:
Impact of the Use of Specific Delivery Systems
As with client satisfaction, architects are far less convinced Best Delivery System for Improving
that the use of any particular delivery system impacts Productivity
productivity than are contractors, with 34% reporting (According to Architects and Contractors Who
that the selection of a delivery system does not influence Have Worked With These Delivery Systems)
productivity, compared with 12% of contractors. Source: McGraw Hill Construction, 2014
Process Efficiency:
Impact of the Use of Specific Delivery Systems
78% of architects and 87% of contractors find that Best Delivery System for Improving
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
Risk of Litigation:
Impact of the Use of Specific Delivery Systems
For the most part, architects and contractors view the Best Delivery System for Reducing the Risk
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
Value management, conducted throughout the lifecycle Best Delivery System for Reducing the Need
of a project, can be an important way to guarantee the for Value Engineering (According to Architects
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
best value for owners, and value engineering is included and Contractors Who Have Worked With These
in this process. However, when value engineering is Delivery Systems)
done solely to reduce costs in late design or during Source: McGraw Hill Construction, 2014
Change Orders:
Impact of the Use of Specific Delivery Systems 1_29a_BEN_ProjectChanges_E5de_#02
The highest percentages of both architects (32%) and Best Delivery System for Fewer Change
contractors (51%) select design-build as the best delivery Orders (According to Architects and Contractors
system to reduce the need for change orders. However, Who Have Worked With These Delivery Systems)
a majority of contractors favor design-build above any Source: McGraw Hill Construction, 2014
W
hen MaineGeneral equipment and a more efficient fan delivery methods on integration
Medical Center system. The team also analyzed the and sustainability outcomes
opened in November building envelope design to identify published last year in the Journal
2013, its integrated a breakpoint in return on investment of Management in Engineering,
project delivery (IPD) team had not from an energy perspective. researchers Sinem Mollaoglu-
only shaved ten months off the Altogether, the owner is expecting Korkmaz, Lipika Swarup and David
construction schedule and returned to save close to a million dollars per Riley establish a link between the
$20 million to the owner in value year from energy savings. level of integration in a project’s
additions and operating efficiencies, The project’s achievements also delivery process and the project’s
but it had also exceeded the project’s extend to social sustainability. The sustainability and overall outcomes.
sustainability target of LEED silver owner placed a high priority on Delivery system per se does not
certification and positioned the maximizing local participation in account for improved sustainability
project to qualify for LEED gold. the project, and the joint-venture outcomes; instead, the approach to
The project’s IPD team members construction management team of the project is what counts: owner
credit the delivery system’s Robins & Morton and HP Cummings commitment, early involvement of the
enhanced collaboration for enabling fostered collaborations and joint constructor, integrative mechanisms
these achievements. “As we worked ventures to meet the project’s (such as charrettes and energy
together as a team, the best ideas requirements from a contractor pool modeling), project chemistry and the
were brought to the table,” says that was initially thought to lack the overall level of team integration.
Stacey Yeragotelis, associate capacity for a job of this size. Over Clearly, though, a delivery system
principal at TRO Jung|Brannen, 97% of subcontractor costs went to in which more of these attributes
architects on the project together Maine subcontractors, with 2,700 are inherent is off to a head start.
with SMRT. “The contractors were jobs created. The study found design-build to be
right there modeling in real time, Significantly, MaineGeneral’s IPD inherently more integrative than
which allowed us to find where contract highlighted sustainability construction management at risk
we could afford more value for the goals from the start and included (CM-at-risk), which in turn proved
owner and add sustainable measures incentives to maintain quality more integrative than design-bid-
to the project.” throughout the project. build. However, they did observe
IPD is not the only way to boost that informal involvement of the
Triple Bottom Line sustainability outcomes through contractor in the early phases of the
Benefits collaboration. Any project delivery design-bid-build process could boost
The project’s energy rating especially system can achieve significant integration up to CM-at-risk levels.
