Sundram Fasteners Ltd

Autolec Division , Plant - 2 Date: 07.08.2019

SUPPLIER ASSESMENT REPO


Supplier Name : SVPC AUTOMOTIVE PVT LTD

Location : AMBATTUR INDUSTRIAL ESTATE

Address: G12, I MAIN ROAD , AMBATTUR INDUSTRIAL ESTATE , CHENNAI 5

Email Id: gunaseelan@svpcindia.com


Phone: & Fax no:
Product Comodity: PRESS COMPONENTS & MACHINING COMPONENTS
M
Name Of Partners/Directors/Proprietors :

Responsible Person For Quality : Mr.Balasubra

Responsible Person For Delivery : Mr.Muthu

Responsible Person For Price : Mr.T

Classification : Micro/ Small/ Large Scale;

Industrial Reg. Details :

CST Reg. No:

Banker's Details;

Statutory consents/ PCB approval which ever applicable:

QMS Certification details;

Last Year Turn Over;


Page 2 of 22

Total working persons;

Company covering PF/ESI :

Major Customer details:

Purpose of Assessment Sco


New supplier for new product

New supplier for existing product > 80

Existing supplier for new product 60 ~ 80%

Existing supplier for new location < 60

Status of Assessment :
Page 3 of 22

Approved by CFT
QAD Function
Engineering function
Materials
* Minimum Applicable System Certification is : ISO 90

System & Process assessment Checklis


Guide lines for rating
Points Criteria in the event Impact of
0 Not aware of the requirements/System not available Major Non-conformanc

Aware of the requirements but not met/System not followed when Minor Non-conforman
1
audited immediate action
Opportunity for impro
2 System is present but is not maintained.
potential for betterme

3 System is present and requirements satisfactorily met. Requirements fully met

NA Element Not Applicable (for Current Product/ process/System) Does not impact Audit

Ratin
Check Point/ Assessment Element
g
A Quality Management System

Does the Supplier holds a valid QMS certification?


1 3
(ISO: 9001 ; 2015/IATF 16949 ; 2016 / Equivalent)

Does the Supplier has documented QMS Manual/Procedure &


2 3
Quality policy ?

Does the Supplier Has documented Organizational Chart with


3 3
er - Organization Basic Requirements

clearly defined roles & responsibilities?

B Government/ Legal/ Statutory Compliance

Does the Supplier complying to the Govt., Legal, Safety &


1 Environmental regulations applicable for the supply of products? 3

Does the supplier obtained relevant statutory approval from


2 competent authorities ? 3
If yes, then validity/ renewal period of approval must be noted.
Supplier - Organization Bas
Page 4 of 22

Does the supplier use any restricted and hazardous substance in


3 manufacturing location? 3
If yes, ensured concerned authority approval & adequate controls?

C Safety

Does the work force adequately trained in the awareness on Safety


1 3
& Environment?

Does the work force provided with appropriate PPE's to perform


2 3
safe work?

Does the supplier has clear floor layout with location of Fire
3 3
extinguisher & Emergency exit identification?

D Environmental requirements
Supplier - Organization Basic

Does the supplier complying to the customer specific requirement


1 3
Requirements

with respect to Environment?

Is there a definite plan & practice for Waste minimisation and


2 3
continual improvement?

Does the Effluent generated by the process properly treated &


3
disposed?
Page 5 of 22

E Customer focus

Does the Supplier has adequate information with respect to


1 Customer Specific Quality Requirements for the parts which they 3
produce?

Does the Supplier has a documented for customer complaint


handling ?
2 3
If Yes, do the procedure insist for quick response & initiation of
containment actions?

Does the Supplier analyse the non-conformance to identify the root


3 cause and submitted corrective/ preventive actions in 3
G8D/equivalent format ?

F Management review & performance monitoring


Supplier - Organization Basic Requirements

Does the Supplier has a system for Management review of operating


1 results in terms of PQCDSM ? 3
If Yes, mention frequency & latest revision date.

Does the supplier align with SFL Rating System based on


2 quality/delivery performance/severity/impact of concern and submit 3
action plan for improvement?

