Material Consumption Statement for Royaltry

First & Final RA Bill


Name of Work- Construction of 3.15 MVA 33/11 kv s/s & interlinking 33kv & 11kv line at vill- Chitalanka (instead of Katekalyan)
under O&M Dn Dantewada for CSD Dantewadaunder ST:RE Dn. Jagdalpur( i/c Control Room). (For Civil Part)
Work Order No.-02-08/CW/2015-16/ Tender No. 318/L-47/2807 Raipur; Dtd. 29/10/2015

S. Clay Burnt
Particular Quantity Unit Cement Sand Metal Moorum
No. Modular Bricks
1 Construction of control room with Toilet 1 No. 460 39.36 45.85 45.76 17714

2 WBM Road (3.75Mtr. Wide). 120 M - - 132 251.88 -


3 Hume pipe culvert (450mm dia) 1 No. 29.95 2.79 8.86 - -
Total 489.95 42.15 186.71 297.64 17714
bags Cum. Cum. Cum. nos.
Rate for 1.5 times of royaltry in Rs. - 20 132 20 0.04
Amount in Rs. - 843 24645.72 5952.8 708.56
Total Rs. 32150.08
Rate for 1.5 times of royaltry in Rs. 48225.12
Say Rs. 48300.00