MOHMAND DAM HYDROPOWER PROJECT

TIMELINE

Sr.
Activities Days Date
#
A PC-I
1. Submitted to Planning Commission 60 01.02.2018
2. Expected clearance by CDWP 30 01.04.2018
3. Expected approval by ECNEC 01.05.2018
Total (A): 88
Meeting with Afd Mission regarding financing of the
B 06-07.03.2018
Project
C EIA Public Hearing 31.03.2018
D Appointment of Consultants (By WAPDA) 08.05.2018
E Appointment of Contractor (By WAPDA) 28.05.2018
Land Acquisition
1. Activation of Project office (incl. land acquisition staff) 31 01.06.2018
Initiation of land acquisition process/ meeting with
2. 30 01.07.2018
Political Agent and staff, Mohmand Agency.
3. Joint WAPDA-PA Survey of Project Area 31 01.08.2018
Advance deposit for PA on allotment of land acquisition
4. 31 01.09.2018
of WA
Completion of land acquisition of Project Area & Access
5. 61 01.11.2018
Road
6. Contractor’s mobilization and commencement of works 30 01.12.2018