SAUDI ARABIAN OIL COMPANY

LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES


CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 2 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

PREP'D APPR'D
REV DESCRIPTION REV'D BY DATE
BY BY

REVISION CONTROL SHEET

REV. DATE PAGE NO. DESCRIPTION


NO
A 29-08-2018 First issue Issued for Review / Comments
B 26-09-2018 Revision Issued to Incorporate Company Comments
C 27-11-2018 Revision Issued to Incorporate Company Comments
00 20-03-2019 Final Issued for Implementation
SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 3 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

Table of Contents

1.0 INTRODUCTION OF THE PROJECT ................................................. 4


2.0 DOCUMENT INTRODUCTION AND PURPOSE .................................. 5
3.0 DEFINITIONS .................................................................................. 5
4.0 REFERENCES ................................................................................. 5
5.0 PERSONNEL RESPONSIBLE ........................................................... 6
6.0 CHANGES ....................................................................................... 6
6.1 COMPANY CHANGES ..................................................................... 6
6.2 CONTRACTOR CHANGES ............................................................... 7
6.2.1 FIELD CHANGE REQUEST .............................................................. 7
6.3 PERFORMACE OF CHANGE ............................................................ 8
6.4 LUMP SUM CHANGE PROPOSALS .................................................. 8
6.5 NON LUMP SUM CHANGE PROPOSALS ......................................... 9
7.0 CHANGE ADMINISTRATION .......................................................... 10
8.0 FAILURE TO AGREE ..................................................................... 11
9.0 “CHANGE ORDER REQUEST" NUMBERING SYSTEM .................... 11
10.0 CHANGE REGISTER ..................................................................... 11
11.0 MEETINGS .................................................................................... 12
12.0 INVOICING OF CHANGE ORDERS ................................................. 12
C
13.0 TERMS AND CONDITIONS ............................................................ 13
SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 4 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

1.0 INTRODUCTION OF THE PROJECT

This lump sum Contract Release Purchase Order (CRPO) scope of work under 81-10-2016
(Bid #29) includes but is not limited to the engineering, procurement, construction/fabrication
and demolition (where applicable) / installation (EPCI), hook-up and pre-commissioning of
offshore maintain potential facilities in safaniya field.

The scope comprises the EPCI & pre-commissioning of eight (8) slipover jackets and decks:

 Eight (8) slipover jackets that will replace existing jackets in Safaniya field which will
be demolished with the existing platform topsides. The designation of these jackets
is as follows:
1. SFNY 378;
2. SFNY 281;
3. SFNY 32;
4. SFNY 31;
5. SFNY 210;
C
6. SFNY 107;
7. SFNY 143;
8. SFNY 154;

 Eight (8) slipover decks that will replace the existing decks in Safaniya field which will
be demolished with the existing jackets. The designation of these decks are as
follows:
1. SFNY 378;
2. SFNY 281;
3. SFNY 32;
4. SFNY 31;
5. SFNY 210
6. SFNY 107;
7. SFNY 143;
8. SFNY 354;

 Installation of subsea infrastructure (6 valve skids, 3 rigid pipelines, 3 flexible lateral


flow lines, 6 submarine umbilical’s, 8 submarine cables, ICCP anode sleds and
associated cable for 8 platforms).
 Disconnect from existing platform and reconnect to new slipover platform existing
subsea infrastructure facilities (2 lateral flexible flowlines, 2 submarine umbilical’s).
SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 5 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

 Install three (3) new headers; Header#11, 13, and 20 following to TP-21.
 Install Eight (8) 15Kv submarine cables connected to TP-21.
2.0 DOCUMENT INTRODUCTION AND PURPOSE

In accordance with CONTRACT No. 6600038261 Out Of Kingdom (OOK) and 660038262
In-Kingdom (IK), Schedule “H”, Paragraph 1.6, which supersedes Schedule “A”,
Paragraph 9 and Attachment I of Schedule “B” requirements, CONTRACTOR hereby
submits this document to meet the contract administration procedures and project control
procedure to manage changes in scope and change as per OOK Schedule “B”, Paragraph
4.8.5.8 and IK Schedule “B”; Paragraphs 4.3.9.19 and 4.3.9.22.