benefited from the collaboration benefits through an explicit Sustainability outcomes generally
among designers, trades and commitment to collaboration. correlated with higher levels of
suppliers. The collaboration is Some systems, however, require integration, as did the probability of
what “really put us over the top” in more effort than others to work exceeding the intended certification
exceeding the project’s LEED target, collaboratively, and that effort may target. Conversely, projects
according to Yeragotelis. Relying on translate into project costs. achieving a high level of integration
real-time information to cut waste scored high on sustainability
from the project, the team found that Collaborative Attributes, outcomes—a pattern that the project
it was able to afford a heat recovery Sustainable Outcomes team on the MaineGeneral Medical
system, an upgrade to rooftop In a study of the influence of project Center would recognize. n
Management-at-Risk Project
Perot Museum of Nature and Science
DALLAS, TEXAS
E
arly contractor involvement
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR
and multidisciplinary
collaboration helped drive
successful delivery of the
highly complex Perot Museum of
Nature and Science, in Dallas, Texas.
Completed in April 2012 under a
construction-manager-at-risk (CM-at-
risk) contract, the $95.6-million
180,000-sq-ft museum’s façade
features more than 700 precast,
custom-molded concrete sections
with ornate details. The façade wraps
a 14-story structure, which includes a
tower, atrium and plinth. The design
called for what the team describes as
“onion-like” layering—constructing
a concrete interior structure
surrounded by large steel framing to The exterior of the musuem (left) consists of 700 unique precast panels.
GPS technology was employed in the modeling of the lobby ceiling (right).
support the exterior precast panels.
The team, led by Balfour
Beatty Construction, Dallas, and co-located, bringing the architect, new technology to most firms.
Morphosis Architects, Culver City, construction manager, owners’ “Morphosis stressed to us from day
Calif., underwent intense budget representative and museum staff one that if we weren’t using the BIM
development, constructability into a shared office environment. model and didn’t share it, the team
and coordination sessions early Wolfe says that the team was better wouldn’t understand what we’re
in the project to help it meet client able to quickly address issues at trying to build,” Wolfe adds.
expectations, says Chris Wolfe, any point in the day, on any subject Balfour Beatty worked off the
senior project manager at Balfour without having to schedule specific Morphosis models to develop its
Beatty. Balfour Beatty was meetings around busy calendars at more detailed construction model.
brought on to the team during off-site locations. As the construction model was
schematic design, while key “Even when we ran into issues, developed, Morphosis would pull it
subcontractors—including the the team wouldn’t point fingers at back into its design model to validate
electrical, mechanical, plumbing, each other,” Wolfe says. “With some that everything lined up correctly.
precast concrete, curtain wall, other procurement methods, like Balfour Beatty managed the
structural glass and ornamental- design-bid-build, there’s always that project’s BIM clash-detection
steel firms—were brought on at adversarial aspect, where [a firm] is process, pulling subcontractor
100% design documents. only looking out for its best interest. superintendents and project
“It was critical for [the core team] [Under design-bid-build], it’s not managers into clash-detection
to be able to work together and come about the good of the entire team, and coordination meetings. Wolfe
up with ideas early in the process,” just what’s good for me.” said that this process—coupled
Wolfe says. “If we had come in after with the early involvement of key
the drawings were designed, we BIM For Collaboration subcontractors—enabled the team
would have had limited opportunities The team also committed to sharing to know ahead of time exactly
to pursue alternate ideas.” building information models what they would be doing so that
Photos by John Davis
To help create a more collaborative (BIM). In the years prior to its 2010 possible clashes with fellow trades
environment, team members groundbreaking, BIM was still a would be addressed.
CONTINUED
TI
N
CO
st
exterior proved to be the most expense of custom molds. Project Facts
at
s
challenging and rewarding aspect Although Gate Precast didn’t use and Figures
of the project. Morphosis initially BIM, Wolfe says that Morphosis Construction Manager
envisioned using a metal panel was able to pull Gate’s information Balfour Beatty Construction
cladding for the exterior, which it has into the model. “Gate could send
Type of Project
used on several previous projects, them 3D CAD files of each shape, Museum
says Arne Emerson, project architect and Morphosis could pull it in and
Size
at Morphosis. However, after working confirm it matches up. Out of all 700 180,000 sq. ft.
through cost modeling, Balfour Beatty of those panels, only one panel was
Construction Start
determined that the design could fabricated wrong.”
