Professional Documents
Culture Documents
Specific-performance
Specific performance
Definition
When a court directs a party to perform the obligation imposed on it. Usually in the context of a
contract.
The parties’ rights are settled and defined in the manner intended
Hasham v Zenab court can still give orders for SP even if time of performance of contract has yet to
arrive.
General principle
1. Discretionary remedy
o Decreed by a court solely at its discretion and not as a matter of right
o Not given at the whim or pleasure of the judge but upon sound and reasonable discretion and
reasoning.
o S21 of SRAThe jurisdiction to decree specific performance is discretionary, and the court is
not bound to grant any such relief merely because it is lawful to do so; but the discretion of the
judge is not arbitrary but sound and reasonable, guided by judicial principles and capable of
correction by a court of appeal.
o Ganam d/o Rajamany v Somoo s/o Sinniah
It is under the discretionary of the courts to grant specific performance; and all of the
circumstances of case, the conduct of parties and their respective interest must be taken
into consideration
o Lamare v Dixon
The defendant wished to lease some cellars. He went to view cellars owned by the
claimant but saw that they were damp.
The claimant promised that he would make the cellars dry before the lease commenced
and the defendant agreed orally to take the lease.
The claimant did not keep his promise and the defendant refused to complete the lease.
The claimant bought an action for breach of contract seeking specific performance of the
lease agreement.
Specific performance was refused due to the claimant not keeping his promise in making
the cellars dry.
o Exercise of discretion to withhold SP mainly in cases involving delay, hardship, mistake or
conduct of the plaintiff
o S.21(2)(a)where the circumstances under which the contract is made are such as to give the
plaintiff an unfair advantage over the defendant, though there may be no fraud or
misrepresentation on the plaintiff’s part; and
o S21(2)(b) where the performance of a contract would involve some hardship on the defendant
which he did not foresee, whereas its non-performance would involve no such hardship on the
plaintiff.
o Wong Kup Sing v Jeram Rubber Estate Ltd
High Court held that the defendants had failed to give reasonable notice to the plaintiff
that it intended to terminate the contract after having agreed to an extension of time for
performance in a contract for the purchase of a rubber estate.
o S18(1)Any person suing for the specific performance of a contract may also ask for
compensation for its breach, either in addition to, or in substitution for, its performance.
o S18(2) If in any such suit the court decides that specific performance ought not to be granted,
but that there is a contract between the parties which has been broken by the defendant and that
the plaintiff is entitled to compensation for that breach, it shall award him compensation
accordingly.
o S.19A contract, otherwise proper to be specifically enforced, may be so enforced, though a
sum be named in it as the amount to be paid in case of its breach, and the party in default is
willing to pay the same.
o Ibrahim bin Saidin v Hitam bin Ali
existence of damages as compensation does not prohibit the party from applying to the
court for specific performance
o s13Where a party to a contract is unable to perform the whole of his part of it, but the part
which must be left unperformed bears only a small proportion to the whole in value, and admits
of compensation in money, the court may, at the suit of either party, direct the specific
performance of so much of the contract as can be performed, and award compensation in money
for the deficiency.
o S. 14Where a party to a contract is unable to perform the whole of his part of it, and the part
which must be left unperformed forms a considerable portion of the whole, or does not admit of
compensation in money, he is not entitled to obtain a decree for specific performance. But the
court may, at the suit of the other party, direct the party in default to perform specifically so
much of his part of the contract as he can perform, provided that the plaintiff relinquishes all
claim to further performance, and all right to compensation either for the deficiency, or for the
loss or damage sustained by him through the default of the defendant.
Litern said nothing when his wife (who had no authority to do so) entered into a
contract or the sale of Litern’s house, and, as a result, the buyers incurred various
expenses in contemplation to completion of the sale-
Litern’s silence amounted to a representation that his wife had authority to sell the
house
Worboys v Carter
Carter (P) owned the lease on Lower Ledge Farm. His business was in trouble and
the farm became run down.
Clark(A) offered help and advised selling the farm lease but Carter objected the
idea
In the event, Clark persuaded him to sign a document which did no more than
appoint Clark as his agent.
Clark mistakenly thought that this gave him authority to sell the farm and he went
ahead with the sale to Worboys.
Worboys then requested of Cater several occasions a date by which Carter might
vacate the farm but carter would not give it.
Worboys measure up Lower Ledge Farm in Carter’s presence and to the
knowledge of Carter, Worboys sold his own farm on the expectation of moving to
Lower Ledge Farm.
Carter confined his objections to the sale to his agent Clark and Worboys sued for
SP
Held that Clark had no actual or apparent authority to sell the property but the
Carter’s conduct in the presence of Worboys amounted a representation that he
approved of the sale.
Carter was estopped from denying the contract and SP granted
o Sky Petroleum Ltd v V.I.P. Petroleum Ltd
Injunction can be obtained on an interlocutory basis, while SP cannot.
