SID - NSN - Simplified Sites - AMX Col - v1
SID - NSN - Simplified Sites - AMX Col - v1
Partner Document
13/February/2014
Table of Contents
1. Overview ........................................................................................... 4
2. Service Item Description ................................................................... 5
2.1 00035253 SA for one existing site / all types / Evaluation .............................................. 5
2.2 00001221 Site Design, new macro site ........................................................................ 7
2.3 00002905 Ground investigation ................................................................................... 8
2.4 00068639 GF site preparations and finishes ................................................................ 9
2.5 00033336 S Pedestrian gate, GF site .......................................................................... 10
2.6 00038497 M Pedestrian gate, GF site ....................................................................... 11
2.7 00069336 S Pedestrian metallic door, GF site ............................................................. 12
2.8 00069436 M Pedestrian metallic door, GF site .......................................................... 13
2.9 00069337 S Vehicle metallic door, GF site .................................................................. 14
2.10 00069437 M Vehicle metallic door, GF site................................................................ 15
2.11 00068566 S Site fencing, GF site .............................................................................. 16
2.12 00068629 M Site fencing, GF site .............................................................................. 17
2.13 00068621 M Masonry wall, GF site............................................................................ 18
2.14 00068589 S Masonry wall, GF site ............................................................................ 19
2.15 00072377 CW Transport, long distance, high vol. ...................................................... 20
2.16 00001270 S Lattice tower on gnd 35m - 40m, S-SP .................................................... 21
2.17 00038430 M Lattice tower on gnd 35m - 40m, S-SP .................................................. 22
2.18 00001273 S Lattice tower on gnd 60m - 65m, S-SP .................................................... 23
2.19 00038435 M Lattice tower on gnd 60m - 65m, S-SP .................................................. 24
2.20 00068573 S Raft foundation for GF tower.................................................................. 25
2.21 00068618 M Raft foundation for GF tower ................................................................. 26
2.22 00049089 S Mains pwr to OD GF site, contractor ........................................................ 27
2.23 00049088 M Mains pwr to OD GF site, contractor ..................................................... 28
2.24 00002954 S Earth electrode, GF site ........................................................................... 29
2.25 00038388 M Earth electrode, GF site ........................................................................ 30
2.26 00068571 S Equipment earthing, GF site .................................................................. 31
2.27 00068615 M Equipment earthing, GF, small .............................................................. 32
2.28 00040825 S Shelf and pole for FlexiBTS ..................................................................... 33
2.29 00040827 M Shelf and pole for FlexiBTS................................................................... 34
2.30 00068646 S Structural concrete ................................................................................ 35
2.31 00068649 M Structural concrete ................................................................................ 36
2.32 00068561 S OD cable tray, narrow ............................................................................ 37
2.33 00068601 M OD cable tray, narrow ........................................................................... 38
2.34 00038285 I floor mount 19-23 cab ............................................................................... 39
2.35 00007509 M floor mount 19-23 cab ............................................................................. 40
2.36 00044997 Existing building structure test .................................................................... 41
2.37 00033890 RT site preparations and finishes ................................................................ 42
2.38 00002955 S Access ladder to RT site .......................................................................... 43
2.39 00068598 M Access ladder to RT site ....................................................................... 44
2.40 00002953 S Earth electrode, RT site ........................................................................... 45
2.41 00038389 M Earth electrode, RT site ........................................................................ 46
2.42 00001315 S Mains pwr to RT site, contractor .............................................................. 47
2.43 00038451 M Mains pwr to RT site, contractor ............................................................ 48
2.44 00068570 S Equipment earthing, RT site .................................................................. 49
2.45 00068616 M Equipment earthing, RT, small .............................................................. 50
2.46 00002941 S Roof fixed antenna support 5m - 7m ........................................................ 51
2.47 00038510 M Roof fixed antenna support 3m - 5m ..................................................... 52
Copyright 2014. Service Item Description Page 2 of 62
Nokia Solutions and Networks.