This document describes and details the Management of Change (MOC) procedures
applicable to the CRPO scope of work. The MOC shall apply to COMPANY,
CONTRACTOR, SUBCONTRACTOR, and SUPPLIERS in accordance to COMPANY
procedures, policies and standards and contract guidelines on lump sum and non-lump sum
changes. The MOC procedure shall ensure that all engineering, procurement, fabrication
and installation/construction scope changes are systematically managed, and properly
evaluated, approved, documented and implemented. Scope related changes are
systematically managed and properly evaluated, approved, documented and implemented.

It details the method and formats to manage the changes as per applicable CONTRACT
clauses.

This document covers the processing and administration of all changes including lump sum C
changes Additional Work Justification’s / Quantity Variance Justification’s (AWJ’s/QVJ’s)
and non-lump sum work issued by separate CRPO, as directed by COMPANY in line with
the CRPO scope of work, and upon clear agreement between COMPANY and
CONTRACTOR on terms and conditions prior to execution of the change. To the maximum
extent possible, strict adherence to the project schedule and applicable cost and contract
guidelines shall be followed at all times. It describes the steps that will be followed during
the tenure of the CRPO by which changes are identified, evaluated and submitted to
Company for review and approval.

3.0 DEFINITIONS

Words and terms used in this document shall have the same meaning as assigned to
them in the applicable LTA for OOK and IK.

4.0 REFERENCES

This document is based on the following referenced sections in the respective LTA.
CONTRACT No. 6600038261 (OOK)
Schedule A: Paragraph 9.0, 19.0
Schedule B: Attachment I - Change Order Administration Procedure
SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 6 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

Schedule B: Paragraph 5.12.3 -Field Change Request


C
Schedule B: Paragraph 4.8.5.8
Schedule C: Contract Price and Payment Provisions
Schedule E: Settlement of Disputes, Arbitration and Choice of Law
Schedule H: Paragraph 1.6, 2.6
CONTRACT No. 6600038261 (IK)
Schedule A: Paragraphs 10.0 and 20.0
Schedule B: Attachment I - Change Order Administration Procedure
Schedule B: Paragraph 16.11.3 - Field Change Request
C
Schedule B: Paragraph 4.3.9.19 and 4.3.9.22
Schedule C: Contract Price and Payment Provisions
Schedule E: Settlement of Disputes, Arbitration and Choice of Law
Schedule H: Paragraphs 1.10 and 2.3

5.0 PERSONNEL RESPONSIBLE

CONTRACTOR REPRESENTATIVE shall be the Asset Holder of this Procedure and shall
be responsible for its correct execution within CONTRACTOR's Organization and may
assign as per OOK CONTRACT Schedule B, 2.9.3

The CONTRACTOR's Contract Administration Manager shall be responsible for the C


functional administration of this Procedure.

6.0 CHANGES

6.1 COMPANY CHANGES

 At any time during the tenure of the CRPO, the Company Representative may
direct CONTRACTOR to make a "Change" within the general scope of the CRPO
such as, but not limited to, alterations of the FACILITIES or changes in the
sequence of performance of the WORK, and CONTRACTOR shall perform the
WORK as changed. Changes shall be set forth only in writing on a document
entitled 'Additional Work Justification (AWJ)' signed by both Parties. Oral changes
C
shall be processed only in line with Schedule H — 1.6.3. In no event shall
CONTRACTOR proceed with the WORK involved in the Change without AWJ.In
SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 7 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

order to address such changes COMPANY will issue a Change Request to


CONTRACTOR.

 If any instruction by COMPANY's Representative constitutes a change in


CONTRACTOR's opinion, CONTRACTOR will, through Letter, request COMPANY's
representative to issue a Change Request. Upon receipt of a letter from
CONTRACTOR requesting that a Change Request be issued, COMPANY shall
review the request and either issue a Change Request or respond to CONTRACTOR
in writing with a letter explaining why a Change Request will not be issued.
Clarification meeting shall be held, in case of not issuing the CR, to discuss and
conclude a mutually agreed decision.

6.2 CONTRACTOR CHANGES

If CONTRACTOR wishes to introduce a Change, then CONTRACTOR will


issue to COMPANY's representative a "Field Change Request". The Field
Change Request shall as a minimum contain the following under "Description
of Change":

 Project Reference / Title;


 Description of the Work affected (specifications, Bill of material, safety,
quality, Construction etc.);
 Location of the work; and
 Schedule impact details.

COMPANY shall review the Field Change Request and either approve the
FCR & issue a Change Request or respond to CONTRACTOR in writing with
a letter explaining why the FCR is rejected.

