PERT Analysis Calculator: Time Estimates Critial Path Tasks Optimistic Typical Pessimistic Te
PERT Analysis Calculator: Time Estimates Critial Path Tasks Optimistic Typical Pessimistic Te
Time Estimates
Critial Path Tasks Optimistic Typical Pessimistic Te
Survey 4 5 7 5.17
Traffic Design 25 30 40 30.83
Approve Design 75 80 90 80.83
Drainage 20 30 45 30.83
Bid Proposal 8 10 12 10.00
Sum 157.67
Enter Desired Completion Time 160
Probability of Completion (%) 66.35%
or
1 Std Dev variance
0.50 0.25
2.50 6.25
2.50 6.25
4.17 17.36
0.67 0.44
10.33 30.56