The Service Supplier (Partner) must consider all the task and materials needed to successfully
complete the service, according to the Service Description document, even if some of them were
not indicated in the present document.
All the services must be performed according to the current standards and specifications provided
by Nokia Solutions and Networks and/or Claro Colombia. These specifications are included in the
Service Description. If some specifications are not included, the partner must consider the current
specification indicated by CLARO.
The service includes all tasks needed to obtain the Final Acceptance document signed by the
customer, and the delivery of the document to Nokia Solutions and Networks.
The service includes, if required, the upload of the scanned documents to IPM and the update of all
the dates included in the tool for control and tracking of the project.
The service includes the cleaning of the work area and the residual management of all the packing
material included with the delivered equipment, according to local standards and applicable laws.
Includes
To obtain, review and organize existing Site documentation from customer
Pre-evaluation survey with Network planning (NWP)
1 Site Evaluation Report (SER) per site (if needed)
Review if Ownership documentation it’s Updated and complete
Validated existing site candidate
Excludes
Site Design work (e.g. AutoCAD or equivalent work)
Site Engineering Works
Arrange, coordinate and take part in the Technical Site Survey (TSS)
To obtain, review and organize existing Site documentation from customer, including
leasing contracts, construction licenses and permits required to start the construction of the
site.
Arrange Pre-evaluation survey with Network planning (NWP).
Complete site evaluation in accordance with Project acquisition process. In general one Site
Evaluation Report (SER) per existing site.
The content of SER is defined in the project document SER and could not be necessary the
generation of this report. The Site Acquisition agent is responsible that the SER report is
properly filled. The following information can be considered as main items to be filled to
SER
Site location (coordinates, address, access description) to confirm
Photos of the site
Name and contacts of the owner and representative
Rental fee and existing contract confirmed
Evaluation of additional re-negotiations, rental fee and terms of contract
Ownership documentation confirmed and updated
Copyright 2014. Service Item Description Page 5 of 62
Nokia Solutions and Networks.
Deliverables
One filled SER report per candidate both in paper and electronic forms (if required).
Validated that documentation of existing candidate is complete and updated.
All relevant data entered into project data management tool and Quality checklist (if
applicable).
Service
Detailed construction works design including construction details, power supply,
mechanical, electrical and topographic design with bill of quantities of materials
Participation in Technical Site Survey and preparation of Technical Site Survey Report
Preparation of permitting designs and documents if needed
Preparation of as-built drawings after completion of all site works
Topographic survey and positioning
Preparation of construction detailed descriptions and Electrical & Grounding systems
calculation
Excludes
Telecom installation planning
Ground investigation
Electrical board design (if applicable)
Service
Site activities including transportation of testing equipment
Investigation of the necessary test sample for the center of the monopole/tower base
Preparation of investigation report including foundation proposal to enable foundation
design in accordance with local codes and regulations
Service
Cleaning of site area.
Removal and disposal of trees and undergrowth from the site according local regulation and
to approval
Top soil removal from the site and transportation to an agreed dumping area
Finishing the site area according to the specifications and site specific detailed design with
gravel and Geotextile fabric material.
