Professional Documents
Culture Documents
In-depth: Philippines
2015 Investment Guide
by KPMG in the Philippines
In this issue:
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Infrastructure
The Infrastructure Issue
In-depth: Philippines
Philippines
2014-2015 Edition
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Cont
Contents
Contents
ents
Contents
Introduction 01 02 03
02Introduction
Contributors
Introduction
Introduction 0203
Acknowledgements
Contributors
Contributors
Contributors 03
04 Acknowledgements
03 Acknowledgements
Appendix
Acknowledgements 67Appendix
04
04 Appendix 04Glossary
85
Glossary 74 About
85
Appendix 85
86 86
theAbout
Glossary Philippines
Glossary
About 8675About
the the
Philippines
the Philippines 87
87Philipp
05
08
08
08 11
14 22
14
14 19
22 25
22 3636 45
36 31
45
45
TheA Promising
TheThe EconomicNEDA
Economic
Economic TheNEDA
NEDA Philippine DPWHPaving
DPWH
DPWH -the-Way
Paving
Paving
- Paving Building
Building
Building TheAddressing
TheThe
Economy
Promise
Promise
Promise Medium
medium
medium
medium termterm
term Through
the thethe
wayway wayGood
through
through
through Through
through
through
through the Challenges
Challenges
Challenges
Development
development Good
development
development Governance
Good
Good Partnerships Challenges
Partnerships of an
Partnerships of an
of an
planPlan
plan
plan Governance
Governance
Governance of an
Emerging
Emerging
Emerging
GlobalGlobal
Emerging
Global
CityGlobal
CityCity
City
2 | Infrastruct
2 | Infrastruct
2 | Infrastruct ure Guide:
ure Guide:
ure Guide: Philippines
Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
tct
ory ofof
ofory Directory
Gover nment
Gover
Government nment Ag 90 90
of Government
Agencies
encies
Agencies 90
Agencies
KPMG
KPMGKPMG 76
Direct
About
ory
Direct
Directory ofof
ofory
ParKPMG
Par
Par
tners 77and
tners
tners
and Directory
and
Pr PrPr 92
incipals 9292Our
of Partners
incipals
incipals Our OurV
and 94
alues 94
94
Principals
Values
Values 78 Our Values 79
57
57 63
39 6347 71
71
53 80
80
57 61
Water
Water Enhancing Issues
Issues
Developing
in in Taxation
TaxationTaxation
of of of Project
Project
Funding
RiskRisk of Project Risk
Resources
Water
Resources Developing
Energy
Developing Infrastructure
Infrastructure
Infrastructure Management
Infrastructure
Management Management
Resources Energy
Energy Projects
Resources Projects Projects Projects
Resources
Resources
Infrastruct
Infrastructure
Infrastructure ure Guide:
Guide: Philippines
Philippines |3 |3
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
ntroduction
Intr oduction
Introduction
Philippine real
Philippine gross
The real domestic
Philippines
gross domestic product
continues to (GDP)
productbe one grew
(GDP) of gre
the5.7w percent
strongest
5.7 percent in the
and first quarter
fastest-growing
in the first quarter
of 2014, which
of 2014, waswas
economies
which low iner than
Southeast
low the 7
er than .2 percent
Asia.
the 7.2With groimpressive
an
percent wth for full
growth year
foraverage 201GDP
full year 3201
and the theof
3growth
and
6.8 percent 6.3%
6.8 percentgrowthsince
gro in 20
wth the start
in12.
2012. ofNotwithst
the Aquino
Notwithst anding administration
the slo
anding thewdo wn in
slowdo 2010,
whic
wn h was
which thewas
country
attributed
attributed
to the the remains
to impactimpact ofstrong
of the nat
theural inural
nat its economic
disasters in 20in
disasters management
13201on3agricult andand
ure
on agricult is committed
ure to a to
and to
tightening
a tightening
biasbias in improving
in monet monetar y its
ar y policies, investment climate
the Philippines
policies, the Philippines wasinw order
still tothird
the
as still achieve
the further
fastest
third progress.
growing
fastest growing
economy
economy Rating
in Asia agencies
af
in AsiaterafChina have
and also
ter China consistently
MalaMalaysia.
and ysia. In the In upgraded
last five five
the last theyears,
years, credit ratings
the Philippines
the of the
Philippines
real real
GDPGDP Philippines.
gre wgreatwanataanvMoody’s
erage
averageof assigned
6.33 a positive
percent,
of 6.33 the third
percent, theoutlook of Baa3
highest
third growth
highest to wth
gro the
ratecountry in
afterafter
rate
Singapore
SingaporeSeptember
and and
China.China.2014 while Standard & Poor’s improved its rating with a stable
outlook of BBB in May 2014. Fitch affirmed the country’s long-term
Roberto
oberto Roberto G. Manabat
G. Manabat
G. Manabat foreign
The countr
The countr y's and
y's strong
strong local currency
performance
performance hasissuer
has caughtcaught default
the atthe ratings
attention
tention at ‘BBB-’
of global
of global
and ‘BBB,’
Chairman
hairman Chairman
& CEO & CEO
& CEO investors
investors and respectively,
and
has has
been been in
recogniz March
recogniz
ed, 2014.
ed,
some some
what what belatedly,
belatedly , by by rating
rating
1
Enhancing Competitiveness in an Uncertain World, World Bank East Asia and Pacific Economic Update. October 2014.
1 | Infrastructure
2 | Infrastruct In-depth:
ure Guide: Philippines
Philippines
2 | Infrastructure Guide: Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
C
Infrastructure
Infrastruct ure Guide: In-depth: Philippines
Philippines |2
Infrastructure Guide: Philippines |3 |3
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
ontribut
Contr ors
Contributors
ibut ors
Contributors
The Economic
The EconomicPromise
The Economic Promise
Promise The Challeng es ofThe
The Challenges anofChallenges
an of an
Project Risk Risk
Project Management Building
Project
Management is through
Risk Management
is is Emer
Emer Enhancing
ging ging
Global WaterGlobal
Emerging
Global Resources
frequently overlooked
frequently Partnerships
yet isyet
frequently
overlooked oneis of
overlooked
one of yet is one of City City
Jerome City
Garcia is a Principal in the
Transactions & Restructuring
the more critical
the more thePaul
elements
critical Afable
more is
tocurrently
tocritical
elements elementsa senior
to Project Risk Management
Project
Project Risk Management is Management
Risk is is
successful project
successful
manager in the Advisory group of
deliv eries.
successful
project project deliveries.
deliveries. frequently ogroup
frequently
of R.G. Manabat & Co. He
verlooked yet isyet
frequently
overlooked oneis of
overlooked
one of yet is one of
R.G. Manabat & Co. He has has over 15 years of experience in
Generally, delivering aservice
project’
Generally, s
delivering the more critical
the more elements
the
the critical more tocritical
ofelements to elements to
Generally, deliv ering a project’s
experience inadifferent
project’s areas mergers and
defined scope
defined on time
scope defined
on and scope
time within
and
industries such onastime
within andfinancial
energy, within successful project
successful delivinvestment
project
acquisitions, eries.
successful project
deliveries. deliveries.
banking,
budget are characteristics
budget budget
are characteristicsof
areproject
services, characteristics
of project
public ofand
sector, retail project Generally, deliv
Generally, ering
deliv
corporate a project’
Generally,
ering s financial a project’s
delivering
a project’s
finance, and
success.
success. success.
real estate. defined scope
defined on time
scope
advisory,defined
on andbeen
time
having within
scope on time and within
andpreviously
within
connected with several
investment banks and financial
Paul Patrick R. Afable Jerome Andrew institutions.
H. Garcia
2 3 | Infrastructure
| Infrastruct Guide: In-depth:
2ure| Infrastructure
Philippines Philippines
Guide: Philippines
nfrastruct ure Guide: Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
WeWe We
areare are fgrateful
grateful or fthe
grateful or for
valuable
the
Project the
valuable
Risk vinsights
aluable
Management insights
of the
insights of the following:
following:
of the following:
Project Risk Management
Geno Armstrong is a principal in Jonathan Jong is a Chartered Civil
KPMG’s Major Projects Advisory Engineer and experienced project
Mr.
Mr.services
Rolando Mr.G.
Rolando Rolando
practice. TG.
He G. Tungpalan
hasTungpalan
ungpalan manager who has advised
substantial experience with cost infrastructure clients on project
Deputy
Deputy Deputy
Director
Director Director-General,
-General,
-General,
auditing, Inrisk and Investment
vestment
Investment
independent Programmingdelivery, project controls, risk
Programming
Programming
National National
National Economic
Economic
controls Economic
Development
assessments, and Development
Development Authority
Authority
Authority management, project monitoring
assisting companies in developing and project reporting. He has
appropriate strategies that extensive experience in
Ms.Ms.
Mar iaMs.
Mar
promote Maria
ia Catalina
Catalina
successful E.Catalina
project E. Cabral
E. Cabral
Cabral construction, infrastructure,
delivery. transportation, aviation, rail and
Geno Armstrong Assistant
Assistant
Assistant Secretary Secretary
Secretary Jonathan Jong mass-transit projects.
Department
Department
Department of Public Woforks
of Public Public
W andW
orks orks
and and
Highw
Highw Highways
aysays
Project
Ms. Ms. Risk
Cosett Mes. Cosette
Management
Cosett e Canilao
Canilao Canilao
We are grateful for the valuable insights of the
Reid Tucker is currently a director following:
inExecutive
KPMG’s MajorExecutive
Executive Director
Director
Projects AdvisoryDirector
Pulbic-Private
Pulbic-Private
Pulbic-Private practice
Partner with Partner
Partner
ship ship
over ship
Center
16 years
Center of Center
of the
of the of the Philippines
Mr. Philippines
Philippines
Rolando G. Tungpalan
project management, construction
Deputy Director-General, Investment Programming
management, project accounting
National Economic Development Authority
and contract
Mr. Mr.
Geno GenoMr.
Ar GenoInArmstrong
administration.
Armstrong
mstrong
addition, Reid has assisted in
Principal,
Principal,
establishing Principal,
Advisory
Advisory
project management Advisory
Ms. Maria Catalina E. Cabral
KPMG LLP Assistant Secretary
(U.S.)
KPMG KPMG LLPLLP
office organizations for (U.S.)
delivering
(U.S.)
major power and utility Department of Public Works and Highways
Reid Tucker construction programs.
Mr. Mr. Mr.
ReidReid Reid Tucker
Tucker
Tucker Ms. Cosette Canilao
Executive Director
Director
Director Director, Advisory
, Advisory
, Advisory Pulbic-Private Partnership Center of the Philippines
KPMG LLPKPMG
KPMG LLP LLP (U.S.)
(U.S.)
(U.S.)
Infrastruct
Infrastruct ureInfrastructure
ure Infrastructure
Guide:Guide: In-depth:
Guide: | 3 Philippines
| 3 Philippines
Philippines
Philippines |3 |4
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
AAPr
Proomising
mising
Econom
Economyy
Cristina Roxas, Advisory Partner, KPMG in the Philippines
Emmanuel P. Bonoan, Vice Chairman and Head ofTax, KPMG in the Philippines
Philippine gross domestic product (GDP) grew 5.7 percent in the first quarter of 2014, which was
Philippine
lower gross
than the domestic
7.2 percent product
growth for(GDP)
full yeargrew 5.7and
2013 percent in percent
the 6.8 the first growth
quarter inof2012.
2014, which was lower
than the 7.2 percent growth for full year 2013 and the 6.8 percent growth
Notwithstanding the slowdown – which was attributed to the impact of the natural disasters in 2012. Notwithstanding
in the
slowdown – which was attributed to the impact of the natural disasters in 2013 on
2013 on agriculture and to a tightening bias in monetary policies – the Philippines was still the thirdagriculture and to a
tightening
fastest biaseconomy
growing in monetary policies
in Asia – the Philippines
after China and Malaysia.wasInstill
thethe third
last fivefastest
years, growing
Philippineeconomy
GDP in Asia
after China and Malaysia. In the last five years, the Philippine GDP grew at
grew at an average of 6.33 percent, the third highest growth rate after Singapore and China. an average of 6.33 percent,
the third highest growth rate after Singapore and China.
The country's strong performance has caught the The recent turn of economic developments in the
The country's
attention of globalstrong performance
investors has caught
and has been the attentioncountry
recognized, The recent turn of economic
has prompted investors developments
and analysts toinaddthe country
of global investors and has been recognized,
somewhat belatedly, by rating agencies. Last year, somewhat the has prompted
Philippines in investors
various and
lists of analysts to
countries add the Philippines
thebelatedly, by rating
three rating agencies.
agencies, LastStandard
Moody’s, year, the&three rating in various the
representing listsnext
of countries representing
wave, beyond the next wave,
Brazil, Russia,
agencies,
Poor’s (S&P) Moody’s, Standard
and Fitch finally & Poor’s
upgraded the(S&P) and Fitch
country’s beyond
India Brazil,
and China Russia,
(the India
BRICs), and China economies
of promising (the BRICs), of
finally
rating on upgraded the country’s
external debt ratinggrade
to investment on external
– debt to withpromising
significanteconomies with significant upside potentials:
upside potentials:
investment
although grade –have,
the markets although the markets
for several years,have,
beenfor several
years,
pricing been pricing
Philippine debt Philippine debt at tighter
at tighter spreads than itsspreads than Global
Global GrowthGrowth Generators
Generators (GGG)
(GGG) countries
countries “with the
“with
its credit
credit rating.rating. the most
most promising
promising growth
growth prospects
prospects in
in the
the coming
decades:
coming Bangladesh,
decades: China,
Bangladesh, Egypt,
China, India, Indonesia,
Egypt,
Underlying
Underlying thethe remarkable
remarkable perf
perf ormance
ormance areare strong
strong Iraq,
India, Mongolia,
Indonesia, Nigeria,
Iraq, Philippines,
Mongolia, Nigeria,Sri Lanka and
1 1
1 1
CitiCiti
Global “Gro
Global wthwth
“Gro Generators: MoMo
Generators: ving beybey
ving ondond
‘Emerging
‘EmergingMark ets’ and
Markets ‘BRIC’”
’ and . Global
‘BRIC’” Economics
. Global VieVie
Economics w 21 February
w 21 2011.
February 2011.
2 2
Goldman
Goldman SacSachs.
hs. “The N-1N-11:
“The 1: More Than
More AnAn
Than Acronym. ” Global
Acronym. Economics
” Global EconomicsPaper NoNo
Paper 153. 28 28
153. March 2007
March . .
2007
3 3
Wall Street
Wall Journal,
Street “Beyond
Journal, BRIC:
“Beyond TheThe
BRIC: NeNe
xt Break out Stars
xt Breakout of Emerging
Stars Mark
of Emerging ets.” Priv
Markets. ateate
” Priv Equit y Beat.
Equity 15 15
Beat. May 2013.
May 2013.
5 | Infrastructure In-depth:
2 | Infrastructure Philippines
Guide: Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
complement the rapidly growing services sector, domestic
becoming, along with the BRICs, the world’s Infrastructure:
and foreign the Challenge
private investments have toand
beOpportunity
attracted to the
largest economies of the 4 21st century. (Time, Among the key challenges to
manufacturing sector to create jobs in largean investment-led
numbers for
becoming, along
March 2014) 4 inclusive growth
growth.are the significant gaps in the country’s
with PPICS: Peru, Philippines, Indonesia, Colombia, infrastructure and resolving the infrastructure deficits
and Sri Lanka as countries “which
5 are will bythe
Infrastructure: itself be a main
Challenge anddriver for growth.
Opportunity
March 2014) accelerating their development.” (COFACE, Among the key challenges to an investment-led growth are
March 2014) 5 Indonesia, Colombia, and Sri The major
PPICS: Peru, Philippines, the significant gapsgaps
in theincountry’s
the country’s roads, ports,
infrastructure and airports,
Lanka as countries “which are accelerating their resolving the infrastructure deficits will by itself be a been
urban mass transit, water, and energy have main the
In order to ”realize the promise of its strong potential
development. (COFACE, March 2014) driver forcumulative
growth. result of years of underinvestment and
for improving the lives of ordinary Filipinos and delays in implementing public capital expenditures,
transforming the economy, the Philippines will have
In order to realize the promise of its strong potential for The major gapsconstraints,
fiscal and weak
in the country’s roads,institutions for urban
ports, airports,
improvingtotheachieve consistent
lives of ordinary real economic
Filipinos growth of six to
and transforming governance.
mass transit, water, and energy have been the cumulative
seventhe
the economy, percent sustained
Philippines for seven
will have to 10 years. It has
to achieve result of years of underinvestment and delays in
toreal
shifteconomic
from a consumption-led
growth of six togrowth to an According
consistent seven percent implementing publictocapital
the latest survey in the
expenditures, World
fiscal Economic
constraints,
sustainedinvestment-led
for seven to 10one. To complement
years. It has to shiftthe
fromrapidly
a Forum Global Competitiveness
and weak institutions for governance. Report from 2013 to
growing growth
consumption-led servicestosector, domestic and
an investment-led foreign
one. To private 2014, the Philippines ranks a very poor 98 in the
investments have to be attracted to the overall
According to thequality
latest of infrastructure
survey compared
in the World Economic to its Asian
manufacturing Competitiveness
Global Infrastructure sector to create jobs in large numbers
Country
Global Infrastructure Competitiveness Ranking
Indicator Philippines Singapore Malaysia Thailand Indonesia Vietnam
Country Country
Quality of roads 87 7 23 42 78 102
Indicator
Quality of railroad infrastructure 89
Philippines
10
Singapore
18
Malaysia
72
Thailand
44
Indonesia
58
Vietnam
Quality
Quality of port of roads
infrastructure 116 87 2 7 24 23 56 4289 7898 102
Quality of railroad infrastructure 89 10 18 72 44 58
Quality of air infrastructure 113 1 20 34 68 92
Quality of port infrastructure 116 2 24 56 89 98
Quality of electricity Supply 93 8 37 58 89 95
Quality of air infrastructure 113 1 20 34 68 92
Fixed telephone connectivity
Quality of electricity supply 109 93 29 8 79 37 96 5882 8988 95
Mobile telephone connectivity
Fixed telephone connectivity 81 109 18 29 27 79 49 9662 8221 88
Overall Mobile telephone connectivity 98 81 5 18 25 27 61 4982 62110 21
Overall
Source: World Economic Forum (WEF) Global Competitiveness 98
Report 2013-2014 5 25 61 82 110
Source: World Economic Forum (WEF) Global Competitiveness Report 2013-2014
4
Michael Shuman
4 “Forget the BRICs; Meet the PINES.” TIME Business Emerging Markets 13 March 2014
5 Michael
Coface “COFACE Shuman “Forget
IDENTIFIES the BRICs;
10 EMERGING Meet the PINES.
COUNTRIES HOT ON” TIME Business
THE HEELS OFEmerging Markets
THE BRICS, 13 Risk
Country March 2014
and Economic Studies. 25 March 2014.
5
Coface “COFACE IDENTIFIES 10 EMERGING COUNTRIES HOT ON THE HEELS OF THE BRICS, Country Risk and Economic Studies. 25 March 2014.
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines |3 |6
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
TheThe Philippines’
Philippines’ overall
ov erall ranking
ranking is second
is second from
from thethe
botbottom after
tom after Vietnam.
Vietnam. It ranked
It ranked thethe worst
worst on on
fivefive indicators
indicators andand came
in second from the bottom after Vietnam on the other two indicators, which are quality of roads
came in second from the bottom after Vietnam on the other two indicators, which are quality of roads and and electricity supply.
electricity supply.
For specific sectors, there have been some improvements over the recent years, but the Philippines still ranks low among
For144 countries
specific in the
sectors, survey.
there have been some improvements over the recent years, but the Philippines still ranks low
among 144 countries in the survey.
Ranking and status of the Philippines, 2010-2012, and selected ASEAN countries, 2012, in key infrastructure indicators
Ranking and status of the Philippines, 2010-2012, and selected ASEAN countries, 2012, in key infrastructure indicators
Ranking/status of selected ASEAN countries in 2012
Ranking/status of selected ASEAN countries in 2012 Ranking/status
Indicator Philippine ranking/status of selected ASEAN countries in 2012
Indicator 2010 2 011 2012 Malaysia Thailand
2010 2011 2012 Malaysia Thailand Cambodia
Indonesia Indonesia Cambodia
Vietnam Vietnam
Source:e-Government
Table 10.1 fromranking 8
NEDA (2014) Philippine Development 78
Plan
of–183
Midterm Update
(nowith Results Matrices.
data;
190
88 of 40 92 97 155 83
Chapter 10: Accelerating infrastructure development, p. 3/24. Reproduced with permission.
survey conducted
twice atwice
year)a year)
Real life costs of infrastructure bottlenecks
9
GoingWater
beyond
supplythe statistical
coverage comparisons, the infrastructure
84.8% deficiencies (no
84.4% translate
data) to real100%
costs to
96%the economy
- - in 96%
termsSanitation
of productivity
coverage 9 and efficiency and to ordinary
92.5%
citizens in
91.9%
terms of travel time,
(no data)
congestion,
100%
pollution,
100% -
and poor
- -
access to basic utilities.
Hospital beds per 1,000 people 10 0.5 (c. 2009) 1.0 (no data) 1.8 2.10 - - 2.2
(2009-2011) (c. 2010) (c. 2010)
For public transport, commuters anecdotally report a commute of three to four hours every day, requiring several
Source: Table
transfers from10.1 from NEDA
tricycle, (2014) Philippine
minivans, Development
rail and bus from Plan – Midterm
the suburbsUpdate with Results
to Makati, Matrices.
Metro Manila’s main business district.
Chapter 10: Accelerating infrastructure development, p. 3/24. Reproduced with permission.
Bloomberg quoted a jeepney driver who has been driving for 20 years who said that a 15-kilometer route which
used to take 30 to 40 minutes now takes two hours, cutting down his turnaround time and daily income.11
increase in jeepney trips (less efficient for transporting people) was twice as much as the increase in bus trips.12
For a transport system to be successful in large volumes of passengers in urban areas, the system should be able to shift
ridership away from cars, jeepneys and buses to urban mass transit systems – with cars as the least socio-economically
Correlating the trends in person trips and vehicle trips, the trend reflects an increase in car ownership and a decline
efficient people movers across this range of transport modes to trains as the most efficient.
in the occupancy rate per vehicle. These trends do not augur well for more efficiency in moving people and
reducing congestion.
What has been happening, however, has been the opposite. From 1996 to 2012, person trips by car increased 15 percent
whileCompetitiveness
6 Global trips using public transport (jeepneys and buses) declined by 7 percent.
Reports for 2010-2011, 2011-2012 and 2012-2013 by World Economic Forum
7
Measuring the Information Society (MIS) Reports for 2011, 2012 and 2013 by International Telecommunication Union (ITU)
8 6
Global
United Competitiveness
Nations Reports forSurvey
Global e-Government 2010-202011,
10 2011-2012
and 2012
and 2012-2013 by World Economic Forum
Measuring
9 Annual Povertythe Information
Indicators Society
Survey (MIS)
Report for Reports
2010 andfor 2011,
2011 by 2012 andStatistics
National 2013 by International Telecommunication
Office (for Philippines); ProgressUnion (ITU) and
on Sanitation
8
UnitedWater:
Drinking Nations Global
2013 e-Government
Update by WHO and Survey
UNICEF 2010 and
(for 2012
countries)
ASEAN
10 9
Annual
World Bank Poverty
– HealthIndicators
NutritionSurvey Report forStatistics
and Population 2010 and 2011 by National Statistics Office (for Philippines); Progress on Sanitation and
11
DrinkingNews,
Bloomberg Water:“Epic
2013Gridlock
Update by WHOover
Reigns andManila’s
UNICEF23 (forMillion.