November 2009
increase the project budget by up to
75%. As an alternative, Morphosis Collaborative Design Completed
April 2012
also recommended using shotcrete Solutions
and sculpting the façade, another In the theater, the Morphosis design
technique that the firm had previously included curves so complex that Project Highlights
used. However, the team could not geometries changed roughly every ■ Construction manager
find local contractors who were six inches, Emerson says. The team brought on during
comfortable using that technique. worked with subcontractor Baker schematic design
“Once we got to Dallas, we realized Triangle to devised a way to “slice ■ Key subcontractors
there are some very local conditions the sections like a loaf of bread” and brought on at 100%
there and it would make a lot more create a system of ribs that could be design documents
sense from an economic standpoint framed by just two workers. “That ■ Enhanced collaboration
to adhere to those [concepts],” is one of the best examples I’ve through BIM use
Emerson says. seen of how you can collaborate in ■ Innovative use of easily
Wolfe says that the precast BIM to optimize construction and modifiable casting
solution illustrated how a contractor fabrication,” he says. beds to create 700 unique
with local knowledge can help Although the team collaborated pre-cast concrete panels
inform the design process. To handle early to help prevent issues during ■ Created simplified
precast duties, the team brought in construction, it also had to come installation solution
Gate Precast, which joined at the together to meet challenges after for complex wall and
100% design documents phase. “We the project broke ground. During soil ceiling geometries
do a lot of precast concrete in Texas,” excavation, a massive abandoned
he adds. “Morphosis had never concrete structure was discovered.
worked with [precast exterior panels] Its location conflicted with both the
before, but we were able to take their museum’s foundation placement
vision and team them with the local and the main electrical feeds for the The GPS coordinates were input
providers who could accomplish it.” building. The traditional solution into the building model, surfaced
The façade emulates a would be to demolish and remove and sent to the structural engineer
sedimentary geologic formation. the structure in order to complete for review. The structural engineer
Each of the 700 panels is unique, and the foundation as designed. This could evaluate all the structural
many panels are curved, canted and could have caused a six- to eight- components that were being
have a radius. For budget reasons, week delay. Instead, the team used impacted by this existing structure
the team came up with a module GPS technology, which it was and proposed solutions to
concept, creating 16 different casting already using for as-built utility address the conflicts. By using
beds that could be quickly modified installations and underground this approach, the team was able
to give each of the 700 panels a electrical and plumbing rough-ins. to remain on schedule. ■
The lowest percentages of architects and contractors find Effectiveness of Project Information
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
It appears that the days of hard, low-bid project-team Impact of Team Selection Method on
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
selection may be waning. Between the two choices Schedule (According to Owners)
of a qualifications-based or a fee-based/lowest-cost Source: McGraw Hill Construction, 2014
within project teams. However, while some are able to use contracts
that share risk and reward, others look to gain benefits by employing
IPD principles and practices without the contractual obligations.
T
o enhance collaboration that the company’s staff sees it as an project that used IPD techniques.
within project teams, many opportunity rather than a threat. The project called for delivery in
firms are adopting the “Certainly there are risks, but we 18 months—half the estimated
principles and practices also see the opportunities relative to schedule under traditional delivery.
of IPD.To date, there is considerable what we want to accomplish,” he says. The partners collaborated early to
variance in the depth of IPD adoption “It’s been a very mature risk-reward deliver 18 construction packages.The
and the types of techniques used. assessment, not just a legal group team collocated throughout the entire
Advanced users employ multiparty throwing up a roadblock.” project to help enhance teamwork.
agreements—also known as an Contracts also provided performance
integrated form of agreement (IFOA)— Non-Contractual IPD incentives and disincentives.