Removal and disposal of all waste material arising from construction and final site cleaning
Site supervision and the project management
Material
Gravel
Geotextile fabric material
Excludes
Foundation works
Access road and vehicle turn around area
Bill of Quantities
Component description Occ. Qnt Unit
Gravel (10 cm depth) 100 % 1 M2
Geotextile fabric material 100 % 1 M2
Service
Installation on site
Pedestrian gate system
Foundation of poles including excavation, formwork, reinforcement, concrete
Lock
Key holder
Site supervision and project management
Excludes
Material
Supply of:
Pedestrian gate system
Formwork material
Reinforcement
Concrete
Lock
Key holder
Excludes
Fence
Bill of Quantities
Component description Occ. Qnt Unit
Gate system 100 % 1 lot
Formwork material 100 % 1 lot
Concrete reinforcement 100 % 1 lot
Structural concrete 100 % 1 m3
Lock 100 % 1 pcs
Key holder 100 % 1 pcs
Service
Installation on site
Pedestrian metallic door
Construction of concrete frame, including excavation, formwork, reinforcement, concrete
Lock
Key holder
Site supervision and project management
Excludes
Material
Supply of:
Pedestrian metallic door according to the project specifications
Formwork material
Reinforcement
Concrete
Lock
Key holder
Excludes
Masonry wall
Bill of Quantities
Component description Occ. Qnt Unit
Metallic door 100 % 1 lot
Formwork material 100 % 1 lot
Concrete reinforcement 100 % 1 lot
Structural concrete 100 % 1 m3
Lock 100 % 1 pcs
Key holder 100 % 1 pcs
Service
Installation on site
Vehicle metallic door
Construction of concrete frame, including excavation, formwork, reinforcement, concrete
Lock
Key holder
Site supervision and project management
Excludes
Material
Supply of:
Vehicle metallic door according to the project specifications
Formwork material
Reinforcement
Concrete
Lock
Key holder
Excludes
Masonry wall
Bill of Quantities
Component description Occ. Qnt Unit
Vehicle Metallic door 100 % 1 lot
Formwork material 100 % 1 lot
Concrete reinforcement 100 % 1 lot
Structural concrete 100 % 1 m3
Lock 100 % 1 pcs
Key holder 100 % 1 pcs
Service
Installation on site
Poles
Mesh
Frames
Fixing bolts
Connection to site main grounding
Foundation for poles including, excavation, formwork, reinforcement, concrete, backfilling
Site supervision and project management
Excludes
Gates and locks
Key holder
Material
Supply of:
Poles
Mesh
Frames
Fixing bolts
Grounding material to connect the fence to site main grounding system
Formwork material, reinforcement and concrete pole foundation
Excludes
Gates and locks
Key holder
Bill of Quantities
Component description Occ. Qnt Unit
Pole 100 % 1 pcs
Mesh 100 % 1 m2
Frames 100 % 1 Lot
Grounding wire incl. accessories 100 % 1 lot
Fixing bolts 100 % 1 lot
Formwork material 100 % 1 lot
Reinforcement material 100 % 1 lot
Concrete 100 % 1 m3
Material
Supply of:
Bricks
Masonry mortar
Formwork material
Reinforcement
Concrete
Excludes
Gates, plaster
Key holder
Bill of Quantities
Component description Occ. Qnt Unit
Bricks 100 % 1 Lot
Masonry mortar 100 % 1 Lot
Formwork material 100 % 1 Lot
Concrete reinforcement 100 % 1 Lot
Structural concrete 100 % 1 Lot
Service
Construction and installation on site
Masonry wall in brick (visible - no plaster)
Filled joints
Foundation including excavation, formwork, reinforcement, concrete
Excludes
Gates, plaster
Key holder
Service
Loading of the cargo onto the truck/lorry at the storage as described below.
Over 300 km transportation of Materials in a truck/lorry from the storage area to site.
Carrying or moving the cargo from the vehicle into the equipment room, battery room,
rooftop or other designated area at the site.
Accommodation of the passengers and secure parking of the vehicle if overnight stay is
needed.
Insurance of the persons, vehicles, tools, Materials and equipment within the scope of this
service Item.
Excludes
Transportation by helicopter or any other special vehicle different than truck/lorry.
Hoisting of the cargo by crane.
Travel of personnel other than the driver and the aids for cargo loading and unloading.
Service
The site supervision and the project management
Detailed structural design for a new tower including foundation design (High: 36m / Wind
Speed 120 Km/hr / Base dimension to be considered 1.0 x 1.0 m / Load: As indicated in the
Service Description)
Bill of quantities
Workshop drawings
Structural calculations
Transportation to the site.
Vertical alignment test and generation of results report.
Installation on site:
Galvanized steel self-supporting lattice tower including working platforms and antenna
mounting parts as detailed in the specification and drawings.
Pre-installed ladder system including cable ladder, climbing ladder and safety system
Crane if needed for erection of tower and moving the crane to the tower location
Painting
Lightning protection and equipment earthling
Aviation warning lights system for towers up to 36m, includes Controller and Photoelectric
cell.