ASEAN countries)
” 10 April 2014.
12 10
World
JICA, Bank –for
Roadmap Health Nutrition
Transport andDevelopment
Sector Population Statistics
for Metro Manila and Its Surrounding Areas
11
Bloomberg
(Region III and News,
Region“Epic
IV-A).Gridlock Reigns
Final Report over
Main Manila’s
Text. March23 Million.
2014 ” 10. April 2014.
p. 2-37
7 | Infrastructure In-depth:
2 | Infrastructure Philippines
Guide: Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
The congestion caused by the inadequacy of mass Citigroup
Without toan
bealternative
as much as PhP320linkage
transport billion (about
between2.9 the
The congestion
transitscaused by the
is feeding oninadequacy of mass
itself, as Metro transits
Manila residents percent of GDP), putting
economic zones in the at risk about a million
is feeding buy
on itself, as Metro Manila residents
more cars but use them less efficiently: carbuy more manufacturing jobs. Citigroup also said that the ensuing
Cavite-Laguna-Batangas-Rizal-Quezon
cars but use them less
occupancy efficiently:
decreased car 2.5
from occupancy
to 1.7 persons per car. transportation
(CALABARZON) bottleneck could chop
area, Citigroup atestimated
has least 1 percent
the to
decreasedThe from 2.5 to 1.7 persons per car. The efficiency
efficiency of public transportation has also of as economic
much as 5cost
percent offtruck
of the the country’s GDP estimated
ban has been mostly
public transportation has also suffered with
suffered with vehicle occupancy for jeepneysvehicle through the impact
by Citigroup to beonasthe
muchcountry’s
as US$7nontechnology export
.25 billion (about
occupancy 12
for jeepneys
declining fromdeclining
15.1 to 10,from 15.1
while fortobuses
10, while for
vehicle commodities.
2.9 percent of GDP), putting at risk about a million
buses vehicle occupancy decreased from 46.5
occupancy decreased from 46.5 to 35.5 passengers.to 35.5 manufacturing jobs.16 Citigroup also said that the
passengers. MoreMore trips
trips made
made in vehicles
in vehicles areare
lessless efficient,
efficient, and Theensuing
truck ban has further implications
transportation on the
bottleneck could cost
chop atof cargo
least
and thesethese
vehicles, in general, are being used less
vehicles, in general, are being used less shipping. Shipping
1 percent companies
to as much such asoffHapag
as 5 percent Lloyd
the country’s
efficiently.efficiently.13 impose a congestion
GDP mostly surcharge
through the impactof US$100 per twenty-foot
on the country’s
equivalent unit (TEU) on all imports
nontechnology export commodities. into Manila as a result
In the meantime, traffic studies
In the meantime, show
traffic thatshow
studies most that
roads are
most of higher operational costs.
operating roads
at close to capacity, resulting in frequent
are operating at close to capacity, resulting in The truck ban has further implications on the cost of
gridlocks and reduced
frequent travel and
gridlocks speeds. A recent
reduced travelJapan
speeds. A Forcargo
air infrastructure,
shipping. according
Shipping to Deputy
companies Director
such as HapagGeneral
16
International Cooperation Agency (JICA)
recent Japan International Cooperationstudy reported
Agency (JICA) JohnLloydAndrews
imposeofathe Civil Aviation
congestion Authority
surcharge of the per
of US$100
that with astudy
few exceptions,
reported that the average
with a fewspeed in major
exceptions, the Philippines
twenty-foot (CAAP), airlinesunit
equivalent have been
(TEU) onincurring
all importslosses
into of
Metro Manila roads
average is 10 in
speed kph, withMetro
major 75 percent
Manilatoroads
92 is 10 kph, more thanas
Manila PhP7 billion
a result of ahigher
year inoperational
fuel expenses costs.because
17 of
percent ofwith
travel
75inpercent
the network below 20ofkph.
to 92 percent travel in the network the worsening congestion at Ninoy Aquino International
below 20 kph.14 Airport
On 13 (NAIA).
September Planes unable
2014, the to immediately
Manila land, for
City government
The same JICA study has estimated that the economic example, would need to burn extra amounts
temporarily lifted the seven-month old truck ban of fuel.in
cost of congestion
The sameatJICA
PhP2.4 billion
study has per day in Metro
estimated that the Andrews estimated that about 200,000 to
light of the severe congestion in the Port of Manila 400,000
Manila, and another
economic PhP1.0
cost of billion in
congestion the Bulacan,
at US$54.35Rizal,
million per kilograms
and major in additional
losses to fuel are expended
exporters as a result
and importers, foodof the
Laguna and 13
dayCavite area.Manila,
in Metro This amounts to PhP1.2
and another trillionmillion
US$22.65 per in congestion,
shortages,orrisingPhP10 million
prices of to PhP20
basic million
goods, a day,
traffic jams,by the
year in thethe
Mega Manila area or 11 percent of GDP .
Bulacan, Rizal, Laguna and Cavite area. This airlines.
and the Airlines
threatincur close
of an17 to PhP3.7
estimated US$7 billion a year
.25 billion in to
loss
amounts to US$27.18 billion per year in the Mega added fuel expenses
the economy and lose
attributed another
to the PhP3.7
truck ban. billion
Prior from
to the
A truck ban scheme
Manila areahasor been in place
11 percent in Metro
of GDP . 15 Manila “engine costs and cost of aircraft time. ”
lifting of the truck ban the government formed a Task
since 1978 whereby cargo trucks with a gross vehicle Force Pantalan to oversee traffic management along
weight (GVW) of more
A truck than 4,000
ban scheme kg areinprohibited
has been place in Metrofrom In the
the power space, the critical
major thoroughfares power
leading outsituation in the
of the Port of
passing along major thoroughfares during peak
Manila since 1978 whereby cargo trucks with traffic rush
a gross country is 18well-documented. Electricity prices are the
Manila.
hours in the morning
vehicle weightand(GVW)
in the afternoon.
of more than The scheme
4,000 kg are highest in Asia, even higher than Japan. There is limited
14
has been modified
prohibitedoverfrom the years in
passing terms
along of restricted
major thoroughfares supply in the
For air Philippinesaccording
infrastructure, comparedtotoDeputy
other countries.
Director
18
hours, alternative
during peak traffic rush hours in thenet
routes, and GVWs but the effect has
morning and in According to an American Chamber of
General John Andrews of the Civil AviationCommerce report,
Authority
been the reduction in efficiency and increase
the afternoon. The scheme has been modified in the cost ofover Thailand has 40,699MW power capacity serving 67
of the Philippines (CAAP), airlines have been incurring million
transporting
thegoods
years in
in Metro
terms Manila. The underutilization
of restricted hours, alternative of people. South Korea has 79,859MW serving 49
losses of more than US$158.56 million a year in fuel million
freight vehicles
routes,has
and induced
GVWs freight
but theforwarders
net effect hasto have
been the while the Philippines
expenses becausehas onlyworsening
of the 15,680MW for 90.3 million
congestion at
more trucks than necessary
reduction to handle
in efficiency the cargoes
and increase in thein and people.
Ninoy In per capita
Aquino terms, electricity
International consumption
Airport (NAIA).19
Planesin the
15cost of
out of ports
transporting goods in Metro Manila. The trips
during the limited time windows. Trucks Philippines
unable toisimmediately
the lowest at 588for
land, kilowatt-hour (kwh).need
example, would
per day are cut down fromofthree
underutilization to vehicles
freight one. Thehas additional
induced freight to burn extra amounts of fuel. Andrews estimated
transport costs are then passed on to consumers.
forwarders to have more trucks than necessary to Electricity
that about supply and demand
200,000 indicators,
to 400,000 ASEAN-6,
kilograms 2008
in additional
handle the cargoes in and out of ports during the Installed
fuel are expended as a result of the congestion, or
Recently, the citytime
limited of Manila imposed
windows. a ban
Trucks onper
trips eight
day are cut Capacity
US$226,000 to US$453,000 a day, by the airlines.
wheelers down
and vehicles with a gross weight of 4,500 kgs
from three to one. The additional transport (MilAirlines
KW), incur close to US$83.79 million a year in
from plying Manila’s
costs streets
are then between
passed on to 5:00am to 9:00pm,
consumers. 2008
addedTotalfuel expenses and lose another US$83.79
with a temporary concession for six to eight months, domestic
million from “engine costs and cost of aircraft time.”
allowing aRecently,
window from 10:00am
the city to 3:00pm.
of Manila imposedWithout
a ban onaneight production
alternativewheelers
transportand
linkage between the economic zones
vehicles with a gross weight of 4,500 (GWh),
In the power space, the critical power situation in the
in the Cavite-Laguna-Batangas-Rizal-Quezon
kgs from plying Manila’s streets between 5:00am to 2008
country Total supply,
is well-documented. Electricity prices are
(CALABARZON)
9:00pm, area,
withCitigroup has estimated
a temporary concession the
for six to eight includes
the highest in Asia, even higher than Japan. There is
economic months,
cost of the
allowing a window from 10:00amby
truck ban has been estimated to 3:00pm. netalso
exports
limited supply in the Philippines compared to
12
JICA, Roadmap for Transport Sector Development for Metro Manila and Its Surrounding Areas
(Region III13and Region IV-A). Final Report Main Text. March 2014 p. 2-37.
Ibid.
13 Ibid.
14 JICA (2014) p. 2-38.
14 JICA (2014) p. 2-38.
15 Op. cit. p. 2-41
15 Op. cit. p. 2-41
16 Citi Macro Research Note 7 March 2014
16 Citi Macro Research Note 7 March 2014
17 SeaNews, Truck ban prompts Hapag-Lloyd to levy Manila import congestion charge, 3 June 2014.
17 SeaNews, Truck ban prompts Hapag-Lloyd to levy Manila import congestion charge, 3 June 2014.
18
18
“Erap lifts Manila city truck ban”, Philippine Daily Inquirer, 14 September 2014.
19 Inquirer, “Airlines losing P7 billion due to congested airport.” 29 May 2014.
Philippine DailyPhilippine Daily Inquirer, “Airlines losing P7 billion due to congested airport.” 29 May 2014. Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines |3 |8
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Electricity supply and demand indicators, ASEAN-6, 2008
Electricity supply and demand indicators, ASEAN-6, 2008
Installed
Installed TotalTotal Total supply,Total Total
Total supply, PopulationConsumption
Population Consumption Distribution
Distribution &
&
Capacity domestic includes
includes consumption,
consumption, (million), per capita
Capacity domestic (million), per capita transfer
transfer
(Mil KW), production net exports
net exports includes use
includes use 2008 (kWh), 2008 losses as losses
% of
as % of
2008(Mil KW), production
(GWh), (GWh), 2008 2008 of energy
(GWh), of energy 2008 (kWh), 2008total supply,
1
total supply,
2008 sector sector
but netbut net 2008 1
2008 (GWh), 1
of distribution 2008
of distribution
2008 & transfer
& transfer
losses (GWh),
2008 losses (GWh),
2008
Indonesia
Indonesia 27.8016
27.8016 149,437
149,437 149,437
149,437 134,399
134,399 227.3 227.3 591.2 591.2 10.1%10.1%
Korea, South 79.859 446,428 446,428 429,052 48.7 8,801.6 3.9%
Korea, South 79.859 446,428 446,428 429,052 48.7 8,8
8,8001.6 3.9%
Malaysia* 22.973 96,916 97,392 94,721 27.0 3,506.3 2.3%
Malaysia* 22.973 96,916 97,392 94,721 27.0 3,506.3 2.3%
Philippines 15.680 60,821 60,821 53,140 90.3 588.2 12.6%
Philippines 15.680 60,821 60,821 53,
53,1140 90.3 588.2 12.6%
Singapore 10.950 41,717 41,717 39,610 4.8 8,184.9 5.1%
Singapore 10.950 41,717 41,717 39,610 4.8 8,184.9 5.1%
Thailand** 40.669 149,032 147,427 140,079 67.4 2,078.7 6.1%
Thailand** 40.669 149,032 147,427 140,079 67.4 2,078.7 6.1%
Vietnam 13.850 76,269 73,049 68,907 86.2 799.3 10.1%
Vietnam 13.850 76,269 73,049 68,907 86.2 799.3 10.1%
Notes: *netInternational
Sources: energy exporter, **net
Energy energy
Agency andimporter, 1-Author’s
US Energy calculation
Information Administration; World Bank for the population
Sources: International Energy Agency and US Energy Information Administration; World Bank for the population
Notes: *net energy exporter, **net energy importer, 1-Author’s calculation
9 |8Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
The macroeconomic
The macroeconomic stability and
stability and domestic domestic financial
financial For the non-PPP projects to be executed through
evolution in recent years have created
evolution in recent years have created a base of domestica base of regular procurement, local private contractors can
ocal currency funding that can support the volume andsupport the
domestic local currency funding that can look forward to an improving governance framework
enors requiredvolume and tenors projects.
by infrastructure required by infrastructure projects. in the awarding of projects. Foreign contractors are
allowed to bid only for the so-called foreign assisted
What’s in it for the private sector? projects (FAPs) usually funded from grants and loans
The emphasis being given to the PPP modality from official development assistance (ODA) sources.
attests to the recognition and expectation that the
private sector will have a major role in solving
infrastructure bottlenecks. Among the key
challenges that remain is the need to calibrate the For further information, please contact:
risk-reward configuration offered to private investors
in PPP projects in order to have an optimal allocation
Roberto G. Manabat
of risks while attracting sufficient response from
investors to bid for the projects. This will be Chairman & CEO
important for foreign investors which are allowed to KPMG in the Philippines
Emmanuel P. Bonoan
Vice Chairman and Head of Tax
Infrastructure
InfrastructureIn-depth: Philippines| | 10
Guide: Philippines 9
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
The
Philippine
Philippine
Medium
mediumt
teer
rm m
Development
development Planplan
CristinaPRoxas,
Emmanuel Advisory
. Bonoan, Partner,
Vice Chairman KPMG
and Head in the
ofTax, Philippines
KPMG in the Philippines
2012
Source: Department of Budget and Management and National Economic and Development Authority 2016
Source: Department of Budget and Management and National Economic and Development Authority
Infrastructure development is to beNote: a key driver
Actual figuretoforachieve
2012. this rapid and sustained growth.
1
NEDA (2014) Philippine Development Plan 2011-2016– Medium Term Update with Results Matrix. Chapter 10:
1
NEDA (2014) Philippine Development Plan 2011-2016– Medium Term Update with Results Matrix. Chapter 10:
11 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Public Investment
Public Investment ProgramProgram (PIP) targets
(PIP) targets by theme*
by theme
in PhP mn in PhP mn
PDP Theme Total %
PDP Theme Total (2013 - 2016)%
(2013 - 2016)
Accelerating Infrastructure Development 2,461,220 53.2
Notes: *With possible duplication
Social
Accelerating Development
Infrastructure Sector
Development 2,461,220733,145 53.2 21.2 of investment targets reflected for
Competitive arid Sustainable Agriculture and Fisheries Sector 549,063 15.2 cross-cutting programs and
Social Development Sector 733,145 21.2
Peace and Security 207,139 4.3 projects (PAPs); May not add up
Competitive arid Sustainable
Sustainable Agriculture and
and CIimate-Resilient Fisheries Sector
Environment 549,063 176,443
and Natural Resources 15.2 4.9 due to rounding off. PIP consists of
both core investment programs
Peace and Competitive
Security and Innovative Industry and Services Sector 207,139 23,230 4.3 0.6 and projects (CIPs) and non-CIPs.
Good
Sustainable andGovernance and theEnvironment
CIimate-Resilient Rule of Lawand Natural Resources 176,443 15,752 4.9 0.4
Macroeconomic Policy 4,115 0.1 Source: Enhancing Resilience to
Competitive and Innovative Industry and Services Sector 23,230 0.6 Sustain Inclusive Growth March
Resilient and Inclusive Financial System 164 0.0
2014 Presentation of the Bangko
Good Governance
TOTAL and the Rule of Law 15,752 0.4
4,170,332 100.0 Sentral ng Pilipinas
Macroeconomic Policy 4,115 0.1
ResilientThe
and performance for the
Inclusive Financial first several months of 2014 is in line
System 164with the targets0.0 for full year 2014. Public
TOTAL infrastructure expenditures are budgeted to increase by 40 percent to US$9.15
4,170,332 100.00billion from US$6.52 billion in 2013,
which ramps up from the 36 percent growth in the public infrastructure budget in 2013. The bulk of the
expenditures will be in Roads and Bridges at US$3.37 billion for full year 2014. This is before any supplemental
budgets for the Haiyan reconstruction requirements.
There are several reasons why infrastructure spending to GDP has been historically low which continued to be
reflected in the major approval criteria for projects at the National Economic and Development
Authority-Investment Coordination Committee (NEDA-ICC). Projects are evaluated at the NEDA-ICC based on the
“fiscal, monetary and balance of payments (BOP) implications of major capital projects” taking into account the
peso requirement and foreign exchange requirements of the project in terms of current and capital outlays,
sources of funds and conditions for proposed financing, “compliance with the foreign debt ceiling under Republic
Act (RA) No. 4860 or the Foreign Borrowings Act of 1966.”
Such criteria were driven by the difficult macro environment which prevailed in the past few decades. The country
had to contend with the challenge of executing stable monetary policies on a consistent basis which was made
difficult by a weak fiscal base, chronic BOP problems, low international reserves, very high external debt (which
was restructured in the early 1990s), and limited access to international capital markets. The macroeconomic
conditions of the country posed a binding constraint on infrastructure spending. Other historical reasons were the
weak bureaucratic institutions inherited from the Marcos martial law government.
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 12
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Major
Major Government
Government Spending
Spending Initiatives
Initiatives: Ramped-up investments on public infrastructure
Ramped-up
Particulars investments on public infrastructure
2012 Actual 2013 GAA 2014 GAA Growth Rate (%)
(PhP mn) (PhP mn) (PhP mn) 2012-2013 2013-2014
Particulars 2012 Actual 2013 GAA 2014 GAA Growth Rate (%) There are several reasons why
Roads and Bridges 84,218 (PhP mn) 149,599
108,097 28.4 38.4
(PhP mn) (PhP mn) 2012-2013 2013-2014 infrastructure spending to GDP has
Basic Educational Facilities* 11,012 26,268 50,967 138.5 94.0
Roads and Bridges
Flood Control/Seawalls 84,218 108,097
11,331 149,599
16,536 28.4
34,806 38.4
45.9
been historically low which
110.5
Basic Educational Facilities*
Housing 11,012 26,268
10,518 50,967
22,373 138.5 94.0
16,317 112.7 (27continued
.1) to be reflected in the
National
Flood Irrigation
Control/Seawalls 11,331 24,193
16,536 22,212
34,806 15,785
45.9 (8.2)
110.5 major approval criteria for projects at
(28.9)
Farm-to-Market
Housing Roads 10,518 4,868
22,373 5,657
16,317 12,603
112.7 (27 16.2
.1) the National Economic and
122.8
Health Facilities Enhancement Program 5,078 13,558 9,138 167.0 (32.6)
Development Authority-Investment
National Irrigation 24,193 22,212 15,785 (8.2) (28.9)
Electrification 4,950 6,374 9,679 28.8 51.8
Farm-to-Market Roads 4,868 5,657 12,603 16.2 122.8 Coordination Committee (NEDA-ICC).
Airports/Air Navigational Facilities 802 5,195 9,114 547.8 75.4
Health Facilities
Other Public Works Enhancement 5,078 13,558
15,120 9,138
1,321 167
10 .0 (32.6)
(91.3) Projects are evaluated at the
(99.2)
Water Supply
Program 1,516 1,839 6,954 21.3 NEDA-ICC based on the “fiscal,
278.1
75.5
13 | Infrastructure In-depth:
2 | Infrastructure Philippines
Guide: Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
As in previous Public Investment
As in previous Plans, there
Public Investment is an
Plans, effort
there to
is an constructing roads, bridges, flood control, and
have an effort
integrated approach in the development
to have an integrated approach in the plan, government buildings with the projects and programs
various termed
developmentas “cross
plan,cutting”
variousor “crossasreference”
termed “cross cutting” of the Department of Tourism (DOT), Department of
projects.or As explained
“cross by NEDA
reference” Director
projects. AsGeneral
explainedRolando
by Education (DepEd), Department of Agriculture (DA)
Tungpalan,
NEDA the Director
overall investment is not just
General Rolando a collation
Tungpalan, the of
overall and local governments.
individualinvestment
projects and programs
is not (PAPs) submitted
just a collation by projects
of individual each Addressing the specific constraints faced by the poor
agency, but
and there has to
programs be a strategic
(PAPs) submittedroadmap
by each that
agency, but requires
Theconsideration of geophysical
convergence program of DPWHcharacteristics
and DOT will
integrates
there has to be a strategic roadmap that traffic,
the impact of PAPs on transportation, The integrated
integrates coordinate approach
construction is reflected of access in the roadsConvergence
to priority
drainage,theetc.
impact of PAPs on transportation, traffic, Strategies tourism destinations under the National Tourism
its
challenge of midterm
The inclusive update
growth introduces
by identifying the top
a spatial dimension and programs
upgrade of the Department
principal airports toofinternational Tourism (DOT), and
numberstopof provinces
poor families or high poverty incidence, and
most affected by poverty either in Agriculture (DA) and local governments.
also planned for Marinduque, San Jose, Siargao,
those provinces
terms ofmost
high exposed
numbers toof environmental
poor families orhazards.
high Vigan, Basco, Bukidnon, General Santos, and Roxas
For eachpoverty
category,
incidence, and those specific
the plan proposes provincessocial
most The convergence
airports. Tourism program ports ofwillDPWH and DOT in
be upgraded will ports
like
interventions suchtoas
exposed employment hazards.
environmental creation, diversifying coordinate Ivanaconstruction
Port in Batanes, of access Panganngan roads toPort priorityin Bohol, tourism
For each category, the plan proposes specific social (NTDP). The Department of Transportation and
Aklan.
interventions such as employment creation, Communications (DOTC) will upgrade principal airports to
I – provinces with highest II – provinces with highest III – provinces prone to multiple
and coordinates its projects under its mandate of Port in Camiguin, and Cagban Jetty Port in Aklan.
Category I – provinces with highest Category II – provinces with highest Category III – provinces prone to
number of the poor proportion of the poor multiple hazards
Addressing the specific • Rapid growth opportunities • Very remote, sparsely • Prone to multiple hazards
constraints faced by the exist but not for the poor populated
poor requires consideration • In-migrants are attracted but • Limited growth opportunities
of geophysical they cannot participate in the • Confronted by conflict and/or
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 14
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Inno
Inno vation
vation andand growth
growth corridors
corridors in Mindanao
in Mindanao Underquality
massive the overall goal of “poverty
employment” along withreduction
the useinof multiple
Mindanao Food, Agribusiness and Logistics the dimensions
so-called and
“logical the creation
framework” of massive
for quality
formulating
Mindanao
Corridor Food, AgribusinessSantos);
(Tagum-Davao-General and Logistics Corridor development employment” plans, along with the midterm
the updated use of the so-called “logical
Philippine
(Tagum-Davao-General Santos);
Mindanao Industrial Trade Corridor (Western and framework”
Development Planforidentifies
formulating twodevelopment
intermediateplans, goals
the
Mindanao
Northern Industrial Trade Corridor (Western and
Mindanao); updated
of (1) rapid andmidterm
sustained Philippine
economicDevelopment
growth while Plan identifies
Northern Mindanao);
Mindanao Food Basket Corridor (Central two intermediate
achieving goals of (1) opportunities.