in which risks and rewards are shared. Susan Klawans, vice president and Kevin McCain, vice president of
Many organizations are unwilling or director of operational excellence Skanska USA Building, has seen
unable to sign such agreements, yet and planning at Gilbane Building, success with an integrated approach
they want the benefits of IPD and, says that while owners are often without an multiparty contract on
therefore, pursue IPD-like behavior, interested in IPD, many are unwilling hospital projects. On one project,
agreeing to use collaborative or unable to execute contracts. a bond initiative would not allow
techniques, but with less formalized “Some public [owners] can’t [use the use of an IFOA. Instead, the
contractual obligations. multiparty contracts] because of parties signed an agreement that
Disney is among the owners procurement laws,” she says. “Some outlined how the team would work
committed to contractual IPD. owners look at it as giving up control. collaboratively.Target-value design
Craig Russell, chief design and Others take a look at it in their legal was used, including early assistance
project-delivery executive at Walt departments or risk-management from key subcontractors.The subs
Disney Imagineering, reports that departments and won’t try something provided early cost estimates and were
the company is developing multiparty new and unprecedented.Yet, we incentivized to maintain—or reduce—
agreements to help it deploy IPD. have a lot of clients who can’t get a those estimates. If the final estimates
Russell says Disney’s main goal in [multiparty] agreement that want the ran over, their contracts could be put
the initiative is to improve predictability principles of IPD [worked into] some of out for bid. “We incorporated all of
and efficiency in schedules and their projects.” the things you’d see in a multiparty
budgets. “This is not about cutting Klawans says that IPD practices agreement, except no one had skin in
costs,” he says. “We need to hit are a good fit with the firm’s existing the game,” McCain says.
our targets.” construction manager at risk methods. Raul Rosales, project executive
Russell says that the company “IPD calls for mutual respect and at Skanska, who has worked on
has crafted several forms that allow trust, mutual benefit and reward, contractual and informal IPD projects,
Disney to tailor contracts meet specific collaborative innovation and decision- says having an IFOA greatly enhances
project needs. Disney is looking for making and early involvement of the level of collaboration. “When there
“sustainable partnerships on a win-win participants,” she says. “We can do that is a contractual [agreement], you can’t
basis” with the firms contracted on its under a CM-at-risk contract.” run away from issues,” he says. “The
projects, he says. For the Henry J. Carter Specialty terms of an agreement don’t guarantee
Although the initiative marks Hospital and Nursing Facility in East results, but it requires a high level of
a significant shift in procurement Harlem, Gilbane joint-ventured with sophistication on everyone’s part that
systems for Disney, Russell says McKissack & McKissack on a CM-at-risk improves your odds of success.” n
All respondents—architects, contractors and owners— Most Influential Drivers for Respondents to
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
were asked what would or has encouraged their firms to Engage in a Project Using Integrated Project
engage in an IPD project, but they were asked in different Delivery (According to Owners)
ways. Architects and contractors were asked to rank the Source: McGraw Hill Construction, 2014
top three most influential drivers, while owners were Ability to Address Schedule Concerns
asked to rate the degree of influence of each driver.
78%
Owner Mandate
Architects and Contractors
51%
The chart at the right represents all of the factors ranked
first, second or third by architects and contractors. 49%
However, when looking solely at the factors ranked first, Flexibility to Pursue Innovative Approaches
the top choice by a wide margin is owner mandate for 44%
both architects and contractors. The highest percentage
44%
of contractors also select owner mandate among their top
three choices, but the highest percentage of architects Ability to Address Schedule Concerns
(56%) rank the ability to increase the quality of the final 30%
building among the top three drivers. This finding is 21%
interesting because it reveals that architects familiar with
Ability to Control Costs Effectively
IPD associate it with increased building quality. The third
driver important to architects and contractors alike is the 27%
flexibility to pursue innovative approaches. 35%
Architects and contractors agree that other industry Positive Influences on the Use of Integrated
firms have a large influence on the use of IPD, with over Project Delivery
50% of both groups selecting this as a factor with a (According to Architects and Contractors)
positive influence. However, it is notable that a much Source: McGraw Hill Construction, 2014
higher percentage of architects and contractors find that
industry firms influence the use of design-build (72% of Architects
architects and 80% of contractors) or CM-at-risk (82% Contractors
of architects and 93% of contractors). (See page 27 for Construction Industry Firms