Includes cabling installation for power and grounding.
Alarm connection
Testing and commissioning the lights system
Lights System test report (if required by the operator)
Excludes
Foundation works including installation of the anchor bolts for tower
Earth electrode
Horizontal cable bridge
Actual site design for a site
Ground investigation
Material
Supply of:
Galvanized steel self-supporting lattice tower including working platforms, equipment
platform, and antenna mounting parts as detailed in the specification and drawings. (For 9
RF antennas and for 2 MW antennas up to 1.2m diameter) (High: 36m / Wind Speed 120
Km/hr / Base dimension to be considered 1.0 x 1.0 m / Load: As indicated in the Service
Description)
Anchor bolts
Pre-installed ladder system including cable ladder, climbing ladder and safety system
Standard Aviation warning light system for towers up to 36m including controller system,
photoelectric cell and cabling.
Paint according to local standard.
Lightning protection and equipment earthling (includes up to 3 galvanized grounding bar).
Excludes
Earth electrode
Foundation
Horizontal cable bridge
Solar Aviation Warning Light
Bill of Quantities
Component description Occ. Qnt Unit
Galvanized steel self supporting lattice tower and accessories 100 % 1 pcs
Working platform and Equipment Platform (according to tower design) 100 % 1 Lot
Climbing safety system for Ladder 100 % 1 Lot
Ladder for tower 100 % 1 Lot
Cable ladder system 100 % 1 lot
Anchor bolts 100 % 1 lot
Antenna mounting systems (6 supports for 2 RF antennas & RF Modules, 3 are 100 % 1 lot
“H” type and 3 “Diversidad” type, and 2 supports for up to 1.2 m diameter MW
antennas)
Aviation Warning Light system up to 45m (incl. Controller system, Photoelectric 100 % 1 lot
cell and cabling)
Paint 100 % 1 lot
Service
The site supervision and the project management
Detailed structural design for a new tower including foundation design (High: 60m / Wind
Speed 190 Km/hr / Load: As indicated in the Service Description)
Bill of quantities
Workshop drawings
Structural calculations
Transportation to the site.
Vertical alignment test and generation of results report.
Installation on site:
Galvanized steel self-supporting lattice tower including working platforms and antenna
mounting parts as detailed in the specification and drawings.
Pre-installed ladder system including cable ladder, climbing ladder and safety system
Crane if needed for erection of tower and moving the crane to the tower location
Painting
Lightning protection and equipment earthling
Aviation warning lights system for towers up to 60 m, includes Controller and Photoelectric
cell.
Includes cabling installation for power and grounding.
Alarm connection
Testing and commissioning the lights system
Lights System test report (if required by the operator)
Excludes
Foundation works including installation of the anchor bolts for tower
Earth electrode
Horizontal cable bridge
Actual site design for a site
Ground investigation
Material
Supply of:
Galvanized steel self-supporting lattice tower including working platforms, equipment
platform, and antenna mounting parts as detailed in the specification and drawings. (For 9
RF antennas and for 2 MW antennas up to 1.2m diameter) (High: 60 m / Wind Speed 190
Km/hr / Load: As indicated in the Service Description)
Anchor bolts
Pre-installed ladder system including cable ladder, climbing ladder and safety system
Standard Aviation warning light system for towers up to 60 m including controller system,
photoelectric cell and cabling.
Paint according to local standard.
Lightning protection and equipment earthling (includes up to 3 galvanized grounding bar).
