You are on page 1of 5

Piping 101: 5.2 Plant maintenance: Pressure Vessel Repair http://sgpiping101.blogspot.com/2015/06/52-plant-maintenance-pressure...

Monday, June 1, 2015 About Me

ANG CK
5.2 Plant maintenance: Pressure Vessel Repair
View my complete profile
Operation stage
Operator: Ensure these vessels operates within their specified design limits and measures shall be Index of posts

taken to ensure no overpressure beyond the specified allowable times. Not more than 500h/yr for 1.0 Welcome (2015-01-05)
20% overpressure and not more than 100h/yr for 33% overpressure.
3.1 Piping specifications (2015-01-17)
Mechanical Integrity: Ensure these vessels are constantly monitored on-stream visually, check all 3.2 Valve Spec & Purchase (2016-09-23)
vessel body paint, nozzles, stud bolts, supports and anchors are in good condition without distortion 3.3 Valve types, parts, accessories and application,
or corrosion, inspect under insulation if any suspected damage to insulation are observed and apply (2015-01-29)
suitable non-destructive testing over time time of operation to observe any signs of material failure, 3.4 Insulation (2015-03-29)
especially in processes susceptible to such failure modes. Read API 570 for the recommended 3.5 Stud bolts / Hex nuts and their relation to
inspection intervals and API 571 damage mechanisms for some examples of damages with photos. Flanges (2015-08-04)
3.6 Steam traps (2015-11-28)
4.1 Welding Terminologies (2015-02-09)
Repair stage 4.2 Welding rod, filler wires and materials
(2015-02-19)
What constitutes to a Repair?
4.3 Weld & Fabrication: Non-Destructive Testing
A method to restore the equipment condition to where it can operate safely within the Maximum Allowable Basics (2015-06-12)
Operating Pressure (MAWP) and Allowable operating temperatures. 4.4 Welding discontinuties (2016-12-02)
4.5 Weld & Fabrication: Pressure vessel basics
Adding of nozzles can also constitute to a repair, if (2015-06-06)
- It does not require a reinforcement pad 4.6 Weld & Fabrication: Reviewing PV Elite
- It is smaller than any existing nozzles on the vessel Datasheets (2015-06-06)
5.1 Plant Maintenance: Static Equipment and
typical maintenance jobs (2015-02-19)
Adding of any other nozzles are termed an "Alteration", which usually comes with rerating as the vessel
strength could be significantly reduced. 5.2 Plant maintenance: Pressure Vessel Repair
(2015-06-01)
5.3 Plant Maintenance: MOM Statutory Inspections
(Singapore) (2016-09-24)
Avoiding Repairs 5.4 Plant Maintenance: Valve Repair (2016-04-26)
First thing when problems are identified, management point of view may be safety, cost, operational we don't 5.5 Plant Maintenance: Refractory Repair
know. But these are all the potential problems to avoid a repair, can we actually avoid? (2016-12-02)

The answer is yes, and how do we do it?


Blog Archive
Rerating 2016 (5)
Rerating to a lower MAWP and operating pressure for thinned vessel walls 2015 (13)
for continued operations until minimum thickness is hit again. This is usually
November (1)
the easiest way out.
August (1)
Rerating shall be performed by an Engineer or Manufacturer.
June (4)
Fit For Service Assessments (FFS) 4.3 Weld &
In reference to API 510, Chapter 7, it shows how to assess the pressure Fabrication:
Non-
vessel in damaged condition to extend its life. Not all scenarios are covered, Destructive
they cover only the usual problems for example pitting, localized wall thinning Testing Ba...
and wall thinning near by a weld seam. 4.6 Weld &
If the problem cannot be found in API 510 Chapter 7, move on to API 579-1 Fabrication:
Reviewing PV
or ASME FFS-1 for the full assessment. They come in level 1 to 3, for 1 is Elite Datashe...
simplest and 3 is detailed.
4.5 Weld &
Level 1 are usually performed by End User Engineers, and level 2 and 3 Fabrication:
usually outsourced to software or consultants. Pressure
vessel basics
5.2 Plant
Nevertheless, basic Risk Assessments should at least be carried out to evaluate the Consequence or maintenance:
Probability of a leak before putting the damaged equipment back to service. Pressure
Vessel Repair

Is it hazardous to working persons? March (1)


Is it environmentally harmful ? February (3)
Would it affect operations and customers adversely? January (3)

When are Repairs required?

The number one reason for a repair would be corrective maintenance. This is usually carried out as follows:

[Unplanned] As leakage or damage has been initiated.


[Unplanned] Thinning beyond acceptable thickness, damage is unsafe for continued
operation, rerating is not possible and FFS assessment fails,
[Planned] Equipment suffers from damages which can last till the next outage

1 dari 5 25/05/2019 12.28


Piping 101: 5.2 Plant maintenance: Pressure Vessel Repair http://sgpiping101.blogspot.com/2015/06/52-plant-maintenance-pressure...

Repairs in USA and Repairs elsewhere


National Board U-stamp vessels: In the USA, the repair shall be performed by a certified NB R-Stamp repair
shop under approval of Authorized Inspector in compliance to NB-23.
If outside of USA, check local jurisdiction or company best practice for R stamp
requirements. If required is usually for Quality Assurance or Company requirements
Generally pressure vessel repairs without R stamp are commonly done. Alternative
codes and guidelines can also be used for repairs such as ASME PCC-2 or API 510.
Check Company guidelines, if none to consult a pressure vessel engineer.

