Professional Documents
Culture Documents
SUBJECT : 12
UNIT COST ANALYSIS
As of 23 Nov. 2000
45.0
UNIT COST DIRECT COST
ITEM QTY UNIT
Matl mhr Labor Equip Subcon Matl Labor Equip Subcon
1.0 Road Excavation / Stripping 4,759.00 m3 0.00 0.02 0.90 14.61 4,283.10 69,528.99
Equipment
dozer (D6H), 100m3/hr 48.00 hr 1,448.38 69,522.12
Manpower
dozer operator 48.00 hr 70.62 3,389.54
2.0 Structure Excavation 776.00 m3 0.00 0.05 2.25 31.26 1,746.00 24,257.76
Equipment
backhoe LS-4300FJ2 (1.4cu.m), 40m3/hr 20.00 hr 1,212.59 24,251.78
Manpower
backhoe operator 20.00 hr 70.62 1,412.31
3.0 Backfilling & Compaction Works 13,387.00 m3 192.68 0.07 3.15 29.83 ### 42,169.05 399,334.21
Materials
Excavated material (plus 20% LVF) 5,711.00 m3
Imported fill (plus 20% LVF) 9,212.00 m3 280.00 2,579,360.00
Equipment
dozer (D6H), 100m3/hr 150.00 hr 1,448.38 217,256.63
vibratory roller 150.00 hr 722.47 108,370.69
water truck 150.00 hr 490.53 73,579.50
Manpower
dozer operator 150.00 hr 70.62 10,592.31
roller operator 150.00 hr 70.62 10,592.31
water truck driver 150.00 hr 61.46 9,219.18
laborer, 2 300.00 hr 38.08 11,424.82
Page 1 of 24
10/17/2019
PROJECT :
SUBJECT : 12
UNIT COST ANALYSIS
As of 23 Nov. 2000
45.0
UNIT COST DIRECT COST
ITEM QTY UNIT
Matl mhr Labor Equip Subcon Matl Labor Equip Subcon
4.0 Backfilling & Compaction Works to Structures 454.00 m3 0.00 0.08 3.60 2.92 1,634.40 1,325.68
Equipment
tamper rammer, 15 m3/hr 31.00 hr 42.63 1,321.41
Manpower
tamper rammer operator 31.00 hr 48.21 1,494.51
Page 2 of 24
10/17/2019
PROJECT :
SUBJECT : 12
UNIT COST ANALYSIS
As of 23 Nov. 2000
45.0
UNIT COST DIRECT COST
ITEM QTY UNIT
Matl mhr Labor Equip Subcon Matl Labor Equip Subcon
5.0 Disposal / Stockpiling 5,535.00 m3 0.00 0.02 0.90 5.86 4,981.50 32,435.10
Equipment
payloader, 120 m3/hr 47.00 689.33 32,398.45
Manpower
payloader operator 47.00 70.62 3,318.93
5.0 Sub-grade preparation 33,307.00 m2 0.00 0.04 1.80 10.67 59,952.60 355,385.69
Sub-grade preparation 33,307.00 m2
Equipment
road grader, 200m2/hr 167.00 hr 913.29 152,520.06
vib. roller 167.00 hr 722.47 120,652.70
water truck 167.00 hr 490.53 81,918.51
Manpower
road grader operator 167.00 hr 70.62 11,792.78
vib. roller operator 167.00 hr 70.62 11,792.78
water truck driver 167.00 hr 61.46 10,264.02
laborer, 2 334.00 hr 38.08 12,719.64
Manpower
road grader operator 15.00 hr 70.62 1,059.23
7.0 Granular Base Course 6,534.00 m3 598.00 0.16 7.20 54.35 ### 47,044.80 355,122.90
Materials (plus 15% LVF) 7,514.10 m3 520.00 3,907,332.00
Page 3 of 24
10/17/2019
PROJECT :
SUBJECT : 12
UNIT COST ANALYSIS
As of 23 Nov. 2000
45.0
UNIT COST DIRECT COST
ITEM QTY UNIT
Matl mhr Labor Equip Subcon Matl Labor Equip Subcon
8.0 Gravel Bed 70.00 m3 414.00 0.17 7.65 3.66 28,980.00 535.50 256.20
Materials (plus 15% LVF) 80.50 m3 360.00 28,980.00
Equipment
tamper rammer, 15 m3/hr 6.00 hr 42.63 255.76
Manpower
tamper rammer operator 6.00 hr 48.21 289.26
helper for spreading, 1 6.00 hr 38.08 228.50
Page 4 of 24
10/17/2019
PROJECT :
SUBJECT : 12
UNIT COST ANALYSIS
As of 23 Nov. 2000
45.0
UNIT COST DIRECT COST
ITEM QTY UNIT
Matl mhr Labor Equip Subcon Matl Labor Equip Subcon