6.2.1 FIELD CHANGE REQUEST

CONTRACTOR shall prepare and submit Field Change Requests with


drawings and/or documents (marked in red) attached to the request, as a
minimum, for the following situations:
1) Discrepancies found during document review;
2) Discrepancies found during drawing certification described in OOK
Contract Schedule B, Paragraph 5.12.3 and IK CONTRACT Schedule B;
Paragraph 16.11.3
3) Material substitutions, with all updated drawing and proposed substitute
material information noted;
SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 8 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

4) Changes to documents approved by COMPANY but where COMPANY has


not issued a revised drawing for such change; and
5) Changes proposed by CONTRACTOR.

Within Thirty (30) days after OOK Contract/CRPO Award, and 14 days after
IK CONTRACT / CRPO award, CONTRACTOR shall submit, for approval by
COMPANY, a proposed FCR Form and a procedure to control the issue and
approval of FCR's. All changes accomplished through FCR's shall be
incorporated into final 'As-Built' drawings.
Refer FCR format under Attachment 1

6.3 PERFORMACE OF CHANGE

All WORK involved in a Change shall be performed in accordance with the


terms and conditions of the Contract and the AWJ. All change related activities
through an approved AWJ shall be reflected within a revised/updated work
schedule, including progress reporting and the pertaining weightage and C
CRPO price form revisions including invoice requirements. The work schedule
shall be revised to include AWJ and the weightage shall be distributed
accordingly to include the AWJ.

6.4 LUMP SUM CHANGE PROPOSALS

If COMPANY elected to negotiate the Additional Work Justification (AWJ) /


Quantity Variance Justification (QVJ) on Lump Sum (LS) basis, then the
Change Request and Estimates for LS AWJ/QVJ shall be prepared in
accordance with the following:

A. COMPANY shall initiate a Change by submitting a Change Request to


CONTRACTOR

B. CONTRACTOR shall submit both Technical and Commercial proposals to


the local bid box within the bid closing date

C. If CONTRACTOR determines that the bid closing date cannot be met, it shall
Promptly notify the Company Representative in writing, including the
reason for the delay and the date the Change Proposals will be
available for COMPANY review.

D. CONTRACTOR's Technical and Commercial Proposals


(including a detailed cost breakdown) shall be prepared in duplicate
through a letter. CONTRACTOR shall deliver these Proposals in a
SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 9 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

sealed envelope marked with CONTRACTOR's name, Contract


Number, Contract title, CRPO number and title to the local bid box.

E. Upon determination by COMPANY that the Change will proceed


based on the agreed negotiated CONTRACTOR's Lump Sum price to
execute the Change, the AWJ/QVJ form shall be prepared and signed by
both COMPANY Representative and CONTRACTOR Representative.

6.5 NON LUMP SUM CHANGE PROPOSALS

In cases where the COMPANY decided to proceed with a Change based on WUR and/or
TUR, then AWJ/QVJ shall be prepared based on actual approved quantities with
corresponding Contract rates or competitively selected Third Party quotation in accordance
with Contract terms and conditions.

 The Time Unit Rate basis in accordance with Schedule C - Paragraphs 3 and 4 and Pricing
Attachment I.
 The Work Unit Rate basis in accordance with Schedule C - Paragraph 5 and Pricing Attachment
I.

With respect to the WORK to be compensated on a Time Unit Rate basis pursuant to above,
on each scheduled working day, not later than 10:00 a.m., CONTRACTOR shall submit to the
Company Representative detailed Day work time sheets, in duplicate, listing the categories and
amounts of labor and equipment for which Change Order compensation is to be charged for
the previous work day. CONTRACTOR shall commence submission of such time sheets
immediately upon commencement of the Change Order WORK and continue to submit them
until completion of the Change Order WORK. Company Representative's signature on the time
sheet shall constitute only an attestation of the time periods involved.

Refer Attachment No. 3 for Day work time Sheet Format.

For Offshore Changes, Contractor shall record all extra works offshore under the construction
vessel/barge Daily Progress Reports (DPR) or Day work time sheet.

In case any extra work extends the duration of the construction vessel or barge, Contractor
will request additional compensation for such additional period using the vessel rates stipulated in
the contract.

Where extra works are performed in parallel with lump sum works, the proportional utilization
of the productive crew shall be applied to the marine spread rate in order to ascertain the extra
work value.
SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 10 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

In case of standby due to Company caused delay, Contractor will request additional
compensation for such period. Prior to such request, CONTRACTOR shall comply with the C
procedures per OOK schedule “H” Para. 14 to correctly determine the basis by which
CONTRACTOR can invoice for standby time.