(2) equal development rapid and sustained economic
Mindanao Food Basket Corridor (Central
Mindanao-Bukidnon); growth while achieving (2) equal development
Mindanao-Bukidnon);
Mindanao Biodiversity and Ecotourism Corridor Thereopportunities.
are, in turn, seven “infrastructure-supported
Mindanao BiodiversityOriental
(Surigao-Agusan-Davao and Ecotourism
including Corridor
former sector outcomes”, which are driven by five
(Surigao-Agusan-Davao
Paper Industries CorporateOriental including former Paper
of the Philippinos There are, in
“infrastructure turn, seven outcomes”
Intermediate “infrastructure-supported
and 14 sector
Industries
[PICOP] Corporate of
concessionaire the Philippinos
areas); and [PICOP]
outcomes”
specific , which are driven by five “infrastructure
strategies.
concessionaire areas); and
Mindanao Mariculture and Trade Corridor Intermediate outcomes” and 14 specific strategies.
(Zambasulta:Mariculture
Mindanao and Trade Corridor (Zambasulta:
Zamboanga-Basilan-Sulu-Tawi-Tawi) The sector outcomes, which are impacted by the
Zamboanga-Basilan-Sulu-Tawi-Tawi)
Source: Philippine Development Plan 2011-2016 stateThe
of sector outcomes,
the country’s which are have
infrastructure, impacted
to doby the state of
with
Source: Philippine Development Plan 2011-2016
http://plans.neda.gov.ph/pdp/chapter-10-accelerating-infrastructure-develo
pment/
http://plans.neda.gov.ph/pdp/chapter-10-accelerating-infrastructure-development/
(1) the
globalcountry’s infrastructure,
competitiveness in thehave to do
industrial with
sector;(1) global
(2)
competitiveness
competitiv eness in the in the industrial
agricultural sector;
sector, (3)(2)
Another
Another manifest
manifestation of of
ation thethe
integrated
integrated effort
effortareare
thethe long effective
competitiveness
governance,in(4) the agricultural
stable nationalsector, (3) effective
security, (5)
long term “dream plans” for 2035 for
term “dream plans” for 2035 for transportation transportation governance,sustainability,
environmental (4) stable national security, (5) environmental
(6) improvements in
development
development forfor
Metro
MetroManila
Manilaand Metro
and Metro CebuCebu putput humansustainability,
capabilities, (6)and
improvements
(7) reductioninofhuman capabilities, and
vulnerabilities
together
together with thethe
with assistance
assistance of of
thetheJapan
Japan International (7) reduction
to natural calamities.of vulnerabilities to natural calamities.
International
Cooperation Cooperation
Agency (JICA),Agency (JICA),
which which more livable,
envisions
envisions more livable, less congested,
less congested, environmentally friendly mega-urban areasThese These sector
sector outcomes
outcomes will will depend
depend on fivone five intermediate
environmentally friendly mega-urban
conducive to productive employment. areasAtconducive
the same time, intermediate outcomes: (1) the enhancement
outcomes: of competitiveness
(1) the enhancement of and
to the
productive
World Bankemployment.
is involvedAtinthe same time,
formulating plansthefor the productivity, (2)
competitiveness andbetter governance,
productivity, (3) improved security,
(2) better
World
regionsBankthat
is involved in formulating
do not belong plans for
to the National the Region governance,
Capital (4) environmental
(3) improved quality, and most
security, significantly, (5)
(4) environmental
regions
(NCR).that do not belong to the National Capital adequacy
quality, and most andsignificantly,
accessibility (5) of basic infrastructure
adequacy and services
Region (NCR). Under the overall goal of “poverty includingof
accessibility the far-flung
basic areas. services including
infrastructure
reduction in multiple dimensions and the creation of the far-flung areas.
Results framework on accelerating infrastructure development
Results framework on accelerating infrastructure development
Goals
Goals
Poverty in multiple dimensions reduced and massive quality employment created
Poverty in multiple dimensions reduced and massive quality employment created
Rapid and sustained Equal development
Intermediate goals
Intermediate
Rapid and sustained economic growth opportunities achieved
Equal development
goals
economic growth opportunities achieved
Infrastructure
Competitiveness
Governance
Safer and Environmental
Adequacy and
intermediateCompetitiveness
enhanced and
productivity incresed in
improved more
secured
environment
quality
improved Adequacy
accessibility of basic
and
infrastructure services
Safer and
outcomesproductivity
the industry, services enhanced, and
created and accessibilityinfrastrucutre
of basic gaps in
Infrastructure enhanced and and agriculture sectors
Governance more secured Environmental
sustained infrastructure services
far-flung areas reduced
intermediate
incresed in improved environment quality enhanced, and
the industry, services created and improved
outcomes
and agriculture sectors
infrastrucutre gaps in
sustained far-flung areas reduced
15 |2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
The fourteen infrastructure development strategies Intermediate outcome B: Adequacy and accessibility of basic
are directed towards the five intermediate infrastructure services enhanced and infrastructure gaps in
Intermediate outcome E.far-flung
Environmental quality improved
infrastructure outcomes which support the sector areas reduced
outcomes.
Strategy 5: Improve access to and adequacy of basic
Intermediate outcome A: Competitiveness enhanced and productivity Strategyinfrastructure
12: Strengthen resilience to climate change
services
increasedFor each
in the strategy,
industry, there
services is a results
and agriculture matrix (RM) which
sectors and disasters
specifies mostly physical indicators and targets to
Strategy 6: Address infrastructure gaps in
measure the government’s success in each strategy.
Strategy 1: Improve connectivity and efficiency Strategyfar-flung
13: Improve
areaswastewater and solid waste
among urban centers, regional growth hubs management
For Intermediate outcome A, Strategy 1: Improve
connectivity and efficiency among urban centers, and Intermediate outcome B: Adequacy and accessibility of basic
infrastructure
Strategy services
14: Supportenhanced
measuresandtoinfrastructure
improve air gaps in
regionalStrategy
growth 2: hubs,
Supportthe following
agricultural is the Results
production
quality far-flung areas reduced
Matrix from 2013 to 2016 in the original Philippine
Development Plan, and the revalidated results matrixSource: Philippine DevelopmentStrategy 5: Improve access to and adequacy of basic
Plan 2011-2016
in the midterm
Strategy 3:update. The end-of-plan
Pursue energy targets have http://plans.neda.gov.ph/pdp/chapter-10-accelerating-infrastructure-development/
and water security infrastructure services
been mostly reaffirmed. (See Appendix A and B)
The targets
Strategyare4:as specific
Improve as the
business transfer
climate through time The strategies are not Strategy 6: Address infrastructure gaps in
just motherhood
far-flung areas
statements.
institutional and policy reforms,
between MRT/LRT platform to platform and and legislation
concourse to platform; the number of passengers perFor each strategy, there is a results matrix (RM) which
square meter vs. the optimal; the volume of tonnage specifies mostlyIntermediate physical indicators and targets to
outcome C: Governance improved
transported through measure the government’s success in each strategy.
Intermediate outcome B: Adequacy andthe Central
accessibility RORO
of basic spine; the
infrastructure
number of passengers transported through airlines;
services enhanced and infrastructure gaps in far-flung areas reduced
and percentage of mobile services with broadband For Intermediate outcome A, Strategy
Strategy 7: Promote 1: Improve
good governance through
facilities. connectivity and efficiency among
information andurban centers,
communication and
technologies (ICTs)
Strategy 5: Improve access to and adequacy of basic regional growth hubs, the following is the Results Matrix
infrastructure services
As reflection of the scale and complexity of the from 2013 to 2016 in the original Philippine Development
Strategy 8: Improve coordination and planning, and
transportation problem in Metro Manila and other Plan, and the revalidated resultsgovernment
streamline matrix inprocesses
the midterm
Strategy 6: Address infrastructure gaps in
urban areas, it indicates that the target set for the update. The end-of-plan targets have been mostly
far-flung areas reaffirmed. (See Appendix A.1 and A.2)
average travel time via road along key urban corridors Strategy 9: Optimize resources and investments in
is to decrease from the baseline of 20.59 minutes in infrastructure
2012 to just 20.03 minutes by 2016. An improvement The targets are as specific the “transfer time between
of travel time C:byGovernance
56 secondsimproved
will hardly be felt by MRT/LRT: platform to platform and concourse to
Intermediate outcome
urban commuters. Perhaps what the target platform”;Intermediate
the number of passengers
outcome D: Safer andper square
more meter
secured vs.
environment
the optimal; the volume of created
tonnage andtransported
sustained through
represents is the objective that traffic in Metro
Manila’sStrategy
main 7:
corridors will at
Promote good least notthrough
governance worsen the Central RORO spine; the number of passengers
information and
between 2014 to 2016. communication technologies (ICTs) transported through airlines;
Strategyand percentage
10: Provide of security
safety and mobilemeasures
services with broadband facilities.
The targets for8:the
Strategy transfer
Improve times and
coordination for planning,
LRT andand MRT
passengers to go
streamline four to five minutes also As reflection of the scale
down byprocesses
government
and 11:
Strategy complexity
conflict-affected
of the in
Enable development
areas and other urban
do not seem material. transportation problem in Metro Manila
areas, it indicates that the target set for the average travel
Strategy 9:outcome
Intermediate OptimizeA:resources and investments
Competitiveness enhancedin and time via road along key urban corridors is to decrease from
infrastructure
productivity increased in the industry, services and agriculture the baselineIntermediate outcomein E.2012
Environmental quality improved
of 20.59 minutes to just 20.03
sectors
minutes by 2016. An improvement of travel time by 56
Strategy 1: Improve connectivity and efficiency
seconds will hardly be felt by urban commuters. Perhaps
Strategy 12: Strengthen resilience to climate change
Intermediate outcome D:among Safer urban
and more secured
centers, regional growth hubs what the target represents is the objective that traffic in
and disasters
environment created and sustained Metro Manila’s main corridors will at least not worsen
between 2014 to 2016.
Strategy 2: Support agricultural production Strategy 13: Improve wastewater and solid waste
Strategy 10: Provide safety and security measures management
The targets for the transfer times for LRT and MRT
passengers to go down by four to five minutes also do not
Strategy 3: Pursue energy and water security seem material. Strategy 14: Support measures to improve air
Strategy 11: Enable development in
quality
conflict-affected areas
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 16
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
For otherthe
For other items in the Results Matrix, items in thetargets
physical Resultsthat
Matrix, the physical
appear targets that
to be significant are:appear to be significant are:
Indicators Baseline (2012) End of Plan Percent change
Indicators Baseline (2012)End of Plan Percent change
Load transported via Central RoRo spine (tons per ship-hour) 189 251 32% increase
Davao 126 per ship-hour) 179
Load transported via Central RoRo spine (tons 189 42%
251 increase32% increase
Cagayan de Oro Davao
42 47
126
11.9%
179
increase42% increase
Batangas 21 25 19.0% increase
Cagayan
Passengers transported via air per annum de Oro 37,960,765 42
56,084,528 4747
.7% increase11.9% increase
Batangas
Source: Philippine Development Plan revalidated results matrix and author’s calculations. 21 25 19.0% increase
Another
For strategy 2, supporting agricultural salient observation
production, the physical is targets
that therefer
lead to
agency for the of
the percent strategies
potentialwill
areasmostly
withbe the
DOTC
irrigation services. (See Appendix C) which has been managing challenges in rolling out public-private partnership (PPP)
projects.
For Strategy 3 covering water and energy security, there are specific physical targets for the ratio of power supply
to demand; non-revenue water; For24/7strategy 2, supporting
water service agricultural
availability; production,
etc. The the physical
physical targets do nottargets
reflect refer to the percent of
ambitious
target indicators. (See Appendixpotential
D) areas with irrigation services.
The government also intends to develop master plans for river basins, including water resource assessments or water
availability studies, particularly for water-critical areas, and to identify new water sources for domestic, commercial,
industrial, irrigation and other needs.
rate
by investing trajectory
in the of 7-8 percent
right infrastructure by investing
both purely public andin the
purely private
rightinfrastructure
infrastructure so that
boththepurely
sustainability
public of such
and purely
growth can be assured. But at the same time, we are not just
private infrastructure so that the sustainability
blinded by high growth. As important as high growth is the
of
such growth can be assured. But
inclusive growth. Geographically, we have mapped out
at the same
where we time, we aare
can make dent not just blinded
of poverty by ”high growth. As
reduction.
important
NEDA Deputy asDirector
high growth
RolandoisTungpalan
the inclusive growth.
Geographically, we have mapped out where we
can make a dent of poverty reduction.”
- NEDA Deputy
Surface water will be prioritized Director Rolando
over groundwater resources,Tungpalan
where
appropriate particularly in water-critical areas such as Metro Manila,
Metro Cebu, Metro Davao, Angeles City, Metro Iloilo, Cagayan de
Oro City and Surface
Bulacan.water
Alternative
will be water sources
prioritized overto the Angat Dam,
groundwater
which supplies 97 percent
resources, of Metro
where Manila’s
appropriate water requirements,
particularly are
in water-critical
also being explored.
areas such as Metro Manila, Metro Cebu, Metro Davao,
Angeles City, Metro Iloilo, Cagayan de Oro City and
This is to reduce the risks
Bulacan. arising from
Alternative waterbeing dependent
sources on a single
to the Angat Dam,
water sourcewhich
for various consumption
supplies 97 percentneeds. TheManila’s
of Metro two other water
water
PPP projectsrequirements,
are Laiban Dam areand the
also Bulacan
being Bulk Water projects.
explored.
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 18
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Paving
Pavingthe
theWay
Through Goodgood
way through
Go
govver
ernance
nance
Cristina Roxas, Advisory Partner, KPMG in the Philippines
Michael Arcatomy H. Guarin, Advisory Partner, KPMG in the Philippines
Infrastr uctureure
Infrastruct spending
spending bybthe Department
y the Departmentof of
Public WoW
Public rks and
orks Highw
and ays (DPWH)
Highway s (DPWH) is eisxpected
expected to to reach
reach US$4.30
PhP190 billionbillion in 2014,
in 2014, which which
wouldwould be more
be more than than
doubledouble the US$2.05
the PhP90.67 billion
billion levellevel in 2011.
in 2011. Infrastructure
Infrastructure
spending has spending
been growinghas been growing
at 28 at a28year
percent percent
in thealast
yearthree
in theyears.
last three years.
The bulk of The bulk of and the
the spending
thehighest
spending and the highest growth has been in highways, which jumped from
growth has been in highways, which jumped from PhP68 billion in 2011 to PhP128 billion US$1.54 billion in in 2014.
2011
ThetoDPWH
US$2.90 billionforin2015
budget 2014.could
The DPWH
go up tobudget
as muchfor as
2015 couldbillion.
PhP300 go up to as much as US$6.79
billion.
DPWH has set ambitious targets to overcome the country’s deficit in terms of the quality of roads in comparison with
Theneighbouring
DPWH has set countries.
ambitious Bytargets
2016, the target is tothe
to overcome completely
country’spave thein32,000
deficit terms ofkilometers (km)
the quality of national
of roads in roads, from only
86 percent
comparison as of
with 2013. The quality
neighbouring for the
countries. By paved roads
2016, the is targeted
target to be at the
is to completely international
pave the 32,000roughness
kilometersscale
(km) of
of 4. DPWH
is upgrading
national 117,000
roads, from onlylineal meters as
86 percent of of
bridges
2013. nationwide.
The quality Added
for the to the task
paved roadsare
is the rehabilitation
targeted to be at and
the reconstruction
requirements
international in the regions
roughness scale ofdamaged by Typhoon
4. The DPWH Haiyan.117,000 lineal meters of bridges nationwide. Added to
is upgrading
the task are the rehabilitation and reconstruction requirements in the regions damaged by Typhoon Haiyan.
The Global Competitiveness Report
TheRanking
DPWH ofis the
alsoPhilippines
supportingsignificantly
the development programs
improved of other
from no. agencies such
114 (2010-2011) as87
to no. the agriculture, tourism, and
education departments
(2013-2014) under
in the quality ofits Strategic
roads Convergence
indicator in the WEFProgram (SCP).
Global Competitiveness Index
Quality of Roads
The Global Competitiveness Report
The ranking of the Philippines significantly improved from(2010 -no.
2013)
114 (2010-2011) to no. 87 (2013-2014) in the quality
of roads indicator in the World Economic Forum (WEF) Global 2011
6.0 5.7 5.7 5.4 5.4
2010 - 2011 - 2012
Competitiveness 2012 - 2013
Index 2013 - 2014
5.1 5 5 4.9
5.0
Quality of Roads
4.0 (20103.5 3.5 3.4 3.7
- 2013) 2.8 3.1 3.4 3.6
5.7 5.7 5.4 5.4 2010 - 2011 2011 - 2012 2.7 2.6 2.7 3.1
2012 - 2013 2013 - 2014
6.0 3.0
5.1 5 5 4.9
5.0 2.0
4.0 1.0 3.5 3.5 3.4 3.7 2.8 3.1 3.4 3.6
2.7 2.6 2.7 3.1
3.0 0.0
Malaysia Thailand Indonesia Vietnam Philippines
2.0
Legend: 1 = extremely underdeveloped; 7 = extensive and efficient by international standards (Based on 146 Countries)
WEF: World Economic Forum
1.0
0.0
Malaysia Thailand Indonesia Vietnam Philippines
Source: Bangko Sentral ng Pilipinas presentation on Enhancing Resilience to Sustain Inclusive Growth March 2014
Notes: 1 = extremely underdeveloped; 7 = extensive and efficient by international standards (Based on 146 Countries)
Source: Bangko Sentral ng Pilipinas presentation on Enhancing Resilience to Sustain Inclusive Growth March 2014
19 | Infrastructure In-depth:
2 | Infrastructure Philippines
Guide: Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
2011-2015 DPWH Infrastructure Program:
The DPWH is also
Capital supporting
Outlays the development programs of other agencies such as the agriculture, tourism, and educa-
(By Category)
tion departments under its Strategic Convergence Program (SCP).
300.0
41%
2011-2015 DPWH Infrastructure Program:
Capital Outlays (By Category)
250.0
Amount (in Billion Pesos)
300.0 32%
41%
200.0
250.0 45%
Amount (in Billion Pesos)
150.0 32%
200.0 10%
100.0 45%
150.0
50.0 10%
100.0
2011 2012 2013 2014 Proposed 2015
50.0
Highways 68.0 78.1 100.9 129.4 173.5
Flood Control 11.3 10.8 15.9 33.6 44.8
The DPWH has introduced the concept of High Standard Highways (HSH) which are limited access, high speed highways
for long distance trips in a 200 km radius in the National Capital Region (NCR). These will be constructed under the
public-private partnership (PPP) program. By 2020, the HSH network is projected to increase from 420 kilometers to 626
kilometers. Another 236 kilometers are proposed to be constructed by 2030, and 130 kilometers beyond 2030, for a total
of 995 kilometers.
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 20
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
But even more significant than the quantum increase Governance Reform and Anti-Corruption Program
in infrastructure spending and physical Key Reforms Policies and Program
accomplishments by DPWH are qualitative changes
Objective programming criteria based on
in governance which are transforming the way the
planning applications (i.e. PMS-HDM 4);
DPWH is delivering on its mandate. A “massive Project Status available on the DPWH
increase in spending” by government is usually Right Projects website;
associated with massive irregularities and Public consultation and disclosure on public
expenditure (eNGAS) and project
governance issues as well. Under the banner of a identification up to project completion.
“good governance reform and anti-corruption
Detailed Design, Program of Work and
program”, DPWH Secretary Rogelio Singson has Detailed Cost/Estimates prepared/evaluated
launched various initiatives to safeguard against such Right Cost based on restructured Indirect/Direct Cost;
risks. In pursuing its ambitious targets, the DPWH Open, Transparent and Competitive Bidding
which resulted in savings.
adopted the following priorities:
24/7 DPWH Call Center (165-02) to address
queries and complaints;
Right Quality Outsourced project inspection and quality
assurance;
Developing ISO Standards of DPWH Offices.
1. Right Projects 2. Right Cost 3. Right Quality
Accredited 47 Civil Society Organizations
(CSOs) partners for monitoring;
Right On Time Bantay Lansangan Road Sector Report Card
Rating
Close monitoring of project implementation.
4. Right Time 5. Right People
Source: Bangko Sentral ng Pilipinas presentation on Enhancing
Resilience to Sustain Inclusive Growth March 2014
The DPWH adopted concrete steps and approaches
to make sure that these priorities do not remain as In collaboration with the Philippine Contractors
mere slogans. Many of these steps are ingeniously Association (PCA) and the DPWH’s Accreditation
simple but are proving to be effective in curbing Board, the eligibility of contractors to bid is based on
moral hazards
But even more andsignificant
spending than irregularities.
the quantum increase in Governance
their certificationReform
and credit andrating.
Anti-Corruption
To ascertain Program
the
infrastructure spending and physical accomplishments by financial capacity, the DPWH requires no less than a
The procurement
DPWH process
are qualitative has been
changes made morewhich are
in governance certification
Key Reformsfrom the Bureau ofPolicies Internaland Revenue
Program
transparent
transforming andthe simplified
way DPWH to ensure the most
is delivering on its mandate. (BIR).
qualified proponents are chosen. The number of Objective programming criteria based on
Right Projects
signatures
A “massive required hasinalso
increase been reduced
spending” to five. is usually The DPWH is working planning
by government to cluster applications (i.e. PMS-HDM 4);
projects to ensure
Project Status available on the DPWH
This lowers the
associated withchances
massive forirregularities
moral hazardand in the form
governance that these are executedWebsite; by contractors with the
ofissues
bureaucratic
as well.interference. The number
Under the banner of
of a “good governance proper capabilities and equipment.
Public consultationSmaller project on public
and disclosure
documents
reform andrequired to be submitted
anti-corruption program”has also been
, DPWH Secretary lot sizes are also beingexpenditurediscontinued as much
(eNGAS) as
and project
reduced
Rogeliofrom 20 tohas
Singson five. launched various initiatives to possible. The DPWH annual identification
reportupforto project completion.
2012 states
safeguard against such risks. In pursuing its ambitious the following anecdote: Detailed Design, Program of Work and
Additionally,
targets, thethe DPWH
DPWH used tothe
adopted require bidders
following to
priorities: Right Cost Detailed Cost/Estimates prepared/evaluated
submit letters of intent for projects being tendered “Bidding irregularities based in onDPWH Region
restructured 4-B. The Cost;
Indirect/Direct
and the potential
1. Right bidders
project are posted in public. This District EngineeringOpen, Office (DEO) and
Transparent in Mamburao,
Competitive Bidding
step allowed bidders
2. Right costto find out who the other Occidental Mindoro which resulted
began in savings.
a project worth
bidders competing for the project. Notwithstanding
3. Right quality PhP473.457 million (US$ 10.72 million),
24/7 DPWH Call Center (165-02) well to address
laws and 4. rules to the
Right contrary, the process was prone
on time Right Quality
beyond the PhP50 million
queries and(US$1.13
complaints; million) that
to collusive 5. behaviour
Right people to the disadvantage of the district engineers can sign off
Outsourced on their
project own. and
inspection To quality
DPWH. Under the current process, bidders simply bypass clearanceassurance;from regional and central
procure
The DPWH the bid documents
adopted and submit
concrete steps and their bids with to
approaches offices, they cut the projectISO
Developing Standards
into componentsof DPWH Offices.
the DPWH
make sureproviding
that these no priorities
information do on
notwho the as
remain other
mere that would not breach the said limit. DPWH
Accredited 47 Civil Society Organizations
cancelled
Right On Timethe bidding (CSOs)ofpartners
these projects,
bidders
slogans.are.Many
In theofpast
these few years,
steps arethis new approach
ingeniously simple but for monitoring;
clustered themBantay into sixLansangan
projects, andRoadrebid
Sectorthese
Report Card
hasareallowed
provingthe to DPWH to generate
be effective in curbingUS$452.93
moral hazards and
in September 2011. Total approved budget for the
Rating
million in savings
spending in terms of the Approved Budget for
irregularities.
contract (ABC)Close for themonitoring
six clustered projects
of project was
implementation.
the Contract (ABC) and the actual cost of the bids PhP463.8 million (US$10.50 million). Through
awarded. The DPWH
The procurement also introduced
process has been standard
made more unittransparent Source:public
Bangkobidding,
Sentral ng Pilipinas
the DPWH presentation
was on Enhancing
able to saveResilience to Sustain
costs
and which are published
simplified to ensure in thetheir
most website
qualified andproponents
has are Inclusive Growth March 2014
PhP46.6 million (US$1.06 million) as the total
initiated a Quality Assurance program which is awarded contract amounted to only PhP417.2
outsourced to an external consultant. million (US$ 9.45 million).”