Excludes
Earth electrode
Foundation
Horizontal cable bridge
Solar Aviation Warning Light
Bill of Quantities
Component description Occ. Qnt Unit
Galvanized steel self supporting lattice tower and accessories 100 % 1 pcs
Working platform and Equipment Platform (according to tower design) 100 % 1 Lot
Climbing safety system for Ladder 100 % 1 Lot
Ladder for tower 100 % 1 Lot
Cable ladder system 100 % 1 lot
Anchor bolts 100 % 1 lot
Antenna mounting systems (6 “H” mount for 2 RF antennas and 2 RF Modules 100 % 1 lot
& 2 MW antenna mount for up to 1.2 m diameter)
Aviation Warning Light system up to 60m (incl. Controller system) 100 % 1 lot
Paint (if needed) 100 % 1 lot
Service
Work done on site
Installation of the concrete reinforcement
Erection of the formwork and removal after work is done
Installation of the anchor bolts
Casting the structural concrete
Excavation and backfilling
Testing and concrete finishes
Site supervision and the project management
Excludes
Remove of leftover excavated material from the site
Rock excavation
Use of explosives
Structural material backfilling
Material
Supply of:
Concrete reinforcement
Formwork material
Structural concrete
Excludes
Supply of the anchor bolts
Bill of Quantities
Component description Occ. Qnt Unit
Concrete reinforcement 100 % 1 lot
Formwork material 100 % 1 lot
Structural concrete 100 % 1 m3
Service
Work done on site
Excavation and backfilling of trenches to perform the pipelines and the manholes
Installation of AC main distribution board
Installation of main switch
Installation of power line and all needed accessories to connect the main distribution power
board to the delivery point of the utility company
All the procedure in the utility company, testing, commissioning and completion of
necessary certification
Construction of concrete or block KW-Meter/Main switch housing (Size: 2.4m x 1.6 m x 1 m)
includes metallic doors and security locks.
Installation of Equipment area lamp including fixing accessories and cabling.
Installation of AC outlet for outdoor.
All needed accessories
Site supervision and project management
Excludes
Managing the paperwork for hiring Electric Service
Material
Supply of:
Ducts and manholes
AC main distribution board (18 circuits, 70A, OD type) + Thermo magnetic Breakers (1 pcs
3x65A + 3 pcs 2x30A + 4 pcs 1x10A). According to operator specifications.
Main switch (Thermo magnetic – 3 phases)
KW-Meter (3F + N) Plug-in base
Power line and all needed accessories to connect the main distribution power board to the
delivery point of the utility company (3F + N)
Material for construction of concrete or block KW-Meter/Main switch housing (Size: 2.4m x
1.6 m x 1 m) includes metallic doors and security locks.
AC outlet for outdoor.
Underground connection cable
Equipment area lamp, including fixing accessories and cabling.
All needed accessories
Bill of Quantities
Component description Occ. Qnt Unit
Ducts (PVC) size according to electrical calculations 100 % 1 lot
Manholes 100 % 1 lot
AC main distribution board (18 circuits, 70A, OD type) + Thermo 100 % 1 pcs
magnetic Breakers (1 pcs 3x65A + 3 pcs 2x30A + 4 pcs 1x10A)
Main switch (Thermo Magnetic – 3 phases) 100 % 1 pcs
KW Meter plug-in base 100 % 1 pcs
Power line (3F+N) – Cable size according to electrical calculations 100 % 30 m
KW-Meter / Main Switch housing (Concrete or Block) 100 % 1 lot
Underground connection cable 100 % 1 lot
Equipment area lamp (incl. fixing accessories and cabling) 100 % 1 lot
Accessories 100 % 1 lot
AC Outlet for Outdoor 100 % 1 lot
Excludes
Chemical grounding rods or any other grounding system different to the indicated as
included.
Material
Supply of:
Underground earthing ring
Grounding rods
Grounding inspection boxes
All needed accessories
Excludes
Chemical grounding rods or any other grounding system different to the indicated as
included.
Bill of Quantities
Component description Occ. Qnt Unit
Underground earthing ring 100 % 1 lot
Grounding rods 100 % 5 pcs
Grounding inspection boxes 100 % 5 pcs
Accessories 100 % 1 lot
Service
Installation on site
Connection of Main Grounding Bar to main grounding system
Down conductor from earthing points to the earth electrode
All needed accessories
Excludes
Earthing bars for antennas are included in structural modules (e.g. tower, mast, etc.)