Compaction for ordinary backfill 85.00 m2 0.00 0.04 1.80 3.46 0.00 153.00 294.10
Equipment
vibrating plate compactor, 40m2/hr 3.00 hr 98.00 294.00
Labor
vibrating plate compactor operator 3.00 hr 43.68 131.03
Disposal / Stockpiling 27.00 m3 0.00 0.06 2.70 25.54 0.00 72.90 689.58
Equipment
payloader, 100m3/hr 1.00 hr 689.33 689.33
Labor
payloader operator 1.00 hr 70.62 70.62
Gravel Sand bedding 13.00 m3 360.00 0.40 18.00 0.00 0.00 4,680.00 234.00
Material
banday banda 13.00 m3 360.00 4,680.00
Labor
helper (2), 5 m3/hr 6.00 hr 38.08 228.50
Page 5 of 24
10/17/2019
PROJECT :
SUBJECT : 12
UNIT COST ANALYSIS
As of 23 Nov. 2000
45.0
UNIT COST DIRECT COST
ITEM QTY UNIT
Matl mhr Labor Equip Subcon Matl Labor Equip Subcon
Compaction for sand bedding 85.00 m2 0.00 0.03 1.35 2.31 0.00 114.75 196.35
Equipment
vibrating plate compactor, 50m2/hr 2.00 hr 98.00 196.00
Labor
vibrating plate compactor operator 2.00 hr 43.68 87.36
Compaction for ordinary backfill 291.00 m2 0.00 0.03 1.35 2.70 0.00 392.85 785.70
Equipment
Page 6 of 24
10/17/2019
PROJECT :
SUBJECT : 12
UNIT COST ANALYSIS
As of 23 Nov. 2000
45.0
UNIT COST DIRECT COST
ITEM QTY UNIT
Matl mhr Labor Equip Subcon Matl Labor Equip Subcon
Gravel Sand bedding 29.00 m3 360.00 0.36 16.20 0.00 0.00 10,440.00 469.80
Material
banday banda 29.00 m3 360.00 10,440.00
Labor
helper (2), 5 m3/hr 12.00 hr 38.08 456.99
Compaction for sand bedding 291.00 m2 0.00 0.02 0.90 2.03 0.00 261.90 590.73
Equipment
vibrating plate compactor, 50m2/hr 6.00 hr 98.00 588.00
Labor
vibrating plate compactor operator 6.00 hr 38.08 228.50
Page 7 of 24
10/17/2019
PROJECT :
SUBJECT : 12
UNIT COST ANALYSIS
As of 23 Nov. 2000
45.0
UNIT COST DIRECT COST
ITEM QTY UNIT
Matl mhr Labor Equip Subcon Matl Labor Equip Subcon
Equipment
backhoe LS-4300FJ2 (1.40 cu.m), 50m3/hr 15.00 hr 1,212.59 18,188.83
Labor
backhoe operator 15.00 hr 70.62 1,059.23
helper 15.00 hr 38.08 571.24
Compaction for ordinary backfill 561.00 m2 0.00 0.03 1.35 2.63 0.00 757.35 1,475.43
Equipment
vibrating plate compactor, 40m2/hr 15.00 hr 98.00 1,470.00
Labor
vibrating plate compactor operator 15.00 hr 43.68 655.17
Disposal / Stockpiling 290.00 m3 0.00 0.02 0.90 7.14 0.00 261.00 2,070.60
Equipment
payloader, 100m3/hr 3.00 hr 689.33 2,067.99
Labor
payloader operator 3.00 hr 70.62 211.85
Gravel Sand bedding 49.00 m3 360.00 0.35 15.75 0.00 0.00 17,640.00 771.75
Material
banday banda 49.00 m3 360.00 17,640.00
Labor
helper (2), 5 m3/hr 20.00 hr 38.08 761.65
Page 8 of 24
10/17/2019
PROJECT :
SUBJECT : 12
UNIT COST ANALYSIS
As of 23 Nov. 2000
45.0
UNIT COST DIRECT COST
ITEM QTY UNIT
Matl mhr Labor Equip Subcon Matl Labor Equip Subcon
Compaction for sand bedding 561.00 m2 0.00 0.03 1.35 2.10 0.00 757.35 1,178.10
Equipment
vibrating plate compactor, 50m2/hr 12.00 hr 98.00 1,176.00
Labor
vibrating plate compactor operator 12.00 hr 43.68 524.14
Compaction for ordinary backfill 385.00 m2 0.00 0.03 1.35 2.55 0.00 519.75 981.75
Equipment
vibrating plate compactor, 40m2/hr 10.00 hr 98.00 980.00
Page 9 of 24
10/17/2019
PROJECT :
SUBJECT : 12
UNIT COST ANALYSIS
As of 23 Nov. 2000
45.0
UNIT COST DIRECT COST
ITEM QTY UNIT
Matl mhr Labor Equip Subcon Matl Labor Equip Subcon
