Professional Documents
Culture Documents
FOREWORD
The writer wants to thank to Almighty God because of His bless and
grace, he can finish this paper. This paper titled ” Waterworks Task ”. The writer
wrote it to fulfill the final assignment of waterworks course.
The writer also delivers his gratitude to Mr. Yedida, the waterworks
lecturer of ITENAS Bandung and Mr. Bangbang, the waterworks lecturer
assistant of ITENAS Bandung, for their guidance to complete it. This paper
provides the reader about the design of waterworks. The writer realizes that this
paper is far from perfect in the arrangement or in the content of the paper. The
writer hopes that the suggestions from the reader can be a support to make
her better in the next paper project.
Finally, the writer expects that it can be a medium for the reader to deepen
the knowledge about the figure of speech and its application.
FOREWORD ........................................................................................................... i
CONTENTS ............................................................................................................ ii
CHAPTER I INTRODUCTION ............................................................................. 1
3.4 Tahap 4 Hitungan Hi, Beff Dan Lengkung Debit Setelah Ada Mercu .. 17
3.5 Tahap 5 Elevasi Tembok Pangkal Udik Dan Hilir Bendung ................. 20
3.9.3 Jika pintu dibuka setinggi pembilas bawah (under slice) ............... 28
3.9.4 Jika pintu dibuka setengah pembilas bawah (under slice) .............. 28
1. CHAPTER I
INTRODUCTION
1.1 Background
Dams are buildings that are designed for the river stem so that the river
water reservoir is obtained. On making dams must be designed with high safety
standards . So this dam is safe against runoff (in floods plan), piping and
earthquake loads that occur. Dam to dam can be caused by overtopping or piping.
Overtopping, is collapse of the dam due to overflow of water through the top of
the dam because the large inflow discharge exceeds the capacity of water in
capacity. Dam to dam can be caused by overtopping or piping. Overtopping, is
collapse of the dam due to overflow of water through the top of the dam because
the large inflow discharge exceeds the capacity of water in capacity . Dam
collapse can also be caused by the flow of water through the holes in dam body
foundation which is often called piping, in the process . Seepage water will slowly
bring material to the body's stability dam. In addition to seepage that occurs due to
overtopping or piping, the incidence of rain that is quite high in the upstream part
of the dam can also becausing additional volume on the dam that trigger scollapse
of dams that have conditions that are not stable.
1.3 Purpose
The purpose of this task is to learn how to and planning and design dam ,
draw cross-sections and lengthen the dam .
1.4 Benefits
Provide an overview or knowledge of how to plan a building complement
to the dam.
2. CHAPTER II
LITERATURE REVIEW
𝐴 = (𝐵 + 𝑚ℎ)ℎ
𝑃 = 𝐵 + 2ℎ (𝑚2 + 1)𝑜,5
𝐴
𝑅=
𝑃
about the exploitation of weirs, because the drainage of water above the
door is more difficult than the irrigation of water above the dam, so the
Explanation :
n = number of pillars
Kp = coefficient of contraction pillar
Ka = coefficient of contraction
Hi = height of energy (m)
Bn= the actually width of mercu
Beff = effective dam width
Table. Coefisien for Ka and Kp
a. Round Dam
For round beams we have a much higher discharge coefficient (44%)
than a wide threshold coefficient. This type has many advantages
because it will reduce upstream water level during floods. Price of the
debit coefficient become higher because of the arc stream line and
negative pressure on the mercu. For dam with 2 downstream radii, it
will be used to find the price of the discharge coefficient.