Earth electrode
Material
Supply of:
Down conductor from earthing points to the earth electrode
Main Grounding Bar for Equipments
All needed accessories
Excludes
Earthing bars for antennas are included in structural modules (e.g. tower, mast, etc.)
Earth electrode
Bill of Quantities
Component description Occ. Qnt Unit
Down conductor (min 50mm2) 100 % 3 m
Main Grounding Bar 100 % 1 lot
Accessories 100 % 1 lot
Service
Installation on site
Steel shelf for Flexi BTS modules and Power system according to operator specifications.
Steel Pole 3” x 2m installation. Includes construction of concrete base.
Site supervision and the project management
Excludes
Material
Supply of:
Steel shelf for FlexiBTS modules and Power System (According to operator specifications)
Steel Pole 3” x 2m Material. Includes Material for construction of concrete base and fixing
materials.
Fixing accessories
Bill of Quantities
Component description Occ. Qnt Unit
Steel shelf for FlexiBTS modules and Power System 100 % 1 pcs
Steel Pole 3” x 2m with plate base (Includes Material for construction 100 % 1 lot
of concrete base and fixing materials)
Fixing accessories 100 % 1 lot
Service
Work done on site
Installation of the concrete reinforcement
Erection of the formwork
Installation of possible anchoring accessories
Casting the structural concrete
Site supervision and the project management
Excludes
Material
Supply of:
Concrete reinforcement
Formwork material
Structural concrete
Excludes
Supply of possible anchoring accessories for connecting structures
Bill of Quantities
Component description Occ. Qnt Unit
Concrete reinforcement 100 % 1 lot
Formwork material 100 % 1 lot
Structural concrete 100 % 1 m3
Service
Installation on site
Cable tray system
Substructure system such as concrete blocks with fixing accessories and rubber sheets to
protect rooftop surface
Site supervision and the project management
Excludes
Lifting to rooftop using crane
Supporting pole in case of cable bridge
Material
Supply of:
Cable tray system up to 40 cm wide
Substructure system such as concrete blocks with fixing accessories and rubber sheets to
protect rooftop surface
Bill of Quantities
Component description Occ. Qnt Unit
Cable tray system up to 40 cm wide 100 % 1 m
Substructure system incl. fixing accessories, concrete blocks and rubber sheets 100 % 1 lot
Service
Installation of a floor-standing 19 or 23 inch cabinet with floor fixing material and label.
Installation of AC power cable with fixing material and labels up to the defined length.
Installation labels for AC power breaker and ground termination point (bus bar port).
Installation of the grounding cable up to the defined length including labeling of the ground
termination point
Transportation of cabinet from operator warehouse to the site.
Material
Excludes
Installation of DC power distribution frame.
Installation of DC power cable with fixing material, labels and connectors (lugs) up to the
defined length.
Transportation using other vehicle different than Truck.
Configuration and commissioning of Air Conditioned, if attached to the cabinet.
Bill of Quantities
Pos Category Occurrence Qnt Unit Component Remark
Material
Supply of a floor-standing 19 or 23 inch cabinet with floor fixing material and label.
Supply of AC power cable with fixing material and labels up to the defined length.
Supply labels for AC power breaker and ground termination point (bus bar port).
Supply of the grounding cable up to the defined length including labeling of the ground
termination point.
Excludes
Supply of DC power distribution frame.
Supply of DC power cable with fixing material, labels and connectors (lugs) up to the
defined length.
Bill of Quantities
Pos Category Occurrence Qnt Unit Component Remark
Service
Obtaining all needed information
Carring out tests on site for clarifying material strength for an existing structure in
accordance with local codes and regulations including all test equipment
Perform calculation and analysis of Building structure
Laboratory tests if applicable
Preparation of a report
Structural strengthening design
The scope includes only the analysis of the building structures related or affected by the
new elements that are planned to be installed and not for the complete building, unless it’s
necessary.
Excludes
Actual site design for an existing site
Excludes
Access ladder to rooftop including all fixing accessories in accordance with site specific
design for building and rooftop.