21 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
In collaboration with the Philippine Contractors Association
and the DPWH’s Accreditation Board, the eligibility of In terms of getting the right people, DPWH has initiated a
contractors to bid is based on their certification and credit cadet engineer program to encourage young entry level
rating. To ascertain the financial capacity, the DPWH engineers to pursue a career in government service. They
requires no less than a certification from the Bureau of are required to take qualifying exams, designed by the
Internal Revenue (BIR). Development Academy of the Philippines (DAP) and the
Civil Service Commission (CSC), not just on the eligibility
DPWH is working to cluster projects to ensure that these but also on their management competencies. The
are executed by contractors with the proper capabilities and competency test is a way of making sure that the right
equipment. Smaller project lot sizes are also being candidates are selected based on qualifications and not on
discontinued as much as possible. The DPWH annual endorsement by government officials. Over time, this will
report for 2012 states the following anecdote: result in the upgrading of the overall skills and
professionalism in DPWH.
“Bidding irregularities in DPWH Region 4-B. The
District Engineering Office (DEO) in Mamburao, In addition, DPWH has also enlisted the support of civil
Occidental Mindoro began a project worth society groups to improve performance and governance.
PhP473.457 million, well beyond the PhP50 million
that district engineers can sign off on their own. To “Road projects are now being implemented
1
bypass clearance from regional and central offices, according to approved plans and specifications by
they cut the project into components that would not better equipped and qualified contractors with closer
breach the said limit. DPWH cancelled the bidding of project inspection and monitoring, including the
these projects, clustered them into six projects, and monitoring and participation of a network of Civil
rebid these in September 2011. Total approved Society Organizations (CSOs), Non-Government
budget for the contract (ABC) for the six clustered Organizations (NGOs), Church and private sector
projects was PhP463.8 million. Through public organizations. As of February 2012, DPWH
bidding, the DPWH was able to save PhP46.6 million accredited 52 Civil Society Organizations (CSOs) as
asThe
the DPWH has created
total awarded contracta national
amounted roadtodatabase
only of all government service.
partners/observers They
in all are required
stages of projectto take
projects nationwide
PhP417.2 million.” which at any time can give the qualifying exams, designed by the Development
development cycle (identification, preparation,
status of each project. It enables the DPWH to Academy of the Philippines (DAP)
budgeting, procurement, implementation, and theoperation
Civil
optimize the deployment of resources
DPWH has created a national road database of all projects for timely Service Commission (CSC), not just on
and post evaluation) and in other areas of mutual the eligibility
nationwide execution
which atand anycompletion,
time can give andthetostatus
prioritize repairs.
of each but also
interest. ” on their management competencies. The
project. It enables the DPWH to optimize the deployment competency test is a way of making sure that the
In the
of resources forcase
timely of execution
farm to market roads underand
and completion, thetoSCP These reforms right candidates
introducedare in selected basedyears
the last three on qualifications
have
with
prioritize repairs.the Department of Agriculture (DA), the DPWH and not on endorsement by government
begun to make a difference in the public perception officials.
of
insists on one simple basic criterion: that the farm to governance Overattime,
DPWH.this will result in the upgrading of the
In the casemarket
of farmroadto has
marketto connect
roads under to a major
the SCP road or the
with overall skills and professionalism in the DPWH.
highway. This curbs the tendency
Department of Agriculture (DA), DPWH insists on one for the alignment
of farm
simple basic to market
criterion: roads
that the to to
farm bemarket
based more on local
road has to In addition,
Opportunities for thethe DPWH
private has also enlisted the support
sector
connect to political
a majorconsiderations
road or highway. ratherThisthan
curbsthethe
direct of civil society groups to improve performance and
tendency contribution
for the alignmentlinkingoffarm
farmareas to market
to market roadscenters.
to be governance.
The significant opportunities for the private sector are in the
1
based more Theon DPWH is geo-tagging
local political farm to rather
considerations marketthanroadstheto PPP projects in the HSH of the DPWH:
support this. “Road projects are now being implemented
direct contribution linking farm areas to market centers.
according to approved plans and specifications
DPWH is geo-tagging farm to market roads to support this. � Plaridel Bypass Toll Road (DPWH) Laguna
In its SCP with the Department of Tourism (DOT), the Lakeshore Expressway by better equipped and qualified contractors with
Dike Project
closer project inspection and monitoring,
In its SCPDPWHwith theemphasizes
Department theofinterconnections
Tourism (DOT), DPWH between � C-6 Expressway (Southeast,
including the monitoringEastandand North of a
participation
emphasizes portstheand airports to tourist
interconnections destinations.
between ports and Section) (DPWH) network of Civil Society Organizations (CSOs),
airports to tourist destinations. � NLEX East Expressway Organizations
Non-Government (DPWH) (NGOs), Church
The DPWH is also supporting local governments and � Camarines Sur Expressway Project (DPWH)
and private sector organizations. As of February
DPWH is schools in constructing
also supporting rainwater catchment
local governments and schools facilities
in � Skyway2012,
Stage 3
DPWH accredited 52 Civil Society
in order
constructing to augment
rainwater catchmentthe water supply
facilities in specific
in order to Organizations (CSOs) as partners/observers in all
augment locations.
the water supply in specific locations. stages of project development cycle
(identification, preparation, budgeting,
In terms of getting the right people, the DPWH has procurement, implementation, operation and
initiated a cadet engineer program to encourage post evaluation) and in other areas of mutual
young entry level engineers to pursue a career in interest.” 2
1
1 Adding geographical
2
Adding geographical
identification identification
metadata for metadata
each road.for each road.
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 22
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
These reforms
partners/observers
introduced in the
in alllast
stages
threeofyears
project
have
development
begun to make
cyclea (identification,
difference in the
preparation,
public perception
budgeting,
of procurement,
governance
implementation,
at the DPWH. operation and post evaluation) and in other areas of mutual interest.
”
development cycle (identification, preparation, budgeting, procurement, implementation, operation and post
TheThese reforms
significant introduced for
opportunities in the
the last three
private yearsare
sector have begun
in the PPPtoprojects
make a in
difference
the HSH in
ofthe
thepublic
DPWH: perception of governance
at DPWH.
Plaridel Bypass Toll Road (DPWH) Laguna Lakeshore Expressway Dike Project
The significant
Camarinesopportunities
Sur Expressway
for theProject
private(DPWH)
Skyway Stage 3
Plaridel Bypass Toll Road (DPWH) Laguna Lakeshore Expressway Dike Project
23 | Infrastructure In-depth:
2 | Infrastructure Philippines
Guide: Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Other
Other
prospective
prospective
PPPPPP
Projects
Projects
PPP Bridges:
PPP Bridges: Ser vicesSer
to vices
Conduct BusinessBusiness
to Conduct Case Study
Caseand the and
Study
Field validation of national
Field validation of bridges
nationalproposed for PPP
bridges proposed subsequent
the ABC for
subsequentthe corresponding
ABC for the Consultancy
corresponding
is on-going.
for PPP is on-going.
ServicesConsultancy
was alreadyServices
approved. was already approved.
The Researc
Theh, Education
Researc and Institand
h, Education utional
Institutional
Development (REID) Foundation
Development will prepare Quirino Highway
will prepare
(REID) Foundation (Operation
Quirino Highway and Maintenance):
(Operation and Maintenance):
BusinessBusiness
Case Study Casefor Study
the Package
for the I,Package I, Improvement/rehabilitation of a 93.45
Improvement/rehabilitation of akm (2 lanes)
93.45 km (2
construction/rehabilitation of 139 selected
construction/rehabilitation of 139 bridges
selectedin national lanes)
road that traverses
national road Quezon, Camarines
that traverses Quezon,
Luzon bridges in Luzon Norte and Camarines
Camarines Sur and
Norte provinces.
Camarines Sur
TargetforTarget
Invitation to Bid
for Invit – December
ation 2012
to Bid – December 2012 TOR for provinces.
the Consultancy Services to Conduct
ADB, JICA,
ADB,WB Road
JICA, WBSector Portfolio
Road Sector Summary
Portfolio Summary
(P’B) (P’B) ($’M) ($’M) (P’B) (P’B) ($’M) ($’M) (P’B) (P’B) ($’M) ($’M)
Source: DPWH presentation on Strategic Infrastructure Policies and Programs May 2012
Notes:
1. Going
US$1 beyond these specific opportunities which include some very large projects, there is the recognition gaining
= PhP43
2. ground
P’B – pesosinin the
billionprivate infrastructure sector of the improvements in the governance ethic in the DPWH which can
3. $’M – US dollars in million
ultimate translate into the significant expansion of the highway network with higher quality and cost efficiency,
thereby broader economic opportunities for the private sector.
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 24
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Building
BuildingThr
through
ough
PPar
arttnerships
nerships
Cristina Roxas, Advisory Partner, KPMG in the Philippines
Paul Patrick R. Afable, Advisory Senior Manager, KPMG in the Philippines
TheThe
Philippine
Philippineexperience
experience with
with
public-priv
public-priv
ateate
partnership
partnership (PPP)
(PPP) programs
programsgoes
goesbacback
k almost
almost
3030 years. The
years.
countrThey had
countr
theyfirst
had Build-Operate-Transfer
the first Build-Operate-T (BOT)
ransfer
law(BOT)
in Asia
lawinin1990
Asiawhich
in 1990 served
whichasserved
a modelas for
a other
model
countries.
for otherEven
countries.
prior to the
Even BOT
prior
law,
to the first
BOTBOT law, contract
the first BOT
in Asia
contract
was awarded
in Asia was
to Hopewell
awardedforto the
Hopewell
210MWfor Navotas
the 210MW
plant inNavotas
1988. The
plantPhilippines
in 1988. The used
Philippines
the PPP approach
also usedtothe
solve
PPPtheapproach
power crisis
to in the
solve
1990sthewhen
powereight
crisistoin12
the
hour
1990s
blackouts
when eight
paralyzed
to 12thehour
industry
blackouts
andparalyzed
crippled exports.
the industry
Fromand
1991 to 1995,
crippled
4,200MW exports.
of new
Fromprivate
1991power
to 1995,
capacity
4,200MW wereofcommissioned
new private powerwith project
capacitycosts
wastotalling
commissioned
almost US$5
with
billion.
project
In costs
1997, the
totalling
Philippines
almostexecuted
US$5 billion.
the largest
In 1997water
, the Philippines
privatizationexecuted
in the world
the largest
with the
water
award of the
privatization
Metropolitan in the
Waterworks
world withand theSe
awwerage
ard of the
System
Metropolitan
(MWSS) Waterworks
franchise to two
and Sewerage
concessionaires
Systemat a total
(MWSS)
projectfranchise
cost of US$7
to two.5 billion.
concessionaires at a total project cost of US$7.5 billion.
PrivPriv
ateate sector
sector participation
participation in infrastructure
in infrastr ucture investments, NPCThe to the
pesoPower Sector Assets
depreciation and Liabilities
also severely impacted one of the
investments,
however, went however,
throughwent through aphase
a declining decliningin the second halfManagement
MWSS water Corporation (PSALM).
distribution The peso eventually
concessionaires,
of the
phase 1990s.
in the The Asian
second half ofFinancial
the 1990s. Crisis 1997 adversely depreciation
TheinAsian resulting in also severely
buyout and impacted one of the
re-privatization.
affected
Financial the in
Crisis government’s
1997 adversely exposure
affected to the BOT projects in MWSS water distribution concessionaires, eventually
two ways. exposure
government’s The large to pesothe depreciation
BOT projectsmeant in twothat NPC’s resulting
Otherinprojects
buyout undertaken
and re-privatization.
after the first phase of the PPP
take-or-pay
ways. contracts,
(1) The large mostly denominated
peso depreciation meant that in US dollars, program became problematic. Take for example the MRT3
ballooned
National Power dramatically
Corporation’s in peso(NPC) terms. NPC, however, was Other
take-or-pay projects
project. Theundertaken
governmentafter the first 15
guaranteed phase of the
percent equity
not ablemostly
contracts, to passdenominated
on the higherinforeign exchange costs fully PPPreturns
US dollars, program became
in dollar problematic.
terms Take sponsors
to the project for example while tariffs
ballooned dramatically
and immediately in peso terms. NPC, however,
to consumers. the were
MRT3highlyproject. The government
subsidized. guaranteed
This resulted 15 fiscal
in a heavy
was not able to pass on the higher foreign exchange percent
burden equity
which returns in dollar
continues terms
to the to the project
present. Another are the
costs
On fully and immediately
the other to consumers.
hand, the economic recession resulted in a sponsors
(2) Worse, allegedwhile tariffs were
irregularities andhighly subsidized.
discrepancies This the bid
between
theweaker
economic economic
recession growth
resultedthanin had assumed in the resulted
been economic
weaker awardinand a heavy fiscal burden
commercial franchisewhich continues
in US$300 to Ninoy
million
growth than had
projections forbeen assumed
electricity in the Lower
demand. projections for
electricity the Aquino
present.International
Another areAirport
the alleged
(NAIA)irregularities
terminal 3. This resulted
consumption
electricity demand. resulted
Lower in electricity
excess power capacity which NPCandindiscrepancies
consumption the Supremebetween the bid
Court voiding theaward
contractand and a lengthy
was committed
resulted in excess power to pay capacity
for the take-or-pay
which NPC contracts
was whethercommercial
litigation franchise
which hasinnot US$300 million Ninoy
been settled.
they were
committed to dispatched
pay for the or created stranded costs, Aquino International Airport (NAIA) terminal 3. This
not. This contracts
take-or-pay
estimated
whether they at PhP74.3
were billion and
dispatched stranded
or not. debts of PhP2.45resulted
This created A World in theBankSupreme
countryCourt
studyvoiding
in 2005the notedcontract
the involvement
billion (incurred
stranded when NPC
costs, estimated had to borrow
at US$1.68 to cover its
billion and andofa takeover
the private of sector
the project from the had dropped from a
in infrastructure
operating
stranded debtsandoffinancial
US$55.48 losses).
millionThe stranded
(incurred when costs and concessionaire
peak of six percentPiatco, and a lengthy
of gross litigation
domestic which
product (GDP) in
NPC had to borrow
stranded to cover its
debts eventually operating
required restructuring of the has1998
the and not beento one settled.
percentTerminal
by 2002. 3 became
The World fullyBank observed
powerlosses).
financial sector and Thethe privatization
stranded of NPC
costs and under the the operational
stranded that many in August 2014 after Takenaka
of the controversial projectsCorp., the
were unsolicited
debts eventually
Electric Powerrequired
Industrythe restructuring
Reform Act (EPIRA) of the of 2002 which construction
proposals,contractor completed
and that the framework the for
rehabilitation
vetting unsolicited
transferred
power sector and the the
assets and liabilities
privatization of NPCof NPC
under the Power works
tothe in the airport
proposals was vaguewhichandwas originally
gave a lot ofconstructed
leeway for
theSector
Electric Powerand
Assets Industry Reform
Liabilities Act (EPIRA)
Management of
Corporation in 2002. The arbitration proceedings however
corruption.
2002(PSALM).
which transferred the assets and liabilities of between the German firm Fraport, the majority
25 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Under Under
the nethe
w new framework,
framework, the govtheernment
government is willing
is willing to to
assumeassume regulator
regulator y riskybut
riskwill
buttransf
will transf er commercial
er commercial risks risks
to to
private sector. T he national government
private sector. The national government has also been has also been
moremore sparing
sparing in proinviding
providing performance
performance undert undertakings
akings or or
guarantees
guarantees on the onobligations
the obligations
of goof government
vernment agencies
agencies and and
corporations
corporations not to
not only only to avoid
avoid incurthe
incurring ringfiscal
the fiscal
burdensburdens
as in as
theinpre
thevious
previous projects
projects but as
but also also
aw asaya to
way to take
take
advantadvant
age ofage
theofnethe
w ne w confidence
confidence and positive
and positiv investor
e investor
perceptions of the countr y’s economic standing and and
perceptions of the country’ s economic standing
prospects.
prospects.
The govTheernment
government has adopted
has also also adopted various various
modes modes
of PPP of PPP
structstruct
ures ures
outside outside
of theofusual
the usual
BOT BO T or build-lease-transfer
or build-lease-transf er
owner in Piatco continues to be pending (BLinT)(BL
to T)
the to include
include hybrid hybrid
structstruct
ures ures
where
commercially where theate
theattractive;
priv private
sector sector
(iii) PPP mode is the
International Centre for Settlement of Investment is responsible
is responsible terms for
for civil civil
for
w orks wand
approvalorks
mostbyand
the the the implementing
NEDA
implementing
viable option Investment
for agency agency
Coordination
the government to
as in theDisputes
previous (ICSID)
projectsinbut also as a way to (IA)
Singapore. takeis(IA) is responsible
responsible Committee for (ICC)
operation
for operation or
andNEDA
undertake and the maintenance
Cabinet
maintenance project and(O&M),
Committee.
(O&M), or The
results or better
in PPP value
advantage of the new confidence and positive investor vice-vvice-v
ersa,ersa,
andCenterand Build
Build alsoTransfer
Transferacts for
with awith
as money; deferred
non-voting
deferred (iv)payments.
risks payments.
are appropriately
adviser to the IAs inallocated;
the
perceptions of the country’s economic
A World Bank country study in 2005 noted the standing and Different
Different t ypes t ypes
bid
of and
bid of bid
award
parameters (v)
parameterstariffs
process.be yond are
beyond affordable.
the the
typical During
typical the cooperation
prospects.involvement of the private sector in infrastructure “lowest“low est
cost” hadcost”
bid are bidbeing
are being period,
applied,
applied, PPP including
including projects are
highest constructed and/or
highest
operated yusing an output-based specification
dropped from a peak of six percent of premium grosspremium offered
domestic offered
“The andlothe
andimplementing
the west lowest viabilit
agencies
viabilit yfinancing
gap
gapidentify financing
priority projects which
The government has also adopted various modes of(V
(VGF) GF)The
PPP required,
required, shall
etc. be etc.
The VThe
included
GF is approach.
VGF is being
in the
being 3 Concessionaires
Public
adopted adoptedfrom from
Investment are
other
otherProgram required to follow
(PIP).
product (GDP) in 1998 to one percent by 2002.
structures outside ofobserved
the usual that BOTmanyor build-lease-transfercountries
whicThe which PIP hav e used
contains thetheMinimum
approach
the projects, Performance,
to ensure Standards,
programs and activities that &
World Bank of thecountries
controversial h hav e used the approac
Specifications
h to ensure
and keythe performance
(BLT) to include
projectshybrid
were structures
unsolicitedwhere the private
proposals, and
1 affordabilit y of consumer tarif
sector
that they of will
affordabilit be implemented
consumer tariffs while fsbywhile making
the agencies
making project
within
the project the indicators
commercially viable and defined
attractive intoeach project’s
investors. concession
is responsible for civil
framework forworks
vetting and the implementing
unsolicited agency
commercially
proposals was medium-term.
viable and at Note
tractive that
to projects
investors. selected should be
agreement.”3
(IA) is responsible for operation and maintenance
vague and gave a lot of leeway for corruption. To (O&M), or consistent and aligned with the goals and objectives of the
vice-versa, and Build Transfer with deferred
address this, the World Bank suggested2 that the payments.
The The
gov gov
ernment ernment
Philippine
has has reorganized
Development
reorganiz ed the the
Plan.
former former
The
BOT BOT
PIP Center,
also
Center, indicates the
previously attached The thecountry’s initial experience andin4 PPP (whether
projects
Differentgovernment
types of bid try parameters
to reinstate beyond the typical
a process previously
for attracting attached to thetoDepartment
procurement Department
method of eachof Trade of Trade
project
and identified
Industr y (DTI), yielded
intoPPP
the the
PPP Center following attacto “lessons”:
hed
“lowest cost”
privatebid are being applied,
investments including and
on a transparent highest
Industr y (DTI),
competitive PPP
into, official
the development
Center attacassistance
hed thetoNational
the National
[ODAs], or traditional
premiumbasis
offered and the
instead lowest viability
of through unsolicitedgap bids.
financing Economic and
A key and procurement).
Economic Development
Development1.Authority Authority (NEDA). (NEDA).The The PPP
PPP
Be judicious in providing guarantees and
(VGF) required,
condition etc.forThe
thisVGFshiftiswould
being be adopted from
Center
to address Center
theis theisne
other the xusnexus
and theandmain
the maindriverdriv of erthe ofPPP
the PPP
performance undertakings, particularly for those
countriesweaknesses
which have in used the approach to ensure Program.
Program.
the planning, preparing, and executing The TheT
PPPhe PPP
PPP Center
Center
Center w works
aims
orks withto with
roll-out
IAs to IAs to Policy
the
prepare prepare Guidelines on
risks which the private sector is in a better
affordability of consumer tariffs while making
of private infrastructure projects and even basic the well-struct
project
well-struct ured ured
Pipeline
PPP PPP projects
Development,
projects and acts as a tec hnical
position to bear, such as market demandtheir
and acts to
as aid
a agencies
tec hnical in adviser
mapping
adviser out and
commercially viable and attractive to investors.
requirements such as a sufficient budget and the project pipeline and
foreignpriority
exchange projects. ”
depreciation.
skills to prepare quality pre-investment studies for 2. Prefer solicited proposals on projects which are
The government
projects hasthatreorganized
are likely to the former
attract BOTinvestors.
private Center, 1 The PPP Center aligned manages to thethe4national
Project government
Development and
programs
previously attached to the Department of Trade and Monitoring Facility (PDMF)
and priorities. which is the recipient of a
Industry (DTI), into“PPP theprojects
PPP Center shouldattached to the National
be well-prepared, highly revolving fund 3.from ODA afunds
Establish clear for andengaging
transparent consulting
process for
Economic and Development
bankable, andAuthority
should undergo(NEDA). The PPP
competitive firms in providing expertise
project selection in project structuring and
and approvals.
Center is the nexus and(for
bidding thesolicited
main driver of the
projects) or PPP
Swiss challengeinvestment2 4. Build up capacity for preparing solicited projects
requirements.
Program. The PPP Center works
(for unsolicited with IAs
projects). We toputprepare
high regard in through business cases, pre-feasibility studies,
5
well-structured PPP contracts
projects and prepared
acts as in a transparent
technical advisermanner,“PPP is more than bidding
just apackages,
means toetc. address the lack of
promote a level playing field, and can withstand
in the project cycle of project structuring, setting minimum public funds. More than just a financing scheme, PPPs
legal scrutiny.
performance standards Before a project
and specifications, andcancontract
be undertaken It is in sector
bring in private the context innovation of such to lessons
implement thatcritical
the
through PPP, there are certain criteria that must infrastructure government
projects.sought Through to re-launch
PPP, private thesector
PPP Program in
be complied with such as the following: (i) 2010.
economic viability; (ii) financially and
1 World Bank
1 (2005). The Philippines. Meeting Infrastructure Challenges. Infrastructure Sector Department, East Asia and Pacific Region.