Does the Supplier work for continual improvement in terms of


3 3
Productivity, Quality, Cost, Delivery, Safety , Morale & 5S ?

G Resource management

Does the Supplier maintain a list of qualified operators/ Inspectors


1 with back up of their skill assessment/ Monitoring system? 3
(Should cover Contract Labours also)

Does the Supplier have a training plan/ training calendar for there
employees?
2 3
If yes, then is it covers both Functional /System subjects to satisfy
SFL requirements ?

Does the Supplier has a documented contingency plan in case of any


3 emergency in terms of Man, Machine and Material so that customer 3
line should not affected ?

Over All Rating ( Average of A to G)

A Control of Documents & Records

Does the Supplier maintain the Parts design documents such as


1 Drawings, Specification, Approved Process flow, Control plan, 3
Requirements

Inspection report format etc. In latest revision level ?


Page 6 of 22

Quality Management System Basic Requirements


Does the Supplier have a system to maintain the records like PPAP,
2 Inspection reports, Tooling, Purchase order etc.; for all of the active 3
parts?

Does the Documents & Records preserved in proper manner so that


3 3
they are readily retrievable in good condition on customer request?

B Control on monitoring & measuring equipments

Does the Supplier have a system of periodic calibration of gauges &


1 instruments? 3
Does the calibration records are maintained?

Whether calibration traceable to National/ International standards?


2 (External Calibration agency shall be accredited to ISO/IEC 17025 3
or equivalent)

Does Supplier have adequate system for handling, storage and


3 3
preservation of inspection, measuring & test equipments?
Page 7 of 22

C Production Part Approval Process (PPAP)

Does the Supplier submitted PPAP (As per latest AIAG-PPAP


1 3
manual) for automotive application parts?

Does the supplier enclosed essential PPAP documents like Drawing,


2 PFD, PCP, PFMEA , Gauge Plan, Inspection records, SPC, PSW 3
etc.; ?

Are the PPAP records and master samples available and approved
3 3
and preserved well as agreed with customers?

D PFMEA

Does the Supplier prepared & documented Process FMEA's as per


1 latest revision of AIAG Manual for all the parts manufactured ? 3
Quality Management System Basic Requirements

Does the actions initiated considering Severity, Occurrence and


2 3
Detection rating to bring down the RPN?

Does the Supplier has a practice periodic review PFMEA to address


3 3
any 4M change or improvements?

F Process Control Plan

Does the Supplier developed a Control Plan (Part/Family wise) for


production Parts ?
1 3
If yes, does it contains Process & Product characteristics,
measure/monitoring method, frequency and Reaction Plan ?

Does the Critical/ Special Characteristics and Customer specific


2 3
Requirements addressed properly?

Does the Supplier has a practice review Control plan in line with any
3 2
4M change ?

G Standard Operating Procedure (SOP)

Does the Supplier developed Work Instructions (WI) Or Standard


1 Operating Procedure (SOP) for production Parts ? (Part/Family 3
wise)

Does the most recent WI/SOP displayed in each work stations and
2 3
Operators understanding & following it?

Is the SOP adequately addressed with reaction plan & abnormality


3 3
handling procedure? (Do's & Don't Do's)

Over All Rating ( Average of A to G)


Page 8 of 22

Material identification, handling &


A Raw Material Receiving & Inspection

Is there a procedure available for Raw material/ Child Part


1 3
receiving, Inspection & Approval?
Storage

Does the supplier buy material from approved sources by customer


2 and whether it comes with Mill Sheet/ Raw Material Test 3
Certificate?

Is Incoming Material Identification is done ( Before Inspection &


3 3
After Inspection) ?
Page 9 of 22

B Material Handling & Storage

Are the Work Instructions / standards for the Material Handling &
1 storage available and are displayed ? 3
If yes, does the FIFO system & Minimum stock levels defined in it?

Does the material stored with proper identification & proper manner
Material identification, handling & Storage

2 3
to ensure free from dust, dirt, damage and mix-up?

Is Material Lot Control/ Issue control procedure is available ?


