2029-Pj-Jha-015 Re 01-CRS
2029-Pj-Jha-015 Re 01-CRS
Revision. 1 Revision. 2
Sr.
No.
ORPIC / PMC Comment EPC Resolution / Response ORPIC / PMC Comment EPC Resolution / Response
1. Preparation of Anti Termite Solution:
The entire employee shall be
provided with complete PPE
The entire employee shall attend
special induction training to
understand with all associated
hazards with the work
All the workers shall provide the
adequate tools and equipment to
carry out the job safely
1.
Material / suppliers shall be obtain
approved
Emergency Contact numbers shall
be displayed at site.
Eye wash facility shall be available
in case of accidental splash of
PM-Projects, PR-Process, MK-Mechanical, PP-Piping, EL-Electrical, CA -Control & Automation, CL-Civil, TL-Telecom, QA: QAHSE
/conversion/tmp/scratch/440612843.doc Page 1 of 3
Project Name EPC FOR REVAMP OF OIL PIER AT PORT OF SALALAH Reviewed on : 1-11-2016
MMC Project Number 364551OM01 Approval Code
Ref. Document Number : 2029-PJ-JHA-015 Rev.: 01
Ref. Document Title : JHA FOR ANTI TERMITE APPLICATION. Reviewed by : Abraham / Tarique
Revision. 1 Revision. 2
Sr.
No.
ORPIC / PMC Comment EPC Resolution / Response ORPIC / PMC Comment EPC Resolution / Response
PM-Projects, PR-Process, MK-Mechanical, PP-Piping, EL-Electrical, CA -Control & Automation, CL-Civil, TL-Telecom, QA: QAHSE
/conversion/tmp/scratch/440612843.doc Page 2 of 3
Project Name EPC FOR REVAMP OF OIL PIER AT PORT OF SALALAH Reviewed on : 1-11-2016
MMC Project Number 364551OM01 Approval Code
Ref. Document Number : 2029-PJ-JHA-015 Rev.: 01
Ref. Document Title : JHA FOR ANTI TERMITE APPLICATION. Reviewed by : Abraham / Tarique
PM-Projects, PR-Process, MK-Mechanical, PP-Piping, EL-Electrical, CA -Control & Automation, CL-Civil, TL-Telecom, QA: QAHSE