Padma (2013 [5]) states that weir height (P) can be calculated by the
formula:
The high energy above the mercu can be calculated by the high energy
discharge equation
2 3
𝑄 = 𝐶𝑑 × 2⁄3 √ × 𝑔 × 𝐵𝑒𝑓𝑓 × 𝐻 2
3
Information :
Q = debit, m3/dt
ℎ𝑐
𝑎 = 0,28ℎ𝑐 × √
𝑧
Explanation :
g = (9,8 m/dt2)
𝑄𝑛 = 𝜇 × 𝑎 × 𝑏√2 × 𝑔 × 𝑧
Explanation:
μ = discharge coefficient
If using Blight : LT = LV + LH
Explanation :
𝐵 ∑ 𝑀𝑇 − ∑ 𝑀𝐺 𝐵
𝐸𝑘𝑠𝑒𝑛𝑡𝑟𝑖𝑠𝑖𝑡𝑎𝑠 (𝑒) = ( ) − ( )<
2 𝑅𝑉 6
Explanation :
𝑅𝑉 6𝑒
𝑠𝑜𝑖𝑙 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 (𝜎) = (1 + ) < 𝜎𝑖𝑧𝑖𝑛
e = Eccentricity 𝐵𝑒 𝐵𝑒
B = Basic width
MT = Moment of detention
MG = Bolster moment
RV = Vertical style
σ = Land tension
SF = safety factor
c. Stability to shear
The formula for calculating shear stability is :
Explanation : ∑𝑉
𝑆𝐹 = ≥ 1,2
∑𝐻
SF = safety factor
3. CHAPTER 3 CALCULATION
Perhitungan
Asumsi y : 0,5 meter
Mencari luas trapezium
A = (𝑏 + 𝑚 × 𝑦) × 𝑦
= ( 52+1×0,5)×0,5
= 26,25 𝑚2
Mencari keliling trapezium
P = b+2y √1 + 𝑚2
= 52 + 1 × 0,5√1 + 12
= 53,41 m
Mencari jari-jari hidrolis
𝐴
R =𝑃
26,25
= 53,41
= 0,491 m
(52+𝑦×𝑦 2 )
370 = √(52+ 2,828𝑦) × 0,0042 × (52𝑦 + 𝑦 2 )
yb = 1,526 m
b h A P R v Q
52 0.000 0.000 52.00 0.000 0.00 0.000
52 0.500 26.250 53.41 0.491 2.64 69.17
52 0.700 36.890 53.98 0.683 3.11 114.630
52 0.900 47.610 54.55 0.873 3.51 167.194
52 1.000 53.000 54.83 0.967 3.70 195.868
52 1.100 58.410 55.11 1.060 3.87 226.029
52 1.200 63.840 55.39 1.152 4.04 257.608
52 1.300 69.290 55.68 1.245 4.19 290.550
52 1.400 74.760 55.96 1.336 4.34 324.802
52 1.500 80.250 56.24 1.427 4.49 360.319
52 1.529 81.846 56.32 1.453 4.53 370.850
Tabel perhitungan debit Q 100 tahun
= 2,511 m
66.36 m
1 Kondisi Pilar Kp
Untuk pilar berujung segi empat dengan sudut-sudut yang
a dibulatkan pada jari-jari yang hampir sama dengan 0,1 dari 0,02
tabel pilar
b Untuk pilar berujung bulat 0,01
c Untuk pilar berujung runcing 0
2 kondisi tembok pangkal bending Ka
Untuk tembok pangkal segi empat dengan tembok udik 900
a ke arah aliran 0,20
b =1m
B = Lebar mercu sebenarnya (Bb – n.b)
= 55 – 3.1 = 52 m
B eff = 52 − 2(3 × 0 + 0,2)𝐻𝑖
= 52 – 0,40 Hi
3.4 Tahap 4 Hitungan Hi, Beff Dan Lengkung Debit Setelah Ada Mercu
3.4.1 Menghitung Hi
3
2 2
Q = 𝐶𝑑 ∙ 3 × √3 𝑔 × 𝐵𝑒𝑓𝑓 × 𝐻𝑖 2
Q = Debit (m3/detik)
Cd = Koefisien debit (Co.C1.C2)
Cd = 1.9 - 2.1 (ogee)
Cd =2
Jika Ogee maka gunakan Co = 1.39
𝑃 4,36
𝐶1 → = = 2.64470 → 𝑑𝑎𝑟𝑖 𝑔𝑟𝑎𝑓𝑖𝑘 (𝑔𝑎𝑚𝑏𝑎𝑟 6)
𝐻𝑖 1.647
𝑑𝑖𝑝𝑒𝑟𝑜𝑙𝑒ℎ 𝐶1 = 1
C2 = 1, karena hulu bendung tegak.