more information.) This is no doubt due to the relatively
57%
low familiarity with IPD by other buildings-sector firms
(see page 11). If so, wider experience of IPD benefits by 56%
owners may help drive adoption of this delivery system at Professional Associations
a higher rate than the industry currently expects. 56%
Unlike other delivery systems, the influence of 48%
professional associations and green building practices
are far closer to being on par with industry firms in driving Green Building Practices
IPD use, especially according to architects. Professional 47%
associations have played a critical role in educating the 40%
buildings sector about IPD, and this delivery system has
Legal Profession
gained a reputation for helping to achieve sustainable
outcomes. (See page 47 for more information about 16%
collaboration and sustainable outcomes.) 24%
Policy
11%
13%
3_3_EMERGE_InfluenceFactors_D5_#01
Owners were asked to rate the importance of five Adoption of Integrated Project Delivery
obstacles to wider use of IPD. Strikingly, all five are (According to Owners)
considered important by about half of the owners. Source: McGraw Hill Construction, 2014
The top concern is the lack of checks and balances—made Risk of Other Team Members Not Performing
clear in concerns about under-performing team members,
53%
about shared risk reward contracts or about the lack of
oversight among team members—and the cost implications Challenges in the Shared Risk/
of that lack of oversight is also a major issue for owners. Reward Contracts
Proponents of IPD need to be able to demonstrate 50%
to owners that their interests are better served in a Higher Cost Contracts
collaborative environment that is enforced by contract.
50%
Two factors are selected by a relative high percentage Lack of Owner Interest
of architects and contractors as the top obstacle, but 22% 14% 36%
they are selected by very few as the second or third most 16% 16% 32%
important obstacle:
Challenges in the Shared Risk/
• Lack of Good Standardized Construction Documents: Reward Contracts
Top obstacle for 9% of architects and 15% 2% 33% 35%
of contractors
26% 31%
• Higher Cost Contracts: Top obstacle for 9%
5%
of architects and 8% of contractors
O
n June 4, 2008, Colorado the tradition contract because it was glass curtainwall and dome that
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR
Governor Bill Ritter signed the best way to delivery the project. became the dominant feature of the
Senate Bill 206, authorizing “This was the only realistic way to finished building.
the construction of a new do it,” says David Kuntz, senior project “The contracts were silent when
state judicial complex in Denver. manager for Mortenson Construction. it came to an IPD approach and
Named the Ralph L. Carr Colorado “The only other avenue you could expectations of the owner, but
Judicial Center, the building occupies argue, even though the complexity it was very much verbalized by
an entire block bordered by 13th of a job of this magnitude wouldn’t Trammel Crow for us to be highly
Avenue, 14th Avenue, Lincoln Street have been favorable for it, would be collaborative,” Kuntz says. “Most
and Broadway. The 695,000-sq-ft, some type of design-build. A job of of these goals were perspective-
$200-million judicial building was this magnitude under that type of based, but the relationship between
designed and built using an inclusive procurement method would have Fentress, Mortenson and Trammel
and team-based process to deliver it been… difficult, to say the least.” Crow was not. We had to make sure
under budget and two months early. The 12-story state courthouse we were working together to meet
and office tower had program those guidelines but also meet
Taking an Integrated requirements that demanded the schedule. Sometimes we were
Approach design team create a 100-year- going to step on each other’s toes,
The State of Colorado uses a design- lifecycle facility that both honored and the architects had to change their
bid-build contract on its building revered the legacy of the Colorado normal processes and so did we. We
projects, and officials made clear court system, while representing and had to be cognizant that design was
to the developer,Trammel Crow, accommodating its future. It needed evolving and they had to understand,
that they were not willing to take to house a more efficient state judicial going in, that there were certain
on additional risk. However, the system, as the complex consolidates things that we couldn’t build in
developer recognized the need to take seven judicial and legal agencies. 27 months.”
an integrated design approach to this Trammel Crow targeted a LEED-
project.Trammel Crow, construction Gold certification for the facility and Collaborative Approach
manager Mortenson Construction and wanted the building delivered within to Modeling
Fentress Architects verbally agreed to a 27-month construction schedule. What evolved from the early
take an integrative approach despite The design also featured an intricate design meetings was a collaborative
process that relied heavily on
3D modeling, ongoing design
charettes and early involvement of
subcontractors. An office space across
from the personnel from Mortenson,
Fentress,Trammel Crow and key
subcontractors such as the precast
and MEP contractors met regularly
there in the early design phases.