Site supervision and the project management services.
Excludes
Material
Supply of:
Access ladder to rooftop including all fixing accessories in accordance with site specific
design for building and rooftop
Bill of Quantities
Component description Occ. Qnt Unit
Access ladder 100 % 1 pcs
Accessories 100 % 1 lot
Service
Installation on site
Excludes
Chemical grounding rods or any other grounding system different to the indicated as
included.
Material
Supply of:
Underground earthing ring (if needed)
Grounding cable and connectors
Grounding rods
Grounding inspection boxes
All needed accessories
Excludes
Chemical grounding rods or any other grounding system different to the indicated as
included.
Bill of Quantities
Component description Occ. Qnt Unit
Underground earthing ring 100 % 1 lot
Grounding rods 100 % 5 pcs
Grounding inspection boxes 100 % 2 pcs
Accessories 100 % 1 lot
Grounding cable and connectors (min 50mm2) 100% 30 m
Service
Work done on site
Excavation and backfilling of trenches to perform the pipelines and the manholes (if
needed)
Installation of AC main distribution board
Installation of main switch
Installation of power line and all needed accessories to connect the main distribution power
board to the delivery point of the utility company
All the procedure in the utility company, testing, commissioning and completion of
necessary certification
Installation of metal enclosure for KW-Meter/Main switch protection (Size: 0.50 m x 0.80 m
x 0.30 m) includes security locks.
Installation of Equipment area lamp including fixing accessories and cabling.
Installation of AC outlet for outdoor.
All needed accessories
Site supervision and project management
Excludes
Managing the paperwork for hiring Electric Service
Material
Supply of:
Ducts and manholes.
AC main distribution board (18 circuits, 70A, OD type) + Thermo magnetic Breakers (1 pcs
3x65A + 3 pcs 2x30A + 4 pcs 1x10A). According to operator specifications.
Main switch (Thermo magnetic – 3 phases)
KW-Meter (3F + N) Plug-in base & Equipment.
Power line and all needed accessories to connect the main distribution power board to the
delivery point of the utility company (3F + N)
Metal enclosure for KW-Meter/Main switch protection (Size: 0.50 m x 0.80 m x 0.30 m)
includes security locks.
AC Outlet for Outdoor
Underground or aerial connection cable
Equipment area lamp, including fixing accessories and cabling.
All needed accessories
Bill of Quantities
Component description Occ. Qnt Unit
Ducts (PVC or PGG) size according to electrical calculations 100 % 1 lot
Manholes (if needed) 100 % 1 lot
AC main distribution board (18 circuits, 70A, OD type) + Thermo 100 % 1 pcs
magnetic Breakers (1 pcs 3x65A + 3 pcs 2x30A + 4 pcs 1x10A)
Main switch (Thermo Magnetic – 3 phases – 100 A) 100 % 1 pcs
KW Meter plug-in base 100 % 1 pcs
Power line (3F+N) – Cable size according to CLARO specification 100 % 30 m
KW-Meter / Main Switch Metal enclosure (Size: 0.80 x 0.80 x 0.30 100 % 1 lot
mts)
Underground and / or aerial connection cable 100 % 1 lot
Equipment area lamp (incl. fixing accessories and cabling) 100 % 1 lot
Accessories 100 % 1 lot
AC Outlet for Outdoor
Service
Installation on site
Connection of all equipment (shelter, generator etc.) to main grounding system
Down conductor from earthing points to the earth electrode
All needed accessories
Excludes
Earthing bars for antennas are included in structural modules (e.g. tower, mast, etc.)
Earth electrode
Material
Supply of:
Down conductor from earthing points to the earth electrode (incl. connectors)
Main Grounding Bar for Equipments
All needed accessories
Excludes
Earthing bars for antennas are included in structural modules (e.g. tower, mast, etc.)
Earth electrode
Bill of Quantities
Component description Occ. Qnt Unit
Down conductor and connectors 100 % 10 m
Accessories 100 % 1 lot
Main Grounding Bar 100 % 1 lot
Installation on site
Excludes
Lifting of the pole to the rooftop using crane
Aviation warning lights system.