World Bank (2005). The Philippines. Meeting Infrastructure Challenges. Infrastructure Sector Department, East Asia and Pacific Region.
2 A Swiss challenge
2 is challenge
a form of public procurement which requires therequires
government agency which has received an received
unsolicited
A Swiss is a form of public procurement which the government agency which has anproposal to publish
unsolicited proposalthe
to bid
publish the bid
and invite third parties
and inviteto match
third or exceed
parties it. or exceed it.
to match
3
WB (2005)3 op. cit. Chapter
NEDA-PPP 4 “Maximizing
Center the benefits
written response of Private
to KPMG Sector Participation”
prospects.
(BLT) to include hybrid structures where the private sector andGuidelines
objectives of onthe Philippine
Pipeline Development
Development, to
aid agencies
is responsible for civil works and the implementing agency Plan.
inThe PIP also
mapping outindicates the procurement
their project pipeline and priority
The government has also adopted various modes of method of each
(IA) is responsible forofoperation projects. ”
project identified (whether PPP,
PPP structures outside the usualand BOT maintenance
or (O&M), or
official development assistance [ODAs], or
27 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
(GOCCs).
Aside from efficiency gains, PPPs allow the To ensure the continuity of the revised PPP program,
PPP projects, especially those that
proper allocation are supported
of risks to the partybythat
PDMF ,
is best Executive Order No.
the government 136, s. 2013,institutional
is introducing allowed for measures
the
undergo a Value able
for Money
to manage (VfM)
andanalysis
assumeatthetheconsequences
project creation of a PPP Governing Board as the
that would sustain the reforms beyond the current
development stage to risk
of the determine
involved.if PPPs
a project is more
enable viable
the government policy-making body for all PPP-related concerns, and
administration.
to be undertakentothrough
take on PPP
fewerorrisks
through other
due to appropriate risk strengthening the monitoring of projects by
authorizing the procurement of independent
allocation
procurement methods. If awith the private
project taken”7forward as
partner.
is to be The Implementing Rules and Regulations (IRR)
consultants through the PDMF.
a PPP, it must be demonstrated that it will deliver better of the existing BOT Law and NEDA have also
VfM thanPPP projects, especially
the traditional method ofthose thatthrough
delivery are supported by issued the Revised Joint Venture Guidelines for
The Investment Coordination Committee-Cabinet
governmentPDMF , undergo a Value
procurement, and thatfor the
Money (VfM) analysis at
government's government-owned and controlled corporations
Committee (ICC-CC) also introduced reforms in the
resourcestheareproject
managed development stage to
with due regard fordetermine
economy, if a (GOCCs).
appraisal of PPP projects which effectively and
project is more
efficiency and effectiveness. viable to be undertaken through PPP efficiently streamlines the process and delineates the
or through other procurement methods. If a project is Executive Order No. 136, s. 2013, allowed for
roles of concerned agencies. It created the
To enhanceto be
thetaken forward and
transparency as a accountability
PPP, it must beof the the creation of a PPP Governing Board as the
ICC-Technical Working Group (ICC-TWG) for PPP
demonstrated
approval process, a PPPthat it will deliver
Governance Boardbetter
has VfM
beenthan the policy-making body for all PPP-related concerns,
projects, which consists of (i) NEDA: for alignment
institutedtraditional
consistingmethod of deliveryofthrough
of the principals the majorgovernment
agencies and strengthening the monitoring of projects by
and contribution to the national, regional or local
procurement, and that authorizing the procurement of independent
involved in the PPP process suchtheas government's
NEDA, Department resources
of government plans or programs, and socio-economic
consultants through the PDMF.
Finance (DOF), and the Department of Budget and efficiency
are managed with due regard for economy, analysis; (ii) DOF: for risk structure and allocation of
Managementand effectiveness.
(DBM) the project, fiscal requirements and government
The Investment Coordination
undertakings, the project’s financial internal rate of
Committee-Cabinet Committee (ICC-CC) also
The BOT ToLaw enhance
(RA 7718) the istransparency
currently being and reviewed
accountability
by of return, and its impact on fiscal sustainability through
introduced reforms in the appraisal of PPP
governmentthe agencies
approval process, a PPPworking
and legislative Governance Board has
committees assessment of direct and contingent government
projects which effectively and efficiently
to updatebeen instituted
the legal consistingframework
and regulatory of the principals
on issuesof the costs; (iii) Department of Environment and Natural
streamlines the process and delineates the roles
major
such as the agencies
maximum involved insupport
government the PPPfor process such as
a project, Resources- Environmental Management Bureau
of concerned agencies. It created the
NEDA, Department of Finance (DOF), and the (DENR-EMB): for the environmental impact of the
VGF as a mode of subsidy, unsolicited proposals, joint ICC-Technical Working Group (ICC-TWG) for PPP
project; and (iv) PPP Center: for VfM analysis,
ventures,Department
etc. The PPPofCenter Budget is and Management
diligently pushing (DBM).
for the projects, which consists of (i) NEDA: for
commercial financial viability, bankability, and project
enactment of the PPP Act, which amends the existing BOT alignment and contribution to the national,
structuring).The PPP Center also acts as the PPP
The BOT
Law, in order Law (RA
to ensure the 7718) is currently
sustainability of thebeing
PPPreviewed regional or local government plans or programs,
Secretariat for the ICC-TWG and ICC-CC for PPP
Program.by government
It also aims to have agencies and PPP
a robust legislative
pipelineworking
with at projects.
and socio-economic analysis; (ii) DOF: for risk
committees
least 50 projects to update
in various stagestheoflegal
the and regulatory
project cycle by structure and allocation of the project, fiscal
framework
end of 2016; 15 PPP on issues signed;
contracts such as five the maximum
projects requirements and government undertakings, the
Through the enhanced appraisal process which has
government support for a project,
completed; and at least 10 infrastructure projects VGF ashanded
a mode of project’s financial internal rate of return, and its
been in place since January of this year, approvals
subsidy,
over to the privateunsolicited proposals,and
sector for operation jointmaintenance.
ventures, etc. The impact on fiscal sustainability through
have been secured for six projects from the ICC-CC,
PPP Center is diligently pushing for the enactment of assessment of direct and contingent
and four projects from the NEDA Board. The average
the PPPalso Act,initiated
which amends thefor
existing BOT Law, in government costs; (iii) Department of
The government a process managing turnaround time for the appraisal and ICC-CC approval
order to ensure Environment and Natural Resources-
contingent liabilities (CLs)the thatsustainability
may materialize of the
fromPPPPPP of projects is one month from the date of submission
Environmental Management Bureau
Program.
projects and how theseIt alsoCLsaims to have
would a robust PPPfor
be appropriated pipeline
and by the IAs. It is also notable to highlight the
(DENR-EMB): for the environmental impact of
funded. As an interim measure, the government has the
with at least 50 projects in various stages of importance of the conduct of clarificatory and
the project; and (iv) PPP Center: for VfM
project cycle
included provisions forbyCLs endin of
the2016; 15 PPP contracts
Unprogrammed Fund of reconciliation meetings prior to the approval of
analysis, commercial financial viability,
signed;
PhP20 billion in thefiveGeneral
projectsAppropriations
completed; and Actatofleast
2014.10 projects such that project issues are threshed out and
bankability, and project structuring.The PPP
infrastructure projects handed over to the private resolved prior to presentation to the ICC-CC.
Center also acts as the PPP Secretariat for the
The Centersector
also for operation
advocates and reforms
policy maintenance.
to improve the ICC-TWG and ICC-CC for PPP projects.
Aside from these, the government will soon be
legal and regulatory frameworks governing the PPP
issuing the IRR on alternative dispute resolution
Program.The government also initiated a process for managing Through the enhanced appraisal process which
(ADR); the PPP Manual for National Government
contingent liabilities (CLs) that may materialize from has been in place since January of this year,
Agencies (NGAs); policy guidelines on pipeline
To ensurePPPthe projects
continuity andofhow these CLs
the revised PPPwould be the
program, approvals have been secured for six projects
development; and other sector-specific PPP
governmentappropriated
is introducing for and funded. As
institutional an interim
measures thatmeasure, from the ICC-CC, and four projects from the
guidelines to continuously improve the PPP policy
the government
would sustain the reformshas included
beyond provisions for CLs in
the current NEDA Board. The average turnaround time for
environment.
the Unprogrammed Fund of US$452.93 million in the
administration. the appraisal and ICC-CC approval of projects is
General Appropriations Act of 2014. one month from the date of submission by the
Cognizant of the important role of the local
the Implementing Rules and Regulations (IRR) of the IAs. It is also notable to highlight the importance
government units (LGUs) in achieving sustainable
The PPP
existing BOTCenter also
Law and advocates
NEDA policy
have also reforms
issued the to of the conduct of clarificatory and reconciliation
development and inclusive growth, the government
Revised
improveJoint
theVenture Guidelines
legal and for frameworks
regulatory meetings prior to the approval of projects such
government-owned
governing the PPP and controlled corporations
Program. that project issues are threshed out and resolved
prior to presentation to the ICC-CC.
7 Ibid.
TheThe National
National Economic
Economic Development
Development Authority Authority Board,
Board, chaired chairedBenigno
by President by President
Aquino Benigno Aquino
III, approved in III,
early September
approved 2014 aSeptember
in early long term "Dream
2014Plan"
a longfor term
the transport
"Dream infrastructure of Mega
Plan" for the Manilainfrastructure
transport that aims to of
resolve
Mega the heavy congestion
Manila that aims frequently
to resolveexperienced
the heavybycongestion
Metro Manila commuters.
frequently This plan promises
experienced to Manila
by Metro
create a more liveable Greater Capital Region (GCR) with higher mobility and connectivity by
commuters. This plan promises to create a more liveable Greater Capital Region (GCR) with higher2030.
mobility
According to aand connectivity
recent by 2030.
Japan International Cooperation Population growth and density
Agency (JICA) study the population of Metro Manila Between 1980 and 2010, the population in Metro
According to a recent Japan International Cooperation
is expected to reach 13.904 million by 2030, from
Population growth and density
Manila doubled from 5.9 million to 11.9 million while
Agency (JICA) study the population
11.858 million in 2014. The population in the adjoining
of Metro Manila is Between 1980 and 2010, the population in Metro Manila
the rate of growth has slowed down from 2.95
expected to reach 13.904 million by 2030, from 11.858 doubled from 5.9 million to 11.9 million while the rate of
provinces of Bulacan, Rizal, Cavite and Laguna percent annually in the 1980s to 1.79 percent in
million in 2014. The population in the adjoining growth has slowed down from 2.95 percent annually in the
(BRLC) is expected to reach 15.486 million by 2030, 2000-2010. This is lower than the natural rate of
provinces of Bulacan, Rizal, Cavite1 and Laguna (BRLC) is 1980s to 1.79 percent in 2000-2010. This is lower than the
for a total population in Mega Manila of around 30 increase for the whole country growth rate of 1.9
expected to reach 15.486 million by 2030, for a total natural rate of increase for the whole country growth rate
million, making it one of the largest urban areas in the percent – an indicator of some out-migration from
population in Mega Manila
1
of around 30 million, making of 1.9 percent – an indicator of some out-migration from the
world. 2
the core capital region. The population density of
2 core capital region. The population density of 191 persons
it one of the largest urban areas in the world. 191 persons per hectare (ha) in Metro Manila was 70
per hectare (ha) in Metro Manila was 70 times the national
The JICA study observes that the complex social, times the national population density of 2.7 persons
population density of 2.7 persons per hectare. As a
The JICAand
economic, study observes
public sector that the complex
management social,
problems per hectare. As a comparison, this is higher than the
comparison, this is higher than the population density of
economic,
besetting Metro andManila
publiccan
sector management
be boiled down toproblems
five population density of Seoul at 170, Tokyo at 131,
Seoul at 170, Tokyo at 131, Jakarta at 131 and Shanghai at
besetting
major issues:Metro Manila can be boiled down to five major Jakarta at 131 and Shanghai at 124.
124.
issues:1. Uncontrolled urbanization
2. 1. Uncontrolleddegradation
Environmental urbanizationand hazard risk For the adjoining BRLC provinces, population growth
For the adjoining BRLC provinces, population growth
3. 2.LackEnvironmental
of affordable degradation
housing and hazard risk averaged 4.7 percent annually in the 1980s, rising to
averaged 4.7 percent annually in the 1980s, rising to 5.9
4. 3. Lackcongestion
Traffic of affordable housing 5.9 percent in the 1990s, and tapered to 4.0 percent
percent in the 1990s, and tapered to 4.0 percent in
5. 4. Traffic congestion
Concentrated spatial structure in 2000-2010. These growth rates, far in excess of
2000-2010. These growth rates, far in excess of the natural
5. Concentrated spatial structure the natural rate of growth, indicate high rates of
rate of growth, indicate high rates of in-migration from
Given the importance of the region to the economy in in-migration from either the National Capital Region
either the National Capital Region (NCR) or from the rest of
Given
terms of the
share importance of the
in population, region
gross to the economy
domestic product in (NCR) or from the rest of the country. By 2030,
the country. By 2030, Metro Manila is expected to
terms
(GDP), of shareand
industry, in population,
services, the gross domestic
manner product
in which Metro Manila is expected to accommodate an
accommodate an additional two million persons while
(GDP),
these issuesindustry, and services,
are managed the manner
will make in which these additional two million persons while BRLC will
a significant BRLC will absorb an additional six million. Within Metro
issues
impact onare themanaged
country as will make a significant
a whole. These issues impact
alsoon the absorb an additional six million. Within Metro Manila
Manila itself, densities in some cities are even higher by an
country
provide an as a whole.
agenda These issues
for integrating plansalso
andprovide
programsan agenda itself, densities in some cities are even higher by an
order of magnitude. The highest density is in the City of
so for
thatintegrating plans and
the interrelated programs
problems so that
in Metro the interrelated
Manila are order of magnitude. The highest density is in the
Manila proper at 662 persons per hectare. This is followed
problemsinina Metro
addressed coherentManila are addressed in a coherent
manner. City of Manila proper at 662 persons per hectare.
by Mandaluyong at 353, Pasay at 281, Navotas at 280 and
manner.
1 City of
1 Manila
City of and
Manila
theand
cities
theofcities
Caloocan,
of Caloocan,
Las Piñas,
LasMakati,
Piñas, Makati,
Malabon, Malabon,
Mandaluyong,
Mandaluyong,
Marikina,Muntinlupa,
Marikina,Muntinlupa,
Navotas,Navotas,
Parañaque,
Parañaque,
Pasay, Pasig,
Pasay,Quezon
Pasig, Quezon
City, San City,
Juan,
SanTaguig,
Juan,and
Taguig,
Valenzuela,
and Valenzuela,
as well asas the
wellMunicipalit
as the Municipality
y of Pateros.
of Pateros.
2 Japan2International
Source: JapanCooperation
International Agency
Cooperation
Presentation
Agency onPresentation
Roadmap foron Transport
Roadmap Infrastructure
for TransportDevelopment
InfrastructureforDevelopment
Metro Manilafor
and
Metro
Its Surrounding
Manila and
Areas
Its Surrounding
(Region III and Areas
Region
(Region
IV-A)III
Summary
and Region
of the
IV-A)
Outputs
Summary September
of the Outputs
2013 September 2013
31 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
This is followed by Mandaluyong at 353, Pasay at 281, Navotas at 280 2030 Do Nothing
This is followed by Mandaluyong at 353, Pasay at Under a “do nothing” scenario, the transport cost of
and Caloocan at 267. The cities which were growing higher than the Volume/ Capacity Ratio
281, Navotas at 280 and Caloocan at 267. The cities traffic in Metro Manila will (beyond
V/C > 1.50 increase from US$54.35
capacity)
rate of natural increase were Caloocan, Muntinlupa, Parañaque, and
which were growing higher than the rate of natural million per day toV/C
US$135.88
= 1.001.50
– million percapacity)
(at & above day by 2030,
Pasig. 3
increase were Caloocan, Muntinlupa, Parañaque, and while in the peri-urban BRLC
V/C = 0.751.00
– this will capacity)
(reaching increase from
Pasig. According to the JICA study, at the barangay US$22.65 millionV/Cper<day
0.75to(below
US$79.26 million per
According to the JICA study, at the barangay level, “about 50 percent capacity)
level, “about 50 percent of the people live in day. The volume/capacity ratio in the major
of the people live in high-density barangays (> 300 persons/ha
high-density barangays (> 300 persons/ha population thoroughfares will be 15 times in excess.
population density). If the population growth trend continues, Metro
density). If the population growth trend continues,
Manila’s density will increase from 191 persons/ha to 224
Metro Manila’s density will increase from 191 The economic contribution of transport systems is to
persons/ha.”
persons/ha to 224 persons/ha.” provide efficient connectivity among markets, factory
districts, residential communities, shopping areas,
“The outward rapid urbanization and densification from Metro Manila
“The outward rapid urbanization and densification business districts, recreation areas, schools and
to BRLC and beyond is inevitable. Without policy and planning
from Metro Manila to BRLC and beyond is inevitable. hospitals, ports and airports.
intervention, such urban sprawl will have the concomitant worsening
Without policy and planning intervention, such urban
of the urban blight, environmental degradation, severe housing and
sprawl will have the concomitant worsening of the A transport network facilitates the switching to the
sanitation conditions, and traffic congestion,” says the JICA study.
urban blight, environmental degradation, severe most appropriate mode according to the
housing and sanitation conditions,
3 and traffic characteristics of the payload, e.g. commuters,
Under a “do nothing” scenario, the transport cost of traffic in Metro
congestion,” says the JICA study.
Manila will increase from PhP2.4 billion per day to PhP6.0 billion per
day by 2030, while in the peri-urban BRLC this will increase from
Traffic
PhP1 billion per demand and impact
day to PhP3.5 (Mega
billion per day. Manila)
The volume/capacity
Traffic demand
ratio in the and impactwill
major thoroughfares (Mega
be 15 Manila)
times in excess. 2012 2030 ‘30/’12
2012 2030 ‘30/’12
Traffic demand Metro Manila 12.8 14.5 1.13
Traffic demand Metro Manila 12.8 14.5 1.13
(mil.trips/days)
(mil.trips/days) BRLC* BRLC 6.0 8.0 1.33
6.0 8.0 1.33
Public
Public transport transport
share share in total demand 69%
in total demand 69% 1.00
69% 69% 1.00
Occupancy road space by private vehicles 78% 78% 1.00
Occupancy road space by private vehicles 78% 78% 1.00
Transport cost Metro Manila 2.4 6.0 2.50 Source: Japan International
(PhP bil./day)TransportBRLC
cost Metro Manila 1.0 3.5 3.50 2.4 6.0 2.50 Cooperation Agency
(PhP bil./day)
Metro Manila BRLC GHG 4.79 5.72 1.19 1.0 3.5 3.50 Presentation on Roadmap
Air quality PM 0.014 0.019 1.36 for Transport Infrastructure
GHG 4.79 5.72 1.19 Development for Metro
(mil.tons/year) BRLC Metro Manila 3.20
GHG 4.49 1.40
Manila and Its Surrounding
Air quality PM 0.005 0.010 PM
2.00 0.014 0.019 1.36 Areas (Region III and
*Bulacan, Rizal, (mil.tons/year)
Laguna, Cavite GHG 3.20 4.49 1.40 Region IV-A) Summary of
Source: Japan International Cooperation Agency Presentation on Roadmap
BRLC the Outputs September
PM 0.005
for Transport 0.010
Infrastructure 2.00
Development for Metro Manila and Its
2013
Surrounding Areas (Region III and Region IV-A) Summary of the Outputs
3 September 2013
Area immediately adjoining an urban area.
3
Area immediately adjoining an urban area.
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 32
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
high bulk low value, low bulk high value, long
distance trips, etc. The transport system interacts Region III
The rest of
Regional Growth Center the country
dynamically with the growth of urban hubs and (Subic-Clark-Tarlac)
central business districts. The transport development New urban-cove
strategy will be instrumental in influencing the spatial Green city
Gateway port/airport
configuration of Mega Manila.
Mega
2. Promote the shift away from the metro-centric Source: Japan International Cooperation Agency Presentation on
Roadmap for Transport Infrastructure Development for Metro Manila and
urban pattern to a hierarchy of multiple urban Its Surrounding Areas (Region III and Region IV-A) Summary of the
centers and hubs, including large new towns Outputs September 2013
that will be countermagnets to the attraction
of Metro Manila. alternative to Manila. Provincial capitals or city
centers such as in Malolos, Tarlac, Cabanatuan,
Five regional clusters are envisioned consisting of: Olongapo, Malolos, Tagaytay, and Calamba will be
1. Metro Manila expected to be centers of sub-regions by providing a
2. Peri-urban areas in Bulacan wide range of employment opportunities, residential
3. Peri-urban areas in Cavite and Laguna areas, education and health services.
4. The northern regional growth center in
Subic-Clark-Tarlac axis The transport development strategy for the GCR calls
5. The southern regional growth center of for the improvement of gateway ports in Subic and
Batangas, Lipa-Lucena Batangas and the Clark International Airport, the
north-south backbone in the form of expressways
Metro Clark (San Fernando, Angeles City, Mabalacat and mass transit, and the secondary roads for
City, and Porac) and Metro Batangas (Batangas City Regions III and IV-A.
and Lipa City) are envisioned as regional centers and
core cities with self-sustained diverse economies, The development plan for the transport network of
industry, services, higher education, health services, Mega Manila aims to strengthen the north-south
cultural activities, etc. transport axis to guide future urban expansion and to
promote the shift from road-based traffic to rail based
They will serve as regional hubs of the transport mass transit, and to enhance the resiliency of the
network within 100 kms from Metro Manila. They network through an integrated multi-modal transport
will also function as international gateways as an system.
Gateway
Theairports and seaports
major components will be: share of railways in Metro Manila to 41 percent by
GatewayAt
airports
grade roads 2030,
Gateway compared to 10 percent at present.
seaports
Missing links in C3 and C5
Development of New NAIA
137 kms of new roads (existing NAIA will be closed The urban expressway network will cater to long-trip
Flyovers and converted for New CBD) fast travel traffic for those willing to pay for
Sidewalks and pedestrian facilities
Development of CLARK (core congestion-free thoroughfares.
airport for central and
northern cluster; alternative
Expressways to New NAIA) The proposed transport sector dream plan for Metro
426 kilometers of inter-city expressways Manila is projected to avoid the US$135.88
78 kilometer of urban expressways million/day transport cost in the 2030 “do nothing”
scenario by 45 percent and even reduce these from
Urban/suburban rail the current level of US$54.35 million.
246 kilometers of six main lines Shift cargo-handling function
of Metro Manila to Subic and
72 kilometers of five secondary lines
Batangas There will also be remarkable improvements in air
Regenerate Manila Port to
quality. Similar benefits will accrue to the peri-urban
An integrated urban mass transit network
highwill aim to
value-added diversifiedBRLC region. The “reach” of a one-hour travel time
waterfront areas
accommodate an increase in ridership from 1.5 from Manila will expand outward, giving better
million per day in 2012 to 9.1 million by 2030 and access and assisting in decongesting the core city
Source: Japan International Cooperation Agency Presentation on Roadmap for Transport Infrastructure Development for Metro
Manila and Its avoid theAreas
Surrounding worsening
(Region III andof traffic
Region IV-A) by increasing
Summary theSeptember
of the Outputs modal2013 center.