G = Gravitasi (9,81 m/s)
Hi = Tinggi energi di atas mercu (m)
2 2
Q = 2 ∙ 3 × √3 9,81 × (52 – 0,40 𝐻𝑖 1,5 × 𝐻𝑖 2,5
2 2
370 = 2 ∙ 3 × √3 9,81 × (52 – 0,40 𝐻𝑖 1,5 × 𝐻𝑖 2,5 )
Cek Q=Q
No Cd awal H Q H/R P/H Co (tabel) C1 (tabel) C2 Cd akhir Cek
100 th
Tidak
2 1.39 2.104 370 Sama 2.070853 1.39 0.99 1 1.3761 tidak sesuai
ada
3 1.3761 2.118 370 Sama 2.056871 1.39 0.99 1 1.3761 asumsi benar
Tabel Perhitungan Cd
3
2 2
370 = 1.3761 ∙ 3 × √3 9,81 × (52 – 0,40 Hi) × 𝐻𝑖 2
3
370 = 1.3483 ∙ 1,704 × (52 – 0,40 Hi) × 𝐻𝑖 2
Diperoleh Hi yang digunakan pada perhitungan tinggi muka air banjir setelah ada
bending adalah = 2,1183 m
Maka B efektif : 52 – 0,40 × 2.1183 = 51,153 𝑚
3.4.3 Menghitung Hd
Kesimpulan: Setelah ada bendung didapat debit Q = 370 m3/detik dengan tinggi
muka air 2,1183 m yang sesuai dengan debit banjir rencana yaitu Q100 = 370
m3/detik.
Mencari Hd (tinggi energi rencana di atas mercu)
𝑄100 2
𝐻𝑖 = ℎ𝑑 +
((ℎ𝑑 + 𝑝) × 𝐵𝑒𝑓𝑓)2 × 2 × 𝑔
3702
2,1183 = ℎ𝑑 +
((ℎ𝑑 + 4,36) × 51,153)2 × 2 × 9.81
hd = 2,053 m
hd < hi 2,053 < 2,1183….ok
𝑑𝑦 1.85 𝑥 0.85
= 1; = 1, 𝑚𝑎𝑘𝑎 𝑥 = 2,250 𝑚
𝑑𝑥 3,6585
2,2501.85
𝑦= = 1,217 𝑚
2 (2,053 )0.85
Z = (Elevasi dasar sungai udik + P +Hi) – (Elevasi dasar sungai hilir – z + Hb)
= (62 + 4.36 +2,118) – (59 - 2 + 1,529)
= 9,949 m
H = Hi = 2,118 m
𝑍 9,949
= = 4,6973 𝑚
𝐻 2,118
Syarat :
4
< 4,6973 < 10 (terpenuhi)
3
𝐻
a = 0,15 H √ 𝑍 = 0,1465
𝑏. 𝑎 = 8,077 𝑚2
d : 0,15 – 0,25 m Diambil d = 0,15 m
p : 0,5 – 1,5 m Diambil p = 0,5 m
z : 0,15 – 0,3 m Diambil z = 0,15 m
μ : 0,8 – 0,9 m Diambil μ = 0,8 m
t : 0,1 m Diambil t = 0,1 m
Gambar kondisi hidraulik pintu pengambilan (ai) aliran bebas (b) aliran tenggelam
= 45,635 m3/s
Direncanakan 3 pintu
A = b*y = (3)(1,5)(1,5) = 6,75 m2
𝑄 45,635
v=𝐴= = 6,760 m2/dt
6,75
1,5
= (0,65)(3)(1,5)(1,5) √(2)(9,81) (4,36 − ( 2 ))
= 36,924 m3/s
Direncanakan 3 pintu
A = b*y =3× (1,5) × (1,5) = 6,75 m2
𝑄 36,924
v=𝐴= = m2/s
6,75
Luas = 2400 m2
2. L/B ≥ 8
𝐴𝑛 30
hn = = 12 = 2,5 m
𝐵
𝑣𝑛 2 0,42
In = 2 = 2 = 2,138 x 10-5
(𝑅𝑛 3 𝑥 𝐾𝑠 )2 (1,8223 𝑥 58)2
𝑣𝑠 2 1,02
Is = 2 = 2 = 3,1653 x 10-4
(𝑅𝑠 3 𝑥 𝐾𝑠 )2 (0,9543 𝑥 33,3)2
3. Metode Bligh
𝚺Lv + 𝚺Lh ≥ Cb × ∆H × 1,5
𝚺Lv + 𝚺Lh ≥ 7× 8,883 × 1,5
𝚺Lv + 𝚺Lh ≥ 93,27m
4. Metode Lane
𝐿ℎ
𝛴𝐿𝑣 + ≥ 𝐶𝑙 × ∆𝐻
3
𝐿ℎ
𝛴𝐿𝑣 + ≥ 4,5 × 8,883
3
𝐿ℎ
𝛴𝐿𝑣 + ≥ 39,97 𝑚
3
Metode Bligh
𝚺Lv + 𝚺Lh ≤ Cb × ∆H × 1,5
18,5 + 23 ≤ 6,5 × 8,883 × 1,5