“There were lots of 3D models,”
Kuntz says. “Fentress Architects
modeled everything in one BIM
program, and all of their consultants
followed suit. They would give us
Photo Credit: Jackie Shumaker
CONTINUED
TI
N
CO
Project Facts
st
model was always the latest and enough to get it approved,” Kuntz
and Figures
at
s
greatest because it included all of the says. “When it came to millwork there
necessary detail. When we would get were elevations, [where] they didn’t Type of Project
Courthouse/office tower
the shop drawings from them, it was put housing in, they left that to the
always just a day or two later when subcontractors so it only got drawn Size
695,000 square feet over 12
we were able to ... give those rebar once.There was refinement of the
stories
shop drawings to our steel fabricator. model as the process went on.”
This eliminated the procurement For the glass wall and dome, 3D Cost
$200 million
process of getting the drawings to models had to be detailed enough so
a rebar guy, then having to create that materials could be ordered off of Construction Schedule
27 months
detailed rebar drawings, sending it in them. All glass curtainwall and other
for approval, and then fabricating.” building products were installed upon Completed
The design model and structural arrival. No field rework was performed December 2012
models were imported into and no part of the enclosure system Owner/Developer
Mortenson’s coordination model. was field-measured. Trammel Crow Co. for the
State of Colorado
This model would take the design “I can’t imagine what that job
to the next level of complexity, as would cost if it was done today, even Architect
constructability issues were ironed though it’s only a few years later,” Fentress Architects
out and clashes were eliminated. Kuntz says. “The scope was millions Structural/Civil Engineer
More detail was entered for both under budget [a 4.5% overall budget Martin/Martin Consulting
Engineers
glazing and precast subcontractors, savings] and that allowed the owners
as Mortenson would take their to add in other things they wanted MEP Engineer
drawings and import them into the because of the saving. Some of that M-E Engineers
coordination model. was the millwork and other details. Construction Manager
All stud-framing including panels Everything went together without a Mortenson Construction
of walls and kickers for above-ceiling hitch, since we built in tolerances in Subcontractors
racks were input into the model the models to accommodate.” Mechanical: RK Mechanical
at this time. MEP engineer M-E An online, collaborative, PDF- Electrical: Encore Electric
Engineers put in linework to represent based construction documentation Precast: Gage Brothers Precast
ductwork and then the installation and storage tool was used for quality
subcontractors would take that line control on the project. Personnel
Project Savings
and use it as a basis for coordination. knew when a door, for instance, was
■ 4.5% overall budget savings
Coordination was performed for ready to have hardware added and
interior wall studs, conduit racks, fire installed because of a color-coded ■ 60% of building envelope
protection, stonework, millwork and system in the online documentation design clarifications generated
wall-mounted cabinets. Everything tool. Kuntz said the team had huge in early design saving
¾ of an inch and larger was modeled productivity gains through this type
in 3D. of collaboration, including a 50%
reduction in paper on the project.
Integrating to Refine “Our subcontractors had the same
the Model innovation culture as Mortenson, [the
Kuntz described this process as same] technology used for process
refinement, not rework.The architect improvement and efficiency,” Kuntz
and design team would take it to a says. “When you have the right group
point where it was sufficient enough of subcontractors on board you can
to hand off to the construction team. do that.”■
Owners were asked to rate the level of influence of several Respondents to Engage in a DBO/M Project
key drivers in encouraging their firm to engage in DBO/M (According to Owners)
projects. The highest percentage of owners (63%) find that Source: McGraw Hill Construction, 2014
the ability to control costs is an influential driver for their Ability to Control Costs Effectively
company. DBO/M takes the cost control provided by CM-at-
63%
risk or other delivery systems a step further, since it also
extends into the cost of operating a building. Ability to Address Schedule Concerns
About half of the owners also find five additional 52%
factors would be influential in getting their company to
Concerns About Project Complexity
use DBO/M.