API 510 Inspection, Repair, Rerating & Alterations:


Alternatively an API 510 repair procedure can be used also under the approval of the
Authorized Inspector. Refer to Appendix D of API 510 document for the check list
Typical repairs based on API 510 includes Temporary and Permanent Repairs.
Ensure that all minor repairs are authorized by the pressure vessel inspector before
commencement. Approval for major repair may not be given for an ASME Section VIII
designed vessel until approved by an experienced Pressure Vessel Engineer.
Crack repairs shall be consulted with the pressure vessel engineer before proceeding,
as cracks may propagate even after the repair.
Pressure tests may not be required after the repair. Unless it is believed to be necessary
by the inspector. Pressure test if required, may be waived if suitable Volumetric NDE are
in place to ensure integrity of the repair.
Temporary Repairs includes:
Lap patch - This is also commonly known as doubler, sometimes could be
done on-stream as emergency repairs, if the process fluid is not hazardous
or flammable, and welding process permits so. A plate of usually similar
material, properties and profile is welded to the external wall of the pressure
vessel over the leaking spot. There are size/thickness restrictions where you
need to calculate and avoid welding over to or near existing weld seams, the
edges needs to be rounded to minimum 1" radius.

Pipe Cap/Nozzle - Welding a pipe cap or nozzle to seal in the leaking spot.
These are non-penetrating.

Leak sealing - Possible for very small pressure vessels, usually below 8"
diameter. The leaking spot could be box in or wrap sealed by epoxy-metal
binders.
Lap band repair - A huge band is attached around the vessel body, this is not
recommended unless the repair needs to remain in place for a longer period
of time.

Permanent repairs includes:


Shell course replacement - cutting out the damaged section for replacement.
This is usually an expensive job, especially if done on sections of a huge
vertical column, high costs largely attributed to lifting and manpower.

2 dari 5 25/05/2019 12.28


Piping 101: 5.2 Plant maintenance: Pressure Vessel Repair http://sgpiping101.blogspot.com/2015/06/52-plant-maintenance-pressure...

Strip lining - a thin layer of sheet metal, usually of a superior material is lined
internally. Cheaper than the other methods.

Insert Plate - A piece of the pressure vessel is cut out and replaced with a
new piece of metal plate of the same profile over the spot of leakage. The
edges should always be grounded unless the side falls on an existing weld
seam. In contrary to the sketch, the corners of the insert plates shall be
rounded to eliminate residual stresses.

Weld overlay - Adding a layer of weld filler metal over the thinned down
sections of the vessel to restore the wall thickness. Very tedious and time
consuming. Watch the manhours. Take note that the repair thickness shall
not be more than 50% of the minimum required thickness of the vessel
(exclude Corrosion Allowance)

Groove Repair - This method usually used for cracks and pinhole leakages.
The section where leakage is present is grind down to a U or V groove. Weld
metal is then deposited to restore the surface.
Additional Considerations
Materials
SS Cladding/Plate lining to P3, P4, P5 materials tends to crack when
excessive heats are applied during welding. Check for delayed cracking with
UT 24h after job completion.
Hydrogen service vessels shall be outgassed and checked for its hardness
after welding
Post Weld Heat Treatment

3 dari 5 25/05/2019 12.28


Piping 101: 5.2 Plant maintenance: Pressure Vessel Repair http://sgpiping101.blogspot.com/2015/06/52-plant-maintenance-pressure...

Check whether if vessel to be repaired require PWHT during fabrication. If


yes, PWHT shall also be applied during repair in compliance to latest edition
of ASME VIII Div 1 requirements (or refer to MDR). PWHT by oven is unlikely
for in-service vessels however the following are usually used
Local banding PWHT
Preheat in place of PWHT
Controlled Deposition Welding in place of PWHT

Check API 510 Section 8 for the full requirements of PWHT by alternative methods, as there are certain
material tests which needs to be performed, certain requirements to welding procedures on top of ASME IX
WPS/PQR requirements, certain requirements for temperature, certain requirements for welding electrode type
and not forgetting material considerations.

For additional repair procedures and guidelines on top of API 510, refer to ASME PCC-2.

Posted by ANG CK at 2:16 AM

Labels: 5. Plant Maintenance

7 comments:

raveenapaware2017 February 22, 2018 at 3:00 AM

This comment has been removed by the author.

Reply

raveenapaware2017 February 22, 2018 at 3:05 AM

This comment has been removed by the author.

Reply

raveenapaware2017 February 22, 2018 at 3:09 AM

Thanks for sharing such good information.please share more information about Repair and Maintenance
Electrode

Reply

siya jain April 6, 2018 at 3:42 AM

Thanks for sharing such usefull blogs about Repair and Maintenance Electrodes Electrodes, i would like to know
more about SMAW Welding.

Reply

Vosaci grant March 3, 2019 at 9:14 PM

why the comments removed? something smells fishy here

Reply

Subarna Akter March 6, 2019 at 9:00 PM

Really nice blog! posts are relevant and quality! Thank you

Pool repair Lakeway


Pool repair services Lakeway

Reply

subarna April 10, 2019 at 7:39 AM

Loved it! This is really helpful and inspired me.

Pool repair Marble Falls


Swimming pool repair Spicewood

Reply

Comment as:

Publish Notify me

Newer Post Home Older Post

Subscribe to: Post Comments (Atom)

4 dari 5 25/05/2019 12.28


Piping 101: 5.2 Plant maintenance: Pressure Vessel Repair http://sgpiping101.blogspot.com/2015/06/52-plant-maintenance-pressure...

Simple theme. Powered by Blogger.

5 dari 5 25/05/2019 12.28

You might also like