41,5 m ≤ 93,27 m
LAda ≤ LPerlu
Maka, perlu lantai muka sejauh 93,27 – 41,5 = 52 m
Metode Lane
𝐿ℎ
𝛴𝐿𝑣 + ≤ 𝐶𝑙 × ∆𝐻
3
23
18,5 + ≤ 4,5 × 8,883
3
26,167 ≤ 39,97 𝑚
LAda ≤ LPerlu
Maka, perlu lantai muka sejauh 44,415 − 27,176 = 16,249 m
Kesimpulan
Jadi, perlu ada lantai muka sepanjang 52 m
Metode Bligh
𝚺Lv + 𝚺Lh ≥ Cb × ∆H × 1,5
35,5 + 60 ≥ 7 × 8,883 × 1,5
95,5 m ≥ 93,27 m
LAda ≥ LPerlu …..0K
Metode Lane
𝐿ℎ
𝛴𝐿𝑣 + ≥ 𝐶𝑙 × ∆𝐻
3
60
35,5 + ≥ 4,5 × 5,4242
3
55,5 𝑚 ≥ 39,97𝑚
LAda ≥ LPerlu…..OK
1
Ka tg 2 45 o Ps s .h 2 .K a
2 2
∅ 28
Perhitungan : - 𝐾𝑎 = 𝑡𝑔2 (45° − 2) = 𝑡𝑔2 (45° − ) = 0,361
2
1 1
- 𝑃𝑠 = 2 𝛾𝑠 . ℎ2 . 𝐾𝑎 . 1 = . 0,70. 1,492 . 0,361.1 = 0,6813 𝑡
2
Ka tg 2 45 o
2
Kp tg 2 45 o
2
1
Pa .h 2 .K a
2
1
Pp .h 2 .K p
2
Dimana : Pa = gaya akibat tekanan tanah aktif (Ton)
Pp = gaya akibat tekanan tanah pasif (Ton)
t = berat jenis tanah (1,70 t/m3)
h = kedalaman tanah, m
= sudut geser dalam (28o)
Ka = koefisien tekanan tanah aktif
Kp = koefisien tekanan tanah pasif
Perhitungan :
1 1
- 𝑃𝑎 = 2 𝛾. ℎ2 . 𝐾𝑎 = . 0,60. 102 . 0,361 = 30,625 𝑡
2
1 1
- 𝑃𝑝 = 2 𝛾. ℎ2 . 𝐾𝑝 = . 0,70. 12 . 2,768 = 2,35 𝑡
2
Momen
Besar Gaya (t) Lengan Momen (m)
Tekanan Terahadap
Horizontal Vertikal X Y titik L (tm)
Pa 30.625 0 0 3.300 101
Pp 2.35 0 0 1 0,264
∑ 32.975 0 0 4.300 101
Tabel Gaya akibat tekanan tanah
1
PH w .h 2
2
Dimana : PH = gaya akibat tekanan hidrostatis, Ton
h = tinggi air, m
γw = berat jenis air (1 ton/m3)
Perhitungan Gaya dan Momen Akibat Gaya Hidrostatis Muka Air Normal
H = 2,3132 m
1
𝑃𝐻 = × 12 × 4,472 = 2,235 𝑡𝑜𝑛 (Besarnya gaya)
2
Tabel Perhitungan Gaya dan Momen Akibat Gaya Hidrostatis Muka Air Banjir
Besar Gaya (ton) Lengan Momen (m) Momen terhadap Z
Gaya Luas (m2) gamma w
horizontal vertikal X Y X Y
V1 21.7567 1 21.7567 13.17 286.535739
V2 3.3773 1 3.3773 21.17 71.497441
V3 57.9766 1 57.9766 6.73 390.182518
∑ 83.1106 61.3539 27.9 13.17 461.679959 286.535739
Lx H
Ux H x w
Ltot
Dimana : Ux = gaya angkat pada x, (t/m2)
Ltot = panjang total bidang kontak bangunan dan tanah bawah,
m
Lx = jarak sepanjang bidang kontak dari hulu sampai x, m
Hx = tinggi energi dihulu bendung, m
∆H = beda tinggi energi, m
γw = berat jenis air, 1 t/m3
Safety Factor
a. Terhadap guling
∑ 𝑀𝑉 4226,742
𝑆𝐹 = = = 2,36 > 1,5 (𝑔𝑜𝑜𝑑!)
∑ 𝑀𝐻 2429,254
b. Terhadap geser
∑ 𝐹𝑉 3851,31
𝑆𝐹 = = = 1,74 > 1,5 (𝑔𝑜𝑜𝑑!)
∑ 𝐹𝐻 1637,76