• It is not surprising that controlling scheduling is the next 51%
driver since this is a critical way to judge the success Ability to Increase Quality of Final Building
of a project by an owner. However, the percentage 49%
that consider this influential for DBO/M use (52%) is
significantly below those who would be influenced by Flexibility to Pursue Innovative Approaches
the ability of IPD to control schedule (78%). 49%
(See page 53.) Shifting Risks From Owner
• Project complexity, on the other hand, is considered
46%
influential by roughly the same percentage of owners
for DBO/M (51%) as for IPD (55%). Owners may
be aware that a complex building may also present
operational challenges, and having the continuity
Top Drivers That Would Influence
between construction and operations offered by 3_7_EMERGE_DBOM_OwDrivers_C6_#01
Respondents to Engage in a DBO/M Project
DBO/M may help address those challenges.
(According to Architects and Contractors)
• Surprisingly, the lowest percentage of owners select
Source: McGraw Hill Construction, 2014
shifting risk away from them (46%) as a top driver. With
the contractor now taking on some of the operational Ranked 1st—Architects Ranked 2nd or 3rd—Architects
risk, this seems like it should be an important driver. Ranked 1st—Contractors Ranked 2nd or 3rd—Contractors
The low performance may suggest a lack of faith on the Owner Mandate
part of owners that operational risk is truly being shifted
60% 8% 68%
due to their lack of experience with these projects in
44% 7% 51%
the industry.
Financial Structure of a DBO/
Architects and Contractors M Contract
Architects and contractors were asked to select up to 11% 27% 38%
three top factors that would encourage their firm to 27% 38% 65%
engage in a DBO/M project.
Ability to Increase Quality of
Two drivers are selected by the highest percentage of Final Building
architects and contractors, although each carries more 4% 32% 36%
weight with one group than the other.
27% 29%
■ Owner Mandate: This is selected among the top three
2%
by the highest percentage of architects (68%) and the
Flexibility to Pursue
second highest percentage of contractors (51%). Nearly Innovative Approaches
all the respondents who select owner mandate at all
9% 21% 30%
rank it first. This suggests that many are unfamiliar with
29% 31%
the specific benefits that would encourage owners to
2%
mandate this system.
Financial Structure of DBO/M contracts: The highest A small but notable percentage of architects and
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR DATA
■
percentage of contractors ranked this among their top contractors find that the ability to improve the quality of a
three drivers (65%), with 27% of all contractors also building and the ability to innovate would encourage their
ranking it first. A much lower percentage of architects firm to adopt DBO/M. Certainly, both seem to be likely
(38%) rank this in their top three, with very few of all the by-products as a DBO/M contract will encourage design
architects (11%) ranking it first. This is not surprising and construction approaches that improve building
since many contractors are in a position to directly operations. As the industry becomes more familiar with
benefit from working with owners on the operations this delivery system, it will be interesting to see if these
and maintenance of the buildings that they construct, benefits can help drive DBO/M projects in the future.
especially since this work often has a higher profit
margin than the construction itself.
With the level of awareness and use so low in the Positive Influences on the Use of
industry for DBO/M, it is not surprising that a relatively Design-Build-Operate/Maintain
low percentage of architects and contractors find any (According to Architects and Contractors)
factors influential in encouraging the use of this delivery Source: McGraw Hill Construction, 2014
Legal Profession
11%
22%
the DBO/M obstacles important, compared with the Legal Restrictions Prevent Use on Public Projects
ratings they gave to the IPD obstacles. Rather than
48%
suggesting that owners perceive fewer obstacles, this
finding probably suggests less familiarity with DBO/M Too Few Contractors Interested in
and, therefore, with the factors impeding its adoption. Operations and Maintenance
■ Owners share the contractors’ concerns about the lack 48%
of engagement by contractors with O&M, with 48% Contract Terms Are Too Long
reporting that lack of contractor interest in O&M is a
38%
major obstacle.
■ Limitations on the ability to use this system on public Contracts Are Too Expensive
projects are regarded by owners as an equal hindrance, 37%
with 48% considering this an important obstacle.
