You are on page 1of 22

SAP Component: Project System

Version: ECC 6.0 R/3


EHP 5.0

Partial Turn Key Scenario


Document on proposed Partial Turn Key Project as per the new guidance from MSEDCL
Table of Contents
1. Case 1. New process/stock available – Division /Circle ...................................................................... 3
1.1 Create project with partial turnkey profile. .................................................................................... 3
1.2 Maintain material in T-code ZPS_HO_POMAT ................................................................................ 5
1.3 Maintain material in ZPS_MR_REQ ................................................................................................. 5
1.4 Maintain centages amount and extra tax amount to project ........................................................ 6
1.5 Budget allocation. ............................................................................................................................ 7
1.5.1 Copy total plan cost to TOP WBS t-code IM52. ........................................................................... 7
1.5.2 Distribute Budget to each WBS.t-code CJ30. .............................................................................. 7
1.5.3 Released budget t-code CJ32. ...................................................................................................... 8
1.6 Project released. T-code CJ20N.................................................................................................... 9
1.7 Material procurement process .................................................................................................. 10
1.7.1 Materials provided by MSEDCL.............................................................................................. 10
1.7.1.1 Stock in division /circle .............................................................................................................. 10
1.7.1.1.1 Create material requisition for MSEDCL materials T-code-ZMM_PROJECT_MR ................. 10
1.7.1.1.2 Approved MR T-code ZMM_PROJECT_MR_APPV ................................................................. 12
1.7.1.1.3 Stock transfer – transfer material from plant storage to project storage location i.e vendor
storage location T-code - ZMM_PR_STKTRF ............................................................................................. 13
1.7.1.1.4 Gate pass – T-code - ZMM_PROJ_GATEPASS. ....................................................................... 14
1.7.2 Materials provided by vendor T-code ZPS_PO ...................................................................... 16
1.7.3 Good Receipt - MRHO ............................................................................................................ 18
1.7.4 Stock view – MBBS ................................................................................................................. 18
1.8 Creation of JMC .......................................................................................................................... 18
1.9 Creation of RABILL ...................................................................................................................... 19
1.10 Invoice creation T-code ZPS_INV ............................................................................................... 20
1.11 Invoice parking – zfi_project_invoice ........................................................................................ 21
1.11.1 Material parking ..................................................................................................................... 21
1.11.2 Centages service service sheet............................................................................................... 21
1.11.3 Centages invoice parking ....................................................................................................... 22
1. Case 1. New process/stock available – Division /Circle
1.1 Create project with partial turnkey profile.

Here we have created three WBS, in which following are data maintains-

- In WBS IF-15-124.01
Materials are supply by Vendor as well as MSEDCL.
- In WBS IF-15-124.02
Materials are supply by MSEDCL
- In WBS IF-15-124.03
Materials are supply by vendor only.
Note : those materials which are supply by MSEDCL, only reservation are
created i.e in procurement assignment WE is selected.

Maintain activity and item no for MSEDCL materials activity.

Note: if activity and item no is not maintain by user, then MSEDCL materials will be not shown while
doing JMC
1.2 Maintain material in T-code ZPS_HO_POMAT
Maintain project in ZPS_HO_POMAT.

Here we can edit unit price of materials which is provided by MSEDCL.

1.3 Maintain material in ZPS_MR_REQ


Here we maintain those materials which need to be generate material request.

Click on all materials as in this case, all materials need to generate material
request.
If MR is require, do
check (tick)

1.4 Maintain centages amount and extra tax amount to project


T-code- CJ40

Maintain centages amount to each WBS for those materials which are provide by
MSEDCL.
1.5 Budget allocation.
1.5.1 Copy total plan cost to TOP WBS t-code IM52.

1.5.2 Distribute Budget to each WBS.t-code CJ30.


Distribute budget to each wbs using select all, copy view, plan total.
1.5.3 Released budget t-code CJ32.
1.6 Project released. T-code CJ20N.

Released the project.

Note : PR will be created for Vendor procure materials.


1.7 Material procurement process
In Partial turnkey process, there are two type of materials procure –

a) Materials provide by MSEDCL


b) Materials provide by vendor

1.7.1 Materials provided by MSEDCL.


Note: In this case materials are in division/circle stock.

1.7.1.1 Stock in division /circle

1.7.1.1.1 Create material requisition for MSEDCL materials T-code-


ZMM_PROJECT_MR
Note: Prior generating MR, user should check whether materials are in stock.
If materials are in respective circle stock, then user should transfer circle stock to respective division.
T-code MB52 for stock view with respective materials.

MR creation t-code ZMM_PROJECT_MR.

Enter supplying plant and supplying store.


Click on save & print.

1.7.1.1.2 Approved MR T-code ZMM_PROJECT_MR_APPV

Enter MR number.
Click on process

1.7.1.1.3 Stock transfer – transfer material from plant storage to project


storage location i.e vendor storage location T-code -
ZMM_PR_STKTRF
1.7.1.1.4 Gate pass – T-code - ZMM_PROJ_GATEPASS.
Print preview –
Stock view – T-CODE MBBS

1.7.2 Materials provided by vendor T-code ZPS_PO


Note: Before PO creation, system will check, if ZPS_PO_HOMAT and ZPS_MR_REQ is maintained for
MSEDCL materials.
Materials PO-4630000571

Centages PO –4630000572

Note: this amount is calculated


from materials provided by
msedcl which is maintain
ZPS_PO_HOMAT
1.7.3 Good Receipt - MRHO

1.7.4 Stock view – MBBS

1.8 Creation of JMC


JMC Created with JMC number : IF-15-124-MJ0001
Note: Here last two line item are material provided by MSEDCL.

1.9 Creation of RABILL


RABill Created with RABill number : IF-15-124-RA0001

Here last two materials are provided by MSEDCL which is not editable field.
Note: RAbill amount is sum of materials provided by vendor only.

1.10 Invoice creation T-code ZPS_INV


Note :Here centages amount of those material which provided by MSEDCL is also included.

Invoice has been Created with Invoice number : IF-15-124-IV0001

1.11 Invoice parking – zfi_project_invoice


1.11.1Material parking

Document 5105601552 Has Been Parked.

1.11.2Centages service service sheet


Note: here service sheet will be created for both line item i.e for MSEDCL and vendor materials.
1.11.3 Centages invoice parking

Document 5105601554 Has Been Parked