TEST 2
Dec 2015, sem1 2017 / 18
______________________________________________________________________________
ANSWER ALL QUESTIONS
TOTAL MARKS 40
i. Calculate the UCL and LCL for 3-sigma p-chart using the information given.
(6 marks)
p=85/1500 = 0.057
σ = √(0.057)(0.943)/100 = 0.023
UCLp = 0.057 + 3(0.023) = 0.126
LCLp = 0.057 – 3(0.023) = -0.012 = 0
ii. Defectives from the subsequent three days are 10, 5 and 7. Based on p-chart in part(i),
is the process still in control?
(4 marks)
Defectives for the next three days = 0.10, 0.05 and 0.07. All are between LCL and
UCL, therefore the process in still in control
b) An assembly work consisting of two sequential job elements has been studied by using a
stopwatch approach. The observed times for the job elements are shown in Table 2.
Determine the standard time for the assembly work, with the assumption of a combined
personal delay and fatigue of 20%.
(10 marks)
Table 2
Observation (minutes)
Job 1 2 3 4 5 6 Performance
element rating (%)
A 0.15 0.21 0.18 0.19 0.21 0.17 90
B 0.54 0.55 0.57 0.62 0.49 0.46 100
C 0.33 0.31 0.32 0.75 0.30 0.30 85
i. Determine the optimal order quantity for Ejen Ali action figure
(4 marks)
Q* = √(2DS/H) = √2(2500)(25)/4 = 176.7 = 177
d) You are a retail variety shop owner and one of your fatest moving product (product XB) has
an annual demand of 8000 pieces. Your shop operates 250 days per year, and on average,
delivery of product XB from your supplier takes 3 days.