Professional Documents
Culture Documents
Sched Log
Sched Log
exe
=========================================================
Projects:
T 18 MZEC........................................................33KV
OHL WORK
Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retained
Logic
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish Float
Calculate float based on finish date of .........................Each project
Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar
Advanced
--------
Calculate multiple float paths...................................No
Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................124
# Not Started....................................................124
# In Progress....................................................0
# Completed......................................................0
# Relationships..................................................158
# Activities with Constraint.....................................0
Errors:
-------
Warnings:
---------
Activities without predecessors..................................1
Project: T 18 MZEC Activity: M1000 MILE STONE START
Out-of-sequence activities.......................................0
Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................124
# Relationships with other projects..............................0
Data Date........................................................04-Aug-19
08:00 AM
Earliest Early Start Date........................................04-Aug-19
08:00 AM
Latest Early Finish Date.........................................25-Apr-20
05:00 PM
Exceptions:
-----------
Critical Activities..............................................23
Project: T 18 MZEC Activity: CWEP100 PIT EXCAVATION
Project: T 18 MZEC Activity: CWEP110 SHIFTING OF POLES TO
MARKED LOCATION
Project: T 18 MZEC Activity: CWEP120 DRESSING OF POLES
Project: T 18 MZEC Activity: CWEP130 INSTALLATION OF POLES
Project: T 18 MZEC Activity: CWEP140 PIT EXCAVATION FOR STAY
Project: T 18 MZEC Activity: CWEP150 INSTALLATION OF FIBRE
GLASS WIRE
Project: T 18 MZEC Activity: CWEP160 INSTALLATION OF POLE
ACCESORIES
Project: T 18 MZEC Activity: ELW100 STRINGING OF ACSR
PANTHER CONDUCTOR
Project: T 18 MZEC Activity: KM1000 MEETING WITH MZEC CLIENT
Project: T 18 MZEC Activity: M1000 MILE STONE START
Project: T 18 MZEC Activity: MA1000 MATERIAL APPROVAL SHEET
APPROVAL
Project: T 18 MZEC Activity: MP1120 PROCUREMENT OF H TERMNAL
POLE
Project: T 18 MZEC Activity: MP1130 COMPLETETION OF
MATERIALS DELIVERY TO YARD
Project: T 18 MZEC Activity: RO1000 OMANTEL APPROVAL FOR
EXCAVATION PERMIT
Project: T 18 MZEC Activity: RO1050 MINISTRY OF
MUNICIPALITIES APPROVAL FOR EXCAVATION
Project: T 18 MZEC Activity: TC110 ALL TESTING OF CABLES AFTER
TERMINATION & JOINING
Project: T 18 MZEC Activity: TC120 MZEC WITNESS TEST
Project: T 18 MZEC Activity: TC130 SCADA WITNESS TEST
Project: T 18 MZEC Activity: TC140 CLERANCE FOR ENERGISATION
Project: T 18 MZEC Activity: TC150 ENERGISATION OF 33KV FEEDER
Project: T 18 MZEC Activity: TC160 DEMOBILIZATION AND HAND OVER
Project: T 18 MZEC Activity: TC170 AS BUILD DRAWING SUBMITTAL
Project: T 18 MZEC Activity: TC180 MILESTONE FINISH