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 34
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Opportunities for the
Impact of private
proposedsectortransport network Opportunities for the private sector
The focus on the PPP approach
(estimated fortime
travel implementing the urban rail and
from Manila) Theexpressway projects
focus on the opens upfor
PPP approach numerous
implementing the urban
opportunities
Today for private investors. The bidding out of urban rail and expressway
rail and projects
expressway has
projectsgained
opens some traction
up numerous
in the recent months, including LRT1, CALAx, NAIAx. The currentopportunities
pipeline includes US$30.80
for private billion in urban rail
investors.
projects and US$16.33 billion in road and expressway projects. (See Appendix E)
The bidding out of urban rail and expressway projects has
JICA is quick to point out, however, that many of the projects havegained
been on
somethetraction
drawinginboard for years,
the recent and many
months, including LRT1,
of the original designs have been overtaken by the developments CALAx,
on site. NAIAx.
JICA urges:
The current pipeline includes PhP1.36
trillion in urban rail projects and PhP721 billion in road and
“All the projects that had been studied and planned in the past, but which had
expressway so far eluded realization, should
projects.
now be rushed into implementation. The sweet spot (convergence of many favorable factors) may not last long.
For roads, this includes: (i) all the missing sections of C3, C4, and C5; (ii) several flyovers and interchanges; (iii) at
JICA is quick to point out, however, that many of the
least one of the two North Luzon Expressway (NLEx) - South Luzon Expressway (SLEx) connector roads; and (iv)
projects have been on the drawing board for years, and
frontloading by private sector concessionaires of their investment commitments on SLEx, Manila-Cavite
many of the original designs have been overtaken by the
Expressway (CAVITEx), and NLEx. For railways, this includes: (i) LRT 1 Extension to Cavite; (ii) LRT 2 extension to
the East; (iii) MRT-3 capacity expansion and system upgrade; (iv) developments
improvementon site.
and JICA urges:
rehabilitation of the commuter
service on the south and revival of the north service, and (v) MRT-7 from Quezon City Circle to San Jose del
Monte. “All the projects that had been studied and planned
in the past, but which had so far eluded realization,
shouldbe
Similarly, the computerized traffic signalling system of Metro Manila should now be rushed
expanded intoand
rapidly, implementation.
its system
upgraded as part of an intelligent urban transport system. For airports, un-freeze and complete several landside
and airside projects for Manila and Clark airports.” (See Appendix F) The sweet spot (convergence of many favorable
factors) may not last long. For roads, this includes: (i)
Immediate opportunities all the missing sections of C3, C4, and C5; (ii)
60 min several
For the short-term program (2014-2016), US$7.34 billion in expressways and otherflyovers and interchanges;
road projects are projected (iii)toatbe
least one of
implemented, with many of the larger projects to be90 min under the the
procured PPPtwomode.North Luzon US$3.56
Another Expressway (NLEx)
billion in - South
urban railway projects are also scheduled for implementation Luzon Expressway (SLEx) connector roads; and (iv)
120 minin the short-term.
frontloading by private sector concessionaires of
Short-term Program (2014-2016) 150 min their investment commitments on SLEx,
Railways Manila-Cavite Expressway (CAVITEx), and NLEx.
Name of Project Amount (PhP million) Status
Future
1. LRT1 - Cavite Extension (Niyog) For railways,
30,764this includes: (i) LRT 1 Extension to
Committed
2. LRT2 - East Extension Cavite; (ii)9,446
LRT 2 extension to the East; (iii) MRT-3
Committed
capacity expansion and system upgrade; (iv)
3. MRT3 Capacity Extension 10,200 Committed
improvement and rehabilitation of the commuter
4. MRT7 stage 1 (Quezon Ave. - Commonwealth Ave.) 51,870 Committed
service on the south and revival of the north service,
5. AFCS CommonTicketing System 1,722 from Quezon
and (v) MRT-7 Committed
City Circle to San Jose
6. System Rehabilitations for LRT1 and 2 del Monte. 4,500 Committed
7. Mega Manila a. C4 EDSA-Taft Ave. to Roxas Blvd. 24,800 Proposed
North-South Similarly, the computerized traffic signalling system
b. C4: Roosevelt / Congressional Committed
Commuter of Metro Manila should be expanded rapidly, and its
Railway c. C4: West Ave. / North Ave. / Mindanao Ave. system upgraded as partProposed
of an intelligent urban
8. Metro Manila CBD
CBDTTransit S
System
ystem P
Project
roject Study 120
transport system. Proposed
9. F/S of New
NewTTranspor
ransportt System (e.g. Monorail, AGT)
System 75 Proposed
Railways Total For airports, un-freeze and complete
146,897 - several
landside and airside projects for Manila and Clark
Road Public Transport
airports.”
Name of Project Amount (PhP million) Status
1. ITS (3Japan
Source: Provincial BusTerminals)
International Immediate opportunities
6,300 Comitted
Cooperation Agency
2. Presentation
Public Road PassengerTransport
on Roadmap for Reform Study For the short-term program
60 (2014-2016),
Proposed PhP324 billion in
3. BRT
Transport Infrastructure
System 1
expressways and3,500
other road projects are projected to be
Proposed
Development for Metro
Manila and Its Surrounding implemented, with many of the larger projects to be
Road-based
Areas (RegionPublic Transport Total 9,860 -
III and Region
IV-A) Summary of the
procured under the PPP mode. Another PhP157 billion in
Outputs September 2013 urban railway projects are also scheduled for
implementation in the short-term.
7. Metro Roads
Manila a. C4 EDSA-Taft Ave. to Roxas Blvd. 2,430 Committed
Interchanges / b. C4: Roosevelt / Congressional 941 Committed
Name of Project Amount (PhP million) Status
Flyovers
c. C4: West Ave. / North Ave. / Mindanao Ave. 1,502 Committed
1. Missing Link of C5 a. Flyover on CP Garcia in Sucat 251 Committed
d. C5: Greenmeadows 1,575 Committed
b. Coastal Rd/C5/ Acropolis
Extn. South Flyover 210 Committed
e. C5: Pasig-Bagong Ilog Flyover at SLEx 435 235 Committed
Proposed
c. C5 South Extn.
f. Link
2. Global City-Ortigas C2: Gov.
Road Forbes / Espana 1,0708,120 Committed
Proposed
Roads
3.Total
Skyway/FTI/C5 Link 63,29317,880
Committed
4. C3 Missing links (S. Juan to Makati [Sta. Ana oval]) 24,000 Proposed
Expressways
5. EDSA Rehabilitation
Name of Project Amount (PhP million)3,744 Committed
Status
6. Plaridel Bypass, packages 3 & 4
1. Daang Hari-SLEx LinkTollroad 2,000 900 Committed
Committed
7. Metro Manila a. C4 EDSA-Taft Ave. to Roxas Blvd. 2,430 Committed
2. NLEx-SLEx a. Link Expressway (MNTC) 7,800 Committed
Interchanges /
Connectors b. C4: Roosevelt / Congressional 941 Committed
Flyovers b. Skyway 3 section (Citra) 9,000 Committed
c. C4: West Ave. / North Ave. / Mindanao Ave. 1,502 Committed
c. Common section (DPWH) 11,000 Committed
d. C5: Greenmeadows / Acropolis 1,575 Committed
d. Seg. 9&10, and connection to R10 8,600 Committed
e. C5: Pasig-Bagong Ilog 435 Committed
3. NAIA Expressway, phase 2 15,520 Committed
f. C2: Gov. Forbes / Espana 1,070 Committed
4. CALA Expressway, stages 1 and 2 14,232 Committed
Roads Total 63,293 -
5. CLLEX Phase I (La Paz,Tarlac-Cabanatuan) 12,833 Committed
Expressways
6. Calamba-Los Banos Expressway 16,900 Proposed
Name of Project Amount (PhP million) Status
7. C6 extension - Lakeshore Dike Road 43,380 Proposed
1. Daang Hari-SLEx LinkTollroad 2,000 Committed
8. Segment 8.2 of NLEx to Comm. 7000
, Proposed
2. NLEx-SLEx a. Link Expressway (MNTC) 7,800 Committed
Expressways
ConnectorsTotal 148,265 -
b. Skyway 3 section (Citra) 9,000 Committed
Other Roads Total c. Common section (DPWH) 11,000 Committed
Name ofd.Project Amount (PhP million)8,600 Status
Committed
Seg. 9&10, and connection to R10
1. Secondary RoadExpressway,
3. NAIA Packages phase 2 69,10015,520 Proposed
Committed
2. Preparatory studies
4. CALA for several
Expressway, projects
stages 1 and 2 50014,232 Proposed
Committed
5. CLLEX
3. Other Central Phase
Luzon I (La
road Paz,Tarlac-Cabanatuan)
projects 16,00012,833 Committed
Committed
6. Calamba-Los
4. Other Southern Banosprojects
Luzon road Expressway 36,36016,900 Proposed
Committed
7.Other
C6 extension - Lakeshore Dike Road
Roads Total 121,96043,380 -Proposed
8. Segment 8.2 of NLEx to Comm. 7,000 Proposed
Expressways Total 148,265 -
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 36
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Railways
Name of Project Amount (PhP million) Status
1. LRT1 - Cavite Extension (Niyog) 30,764 Committed
2. LRT2 - East Extension 9,446 Committed
3. MRT3 Capacity Extension 10,200 Committed
4. MRT7 stage 1 (Quezon Ave. - Commonwealth Ave.) 51,870 Committed
5. AFCS CommonTicketing System 1,722 Committed
6. System Rehabilitations for LRT1 and 2 4,500 Committed
7. Mega Manila a. C4 EDSA-Taft Ave. to Roxas Blvd. 24,800 Proposed
North-South
b. C4: Roosevelt / Congressional Committed
Commuter
Railway c. C4: West Ave. / North Ave. / Mindanao Ave. Proposed
8. Metro Manila CBDTransit System Project Study 120 Proposed
Other Roads Total
9. F/S of NewTransport System (e.g. Monorail, AGT) 75 Proposed
Name of Project Amount (PhP million) Status
146,897 -
1. Secondary Road Packages 69,100 Proposed
Road Public Transport
2. Preparatory studies for several projects 500 million)
Amount (PhP Proposed Status
Name of Project
3. Other Central Luzon road projects 16,000 Committed
1. ITS (3 Provincial BusTerminals) 6,300 Comitted
4. Other Southern Luzon road projects 36,360 Committed
2. Public Road PassengerTransport Reform Study 60 Proposed
Other Roads Total 121,960 -
3. BRT System 1 3,500 Proposed
Traffic Management Projects
Road-based Public Transport Total 9,860 -
Name of Project Amount (PhP million) Status
Traffic Management Projects
1. Modernization of traffic signaling system 5,000 Comitted
Name of Project Amount (PhP million) Status
2. Systematic Road Safety Interventions 1,000 Proposed
1. Modernization of traffic signaling system 5,000 Comitted
3. ComprehensiveTraffic Management Study 60 Proposed
2. Systematic Road Safety Interventions 1,000 Proposed
Traffic Management Projects Total 6,050 -
3. ComprehensiveTraffic Management Study 60 Proposed
Airports
Traffic Management ProjectsTotal Amount (PhP million) 6,050 Status -
Name of Project
Airports
1. NAIA a. NAIA improvements - airside package 4,249 Committed
Amount (PhP million) Committed Status
b. Name of Project - landside package
NAIA improvements
1. NAIA
2. Clark c. a. NAIA
Clark improvements
improvements - airside
- airside packagepackage 6,802 4,249 Committed Committed
d. Clark improimpro
b. NAIA vements - landside
vements packagepackage
- landside Committed
Committed
3. Feasibility study of a new NAIA
2. Clark c. Clark improvements - airside package 50 6,802 ProposedCommitted
Airport Infrastructure Total d. Clark improvements - landside package 11,125 - Committed
Ports*
3. Feasibility study of a new NAIA 50 Proposed
Name of Project Amount (PhP million) Status
Airport Infrastructure Total 11,125 -
1. Projects for North Harbor 6,000 Committed
Ports
2. Projects for South Harbor
Name of Project Amount1,000
(PhP million) Committed Status
3. MICT 4,000 Committed
1. Projects for North Harbor 6,000 Committed
4. Feasibility Study of NH Redevelopment 75 Proposed
2. Projects for South Harbor 1,000 Committed
5. Other Ports 1,010 Proposed
3. MICT 4,000 Committed
Port Projects Total 12,085 -
4. Feasibility Study of NH Redevelopment 75 Proposed
Notes: *Planned expansion projects recommended for rescheduling to promote diversion of cargo to Batangas and Subic ports as well as decongest Proposed
1,010
5. Other Ports
roads of Metro Manila
37 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
The latestThe latest Plan”
“Dream “Dream forPlan”
Metrofor Metroconducted
Manila Manila conducted
by The plan proposes development strategies that
JICA andby JICA and
recently recently
approved byapproved by the government
the government breaks stretch to the year 2030, and a massive infrastructure
down thebreaks down
problem intothe
fiveproblem into five areas:
areas: uncontrolled development program for railways, roads, airports,
uncontrolled
urbanization, urbanization,
environmental environmental
degradation degradation
and hazard risk, and seaports with a total cost of US$58.88 billion,
lack of affordable housing, traffic congestion, and traffic
and hazard risk, lack of affordable housing, including US$11.78 billion for 2014-16, as against the
congestion,
concentrated and concentrated spatial structure.
spatial structure. estimate of traffic congestion of US$54.35 million a
day cited by the study.
The urban The urban infrastructure
infrastructure challenges challenges in Metro
Metro Manila Manila
complex
are complex
and formidable. and way
The only formidable.
to makeThe only way
a sensible to make
plan to a Private investors can consider several projects in the
sensible
resolve these plan toisresolve
problems thesedevelopment
to consider problems is to Metro Manila plan which are expected to be
strategiesconsider development
for a wider area, longerstrategies for a wider
time horizons, and area, executed under the PPP mode.
longer time horizons, and
multi-sectoral and multi-modal solutions.multi-sectoral and
multi-modal solutions.
Thus the current plan identifies a Greater Capital Region
Thus the current
the encompasses an areaplan
muchidentifies
wider thana Greater Capital
the current For further information, please contact:
RegionArea.
Greater Manila the encompasses
The plan proposes an area much wider than
development For further information, please contact:
strategiesthe current
that stretchGreater
to theManila Area.and a massive
year 2030, Ma. Cynthia C. Hernandez
infrastructure development program for railways, roads, Roberto
AdvisoryG. Manabat
Director
airports, and seaports with a total cost of P2.6 trillion, Chairman & CEO
including P520 billion for 2014-16, as against the estimate KPMG in the Philippines
KPMG
T: +63 2 885Philippines
in the 7000 ext. 485
of traffic congestion of P2.4 billion a day cited by the study.
Private investors can consider several projects in the Metro T:E:+63 2 885 7000
mchernandez@kpmg.com
Manila plan which are expected to be executed under the E: rgmanabat@kpmg.com
PPP mode.
TheThe
Philippines
Philippinesis eisxpected
expected to to
be be
on on
track to
trac meet
k to meetthethe
201201
5 Millennium
5 Millennium DeDevelopment
velopment Goal (MDG)
Goal (MDG) on
on wwater
ater and
and sanit
sanitation.
ation. TThe
he MDG
MDG ttarget
arget was
was toto cut
cut in
in half
half the
the proportion
proportion of of the
the population
population without
without sustainable
sustainable access access
to safetodrinking
safe drinking
waterw aterimprove
and and impro ve sanitation.
sanitation. This translates
This translates to an
to an increase in the
increase in the
proportion ofproportion of Filipino
Filipino families withfamilies
access towith access
water fromto73water fromin73
percent percent
1990 in 1990
to 86.5 to 86.5
percent by 2015.
percent
Citingby 2015.
data fromCiting data from the
the Association Association
of South of South
East Asian East(ASEAN)
Nations Asian Nations (ASEAN)
statistical statistical
unit, the National
unit, the National
Statistical Statistical
Coordination Coordination
Board Board (NSCB)
(NSCB) recorded stated that
that Filipinos withFilipinos
access with
to safeaccess to safe
drinking water
drinking water represented
represented 84.8 percent84.8 percent
of the of theaspopulation
population of 2010. On as of 2010.
this basis,Onthe
this basis,tagged
NSCB the NSCB
this target as
tagged
havingthis target
a high as havingofa being
probability high probability
achieved by of 2015.
being achieved by 2015.
Percentage
Percentage Access Access to Safe Water
to Safe Water
90 90
Percentage (%)
PERCENTAGE (%)
(%)
Percentage(%)
85
85
PERCENTAGE
80
80
75
75
70
70
1990 1995 2000 2005 2010 2015
39 | 2
Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
St atisticsStatatistics at aofglance
a glance of the Philippines'
the Philippines' ProgressProgress
based onbased on the
the MDG MDG indicators
indicators
Goals/Targets/Indicators Baseline Target Latest Probability
Goals/Targets/Indicators Baseline Target Latest Probability
Goal 7: ENSURE ENVIRONMENTAL SUSTAINABILITY
Goal 7 : ENSURE ENVIRONMENTAL SUSTAINABILITY
Target 7.C Halve, by 2015, the proportion of population without sustainable access to safe
Target 7.C drinking
Halve, by 2015, water and of
the proportion improved sanitation
population without sustainable access to safe
This however,
This implies, implies, however,
that 15.73that 15.73people
million millioncontinue
people continue notaccess
not to have to havetoaccess to safe water.
safe drinking drinkingThe
water. The
broad MDGbroad
indicator MDG
masksindicator masks the
the complicated complicated
issues issues
in the water in the Up-to-date
sector. water sector. Up-to-date
information on information onwater
the status of the status of water
facilities and
access isfacilities andavailable
either not access isor either not available
not consistent and or not consistent and consolidated.
consolidated.
Levels ofLevels
Accessofto
Access to Safe Drinking
Safe Drinking Water Water
Access to formal levels of service: 80% Informal Access: 20%
Access to formal levels of service: 80% Informal Access: 20%
Level 3: 45% Level 2: 10% Level 1: 25%
Self-provision through private
Level 3: Level 2: Level 1: wells, tanked or vended water
Source: WB Report, Philippines: Meeting Infrastructure Challenges, 2005, as quoted in the NEDA Philippine Water Supply Sector Roadmap 2nd Edition
Notes:
1. WDs: Water Districts
2. PO: Private Operators (e.g., concessionaires, private developers, etc.)
3. CBOs: Community-based Organizations (e.g., rural or barangay water service associations, cooperatives, etc.)
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 40
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
As defined in NEDA Board Resolution No. 12, Series of 1995:
Level I A protected well or a developed spring with an outlet but without a distribution system as it is
As defined in NEDA Board Resolution No. 12, Series of 1995:
generally adaptable for rural areas where the houses are thinly scattered serving an average of 15
Level I A protected well or a developed spring with an outlet but without a distribution system as it is generally
households
adaptable with
for people having
rural areas to fetch
where water from
the houses up to scattered
are thinly 250 meters distance
serving an average of 15 households with
Level II A piped system with communal or public faucets usually
people having to fetch water from up to 250 meters distanceserving four to six households within 25
Level meters distance
II A piped system with communal or public faucets usually serving four to six households within 25 meters
Level III A fully reticulated system with individual house connections based on a daily water demand of
distance
Level more
III A than 100 liters per
fully reticulated person
system with individual house connections based on a daily water demand of more than
100 liters per person
Based on the National Statistics Office (NSO), the proportion of households in the Philippines in 2004 with access
to water
Basedwas around
on the 80.2Statistics
National percent. Office
Of the(NSO),
80.2 percent with access
the proportion to water from
of households in theformal providers,
Philippines onlywith
in 2004 44 access to
percent are connected to Level III waterworks systems with piped distribution systems
water was around 80.2 percent. Of the 80.2 percent with access to water from formal providers, only 44 which are subject to percent are
national quality standards. The rest of the population get their water from Level II – communal
connected to Level III waterworks systems with piped distribution systems which are subject to national quality faucets or
standpipes,
standards.or The
Level I –get
rest protected wellsfrom
their water without
Levela II
distribution
– communal system of the
faucets or population.
standpipes, The local Igovernment
or Level – protected wells without
units (LGUs) and community-based organizations (CBOs) provide water service
a distribution system. The local government units (LGUs) and community-based organizations to 55 percent of those
(CBOs)with access
provide water
to water. While the Level III coverage for the country as a whole is 42 to 48 percent, there are wide disparities
service to 55 percent of those with access to water. While the Level III coverage for the country as a whole is 42 to 48
between
percent,thethere
urbanareareas
wideoutside of the
disparities Nationalthe
between Capital
urbanRegion (NCR) and
areas outside rural
of the areas. Capital Region (NCR) and rural
National
areas. Level III Coverage, Philippines
Estimated
Population (2010 Est. % of Total Est. Level II
Estimated Level III Coverage, Philippines
Census) (millions) Population Coverage
Water Supply Providers
Population (2010 Census) Est. % of Total Est. Level II Water Supply Providers (s)
Urban - NCR 11.9
(millions) 13%
Population 88% (1)
Coverage Manila Water, Maynilad
Urban - Outside NCR 33.0 36% 50%-65% Water Districts
Urban - NCR 11.9 13% 88% (1) Manila Water, Maynilad
LGUs
Urban - Outside NCR 33.0 36% 50%-65% WaterPDistricts
riv
rivate
ate operators
Rural 47.4 51% 25% (2) Coops, BWSAs, RWSAs
LGUs
Total 92.3 100% 42%-48%
Notes: 1. BWSA: barangay water and sanitation association, 2. Est: estimated, 3. LGU: local government unit, 4. NCR:Private operators
National Capital Region, 5.
41 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Other sector studies have found that water districts The physical challenges of the Philippine water
percent to 52 percent
provide betteronly.
water The improving
service, citingratios are
the corporatized behind the seriousinclude:
situation deficit in investment
localized levels shortages,
raw water to develop
weighed nature
down by of the
watersignificant
districts drop for Metro
and the benefits Manila
of the water resources to meet the rising demand.
flooding, water pollution, overexploitation A main of
from 122LWUA
to 113 credit
percent.andThe NEDA notes
institutional that by 2017
development ,
support. hindrancegroundwater
is the low tariffs which do not allow for
particularly in major cities, and costoveruse
there will be a water deficit in the Metro Manila area. While recovery.ofAnother
surface factor
water.isThere
the absence of a coherent
is increasing pollution of
overall supply
In the(including
revalidatedforresults
irrigation) is close
matrix to sufficiency
for the midterm financinggroundwater
framework for investments
and surface water in water infrastructure.
in many localities
for the country
reviewas ofathe
whole, thereEconomic
National are seasonal and
and Development There haswhile
also marginal
been a bias for Metro
agricultural Manila and
activities haveother
resulted in
geographic shortages.
Authority There
(NEDA) are major
Philippine water constraints
Development in
Plan, the urban areas, including spending
deforestation for water
and degradation of supply, sewerage
watersheds and
Metro Manila and Cebu
government which
target posepercent
is 100 a serious problem
Level to
III coverage and septage
uppermanagement.
catchments,The lack ofina major
resulting monitoring
flooding system
the further
bydevelopment
2016. of these major urban areas. makes it problems.
difficult to assess andalso
There are address the sustainability
few facilities for storageof
developed infrastructure.
infrastructure, specifically reservoirs and tanks, which
The physical challenges
Another dimensionof the Philippine
targeted water
in the situation plan
government is a reflection of their high cost.
include: localized raw water shortages,
is the demand-supply situation.flooding, water
The performance Another major issue is the institutional fragmentation of
pollution,indicator
overexploitation of groundwater
for sufficiency of supply particularly
versus demand in both the The
regulatory bodies
ADB cites theand agencies
database andWorld
of the the water
Resources
major cities, and overuse
projects of surface
a deterioration fromwater. There isin 2011 to
116 percent service providers (WSPs).
