Cost and Quuoted Price of GC & Ex using Labour Hours

GC EX
Material $3,500 $8,000
Labour 4500 $7,500
Overheads 3000 5000
hours
Cost $11,000 $20,500

Required Profit $5,500 $10,250

Quoted Price $16,500 $30,750

Cost and Quoted Price of GC & EX using ABC Costing


GC EX
Material 3500 8000
Labour 4500 7500
Overheads 3500 8000

Cost 11500 23500

Required Profit 5750 11750

Quoted Price 17250 35250


Hours
Working for Overheads

GC EX Budgeted OH 400000
300 500 Total Hours 40000

OAR 10

Working for Overheads

Activity-Cost driver Activity Based Rate GC EX


Supervisor-Site Visits 180 180 1080
Planners-Planning documents 280 280 1400
Property related-Labour hours 6 1800 3000

Total 2260 5480