Material
Supply of:
Antenna pole, including RF antenna mounting system or MW antenna supports.
Cable mounting system
Access steps
Climbing safety system
Earthing system
Lightning protection system
Pole fixing system (includes grout supply)
Painting (only if required)
Excludes
Lifting of the pole to the rooftop using crane
Aviation warning lights system.
Bill of Quantities
Component description Occ. Qnt Unit
Earthing bar 100 % 1 pcs
Lightning protection wire with accessories 100 % 7 m
5m Roof fixed pole system (includes 1 “H” 100 % 1 pcs
support for RF or 2 MW Antenna supports)
Access steps 100 % 1 lot
Climbing safety system 100 % 1 lot
Fixing accessories 100 % 1 lot
Cable mounting system 100 % 1 lot
Lightning arrestor 100 % 1 pcs
Paint (only if required) 50 % 1 pcs
Installation on site
Excludes
Lifting of the pole to the rooftop using crane
Aviation warning lights system.
Material
Supply of:
Antenna pole including antenna mounting system
Concrete flagstones as ballast
Cable mounting system
Access steps
Climbing safety system
Earthing system and lightning protection system
Painting (only if required)
Excludes
Lifting of the pole to the rooftop using crane
Aviation warning lights system.
Bill of Quantities
Component description Occ. Qnt Unit
Earthing bar 100 % 1 pcs
Lightning protection wire with accessories 100 % 5 m
5m Ballast roof pole system (includes 100 % 1 pcs
antenna mounting system for 3 RF
antennas)
Access steps 100 % 1 lot
Climbing safety system 100 % 1 lot
Cable mounting system 100 % 1 lot
Lightning arrestor 100 % 1 pcs
Paint (only if required) 50 % 1 pcs
Service
Installation of mounting system (“H” antenna support + brackets) for RRH modules and RF
Antennas on existing tower, monopole or rooftop pole.
The site supervision and the project management
Excludes
Painting of mounting system
Material
Supply of:
Mounting system (“H” antenna support pole + brackets) on existing tower, pole or building
Excludes
Painting of bracket system
Bill of Quantities
Component description Occ. Qnt Unit
“H” Antenna support + Pole Support for FPKA. 100 % 1 lot
Fixing accessories 100 % 1 lot
Brackets according to site design for existing tower/pole 100 % 1 lot
Service
Installation on site
Cable tray system on an existing tower
Site supervision and the project management
Excludes
Existing tower structure survey , tower strenth analysis and design for installing new cable
tray
Material
Supply of:
Vertical cable tray system (30 cm wide)
Fixing accessories
Bill of Quantities
Component description Occ. Qnt Unit
Vertical cable tray system (30 cm wide) 100 % 1 m
Fixing accessories 100 % 1 lot
Service
Finishing the site area according to the specifications and site specific detailed design
This service covers all works and Material related to surface finishing and final cleaning
Site supervision and the project management
Excludes
Access road and vehicle turn around area
Service
Finding and gathering of information and existing design documents of the existing tower
Detailed construction works design including construction details, power supply,
mechanical, electrical, foundation and topographic design with bill of quantities of materials
Participation in Technical Site Survey and preparation of Technical Site Survey Report
Preparation of permitting designs and documents if needed
Preparation of as-built drawings after completion of all site works
Excludes
Electrical board design
Telecom installation planning
Strength analysis for existing tower
Tower member size measurements
Ground investigation
Strengthening design of the existing tower structures
Design of an eventual reinforce of existing tower foundation
Excludes
Actual site design for an existing tower site
Service
Obtaining all needed information
Finding and gathering of information and existing design documents of the existing tower (if
applicable)
Measuring of an existing tower members on site required for further clarification of tower
strength in accordance with local codes and regulations including all measurement
equipment
Carring out structural calculations for an existing tower in accordance with local codes and
regulations
Preparation of a report
Structural strengthening design
Excludes
Actual site design for an existing tower site