Professional Documents
Culture Documents
b. Fireproofing Status
Cum. Previous Day Today Cum. Today
BQ
AREA Location Install Application Install Application Install Application %
(M2)
Wiremesh Intercote Wiremesh Intercote Wiremesh Intercote
STR P1-1 104 104 104 104 104 100%
STR P1-4 43 43 43 43 43 100%
STR P1-5 41 41 41 41 41 100%
STR P1-6 45 45 45 45 45 100%
STR P1-7 47 47 47 47 47 100%
STR P1-8 67 67 67 67 67 100%
PR31 162 162 162 162 162 100%
P1
PR32 107 107 96 107 96 90%
PR33 140 137 137 137 137 98%
PSP9 28 28 28 28 28 100%
PSP10 44 44 44 44 44 100%
PSP11 40 40 40 40 40 100%
Chi l l ed 24 24 24 24 24 100%
Pi pe Support P1 162 162 162 162 162 100%
STR P2-1 28 28 28 28 28 100%
STR P2-2 1,225 1,225 1,225 1,225 1,225 100%
STR P2-3 140 140 126 140 126 90%
STR P2-4 142 142 142 142 142 100%
STR P2-5 99 19 19
STR P2-6 800 124 124
P2 STR P2-7 157 61 61
STR P2-11 56 56 56 56 56 100%
STR P2-13 56 25 25
PR Eps i s top 37
Aci d 312 153 97 153 97 31%
Pi pe Support P2 444 261 261 261 261 59%
Loca l Pl a tform 55
STR P3-2 199 199 199 199 199 100%
STR P3-3 1,290 1,290 1,290 1,290 1,290 100%
STR P3-4 58 58 58 58 58 100%
STR P3-7 176 176 176 176 176 100%
STR P3-8 674 674 674 674 674 100%
P3
STR P3-9 77 77 77 77 77 100%
Page 1 of 5
STR P3-9 77 77 77 77 77 100%
STR P3-10 40 40 40 40 40 100%
STR P3-12 45 45 45 45 45 100%
Equi pment 449 449 449 449 449 100%
Pi pe Support P3 92 92 92 92 92 100%
PR11 65 65 65 65 65 100%
U1
Pi pe Support U1 33
STR U2-1 217 184 157 184 157 72%
STR U2-2 98 98 98 98 98 100%
STR U2-3 194 194 194 194 194 100%
STR U2-4 17 17 17 17 17 100%
U2 PR03-1 80 80 80 80 80 100%
PR03-2 115 115 115 115 115 100%
PR05 32 32 32 32 32 100%
Sta rtyl 94 94 94 94 94 100%
Pi pe Support U2 81 76 76 76 76 94%
PR06-2 101 101 101 101 101 100%
U4
PR06-3 22 22 22 22 22 100%
Total 8,855 7,464 7,127 7,464 7,127 80%
KRSAG 569 8316 8885 11623 - - - 15 - 15 566 568 7,967 10,604 8,533 11,172 96.04% 96.12%
ATA 581 7718 8299 10975 - - - 8 - 8 563 563 7,739 10,026 8,302 10,589 100.00% 96.48%
JEL 422 4299 4721 6444 - - - - - - 437 437 5,368 6,502 5,805 6,939 100.00% 107.68%
CKN 432 5796 6228 9110 - - - 2 - 2 378 378 5,745 8,982 6,123 9,360 100.00% 102.74%
Total 2004 26129 28133 38152 - - - 25 - 25 1,944 1,946 26,819 36,114 28,763 38,060 102.24% 99.76%
Page 2 of 5
g) Instrument Secondary Cable Pulling
Actual 2nd Cum. Instrument Actual 2nd Cum.