Institute which reports that the Philippines compares
increasingonly
pollution of groundwater
92 percent by the end and surface
of the water in
plan period. favorably with other Asian countries in terms of the
many localities while marginal
Improvements agricultural activities
in the demand-supply ratio have
are The World Bank renewable
annual observed that,water“Water Code with
resources, (1976)
anhas
annual
resulted in deforestation and degradation of
projected in Metro Cebu, Bulacan, Cagayan de Oro watersheds been weakly enforced and the National Water Resources
per capita availability of about 6,100 m3 (cubic meter)
and upperand catchments, resulting
Davao, although theinimprovement
major flooding in problems.
Cebu is Board (NWRB) has been unable
from groundwater to mediate
and surface conflicts
sources, in is
which
There arefrom
also 38
fewpercent
facilities
tofor
52 storage only. The improving water demand,
percent infrastructure, twice theandlevel
provide sufficient
of Asia and sixplanning
times the andglobal
specifically reservoirs
ratios and tanks,
are weighed downwhichby theissignificant
a reflectiondropof for coordination of Water
scarcity Resource
threshold Management
of 1,000 m3.2 (WRM).
their highMetro
cost. Manila
The ADB fromcites
122 thetodatabase
113 percent.of theTheWorld
NEDA NWRB's original location under the Department of Public
Resources Institute
notes which
that by 2017reports thatbe
, there will thea Philippines
water deficit in the Works and Highways (DPWH) created a conflict
The Philippine Development Plan highlights of interest
the
comparesMetro
favorably with other Asian countries in terms
Manila area. While overall supply (including for of between its water resources planning, management
issues behind the serious deficit in investment andlevels
the annual renewable water resources, with an annual
irrigation) is close to sufficiency for the country as a per regulation roles, and the development function
to develop water resources to meet the rising of a public
capita availability of about
whole, there 6,100 m3and
are seasonal (cubic meter) from
geographic shortages.works =ministry.
demand.The original
A main NWRB was
hindrance is thegoverned
low tariffsbywhich
groundwater
There and
aresurface sources,
major water which is in
constraints twice
Metro theManila
level water-users suchallow
do not as LWUA, National
for 1cost Irrigation
recovery. Another factor is the
of Asia and
andsix times
Cebu the global
which pose ascarcity
seriousthreshold
problem to 1,000 Administration
of the absence (NIA),
of aMetropolitan Waterworks
coherent financing and for
framework
m3. further development of these major urban areas. (See Sewerage System (MWSS), National Power Corporation
investments in water infrastructure. There has also
Appendix G) (NPC) and wasachaired
been bias forby DPWH.
Metro ”
Manila and other urban areas,
The Philippine Development Plan highlights the issued
In 2002, the NWRB was transferred to the Office of the
2
ADB (2013), Philippines: Water Supply and Sanitation Sector Assessment, Strategy, and Road Map. January 2013., p. 2.
1
NEDA Philippine Development Plan 2010-2016. Chapter 5: Accelerating infrastructure Development. p. 134.
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 42
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
The institutional stakeholders in the water sector include:
Responsible for administration and enforcement of the 1976 Water
TheWater
National institutional
Resourcesstakeholders
Board (NWRB) in the water sector include:
Code, the framework for water resource management
National Water Resources Board (NWRB) Responsible for administration and enforcement of the 1976 Water
Department of Energy and Natural Resources (DENR) Watershed management
Code, the framework for water resource management
including spending for water supply, sewerage and Natural Resources (DENR) as chair and NEDA as
The World
septage Bank observed
management. The lack that,
of “Water Code (1976) has
a monitoring co-chair.
Outside Metro Manila, front line water services are
been makes
system weaklyitenforced
difficult to and the National
assess Waterthe
and address Resources provided by LGUs. The LWUA Water District concept was
3
Board (NWRB)
sustainability has beeninfrastructure.
of developed unable to mediate conflicts in In terms
createdof water
in 1973service
under providers,
the Local Water there is a wideAct. LGUs
Utilities
water demand, and provide sufficient planning and variety
wereof encouraged
institutional to arrangements
transfer theirand capabilities.
water supply systems to
Thecoordination
World Bankof Water Resource
observed that, “WaterManagement
Code (1976) (WRM). In the Metro
water Manilawhich
districts, franchise area, water services
are corporatized stand-alone entities
hasNWRB's
been weaklyoriginal locationand
enforced under
the the Water of Public are supplying
Department
National provided by MWSS
water in a and two private
franchise area. As government-owned
Works and
Resources Highways
Board (NWRB) (DPWH)
has been created
unablea conflict
to of interest concessionaires:
specialized lender Manila to Water Company,LWUA
water districts, Inc. has the dual role
between
mediate its water
conflicts resources
in water demand, planning, management and (MWCI),
and provide serving
of tariff Manila’s
regulator east zone, and
and institutional Maynilad advisor.
development
regulation
sufficient roles,and
planning andcoordination
the development function of a public Water Services, Inc. (MWSI), serving Manila’s west
of Water
works =ministry.
Resource Management The (WRM).
original NWRBNWRB's was governed by
original zone.As Outside
summarized Metro byManila,
the ADB: front line water
water-users
location under the suchDepartment
as LWUA, National
of PublicIrrigation
Works and services are provided by LGUs. The LWUA Water
Administration (NIA), Metropolitan
Highways (DPWH) created a conflict of interest Waterworks and District concept
“At was
present, created
the in
major 1973 under
utilities the Local
operating Level III
Sewerage
between System
its water (MWSS),
resources Power Corporation Water Utilities
Nationalmanagement
planning, Act. in
systems LGUsurban wereareasencouraged
are (i) water to districts, which
and(NPC) and was
regulation chaired
roles, by DPWH.
and the ”
development function of transfer theirarewater supply systems
local corporate entities toformed
water at the option of
a public works ministry. The original NWRB was districts, which are corporatized
the LGU; (ii) LGU-owned stand-alone
and operatedentities
water
In 2002,bythe
governed NWRB was
water-users suchtransferred the Office of the supplying water
as LWUA,toNational in aand
utilities; franchise
(iii) a few area. As the
private sector operators that
President
Irrigation and reconstituted
Administration to include agencies which are government-owned
(NIA), Metropolitan have beenspecialized lender to
given a franchise or water
authority to operate
not claimants
Waterworks and to water resources,
Sewerage specifically
System (MWSS), the
National districts, LWUA
within hasthethe dual
geographicalrole of tariff regulator
jurisdiction of an LGU or an
Department
Power Corporation of Environment
(NPC) and was andchaired
Naturalby Resources
the (DENR)and institutional development
industrial zone.” advisor.
as chair
DPWH. ”4 and NEDA as co-chair.
As summarized
According toby thethe ADB: at of the end of 2011, 861 water
LWUA,
In terms
In 2002, theofNWRBwater wasservice providers,
transferred to there
the Officeis a wide
of variety “At present,
districts had been theestablished,
major utilitiesofoperating
which 502 Level III
were
theofPresident
institutionalandarrangements
reconstituted and capabilities.
to include agencies In the Metro operational, systems in urban
their areas of
number areservice
(i) waterconnections
districts, ranging
Manila
which are franchise
not claimants area,towater
water services are provided by
resources, fromwhich
500 are local corporate
to 200,000 (with an entities
average formed at the
of 7,011 connections
MWSS and two private concessionaires:
specifically the Department of Environment and Manila Water option
each). of the LGU; (ii) LGU-owned and
Company, Inc. (MWCI), which is the concessionaire serving
Manila’s east zone, and Maynilad Water Services, Inc.
3
(MWSI),
NEDA theDevelopment
Philippine concessionaire serving
Plan 2010-2016. Manila’s
Chapter west zone.
5: Accelerating infrastructure Development. p. 134.
4
World Bank (2003), Philippines: Country Water Resources Assistance Strategy 2003” East Asia Pacific Region p. 7
43 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Water Supply Providers Outside NCR
Water Supply Providers
Urban Outside Outside NCR
NCR: Est. Est. Average Est. % of Level III Est. % of Urban
Est. NCR:
Urban Outside Level III WSP WSP Est. NumberEst.
of Average
Connections Est.
per %Connections
of Level III in Urban
Est. % of Outside
Urban NCR
Est. Level IIICoverage WSPsConnections WSP Connections
Number of - outside
in NCR Outside NCR Population
Coverage Water DistrictsWSPs 502 per WSP7,0
,011 Urban - outside NCR
(1)
(1) 82 Population 53
50-65% 50-65%
Water DistrictsLGUs
LGUs 502 (1) Est. % of Level III7 Est. % of Urban5
350 7,011 900 (2)
Private operators
Private 350
rivate operators 900 (2) Connections in 11 Outside NCR 7
Urban - outside NCR Population
Source: Asian Development Bank report on Philippine Water Supply and Sanitation Sector Assessment, Strategy and Road Map January 2013; (1) Local Water
Source: Asian Development
Utilities Bank
Administration asreport on Philippine
of 31 December Water
2011; Supply and Sanitation
(2) Department of InteriorSector Assessment,
and Local GovernmentStrategy and Road Map January 2013; (1) Local Water
estimate
Utilities Administration as of 31 December
Notes: 1. Est: estimated, 2. LGU: 2011; (2) Department
local government unit,of3.Interior
NCR: and LocalCapital
National Government
Region,estimate
4. WSP: water service provider
Note:
1. operated water utilities; and (iii) a few private
Est: estimated making, coordination, and resource regulation for
2. LGU: local sector
government unit
operators that have been given a franchise the sector. It shall be provided with sufficient
3. NCR: National Capital Region
4. WSP: water orservice
authority to operate within the geographical
provider capacity and authority to implement key policies,
jurisdiction of an LGU or an industrial zone.” plans and projects in the water resources sector.
In the meantime, NWRB should be
operated
Accordingwater utilities;
to the LWUA, and
as(iii) a few
of the private
end sector
of 2011, 861 strengthened so it can continue its function as
operators that have
water districts hadbeen
beengiven a franchise
established, or 502 Development Plan
of which theto prioritize
sector’s the economic
overall creation ofand
a lead agency
resource
authority to operatetheir
within the geographical for the water sector and for
regulator.” capacity building among the
were operational, number of service
jurisdiction
connections of an LGU or
ranging froman 500
industrial zone.” (with an WSPs:
to 200,000
average of 7,011 connections each). “Develop capacities of national government
According to the LWUA, as of the end of 2011, 861 water “Work towards
agenciesa (NGAs),
lead agency
LGUs, for andtheWSPswater sector
for the
districts had been established, of which 502 were
“It is estimated that about 1,000 LGU-run water A lead agency for
sustainable the entire
management water ofsector should
infrastructure and
operational, theirutilities
number of service
operate in urbanconnections
and rural areasranging ultimatelybetter service provision.
be developed. The lead agency should be
from 500 to 200,000 (with the
throughout an average
country. of 7,011 connections
According to the Project The capacities
able to assume of planning
the functions and implementing
of policy making,
each). Management Unit of the Department of the institutions
coordination, and must
resource be developed
regulation to
for improve
the the
sector.
Interior and Local Government (DILG), there are It shall beperformance
provided with of various
sufficient structural
capacity and and
“It is estimated
about 350 that about 1,000Level
LGU-operated LGU-run water with
III systems, authority nonstructural
to implementinfrastructures
key policies, for theand
plans water sector.
an average
utilities operate of about
in urban and900 ruralconnections each.
areas throughout projects in the water resources sector. In the capacities
NGAs and LGUs should enhance their
These utilities are partProject
of the LGU concerned, meantime, in effective
NWRB should water governance,
be strengthened sustainable use of
so it can
the country. According to the Management
with budgetary allotments coming 2 water resources, and planning for climate
Unit of the Department of the Interior anddirectly
Local from continue its function as the sector’s overall
change adaptation (CCA), among others. LGUs
the LGUs. These systems
Government (DILG), there are about 350 are basically economic and resource regulator.”
self-regulated and WSPs should be assisted in developing
LGU-operated Level IIIby the LGU’s
systems, executive
with an average and of
relevant, practical, and up-to-date management
legislative units. LGU-run water
about 900 connections each. These utilities are part utilities face “Developtools capacities of national government
strong political pressure to keep water tariffs that support integrated water resources
of the LGU concerned, with budgetary allotments agenciesmanagement
(NGAs), LGUs, and and WSPs
technologies. for the
Service
low, often below cost recovery levels, and the sustainable management of infrastructure and
coming directly from the LGUs. These systems are providers should likewise be capacitated in plan
absence of commercial practices such as better service provision
basically self-regulated 5 by the LGU’s executive and development, budgeting and operations, among
‘ring-fencing’ likely masks the indirect material
legislativesubsidies
units. LGU-run water utilities face strong
6 The capacities
others, ofinplanning
order to and implementing
improve coverage, efficiency
they receive for water supply.”
political pressure to keep water tariffs low, often institutions
andmust be developed
sustainability to improve”7the
of infrastructure.
below cost recovery levels, and the absence performance of various structural and nonstructural
The institutional fragmentation of the waterof sector in
commercial practices such as ‘ring-fencing’ likely infrastructures
These are basic for requirements
the water sector. NGAs
for the and LGUsto
government
terms of stakeholders and their roles, and the variety
masks the indirect material subsidies they receive should enhance
be able their capacities
to implement integrated in effective water
water resource
of water service providers has prompted the NEDA in
forthe
water supply. ” governance,
management sustainable
practicesuse andof wateraresources,
pursue coherent and
Philippine Development Plan to prioritize the
planning for climate
investment change program
and financing adaptation for(CCA),
the sector.
creation of a lead agency for the water sector and for
The institutional fragmentation of the water sector in terms among others. LGUs and WSPs should be assisted
capacity building among the WSPs:
of stakeholders and their roles, and the variety of water inOpportunities
developing relevant,
for thepractical, and up-to-date
private sector
service providers has prompted the NEDA in the Philippine management
The toolsof
privatization that
thesupport
MWSS integrated
franchise area waterto two
“Work towards a lead agency for the water
sector. concessionaires, Manila Water and Maynilad, was the
A lead agency for the entire water sector should largest water privatization in the world when this was
ultimately be developed. The lead agency should executed in the 1990s.
be able to assume the functions of policy
5
Ring-fencing of regulatory accounts is needed when a regulated public utility (e.g., water supply) financially separates itself from a parent entity that
engages in non-regulated business. This is done mainly to protect consumers of essential services such as power, water, and basic telecommunications
from financial instability or bankruptcy on the part of the parent corporation that might result from losses in the parent’s open-market activities.
2
Ring-fencing ofRing-fencing also keeps
regulatory accounts customer
is needed information
when within
a regulated the utility
public public(e.g.,
utilitywater
business private
supply) from the
financially parent corporation’s
separates itself from a other
parentbusiness, Source: ADB, op.
entity that
cit. p. 22. business. This is done mainly to protect consumers of essential services such as power, water, and basic telecommunications
engages in non-regulated
from financial6 instability
PhilippineorDevelopment
bankruptcy on Plan
the2011-2016
part of the(PDP),
parentp.corporation
135. that might result from losses in the parent’s open-market activities.
7
Ring-fencing also PDP , p. 136.
keeps customer information within the public utility business private from the parent corporation’s other business, Source: ADB, op. cit.
p. 22. Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines |3 | 44
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Opportunities
Since then, there for have the private
been sectorprivate sector
increasing mustbecause of climate
be developed in a change
timely mannerwould to further
ensureexacerbate
participation and investment
The privatization of the MWSS in urban water area
franchise systemsto two domestic water supply.
the demand ThisThus,
for water. may adopt
new water sources
8
in Metro Manila as private
concessionaires, Manila companies were awarded
Water and Maynilad, was the ecoefficient measures,in
must be developed including
a timelythe reuse to
manner of ensure
congressional
largest water franchises or were
privatization in thegranted
world when this was excessive
domesticrainwater and recycled
water supply. This maywastewater for
adopt ecoefficient
concessions
executed inbythe LGUs or special economic zones.
1990s. non-household
measures, 3 purposes to rationalize water
including the reuse of excessive
Private developers have also built water systems in distribution.
rainwater” 9and recycled wastewater for
private
Sincesubdivisions.
then, there have Medium
beento large-scale
increasing private
private sector non-household purposes to rationalize water
WSPs include Boracay
participation Island Water,
and investment in urbanLaguna Water,
water systems in Two large distribution.
new water ”sources projects have been
Clark Water
Metro at the
Manila asClark Freeport
private companiesEconomic
were Zone,
awarded congres- launched under the PPP mode:
Subic Water
sional and Sewerage
franchises or were Company, Inc., Balibago
granted concessions by LGUs or Two large new water sources projects have been launched
Waterworks System,zones.
special economic MactanPrivate
Rock Industries,
developers have also built under 1. New Centennial
the PPP mode: Water Source – Kaliwa Dam
Project (NCWSP) costing US$416.1 million
PrimeWater
water systems Infrastructure
in privateCorporation,
subdivisions. and Calapanto large-
Medium
“The new dam will help gain water security for
Waterworks.
scale private WSPs include Boracay Island Water, Laguna 1. New Centennial Water Source – Kaliwa Dam Project
Metro Manila and its adjoining areas by
Water, Clark Water at the Clark Freeport Economic Zone, (NCWSP) costing US$416.1 million (PhP18.2 billion)
increasing the supply of raw water and reducing
TheSubic
next Water
big ticket
anditems for theCompany,
Sewerage private sector,
Inc., Balibago “The
Metro new dam
Manila’s will help on
dependence gain thewater
Angatsecurity for
however, will beSystem,
Waterworks in the development
Mactan RockofIndustries,
new raw PrimeWater Metro Manila
Reservoir. The privateand proponents
its adjoiningwill areas by increasing
construct
water sources which
Infrastructure is also a priority
Corporation, in theWaterworks.
and Calapan Philippine the supply of raw water and reducing
the 600 million liters a day (MLD) dam as well Metro
as Manila’s
Development Plan: dependence on the Angat
the 2,400 MLD water conveyance tunnel, Reservoir. The private
The next big ticket items for the private sector, however, access roads, bridges and drainage to be used liters
proponents will construct the 600 million in a day
“Develop
will be sustainable new
in the development waterraw
of new sources
watertosources which (MLD)
building dam
the dam.asHowever,
well as the the2,400
projectMLDdoeswater
not
meet
is also demand
a priority in the Philippine Development Plan:
conveyance
include tunnel, access
the construction roads,treatment
of the water bridges and
demand-supply
A comprehensive gaps across
approach, the country
adhering and
to forthe variant. The privateThe
maintenance. sector
Newpartner will recover
Centennial Waterits
project will
planning the development of new water sources investments from the
be undertaken amortization
through the BOT payments
law’s Build-Transfer
Integrated Water Resources Management (IWRM)
should be developed not only to support the during the 25
framework for projecting the demand-supply gaps variant. Theyears contractual
private agreement.
sector partner will recover its
growing population, but also economic activity in MWSS plans to publish the Invitation to payments during
across the country and for planning the development investments from the amortization
growth centers – based on a viable national Pre-qualify and Bid within June 2014, whileMWSSbid
of newplan.water sourcesdry should be developed the 25 years contractual agreement. plans to
land-use Extended seasons because ofnot only submissions are expected in December 2014.
to support the growing population,
climate change would further exacerbate the but also publish the Invitation to Pre-qualify and Bid within
The indicative timelines for the issuance
economic
demand activity
for water. in growth
Thus, new water centers – based on a
sources June 2014, while bid submissions are expected in
viable national land-use plan. Extended dry seasons December 2014. The indicative timelines for the
8
Ecoeffciency is having “more value with less impact on the environment”; it emphasizes monitoring of material and
energy flows of stocks and life cycle assessment. Source: NEDA op. cit. p. 139
9 PDP, p. 139.
3
International Energy Agency, Power Generation Investment in Electricity Markets
45 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
issuance of the notice to proceed and the Resolving the issues of water supply has significant
signing of the contract is set for the first short term and long term implications for country’s
For further information, please contact:
quarter of 2015.”10 economic development and sustainability. A major
of the notice to proceed and the signing of the contract task involves the rationalization of the institutional
is set for the firstBulacan
2. The quarter of 2015.
Bulk ”
Water Supply Project Robertoframework
and regulatory G. Manabat for the water sector, given
(BBWSP) costing US$542.22 million Chairman
the interests & CEO social sectors, and the
of different
Source: MWSS presentation on New Centennial Water Source – Kaliwa Dam
“The
Project (NCWSP) - June 2014 PhP 24.4 billion peso Bulacan Bulk Water
KPMG
multiple in theuses
economic Philippines
of water. The parallel major
System project will provide universal access to task is the development
T: +63 2 885 7000 of physical infrastructure in
2. The Bulacan potable
Bulk water
Waterspecifically
Supply Project for the Bulacan
(BBWSP) termsE:ofrgmanabat@kpmg.com
new raw water sources and production and
Province, increasing
costing US$542.22 the volume
million (PhP23.7 of potable
billion). distribution water in which includes specific projects
“The PhPwater supplied,
24.4 billion pesothe serviceBulk
Bulacan coverage
Waterand the initially identified opportunities for private investors
System project will provide universal access project
number of households served. The to will such as the Kaliwa dam and the Bulacan Bulk Water
be undertaken using the
potable water specifically for the Bulacan Province, projects, and other projects down the road.
increasingBuild-Operate-Transfer
the volume of potable(BOT) waterlaw under athe
supplied,
30-year contract.
service coverage It will cover
and the number the financing,
of households
served. Theconstruction,
project willoperation
be undertakenand maintenance
using the of
Build-Operate-Transfer (BOT) law under a bulk
the needed facilities for treated water
30-year
supply. Bidding for the Bulacan
contract. It will cover the financing, construction, Bulk Water
operationproject will be conducted
and maintenance using a facilities
of the needed performance
or output-based specification
for treated bulk water supply. Bidding for the approach and
bulk Water
Bulacan Bulk water project
charge as willits
bebidding
conductedparameter.
using
The MWSS
a performance hopes to publish
or output-based its Invitation to
specification
approachPre-Qualify
and bulk water and Bid
charge within June
as its 2014.”11
bidding
parameter. The MWSS hopes to publish its Invitation
toThe government
Pre-Qualify willwithin
and Bid also tender, under
June 2014. ” the PPP For further information, please contact:
mode, the transmission improvement project for the
Angat
Source: MWSS Dam worth
presentation US$131.35
on Bulacan million.
Bulk Water Supply Project (BBWSP) -
June 2014 Jerome Andrew H. Garcia
Advisory Principal
The government will also tender, under the PPP mode, the KPMG in the Philippines
transmission improvement project for the Angat Dam worth T: +63 2 885 7000 ext. 208
US$134 million or PhP5.8 billion.
E: jhgarcia@kpmg.com
10
MWSS, Presentation on New Centennial Water Source – Kaliwa Dam Project (NCWSP) - June 2014
11
MWSS, Presentation on Bulacan Bulk Water Supply Project (BBWSP) - June 2014
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 46
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Issues in
developing
Dev eloping
Energy
Ener resources
gy Resour
Pow er er
Pow generation is one
generation sector
is one where
sector whereinv inv
estments
estmentsareare
crucially dependent
crucially dependent ononthethe
privateate
priv sector .
sector. Under
Under therent
the cur current regulator
regulatory y framew
framew ork, additional
ork, additional generation
generation capacit
capacity y, particularly
, particularly for baseload
for baseload plants, can only
plants, can only be
be undertaken byundertaken by private
private investors. New investors. New have
power plants powertoplants have
be built to be builtpower
as merchant as plants, with
merchant power plants, with no government guarantees on market
no government guarantees on market demand risk and no guaranteed offtaker. demand risk and no guaranteed
offtaker.