Daily Progress Reports (see Attachment No. 4 for Format) or Day Work Sheets signed by the
Company Representative which detail standby shall be used between the Company and the
Contractor for the cost allocation.

7.0 CHANGE ADMINISTRATION

Upon receipt of a Change Request from COMPANY, CONTRACTOR shall comply with the
instructions in the Change Request & meet with COMPANY personnel to define the scope of
the change (if so instructed) and to prepare and submit a priced proposal. CONTRACTOR
priced proposal shall include sufficient detail to permit COMPANY to analyze the price (In
case of Lump Sum) and schedule impact, if any. The details shall at a minimum provide:

 List of affected deliverables;


 Breakdown of man-hours by deliverable and job title/equipment item as in Schedule
"C";
 List of materials and quantities with associated cost for each individual item or cost per
unit quantity as applicable; and
 Schedule analysis showing how the Change Order work would be incorporated into the
Work Schedule and any resulting impact on Critical Milestone Dates

The price of the proposal (In case of Lump Sum) shall be mutually agreed in order to use it as the
basis for issuing a Change Order.

Such Changes shall be set forth only in writing on a document entitled 'Change Order' which shall
be signed by both Parties.

In addition to describing the Change, a Change Order shall include:

 Any adjustment in the Critical Milestone Dates or Mechanical completion resulting from the
Change; and

 The lump sum price of or the basis for determining any increase in the compensation due
CONTRACTOR or credit due COMPANY as a result of the Change, if any.

At such time as CONTRACTOR considers that the work under a Change Order is complete,
CONTRACTOR shall so inform the Company Representative in writing and request that
COMPANY initiate a Change Order settlement.
SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 11 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

COMPANY shall review the work under the Change Order and, in a timely manner, either initiate a
Change Order settlement form if COMPANY agrees that the work under the Change Order is
complete; or respond to CONTRACTOR in writing with a letter explaining why COMPANY
considers that the work under the Change Order is not complete and a Change Order Settlement
will not be initiated.

8.0 FAILURE TO AGREE

In accordance with Schedule A, paragraph 19 of Contract 6600038261 (OOK) and


Schedule A, paragraph 20 of Contract 6600038262 (IK); CONTRACTOR shall
notify COMPANY within 30 days following the occurrence or discovery, of any item or event that
will result in extension of time or addition / reduction in compensation to complete the work scope.

 If the CONTRACTOR and COMPANY are not able to satisfactorily resolve the matter within
a reasonable period of time, CONTRACTOR shall, in writing, notify the COMPANY of the claim.

 Within 60 days of the claim notification, CONTRACTOR shall send the COMPANY a detailed
analysis of the claim with relevant supporting data. Failure to provide the written detailed analysis
with relevant supporting data within the said 60 days period shall be deemed as CONTRACTOR's
waiver of any claim based on the item or event.

 If the CONTRACTOR and COMPANY are not able to resolve satisfactorily, the matter shall be
treated as an unresolved dispute and treated in accordance with Schedule E of the pertaining
Contract.

 CONTRACTOR to continue to perform the work and any additional work instructed by
COMPANY, unless COMPANY directs otherwise.

9.0 “CHANGE ORDER REQUEST" NUMBERING SYSTEM

CONTRACTOR will follow COMPANY's change order request numbering and will, for internal
records, populate a corresponding number against the same which will be sequential based on
date of identification.
Each Change Order Request will have a CONTRACTOR Project unique Number commencing
from 001. Should any Change Order Request be subsequently cancelled, the number shall
not be re-used and will remain unique to the cancelled Change Order Request.

10.0 CHANGE REGISTER

The Change Order Register contains information regarding the Change Order / Change Order
Request / Potential Change Requests; such as number, description, issued, pending and % of
contract price, reference document, submission date, value, status and any comments. The
register shall reflect (as per format enclosed in ATTACHMENT 2) the following:

 Change Order Summary: Presenting a table of description, issued, pending and %of contract
price.
SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 12 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

 Change Order Value: Presenting a table of Contracts (OOK, IK and Total), $US value of each,
Saudi Riyal value of each.
 Change Requests in Process: showing a table with numbered descriptions of Change Requests
and any day count of change impact on the project of each.
 Potential Change Requests: listed by numbered description, each PCR that may come about
and any potential schedule impact in days.

Maintenance of the Change Order Register will be CONTRACTOR’s responsibility. All sections of
the Change Order Register will be kept current and issued to COMPANY regularly under the
Monthly Report.