Lack of Good Standardized Contract Documents
A little over one-third of owners consider the cost and 35%
length of DBO/M contracts an issue. This type of concern
can often be assuaged by evidence of cost savings by
owners with experience with a new project approach,
Most Important Obstacles Preventing Wider
as McGraw Hill Construction’s research on other
Adoption of Design-Build-Operate/Maintain
3_10_EMERGE_DBOM_OWObstacles_C7_#01
construction trends suggests.
(According to Architects and Contractors)
Architects and Contractors Source: McGraw Hill Construction, 2014
y
Use of Design-Build-Operate/Maintain
Governor George Deukmejian Courthouse
LONG BEACH, CALIFORNIA
I
n 2007 the state courthouse in example, Hastie says that California
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR
its service-fee payments if certain Clark Construction, says that these the finance component into it with an
performance criteria are not met, considerations factored heavily operations mindset and you bring in
says Jeffrey Fullerton, director of into early decisions about project the operator who will be responsible
Edgemoor Development Group. For aspects, such as material selection for the next 35 years, it changes the
example, if the courthouse has to be and systems architecture. For way you approach things.”
CONTINUED
TI
N
CO
st
concern throughout the project. and international investors.
at
and Figures
s
Independent quality-management To further enhance collaboration
firm Development Industries while improving quality, the team Design-Builder
Clark Design-Build/Edgemoor
worked with the design-builder did extensive building information
Development Group
and trade subcontractors to execute modeling (BIM), followed by physical
its project quality-management mock-ups. Type of Project
State Courthouse
plan throughout design, construction “It was a cycle of validation and
and closeout. verification through modeling and Size
545,000 sq. ft.
The project also utilized TMAD mock-ups to ensure that workflow
Taylor & Gaines as an independent and quality were understood clearly,” Team Selection
building expert to ensure code Hastie says. December 2010
compliance and quality assurance The process enabled the team Completed
throughout design and construction. to use prefabrication and modular September 2013
elements on the project, which aided
Multiparty Collaboration the schedule while improving safety Project Highlights
Although the design-build team and quality, he adds. ■ First social-infrastructure
required co-location of key firms The team was also intensely building project in the United
to help foster collaboration, the focused on the schedule. The fast- States procured under
team often needed to reach out to track project needed to be completed principles of performance-
stakeholders in multiple locations to in 32 months. Under the agreement, based infrastructure
keep lines of communication open. the state paid nothing until the ■ Intensive up-front risk
In addition to weekly design review building was occupied. assessment
meetings and formal milestone “There was a huge incentive to ■ Greater emphasis on long-term
reviews, the team used a web- get to the finish line on time,” Hastie costs, rather than first costs
based platform for all stakeholders says. “Just getting close is not good
Photos by Robb Williamson, AECOM
McGraw Hill Construction (MHC) Owners were also asked more Architect and Contractor
PROJECT DELIVERY SYSTEMS: HOW THEY IMPACT EFFICIENCY AND PROFITABILITY IN THE BUILDINGS SECTOR
conducted the 2014 Project general questions about project Respondents by Firm Type
Delivery Systems study to examine delivery methods. Source: McGraw Hill Construction, 2014
ACKNOWLEDGEMENTS:
The authors wish to thank our premier partners MMC Contractors, the
American Institute of Architects (AIA), Design-Build Institute of America (DBIA)
and the Society for Marketing Professional Services (SMPS), as well as our
McGraw Hill Construction
contributing partner Bentley Systems, for helping us bring this information to
Main Website : construction.com
the market. Specifically, we would like to thank Keith Andrews, Dan Coppinger,
Dodge : construction.com/dodge
Tom Powers and Jacob Vogel from MMC Contractors; Robert Ivy and James
Research & Analytics :
Chu from AIA; Lisa Washington from DBIA; and Ron Worth from SMPS for their
construction.com/dodge/
individual support of this project.
dodge-market-research.asp
Architectural Record : archrecord.com We would also like to thank the firms that provided information about their
Engineering News-Record : enr.com projects and experiences with using a specific delivery system on their
Sweets : sweets.com projects, as well as for their assistance in helping us secure images to
SmartMarket Reports : supplement their project information.
construction.com/market_research
SmartMarket Report
www.construction.com