Labor
vibrating plate compactor operator 10.00 hr 43.68 436.78
Gravel Sand bedding 27.00 m3 360.00 0.38 17.10 0.00 0.00 9,720.00 461.70
Material
banday banda 27.00 m3 360.00 9,720.00
Labor
helper (2), 5 m3/hr 12.00 hr 38.08 456.99
Compaction for sand bedding 385.00 m2 0.00 0.03 1.35 2.04 0.00 519.75 785.40
Equipment
vibrating plate compactor, 50m2/hr 8.00 hr 98.00 784.00
Labor
vibrating plate compactor operator 8.00 hr 43.68 349.42
Page 10 of 24
10/17/2019
PROJECT :
SUBJECT : 12
UNIT COST ANALYSIS
As of 23 Nov. 2000
45.0
UNIT COST DIRECT COST
ITEM QTY UNIT
Matl mhr Labor Equip Subcon Matl Labor Equip Subcon
Labor
backhoe operator 13.00 hr 70.62 918.00
helper 13.00 hr 38.08 495.08
Compaction for ordinary backfill 389.00 m2 0.00 0.03 1.35 2.52 0.00 525.15 980.28
Equipment
vibrating plate compactor, 40m2/hr 10.00 hr 98.00 980.00
Labor
vibrating plate compactor operator 10.00 hr 43.68 436.78
Gravel Sand bedding 36.00 m3 360.00 0.38 17.10 0.00 0.00 12,960.00 615.60
Material
banday banda 36.00 m3 360.00 12,960.00
Labor
helper (2), 5 m3/hr 16.00 hr 38.08 609.32
Compaction for sand bedding 389.00 m2 0.00 0.02 0.90 2.02 0.00 350.10 785.78
Equipment
Page 11 of 24
10/17/2019
PROJECT :
SUBJECT : 12
UNIT COST ANALYSIS
As of 23 Nov. 2000
45.0
UNIT COST DIRECT COST
ITEM QTY UNIT
Matl mhr Labor Equip Subcon Matl Labor Equip Subcon
Page 12 of 24
10/17/2019
UNIT COST
Total
73,812.09 15.51
26,003.76 33.51
### 225.66
Page 13 of 24
10/17/2019
UNIT COST
Total
2,960.08 6.52
Page 14 of 24
10/17/2019
UNIT COST
Total
37,416.60 6.76
415,338.29 12.47
15,039.90 5.10
### 659.55
Page 15 of 24
10/17/2019
UNIT COST
Total
29,771.70 425.31
39,571.65 280.65
33,417.00
2,703.87
3,422.90
Page 16 of 24
10/17/2019
UNIT COST
Total
5,333.58 34.86
4,850.36
282.46
152.33
2,659.80 20.46
2,425.18
141.23
76.17
447.10 5.26
294.00
131.03
762.48 28.24
689.33
4,914.00 378.00
4,680.00
228.50
Page 17 of 24
10/17/2019
UNIT COST
Total
311.10 3.66
196.00
87.36
133,770.45 414.15
118,218.00
6,854.89
8,677.78
10,587.42 26.94
9,700.71
564.92
304.66
5,413.20 17.35
4,850.36
282.46
152.33
1,178.55 4.05
Page 18 of 24
10/17/2019
UNIT COST
Total
784.00
349.42
773.76 8.32
689.33
10,909.80 376.20
10,440.00
456.99
852.63 2.93
588.00
228.50
288,629.35 618.05
261,520.00
11,881.82
15,041.48
19,849.92 26.97
Page 19 of 24
10/17/2019
UNIT COST
Total
18,188.83
1,059.23
571.24
9,490.50 17.10
8,488.12
494.31
266.58
2,232.78 3.98
1,470.00
655.17
2,331.60 8.04
2,067.99
18,411.75 375.75
17,640.00
761.65
Page 20 of 24
10/17/2019
UNIT COST
Total
1,935.45 3.45
1,176.00
524.14
241,340.00 877.60
223,025.00
8,073.54
10,220.50
11,906.40 27.06
10,913.30
635.54
342.74
5,426.19 17.01
4,850.36
282.46
152.33
1,501.50 3.90
980.00
Page 21 of 24
10/17/2019
UNIT COST
Total
436.78
1,566.53 11.27
1,378.66
10,181.70 377.10
9,720.00
456.99
1,305.15 3.39
784.00
349.42
269,352.00 1,247.00
253,800.00
6,854.89
8,677.78
10,394.95 16.37
8,961.27
Page 22 of 24
10/17/2019
UNIT COST
Total
918.00
495.08
8,086.50 17.97
7,275.53
423.69
228.50
1,505.43 3.87
980.00
436.78
1,571.94 7.38
1,378.66
13,575.60 377.10
12,960.00
609.32
1,135.88 2.92
Page 23 of 24
10/17/2019
UNIT COST
Total
784.00
349.42
Page 24 of 24