11.0 MEETINGS
C
Change meetings will be held to:-

1) Verify that all the Changes are identified.

2) To review Changes in process

3) To review Change Order Requests that has been accepted as Change Order since
the last meeting.

4) To discuss any aspects of the Change Order Requests submitted and/or Change
Order system.

5) To review Change Order Register.

6) To discuss any disputed change requests

7) Any other

The frequency of these meetings can increase based on the Project requirements.
Minutes of Meetings shall be prepared in line with Schedule B, Paragraph 2.19. C

12.0 INVOICING OF CHANGE ORDERS

Compensation for WORK performed by CONTRACTOR under a Change Order or credit to


COMPANY for WORK deleted by a Change Order shall be calculated and paid or offset as follows:

In line with Schedule H OOK Paragraph 2.6 and IK Paragraph 2.3, COMPANY shall have the right
to elect that a change order price be paid on milestone or progress basis, where CONTRACTOR
shall separately invoice COMPANY for the portion of the Change Order Price upon the
achievement of such portion.
SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 13 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

On or before the tenth (10th) day of each Gregorian month during the progress of the Change,
CONTRACTOR shall separately invoice COMPANY for a proportionate part of the Change Order
price attributable to work on such Change completed during the preceding month and not included
on previous invoices. CONTRACTOR shall submit a statement with its invoice signed by Company
Representative, which in reasonable detail estimates and itemizes the percentage of the Change
completed during the preceding month. In case of disagreement, Company Representative's
determination as to the percentage of work on the Change completed shall control.

13.0 TERMS AND CONDITIONS

The change management and variation procedures shall be implemented in compliance with the
terms and conditions of the CONTRACT and CRPO scope of work. The procedures shall adhere C
to the COMPANY policies, guidelines and standards. In case of any conflict between the
procedures and COMPANY policies, guidelines and standards, the COMPANY policies shall take
precedence over the procedures.
SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 14 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

ATTACHMENTS

1) FIELD CHANGE REQUEST


2) CHANGE REGISTER
3) DAY WORK SHEET
4) DAILY PROGRESS REPORT
SAUDI ARABIAN OIL COMPANY
COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE
OFFSHORE FACILITIES
FACILITIES
SLIPOVER PLATFORMS,
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
CABLES
BI-10-02016

DOCUMENT NUMBER TITLE


DOCUMENT TITLE PAGE: 15
PAGE: 1 ofof 18
18

ARAMCO: N/A CONTRACT


CHANGE MANAGEMENT / CONTRACT REV: 00
REV: C

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE 27-NOV-2018

LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES

EIGHT (8) SAFANIYA SLIPOVER PLATFORMS, PIPELINES CABLES UNDER (BI-10-02016)


CRPO 6510877951 (OOK) & 6510877952 (IK)

SAUDI ARAMCO CONTRACT No.


6600038261 (OOK) & 6600038262 (IK)

NPCC PROJECT NO. 7306 /7307

DOCUMENT TITLE

CHANGE MANAGEMENT / CONTRACT VARIATION PROCEDURE

ISSUED TO INCORPORATE
C 27-NOV-18
COMPANY COMMENTS

ISSUED TO INCORPORATE
B 26-SEP-18
COMPANY COMMENTS

ISSUED FOR REVIEW / CAM


A SPM (RA) PD (FS) 29-AUG-18
COMMENTS (FMN)
PREP'D APPR'D
REV DESCRIPTION REV'D BY DATE
BY BY
SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 16 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

Note: All Attachments are samples and for illustration purposes only. Detailed formats of C
attachments will be agreed with COMPANY over the phase of the CONTRACT.

Attachment - 1

FIELD CHANGE REQUEST


SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 17 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

Attachment - 2

CHANGE REGISTER
SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 18 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

Attachment - 3

DAY WORK SHEET


SAUDI ARABIAN OIL COMPANY
LONG TERM AGREEMENT (LTA) FOR OFFSHORE FACILITIES
CRPO FOR EIGHT (8) SAFANIYA SLIPOVER PLATFORMS,
PIPELINES CABLES
BI-10-02016

DOCUMENT NUMBER DOCUMENT TITLE PAGE: 19 of 18

ARAMCO: N/A CHANGE MANAGEMENT / CONTRACT REV: 00

NPCC: 7306-7307-PP-GE-008 VARIATION PROCEDURE

Attachment - 4

DAILY PROGRESS SHEET