7. Considerations of “hardship” and expiry of “limitation period” may not necessarily defeat SP
o RM. Venkatachalam Chettiar v N.K.R. Arunasalam Chettiar
8. SP dependant on an option is unaffected if the option is not exercised strictly in the prescribed manner
o Kau Nia Enterprise (Pte) Ltd v Teck Wah Corporation (Pte) Ltd
Specific performance dependant on an option is unaffected if the option is not exercise
strictly in the prescribe manner
9. SP may be claimed and granted even before the time of performance has arrived
o SP may in some circumstances be obtained before the time for performance arriving
o Marks v Lilley
Claimant commenced an action for the SP of a contract for sale of land after contractual
completion date but without having first served notice making time of the essence of the
contract.
It was held that the action not premature , as the equitable right to SP, based on the
defendant’s equitable duty to perform his contract, had already accrued
o Hasham v Zenab
SP of a contract for the sale of land was granted before the contractual completion date
where the defendant was guilty of anticipatory breach of contract.
o Courts do not normally interfere before the time for performance, and may penalise the claimant
in costs.
the specific performance of so much of the contract as can be performed, and award
compensation in money for the deficiency.
Wong Siew Choong Sdn Bhd v Anvest Corp Sdn Bhd
- App is the registered owner of all the land.
- A dispute arose over the transfer of the said land, the resp had claim for specific
performance and damages.
- Court held: As the payment had been made by the Resp for the purchased land, the
beneficial ownership of the remaining land would pass to the Resp
Where part unperformed is large
S.14Where a party to a contract is unable to perform the whole of his part of it, and
the part which must be left unperformed forms a considerable portion of the whole, or
does not admit of compensation in money, he is not entitled to obtain a decree for
specific performance. But the court may, at the suit of the other party, direct the party in
default to perform specifically so much of his part of the contract as he can perform,
provided that the plaintiff relinquishes all claim to further performance, and all right to
compensation either for the deficiency, or for the loss or damage sustained by him
through the default of the defendant.
Independent part
S. 15 When a part of a contract which, taken by itself, can and ought to be
specifically performed, stands on a separate and independent footing from another part
of the same contract which cannot or ought not to be specifically performed, the court
may direct specific performance of the former part
Odessa Tramways Co v Mendel; Ogden Fossick; City Investment Sdn Bhd v
Kooperasi Serbaguna Cuepacs Tanggungan Bhd
- the parts of the contract that the plaintiff seeks to enforce must be severable from the
whole contract.
-
o Plaintiff’s substantial interest in having the contract performed is such that damages is
insufficient
o Defendant has possession of the land due to the contract
C. a contract the terms of which the court cannot find with reasonable certainty
Cooperative Insurance Society Ltd v Argyll Stores (Holdings) Ltd – relevant clause is as
follows:
o To keep the demised premises open for retail trade during the usual hours of business in
the locality and the display windows properly dressed in a suitable manner in keeping
with a good class parade of shops
Unclear to determine as to whether tenant was doing enough to meet the standards in the clause
Lin Nyuk Chan v Wong Sz Tsin
o The uncertainty must be sufficiently serious, that the court cannot order what the
defendant must specifically do.
D. a contract which is in its nature revocable
Puncak Niaga Holdings Bhd v NS Water Sdn Bhd
o no sense of SP where it will amount to futility.
E. contract made by trustees either in excess of their powers or in breach of their trust;
F. a contract made by or on behalf of a corporation or public company created for special purposes,
or by the promoters of the company, which is in excess of its powers;
G. contract the performance of which … over a longer period than three years
Si Rusa Beach Resort Sdn Bhd v Asia Pacific Hotels Management Pte Ltd
o Agreement has been made between App & Resp.
o Dispute arose between them & Resp applied for interim injunction to restrain app from
interfering in the running hotel. Application was successful – App appeal.
o Held: the learned trial judge was correct in holding judgment but had failed in
considering all material facts that app was in possession of hotel. If status to be maintain
the only order that could be made is to allow the App to continue run the hotel until the
action Is finally litigate
S.27 Specific performance of a contract cannot be enforced against a party thereto in any of the following cases:
A. If the consideration to be received by him is so grossly inadequate, with reference to the state of things
existing at the date of the contract, as to be either by itself or coupled with other circumstances
evidence of fraud or of undue advantage taken by the plaintiff;
Falcke v Gray
Gross inadequacy alone is insufficient a reason for refusal of SP as common law allows
for such valid contracts. However, where elements of fraud or undue influence were
used to obtain the grossly inadequate benefit SP will be denied.
B. if his assent was obtained by the misrepresentation (whether wilful or innocent), concealment,
circumvention, or unfair practices, of any party to whom performance would become due under the
contract, or by any promise of the party which has not been substantially fulfilled
Walter v Morgan
gaining unfair advantage by unfair means may not necessarily void a contract in the eyes
of common law. However, equity requires claimants come with clean hands and may
deny applications for SP.
Blomley v Ryan
contract was set aside as the defendant was placed in a weaker bargaining position due
to his lack of education, advanced age, reduced mental strength on account of his
addiction to rum and that the negotiations took place over a drink of rum rendering the
defendant partly drunk and ill.
C. If his assent was given under the influence of mistake of fact, misapprehension, or surprise:
Provided that, when the contract provides for compensation in case of mistake, compensation
may be made for a mistake within the scope of the provision, and the contract specifically
enforced in other respects if proper to be so enforced
D.