Scheduling/Leveling Report - 2019-09-29 06:25:47 - PM.

exe
=========================================================

Default Project..................................................T 18 MZEC

Projects:
T 18 MZEC........................................................33KV
OHL WORK

Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retained
Logic
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish Float
Calculate float based on finish date of .........................Each project
Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar

Advanced
--------
Calculate multiple float paths...................................No

Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................124
# Not Started....................................................124
# In Progress....................................................0
# Completed......................................................0
# Relationships..................................................158
# Activities with Constraint.....................................0

Errors:
-------
Warnings:
---------
Activities without predecessors..................................1
Project: T 18 MZEC Activity: M1000 MILE STONE START

Activities without successors....................................38


Project: T 18 MZEC Activity: DEP100 DISMANTLING 33KV POLES&
ACCESSORIES RETUR TO MZEC
Project: T 18 MZEC Activity: DEP200 DISMANTLING EXIST POLE &
RETURN TO MZEC
Project: T 18 MZEC Activity: ELG150 INSTALLATION OF CABLE
GUARD
Project: T 18 MZEC Activity: ELW220 INSTALLATION OF LA
Project: T 18 MZEC Activity: ES100 DC TOWER ERECTION
Project: T 18 MZEC Activity: ETW130 INSTALLATION OF SAFETY
ACCESSORIES (Aircraft Light,Danger plates etc)
Project: T 18 MZEC Activity: MP1000 PROCUREMENT OF MEDIUM
POLE
Project: T 18 MZEC Activity: MP1010 PROCUREMENT OF
INTERMEDIATE POLE
Project: T 18 MZEC Activity: MP1020 PROCUREMENT OF RIGHT
ANGLE THREE POLE
Project: T 18 MZEC Activity: MP1030 PROCUREMENT OF TERMINAL
CONCRETE POLE
Project: T 18 MZEC Activity: MP1040 PROCUREMENT OF FIBER
GLASS STAY WIRE
Project: T 18 MZEC Activity: MP1050 PROCUREMENT OF CABLE
POST INSULATOR SUPPORT ASSEMBLY
Project: T 18 MZEC Activity: MP1060 PROCUREMENT OF CABLE
SUPPORT ASSEMBLY
Project: T 18 MZEC Activity: MP1070 PROCUREMENT OF OUTDOOR
TERMINATION WITH EARTHING KIT
Project: T 18 MZEC Activity: MP1080 PROCUREMENT OF ABS WITH
INSULATOR
Project: T 18 MZEC Activity: MP1090 PROCUREMENT OF LIGHTNING
ARRESTORS& INSULATOR
Project: T 18 MZEC Activity: MP1100 CABLE STRAIGH THROUGH
JOINT
Project: T 18 MZEC Activity: MP1110 PROCUREMENT OF H
SECTION POLE
Project: T 18 MZEC Activity: MP2010 PROCUREMENT OF CIVIL
MATERIAL
Project: T 18 MZEC Activity: MP2020 PROCUREMENT OF TOWER
ACCESSORIES
Project: T 18 MZEC Activity: MP2030 PROCUREMENT OF EARTH
SHEILD WIRE
Project: T 18 MZEC Activity: MP2040 PROCUREMENT OF SHEILD
WIRE HARD WIRE FITTING
Project: T 18 MZEC Activity: MP2050 PROCUREMENT OF SAFETY
ACCESSORIES
Project: T 18 MZEC Activity: MP2060 COMPLETION OF MATERIAL
PROCUREMENT
Project: T 18 MZEC Activity: MP3000 PROCUREMENT OF H
TERMINAL POLE WITH INSULATOR
Project: T 18 MZEC Activity: MP3060 COMPLETION OF MATERIAL
PROCUREMENT
Project: T 18 MZEC Activity: MP4000 PROCUREMENT OF 200MM DIA
HDPE PIPE
Project: T 18 MZEC Activity: MP4010 PROCUREMENT OF EARTH
MATS FOR ABS
Project: T 18 MZEC Activity: MP4020 PROCUREMENT OF EARTHING
MATERIAL & INSPECTION CHAMBER
Project: T 18 MZEC Activity: MP4030 PROCUREMENT OF
ADDITIONAL EARTHING MATERIAL
Project: T 18 MZEC Activity: MP4040 PROCUREMENT OF CABLE
COVER TILES
Project: T 18 MZEC Activity: MP4050 PROCUREMENT OF CABLE
ROUTE MARKER
Project: T 18 MZEC Activity: MP4070 COMPLETION OF MATERIAL
PROCUREMENT
Project: T 18 MZEC Activity: MP5000 PROCUREMENT OF 33KV
CABLE SUPPORT ARRANGEMENT
Project: T 18 MZEC Activity: MP5010 PROCUREMENT OF ABS
Project: T 18 MZEC Activity: MP5030 COMPLETION OF MATERIAL
PROCUREMENT
Project: T 18 MZEC Activity: TC180 MILESTONE FINISH
Project: T 18 MZEC Activity: UG200 CORE CUTTING IN CONCRETE WALL