No Area Plan Total Unit Cable Pulling Secondary Cable Remaining Percentage % No Area Plan Total Unit Termination Instrument Remaining Percentage %
as of 8-Dec Pulling as of 8-Dec Termination
1 C1 6,545 Meter - 6,545 - 100% 1 C1 278 Nos - 278 - 100%
2 P1 36,031 Meter - 36,031 - 100% 2 P1 843 Nos - 820 23 97%
3 P2 52,047 Meter - 52,047 - 100% 3 P2 1,286 Nos 1 1,225 62 95%
4 P3 32,485 Meter - 32,485 - 100% 4 P3 705 Nos - 675 31 96%
5 P4 18,591 Meter - 18,591 - 100% 5 P4 390 Nos - 358 32 92%
6 U1 7,918 Meter - 7,918 - 100% 6 U1 175 Nos - 166 10 95%
7 U2 26,516 Meter - 24,030 2,486 91% 7 U2 585 Nos 1 353 232 60%
8 U3 4,009 Meter - 4,009 - 100% 8 U3 244 Nos - 244 - 100%
9 U4 1,235 Meter - 1,235 - 100% 9 U4 20 Nos - 20 - 100%
Total 185,377 Meter - 182,891 2,486 99% Total 4,526 Nos 2 4,138 389 91%
j) Insulation Status
Equipment
PREVIOUS DAY TODAY CUM. TODAY
AREA BQ Jacket Jacket Jacket Jacket Jacket Jacket %
Installation Installation Installation
Prefab Fixing Prefab Fixing Prefab Fixing
C1 36 36 36
P1 1,972 1,881 1,736 1,630 13 1,881 1,736 1,643 83%
P2 1,863 1,861 1,399 1,359 13 1,861 1,412 1,359 73%
P3 3,724 3,724 3,718 3,718 3,724 3,718 3,718 100%
P4 1,037 967 876 851 15 967 891 851 82%
U1 227 205 205 205 205 205 205 90%
U2 627 627 568 506 627 568 506 81%
U4 245 245 245 245 245 245 245 100%
TOTAL 9,731 9,546 8,747 8,515 28 13 9,546 8,775 8,528 88%
Piping
PREVIOUS DAY TODAY CUM. TODAY
AREA BQ Jacket Jacket Jacket Jacket Jacket Jacket %
Installation Installation Installation
Prefab Fixing Prefab Fixing Prefab Fixing
C1 10 10 10 10 10 10 10 100%
P1 2,979 938 703 697 938 703 697 23%
P2 4,604 1,416 1,061 1,019 25 1 3 1442 1061 1022 22%
P3 3,962 1,208 977 913 69 31 37 1277 1008 950 24%
P4 1,876 881 583 545 27 881 583 572 30%
U1 598 411 231 231 10 411 241 231 39%
U2 498 241 170 32 3 9 17 245 179 49 10%
U4 130 86 86 86 86 86 86 66%
TOTAL 14,657 5,192 3,821 3,533 98 51 84 5,290 3,872 3,616 25%
Page 3 of 5
CKN ( A/G Piping )
- Continue fabrication A/G pipe at U2, P4 Area
- Continue welding joint A/G pipe & pipe support at U2, P4 Area
- Continue painting A/G pipe at U2, P4 Area
WEN ( Electrical )
- Continue glanding & termination A/G main cable at All Area
- Continue lighting fixture installation at All Area
- Continue tray secondary installation at All Area
KPU ( Instrument )
- Continue secondary tray installation at All Area
- Continue termination cable at SIH Area
- Continue termination cable at Junction Box All Area
- Continue air supply&tubing installation at All Area
- Continue secondary cable pulling at All Area
WILLICH ( Insulation )
- Continue insulation for equipment at All Area
- Continue insulation for pipe at P1, P2, P3, P4 Area
3. Site Photograph
3.1 PIPING A/G ( ATA, JEL )
Welding joint for A/G pipe support Pipe support installation for A/G Pipe
U1 Area (KRSAG) of Alkyl Storage at U2 Area (CKN)
Page 4 of 5
3.3 WEN & KPU ( Elec & Inst )
3.4 WILLICH
Page 5 of 5