3 3
And is there a responsible person allotted to monitor it?

C Part Identification & Traceability

Does the Supplier identify the parts from material receiving stage till
1 Delivery to customers with appropriate traceability? 3
(Route Card/ Tag System)

Does the traceability system includes Part Information's, RM details,


2 Manufacturing information and Part handling/ Preparedness 3
information's?

Does the Supplier have system to highlight 4M change details - with


3 special identification shall be made for to pay attention and details 3
on changes to be mentioned?

Over All Rating ( Average of A to C)

A Inprocess Quality Control

Does the Supplier has effectively implemented Control Plan for the
parts which they produce?
1 3
If yes, then is there records for Set-up/ First Off approval and
monitoring product & process parameters?

Does the Supplier has implemented error proofing/ POKA YOKE to


2 ensure product/ process quality? 3
If yes, then its effectiveness is it periodically monitored & recorded?
anufacturing system basic requirements

Does the supplier use Statistical tool for monitoring and controlling
3 process and product capability for Critical, Key and Major 3
characteristics as designated by Customer in drawing?

B Control of Nonconforming parts

Does the Supplier identify a non-conforming part "Rejected


1 3
tag/Colour Marking/as per requirement" with defect information ?

Does the Rework/Containment is done periodically with approval of


2 3
designated authority ?
Does the supplier analyse the rejection data and initiate actions to
3 control it? 3
Manufacturing sy
Page 10 of 22

C Final Inspection & Packing

Is there a dedicated location to carry out final inspection &


1 3
Packaging ?

Does the Supplier follow customer recommended packing


2 methods/ standards? 3
If yes, then is it comply part number identification, quantity details ?

Is there a dedicated location for the storage of Finished products by


3 ensuring proper identification & also free from dust,dirt,damages & 3
Mix-up?
Page 11 of 22

D Tool & Die management

Is there a proper location for Tool/Die/Mould storage with proper


1 identification? 3
If yes, then is it easily accessible & properly maintained?
Manufacturing system basic requirements

Does the supplier has a documented procedure for Tool life


2 3
monitoring, Improvement ?

Does the supplier maintains history cards/ reports for each tools
3 3
with life monitoring & service/maintenance details?

E Equipment/ Machine Maintenance

Does the supplier has a master list of machines/equipment & its


preventive maintenance plan?
1 3
If yes , then does supplier maintain records for preventive
maintenance of machines?

Whether the Supplier has a system of recording breakdowns &


2 3
maintaining machine history?(Suggest tracking of MTTR & MTBF)

3 Does the Supplier maintain stock of essential/ Critical Spare 3


parts for machines?

Over All Rating ( Average of A to E)

Total Rating

Risk Medium
Evaluation Low Risk Risk

Quality

Delivery

Statuary/
Regulatory
Page 12 of 22

SFL/AD/ Rev: 03 , Date: 09.07.2018

Date: 07.08.2019

ER ASSESMENT REPORT
LTD

ATE

INDUSTRIAL ESTATE , CHENNAI 58

& MACHINING COMPONENTS


Mr..Thirunavukarasu
Mr.T.Rajkumar
Mr.T.Gunaseelan

Mr.Balasubramnian - Quality Mnager & MR

Mr.Muthupandi - Production Incharge

Mr.T.Gunaseelan- Director

Small
Page 13 of 22

Score of Evaluation*

> 80 % - Fully approved Supplier

60 ~ 80% - Conditionaly approved Supplier

< 60 % -Barred approved Supplier


Page 14 of 22

licable System Certification is : ISO 9001:2015

& Process assessment Checklist


Guide lines for rating
Impact of score with respect to event
Major Non-conformance- since requirements not met & disqualified

Minor Non-conformance- since requirements not met & needs


immediate action
Opportunity for improvement - Requirements met, but still there has
potential for betterment

Requirements fully met - System is error proof & process is robust

Does not impact Audit Score

Observations/ Comments
Page 15 of 22
Page 16 of 22
Page 17 of 22
Page 18 of 22
Page 19 of 22
Page 20 of 22
Page 21 of 22
Page 22 of 22

High Risk