Out-of-sequence activities.......................................0

Activities with Actual Dates > Data Date.........................0

Milestone Activities with invalid relationships..................0

Finish milestone and predecessors have different calendars.......0

Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................124
# Relationships with other projects..............................0
Data Date........................................................04-Aug-19
08:00 AM
Earliest Early Start Date........................................04-Aug-19
08:00 AM
Latest Early Finish Date.........................................25-Apr-20
05:00 PM
Exceptions:
-----------
Critical Activities..............................................23
Project: T 18 MZEC Activity: CWEP100 PIT EXCAVATION
Project: T 18 MZEC Activity: CWEP110 SHIFTING OF POLES TO
MARKED LOCATION
Project: T 18 MZEC Activity: CWEP120 DRESSING OF POLES
Project: T 18 MZEC Activity: CWEP130 INSTALLATION OF POLES
Project: T 18 MZEC Activity: CWEP140 PIT EXCAVATION FOR STAY
Project: T 18 MZEC Activity: CWEP150 INSTALLATION OF FIBRE
GLASS WIRE
Project: T 18 MZEC Activity: CWEP160 INSTALLATION OF POLE
ACCESORIES
Project: T 18 MZEC Activity: ELW100 STRINGING OF ACSR
PANTHER CONDUCTOR
Project: T 18 MZEC Activity: KM1000 MEETING WITH MZEC CLIENT
Project: T 18 MZEC Activity: M1000 MILE STONE START
Project: T 18 MZEC Activity: MA1000 MATERIAL APPROVAL SHEET
APPROVAL
Project: T 18 MZEC Activity: MP1120 PROCUREMENT OF H TERMNAL
POLE
Project: T 18 MZEC Activity: MP1130 COMPLETETION OF
MATERIALS DELIVERY TO YARD
Project: T 18 MZEC Activity: RO1000 OMANTEL APPROVAL FOR
EXCAVATION PERMIT
Project: T 18 MZEC Activity: RO1050 MINISTRY OF
MUNICIPALITIES APPROVAL FOR EXCAVATION
Project: T 18 MZEC Activity: TC110 ALL TESTING OF CABLES AFTER
TERMINATION & JOINING
Project: T 18 MZEC Activity: TC120 MZEC WITNESS TEST
Project: T 18 MZEC Activity: TC130 SCADA WITNESS TEST
Project: T 18 MZEC Activity: TC140 CLERANCE FOR ENERGISATION
Project: T 18 MZEC Activity: TC150 ENERGISATION OF 33KV FEEDER
Project: T 18 MZEC Activity: TC160 DEMOBILIZATION AND HAND OVER
Project: T 18 MZEC Activity: TC170 AS BUILD DRAWING SUBMITTAL
Project: T 18 MZEC Activity: TC180 MILESTONE FINISH

Activities with unsatisfied constraints..........................0

Activities with unsatisfied relationships........................0

Activities with external dates...................................0