WELL TESTING EQUIPMENT LAY OUT

Client: Repsol Well:


Field: Test: DST 1

Vent line Vent line


3" 10K
Flowhead

RIG FLOOR ESD 6" Flame arrestor

PSV

Kill line
100 Bbl Gauge tank
Twin compartment
Pneumatic Transfer Pump

Fail Safe Valve In


Rig BOP

FSV PANEL

SDV PANEL
3"Data
Header
Choke Manifold
3" 10 KPsi / 2" Choke
Oil Line to Burner Head

Heater Gas line & Relief line to flare pit

ESD
1 1/2" Adj.

Air for Burner Head


Choke box
M
M Oil line

PSV Air Compressors


DST R. Disk
600 C.F.M

Gas
M line

Relief Line to Flare Pit


PSV Vent Line
Horizontal Separator - 1440 psi /
Oil Line 42" x 15ft
Gas Line
Water Line
Fail Safe Valve Control Line Ball Open
Fail Safe Valve Control Line Ball Closed
Air Line for Emergency Shut Down
Hydraulic Line for Safety Valves WORKSHOP WT LAB CABIN DST LAB CABIN

Air for Burner Head