KILN TWO SHELL CHANGE
SAFETY MEASURES AND REQUIRE!
TS
i) MANDATORY site visit must be carried out, otherwise failure to do so will lead to automatic
disqualification
ii) MUST prove to have done similar works in related manufacturing industry
iii) A thorough site risk assessment to be done before commencement of work.
iv) All personnel involved in the job to be safety inducted for familiarisation with the scope of work
and the risks involved
v) A risk assessment board to be availed on site furnished with the permit to work, risk assessment
form, hot work permit and job procedure.
vi) Ensure all electrical connections have been isolated and a Lock out, Try out, Tag out procedure
have been followed before taking over the plant for the job,
vil) A (ool box talk to he held before commencement of every shift to highlight on the new risks
encountered or expected and how to mitigate them,
viii) A person in charge of safety to be identified and be known to all the personnel during every
shift,
ix) A first aid kit to be availed on site at all times and a shift first aider identified.
x) All oxy-acetylene sets to be inspected and tested for leakages before use and hoses to be clear of
falling hot material, sharp edges and dropping debris.
xi) All personnel shall wear the mandatory PPE at all times and ensure use of other relevant PPE,
depending on the nature of work and condition of the work site.
xii) Housekeeping to be done at every stage of work and thoroughly at every close of shift
TOOLS REQUIRED
i) Two sets of combination spanners ranging from No. 17 to 60
ii) 4Nos. 10 Kg, engineering hemmers,
iil) 4 Nos, steel wedges size 40x250x50mm,
ix) 2.Nos. long claw bars.
v) 2Nos.10 tonne by 5 meter chain blocks
vi) 2 Nos. 200 tonnes Jack plus pumps
vii) 1 Nos. Skg Sledge hammer
viii) 4Nos. Taper wedges
CONSUMABLES REQUIRED
i) Skg Cotton rags
ii) Grephite
iii) Grease blocks
iv) Piano wire/ thin manila ropeEQUIPMENT
i) 75 tonne crane
WORKS TO BE ARRANGED BY THE TCML
Unless otherwise specified in the tender documents, the following works shall be arranged by the owner.
i) Space for accommodating all the equipment and components involved in the work.
Provide all technical drawings required.
Provide all the required as per the drawings.
Provide all equipment, consumable items and materials required.
WORKS TO BE ARRANGED BY CONTRACTOR
| TASK NAME: TCML - RK2 HOURS | COSTING PER SECTION ONE
| PROJECT (KSA)
I | SECTION ONE
|
aT
[2 | Pre-shutdown tasks ~2.00 days day | 16
|__| shift
3 Site establishment - Tooling & 16
equipment
[Crane establishment ~TCML 16
3_| Crew medicals & inductions 8
6 _| Flame off 0
T_| Cooling period 8
8_| Install required scaffold~TCME [10
‘9 [Install HTD axial lock~Lockkiln in [5
_| uphit! position a ee eee
10_| Install pre-fabricated shell supports iz
SECTION TWO
COSTING PER SECTION
TWO (KSH)
11 _| Project commencement
12 | Open kiln 0
13_| Loosening of bolts at station One 4
14 | Refractory removal ~ Areas applicable to | 8
shell replacement only
15_| Rotate kiln and mark cut Tine on shell [4
16 | Dismantle the existing tire chairs 8
17_| Dismantle Inlet seal arrangement is
18 | Remove the existing ~ fire sections- 1B
| Station one
[19] Tack shell supports to take weight of 16sections
20 _| Cut shell ~ Two positions simultaneously | 36
25 | Install alignment brackets ~ Both sections | 12
| where applicable
26 | Install new shell ~ Section 2 (inlet) and
secure Station one tire
[27 | Install new shell ~ Section 1 6
28 | Huck bolt the ~ new tire chairs (26 12
chairs)
29 _| Install remaining alignment brackets 12
30_| Align shell sections 12
31 | Weld sections & NDT ~Two positions | 68
simultaneous!
32 | Remove alignment biackets and dress | 8
shell
33_| Final NDT welds & dressed area ofshell_| 6
34 | Weld anchors & prepare the new tire 6
section
| 35 | Install and weld inlet nose segments 48
|__| assembly ~ Rotation of kiln required
36 | Install replacement inlet lamella seal 12
arrangement
37_|_Install scroll plates-12 pes 12
38 | Remove shell support structures 12
39_| Install and weld the 90° lifters & chairs [24
40_| Remove scaffo
41_| Refiactory installation
42 | Installation of bumer & ancillaries
43_| Remove HTD axial lock
44 | Project conclusion and House keeping | 12
45_| Flame on 0
21 | Weld lifting lugs to existing shell & 18 |
[NDT |
22_| Remove shell ~ Section 2 (inlet) 6 |
23 | Remove shell ~ Section 2 (inlet) 6 |
SECTION THREE COSTING PER SECTION
THREE (KSH)
24 | Dress existing shell edge 36
TOTAL PROJECT COST KSH
(SECTION 1,2 & 3)‘The General Arrangement of Kilns is as per Drawing A/0105
Technical
sicit Criteria | Criteria
| a Tender Returnable Proof Format | Weighti | Sub
| aoe ng Weighting
1 Technical criteria 90%
Is your company certified meee
[1 [nea lseinitechanicat? | Ataeh eutent Cetfcete 10% |
z The bidder shall submit copy of
Gas assign tees completion certificates/ un-priced
abcess ae meh P.O. copies in support of above. If
2 | fibrcaion and welding eguzed purchaser may visit tbe one | 40%
Completion Certifieates of | 0£ bidder's client to verify the details |
similar jobs eal galas submitted by the bidder in support of
: past experience as indicated above
i ‘Attach a detailed work schedule for
|] s anni eoncaiat all the activities/work scope (Gannt | 40%
and installation work PI Chart complete with staffing levels).
| Safety criteria 10%
| Does your company have
| competent, trained, safety Arash a valid WIBA for | J 0%
conscious, and insured personnel__| ™
| Total 100%
| Aminimum overall score of 70% will be used to deem the tenderer technically acceptable and anything
below 70% will deem the tenderer technically unacceptableFinancial
DESCRIPTION av UNIT PRICE
@
i. Tender for the Kiln Shell Change 1 | wp sum
z Other Charges [= wresun
[Sub Totals
VAT
|
Total
NB: Site Visit is Mandatory on 19" May, 2017