Today
Today , the
, the tight
tight demand-supply
demand-supply balance
balance is being
is being feltfelt in the 2016, Target
and the capacity
decline of in
committed
Mindanaoand from indicate private
107.7 percent
Visayas
in the andand
Visayas Mindanao
Mindanao regions,
regions,andandepisodically in Luzon. in 2010 sector-initiated
to 100 percent power by plant
2016. projects,
Only the2013-2016Visayas will
Given the in
episodically lead time Given
Luzon. for construction
the lead time beforefor plants can be show a slight increase in the ratio from 103 percent
commissioned,
construction beforethe immediate
plants can be period and the next
commissioned, the two to to 105 percent Particulars
for the same period. Nevertheless, Grid
Luzon Visayas Mindanao
three years
immediate will and
period be athe testnext
of whether
two to three the current
years power the government expects to meet the target of 100
willindustry
be a test framework
of whether canthe
engender
current powera sufficient response percent
industry Capacityin allof the regions
committed by 2016. (See767
power Appendix
.4 429.6H) 515.0
from private
framework can investors
engenderso that adequate
a sufficient response new from
capacity can plant projects (2013-2016, in MW
be installed
private investors in asotimely manner to
that adequate newmeet the projected
capacity can Target capacity of committed and indicate private
Capacity of indicative 9,702.5 718.0 1,928.0
bedemand.
installed in a timely manner to meet the projected sector-initiated
power plant projectspower(2013-2016,
plant projects,
in MW2013-2016
demand. Particulars Grid 100.0%
Peak demand according to the Philippine Development Plan Ratio of dependable capacity 107Luzon .86% 105.32%
Visayas Mindanao
to peak demand and required reserve (2016)
is expected
Peak to increase
demand according toatthe
4.5Philippine
percent annually from 2009Capacity of committed power
767.4 429.6 515.0
to 2030. ForPlan
Development theisperiod
expected2010to toincrease
2016, this at translates
4.5 to a plant projects (2013-2016), in MW
Source: Philippine Development Plan 2011-2016
total of
percent 11,900MW
annually fromcapacity
2009 to required
2030. For forthetheperiod
Luzon grid; Capacity of indicative power plant
9,702.5 718.0 1,928.0
http://plans.neda.gov.ph/pdp/chapter-10-accelerating-infrastructure-development/
2,150MW
2010 to 2016,for thisthe Visayas grid;
translates and 2,500MW
to a total of 11,900MW for the projects (2013-2016), in MW
Mindanao
capacity grid. for
required Thetherevalidated
Luzon grid; results
2,150MW matrix forin the Ratio of dependable
These targets capacity
are totobe peak
met107.86%
through new 105.32%power projects
100.00%
midterm update of the plan
the Visayas grid; and 2,500MW for the Mindanaocalls for power demand up todemand and required reserve (2016)
totalling 10,469MW in Luzon, of which 767.4MW are
2016
grid. Thetorevalidated
be met – defined as maintaining
results matrix in the midtermabove 100 percent Source:committed.
Philippine Development Plan 2011-2016
The remaining 9,702MW of indicative power
http://plans.neda.gov.ph/pdp/chapter-10-accelerating-infrastructure-development/
the ratio
update of theof dependable
plan calls forcapacity
power demandto total peakup to demand plus plants are expected to come mostly from brownfield
required
2016 to be metreserves.
– defined For asthemaintaining
country as aabove whole, 100the ratio is expansions of existing plants. In the Visayas, total capacity
projected
percent to goofdown
the ratio from 108.14
dependable capacitypercent as of the 2010 These
to total targets
through areistoprojected
2016 be met through to reachnew power of which
1,147MW,
baseline
peak demand to 104.39 percent
plus required by 2016. The
reserves. For thedecrease in the projects 429.6MW totallingare10,469MW
committed.inIn Luzon,
Mindanao,of which total capacity is
ratio isasweighed
country a whole,down by the
the ratio decline into
is projected Luzon
go downfrom the 767.4MW
projected are atcommitted.
2,443MWThe withremaining
515MW committed. 9,702MW of
113.4
from percent
108.14 baseline
percent as ofinthe20102010to baseline
107.86 percentto by 2016, indicative power plants are expected to come mostly
and the
104.39 decline
percent by in Mindanao
2016. from 107
The decrease in.7thepercent
ratio isin 2010 to fromThe brownfield
government expansions
has alsoofset existing
the target plants. In the
of increasing the
100 vbydown
weighed 2016.byOnly the Visayas
the decline will show
in Luzon from the a slight increase Visayas, country’stotal energy
capacityself-sufficiency
through 2016 is projected
(ratio to
of indigenous energy
in the
113.4 ratio from
percent 103 in
baseline percent
2010 to to107
105 .86percent
percent forbythe same reach 1,147MW,
sources such of aswhich 429.6MW
geothermal energy areandcommitted.
natural gas from
period. Neverthless, the government expects to meet the Malampaya) from 58.3 percent in 2010 to 60 percent by
target of 100 percent in all the regions by 2016.
For a more in-depth look on the Philippine electric energy industry, you can refer2016. to R.G. Manabat & Co.s ’ 2013-2014 annual investment guide
entitled The Energy Report: Growth and Opportunities in the Philippine Electric Power Sector available for download at www.kpmg.com.ph.
47 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
worth noting that increasing private sector participation in
The government has also set the target of increasingthe power sectorLight
Electric and more market-based
and Railroad Company regulatory
(MERALCO)
the country’s energy self-sufficiency (ratio of regimes was
has been the global trend during
awarded the franchise to sell electricity the same periodto
indigenous energy sources such as geothermal both in industrial
Manila and as well as emerging around
52 municipalities countries. the The
city.power
1
http://plans.neda.gov.ph/pdp/chapter-10-accelerating-infrastruct
energy and natural gas from Malampaya) from 58.3 sector in many countries are more or less in the same
ure-development/
percent in 2010 to 60 percent by 2016. situation The
as inNational
the Philippines with new capacity to be in the
Power Corporation (NPC), created
mandated as merchant
1930s through power plants assume
Commonwealth Act 120, market
was
These targets are to be and
The liberalized met market-based
through new power power projects
industry put demand originally
risk. intended to develop the country’s
totalling 10,469MW
in place by thein Luzon,
Electric of Power
which 767 .4MWReform
Industry are Act hydroelectric resources.
committed. The remaining 9,702MW of indicative
(EPIRA) relies on the private sector to construct power In fact, the earlier phases of electric power industry in the
plants aregeneration
expected to come
plants to mostly from brownfield
meet demand. Private sector country have been managed by private enterprise.
In 1939, NPC constructed its first project, the
expansions of existing plants. In
investments in power generation, the Visayas, total capacity
however, have 8MW Caliraya Storage Hydro Power Station in
through 2016
beenislower
projected to reach 1,147MW,
than expected of whichenergy
vis-à-vis projected ElectricityLumban,
was first introduced
Laguna. in the Philippines
NPC continued in
to build other
429.6MWdemand.
are committed. In Mindanao, total capacity is 1890 with hydropower facilities,
the installation and by
of three 1956, NPC
electric arc lamps
projected at 2,443MW with 515MW committed. in Escolta, generation
Manila, and accounted
the firstforpower
aboutstation
one-third of the
built in
The current regulatory configuration of the power 1895. Incountry's
1901, Manilatotal Electric
generation Lightcapacity. The
and Railroad
The government has also
sector stems fromsetthetheoutcome
target ofofincreasing the
the Investment Companyremaining
(Meralco)two-thirds
took overwas the infranchise
the hands forof 336
country’sPriority
energyPlan self-sufficiency (ratio of indigenous
(IPP) program used by the country to energy private and municipally-owned
providing electricity to Manila and 57 municipalities electric utilities,
sources such as geothermal energy and natural
resolve the power crisis in the early 1990s and the gas from of which Meralco was the largest,
around the city. Private electric utilities were also accounting for
Malampaya) from 58.3 percent in 2010 to 60
consequences of the program in the aftermath of the percent by 990MW of 1,745.5MW total
established during this period in other major cities demand. Most of
2016. this private generating capacity was thermal
Asian Financial Crisis. It is worth noting that and towns throughout the country.
plant. NPC acquired Meralco's generation and
increasing private sector participation in the power
The liberalized and market-based power industry put in distribution systems outside Manila in 1953
sector and more market-based regulatory regimes The National Power Corporation (NPC), created in the 1930s
place by the Electric Power Industry Reform Act (EPIRA) when Meralco decided to concentrate its
has been the global trend during the same period through CommonwealthelectricityAct 120, was
business in the originally
Manila area.intended
2 to
relies on both
the private sectoras
in industrial towell
construct generation
as emerging plants to develop the country’s
countries. hydroelectric resources.
meet demand. Private sector
Many countries investments
are more or less in in the
power
same
generation, however, have been lower than expected Outside Manila, the electricity services were
situation as the Philippines with new capacity to be Inprovided
1939, NPC by constructed
private companiesits firstorproject, the 8MW
rural cooperatives,
vis-à-vis projected energy demand.
mandated as merchant power plants assume market Caliraya StoragepowerHydrofrom Power Station in Lumban,
either buying private generators or from
demand risk. Laguna.
NPC. NPCforward
Fast continued to to build
1972 when other hydropower
under martial law,
The current regulatory configuration of the power sector facilities, and by 1956, NPC generation accounted
stems from the outcome the government nationalized the generation and
In fact, the earlierofphases
the Investment Priority
of the electric Plan
power fortransmission
about one-third phasesof the
andcountry's
2
regulatedtotal the generation
(IPP) program used by the country to resolve
industry in the country have been managed by the the power capacity.
crisis in the earlyenterprise.
1990s and When,the consequences of the privately-owned distribution sector. in the hands
The remaining two-thirds was
private starting in 1901, Manila of 336 private and municipally-owned electric
program in the aftermath of the Asian Financial 1 Crisis. It is utilities, of which Meralco was the largest,
1
1 Cham Rowena M, The Philippine power sector: issues and solutions. The Philippine Review of Economics. Vol XLIV No 1 June 2007 p. 33-63ic Studies.
Cham Rowena
25 MarchM, The Philippine power sector: issues and solutions. The Philippine Review of Economics. Vol XLIV No 1 June 2007 p. 33-63ic Studies.
2014.
25 March 2014. op. cit.
2 Cham,
2 Cham, op. cit.
49 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
3. access to the transmission and distribution participate on the demand side. WESM started
network, privatized as a long term concession. commercial operations on 26 June 2006. Currently
This took place in 15 January 2009 when the participating in the WESM are 13 generating
transmission company formally turned over the companies with 11 distribution utilities (DUs) and five
25-year concession of the National Transmission registered direct suppliers.
Corporation (TransCo) to the National Grid able to bid out 68.22 percent of NPC contracts to IPPAs.
3. access to the transmission and distribution network,
Corporation of the Philippines (NGCP), which is PSALM is also required to privatize 70 percent of the
Critical Periods
privatized as a long term concession. This took place in
responsible for the development, upgrading, and
15 January 2009 when the transmission company The total energy
On Available
Department output
Capacity:
of Energyof power
(DOE), plants
On Available under contract
Capacity
in its assessment + of the
rehabilitation of the electricity grid. Committed:
formally turned over the 25-year concession of the with NPC to independent power producer
demand-supply situation, has identified critical periods in
4. unbundling of tariffs into generation,
National Transmission Corporation (TransCo) to the administrators
the Luzon, Visayas and (IPPAs) prior togrids.
Luzon
Mindanao the start
Theof an open
largest deficits
transmission, distribution, systems losses, and April-May 2015: Projected Deficit April-June 2017: Projected
National Grid Corporation of the Philippines (NGCP), access
will occur in market.
Luzon of To-date,
up to 635MWPSALM bywas
MarchabletotoJuly
bid 2016,
out
stranded costs, and of 184 MW Deficit of 200 to 450MW
which is responsible for the development, upgrading, and up 68.22 percent in
to 940MW ofthe
NPC contracts
March to IPPAs.2018 period.
to December
5. provisions for resolving the stranded costs and
and rehabilitation of the electricity grid. The deficits in Projected
the Visayas andMarch-December
Mindanao will2018: not be as
stranded debts through universal levies. The March-July 2016: Deficit
4. unbundling of tariffs into generation, transmission, large The
but Department
will be moreof Energy
frequent. (DOE),Deficit
in itsofassessment
government would no longer offer to guarantee of 240 to 635MW Projected 270 to 940
distribution, systems losses, and stranded costs, and of the demand-supply situation, has identified critical
market risks through take-or-pay contracts, and MW
5. provisions for resolving the stranded costs and periods inthe theyears
Luzon, Visayas andareMindanao
would not engage in power generation. In Mindanao, 2013 to 2015
Visayas expectedgrids.to be
stranded debts through universal levies. The
The
critical largestbased
November-December
periods deficits
2014:on will occur in Luzon
December
available of up
2015:prior
supply, to to
Projected
the plants
government would no longer offer to guarantee market Projected Deficit of 30 to 90MW
Suppliers 635MW
committed in by
the March to July Deficit
pipeline. 2016,ofand 60MWup to 940MW in
risks throughwere encouraged
take-or-pay to enter
contracts, into long-term
and would not
bilateral contracts with
engage in power generation. users, with the power to be the March to December 2018 period. The deficits in
April-December 2015: Projected April-June 2016: Projected
delivered through the transmission grid which would the Visayas and Mindanao will not be as large but will
Deficit of 80MW to Max 220MW Deficit of 70 to 100MW
Suppliersbe paidencouraged
were through wheeling
to entercharges. The Wholesale
into long-term bilateral be more frequent. December 2017-December
Electricity Spot Market (WESM) was
contracts with users, with the power to be deliveredcreated 2018: Projected Deficit of 120 to
consisting
through the of IPPs,
transmission gridprivatized
which wouldNPCbegenerators, and
paid through In Mindanao, the years 2013 to 2015 are expected to
305MW
wheelinggenerating
charges. Theplants not yetElectricity
Wholesale privatized Spot
on the supply
Market be critical periods based on available supply, prior to
Mindanao
2013:the plantsDeficit
Projected committed
of 50 to in the pipeline. 2015:
January-February
(WESM) side, while distribution
was created consisting companies, large commercial
of IPPs, privatized NPC
and industrial users, and aggregators wouldon the 110MW
Projected Deficit of 100 to
generators, and generating plants not yet privatized 130MW
supply On
side, whileCapacity:
Available distribution companies, large CriticalCapacity
On Available Periods
2014: + Committed:
Projected Deficit of 50 to November-December 2017:
commercial and industrial users,Capacity
On Available and aggregators would 190MW On AvailableProjected
Capacity + Committed
Deficit of 20 to 50MW
participate on the demand side. WESM started commercial 2015:
Luzon Projected Deficit of 120 to 2018: Projected Deficit of 50 to
operations on 26 June 2006. Currently participating
April - May 2015: Projected Deficit of 184 MW
in the 280MW 200MW
April - June 2017: Projected Deficit of 200 to 450MW
WESM are 13 generating companies with 11 distribution
March - July 2016: Projected Deficit of 240 to 635MW March - December 2018: Projected Deficit of 270 to 940 MW
utilities (DUs) and five registered direct suppliers.
Visayas
November - December 2014: Projected Deficit of 30 to 90MW December 2015: Projected Deficit of 60MW
PSALM is also required to privatize 70 percent of the total
April - December 2015: Projected Deficit of 80MW to Max 220MW April - June 2016: Projected Deficit of 70 to 100MW
energy output of power plants under contract with NPC to
December 2017 - December 2018: Projected Deficit of 120 to 305MW
independent power producer administrators (IPPAs) prior to
Mindanao
the start of an open access market. To-date, PSALM was
2013: Projected Deficit of 50 to 110MW January - February 2015: Projected Deficit of 100 to 130MW
2014: Projected Deficit of 50 to 190MW November - December 2017: Projected Deficit of 20 to 50MW
2015: Projected Deficit of 120 to 280MW 2018: Projected Deficit of 50 to 200MW
Source: Department of Energy presentation on 2013 to 2020 Supply-Demand Outlook and Updates on Mindanao Power Situation August 2013
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 50
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Luzon Supply-Demand Outlook 2013-2020
13500 Luzon Supply-Demand
2014 Outlook 2013-2020
2015 There have
2016 been recent discussions, however, on revising
13000
Mar: Maibarara Geo - 20MW Feb: Southwest Luzon 2 - 150MW the Anda
Mar: EPIRA
Powerframework,
- 82MW prompted by a spike in prices and a
Aug: Puting Bato 1 -135MW Mar: SJCI Power - 9.9MW Dec: EWC Phase 3 - 200MW
12500
Sep: Pililia Wind - 67.5MW Isabela Bio - 18 MW seeming lack of coordination between PSALM, DOE, and
Sep: Avion - 100MW Nov: Puting Bato 2 - 135MW the Energy Regulatory Commission (ERC). Such uncer
Nov: Southwest Luzon 1 - 150 MW Dec: EWC Phase 2 - 200MW
tainty in the regulatory framework may affect investment
12000
Dec: EWC Phase 1 - 200MW
11500
decisions and execution of capacity expansions.
11000
Jul 13
Sep 13
Nov13
Jan 14
Mar 14
May 14
Jul 14
Sep 14
Nov 14
Jan 15
Mar 15
May 15
Jul 15
Sep 15
Nov 15
Jan 16
Mar 16
May 16
Jul 16
Sep 16
Nov 16
Jan 17
Mar 17
May 17
Jul 17
Sep 17
Nov 17
Jan 18
Mar 18
May 18
Jul 18
Sep 18
Nov 18
Jan 19
Mar 19
May 19
Jul 19
Sep 19
Nov 19
Jun 20
Mar 20
May 20
Jul 20
Sep 20
Nov 20
Updates on Mindanao Power Situation August 2013
shown that merchant power investor response has been
Visayas Supply-Demand
Visayas Supply-Demand Outlook 2013-2020
Outlook 2013-2020 adequate to match the capacity requirements, as long as
2016 wholesale prices for base load and for peaking plants are
3200
2014 2015
3000
Mar: Villasiga - 8MW Mar: Sn Carlos Bio - 16MW Jul: Concepcion Coalallowed
1 - 135MW to accurately signal emerging demand situations.
Jun: ASIAN Bio - 3.6MW Sep: Concepcion Coal 2 -135MW
2800 Jun: Nasulo Geo - 50MW Investors are able to plan on base load demand given the
Sep: Toledo - 82MW
2600 expectation that consumers put value and are willing to pay
2400 for security of supply.
2200
May 14
Nov 17
Jan 18
Mar 18
May 18
Jul 18
Sep 18
Nov 18
May 13
Jul 13
Sep 13
Nov13
Jan 14
Jul 14
Sep 14
Nov 14
Jan 15
Mar 15
May 15
Jul 15
Sep 15
Nov 15
Jan 16
Mar 16
May 16
Jul 16
Sep 16
Nov 16
Jan 17
Mar 17
May 17
Jul 17
Sep 17
Jan 19
Mar 19
May 19
Jul 19
Sep 19
Nov 19
Jun 20
Mar 20
May 20
Jul 20
Sep 20
Nov 20
Define clearly the government’s role in electricity
Source: Department of Energy presentation on 2013 to 2020 Supply-Demand Outlook and
Updates on Mindanao Power Situation August 2013 market reform and the terms of its involvement as
Mindanao Supply-Demand Outlook 2013-2020
precisely as possible.
Mindanao Supply-Demand
2900
2015 Outlook 2013-2020
2016
2700
Mar: Therma South 1 - 150MW Sep: FDC Coal - 405MW
2500
Jun: Therma South 2 - 150MW
2300
Sep: Southern Mindanao Coal - 200MW
2100
1900
1700
1500
1300
1100
Jul 18
Sep 18
Nov 18
Jan 19
Mar 19
May 19
Jul 19
Sep 19
Nov 19
Jun 20
Mar 20
May 20
Jul 20
May 13
Jul 13
Sep 13
Nov13
Jan 14
Mar 14
May 14
Jul 14
Sep 14
Nov 14
Jan 15
Mar 15
May 15
Jul 15
Sep 15
Nov 15
Jan 16
Mar 16
May 16
Jul 16
Sep 16
Nov 16
Jan 17
Mar 17
May 17
Jul 17
Sep 17
Nov 17
Jan 18
Mar 18
May 18
Sep 20
Nov 20
Source: Department of Energy presentation on 2013 to 2020 Supply-Demand Outlook and
Start of
Updates onCritical
Mindanao Power SituationProjected
Periods Demand
August 2013 Available Capacity Available + Committed
Source: Department of Energy presentation on 2013 to 2020 Supply-Demand Outlook and Updates on Mindanao Power Situation August 2013
What is significant in the pipeline of indicative power
What is significant
projects in theofpipeline
is that most them are of expansion
indicative power
projects projects
of is that most of them are expansion projects of
existing
existingpowerpower plants.
plants.This would
This wouldbe be
an an
indication
indication that power plants, which have been operating in the country
that
with a connectivity
power plants, which to and
havea track
beenrecord of supplying
operating to the grid, are in a position to expand capacity and obtain
in the country
financing support to take
with a connectivity advantage
to and of the expected
a track record of supplying increases
to the in demand. For those with existing take-or-pay
contracts,
grid, are in a position to expand capacity and obtain financ critical periods in the demand-supply balance, they
this is also a sign that as they look at the expected
willing
besupport
able to take market
to take demand
advantage risksexpected
of the under a merchant
increases contract
in and/or expect to sell into the WESM at
market-based pricing.
demand. For those with existing take-or-pay contracts, this
There haveinbeen
periods recent discussions,
the demand-supply however,
balance, on revising
they will be able theto EPIRA framework, prompted by a spike in prices and
a seeming
take market lack demand
of coordination between
risks under PSALM,
a merchant DOE, and
contract the Energy Regulatory Commission (ERC). Such
and/or
uncertainty
expect toinsell theinto
regulatory
the WESM framework may affect
at market-based investment decisions and execution of capacity expansions. It
pricing.
would be useful to take a page from the experience of other countries with merchant power. In the Organisation
for Economic Co-operation and Development (OECD) countries and emerging markets, merchant power projects
are becoming more common. In OECD countries, it is shown that merchant power investor response has been
4
adequate to match
International the capacity
Energy Agency, requirements,
Power Generation Investmentas long as Markets
in Electricity wholesale prices for base load and for peaking plants are
allowed to accurately signal emerging demand situations. Investors are able to plan on base load demand given
51 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
the expectation that consumers put value and are e.g. through direct price caps which could drive
willing to pay for security of supply. away needed investment.
The International Energy Agency (IEA) has the Monitor adequacy of gas markets and
following recommendations: 4 investments.
The preference of investors in some markets for
Define clearly the government’s role in
Combined Cycle Gas Turbine (CCGT) for building
electricity market reform and the terms of its new power generating capacity means that gas
involvement as precisely as possible. markets assume a greater importance than ever
Attracting investment in power generation for power generation development. For
requires a clear market design, with predictable governments, this means moving forward on
changes and no interference into the market or liberalization of both the gas market and the
into the operation of the independent institutions electricity market, and monitoring the adequacy
established to implement the market reform. The of investment in both gas and electric
government’s role must be clearly set out both infrastructure.
as the agent of the reforms and in its energy
the expectation policy
that consumers
involvementput value
once theand are opens.
market willing to For emerging
Greater demandmarkets,
response similar prescriptions
in electricity markets andis
The Internationalintrinsic
Energy to well-functioning
Agency electricity
(IEA) has the following sufficient response from investors.
supply according to price rather than through
A key
recommendations:markets. recommendation
brownouts is to have
or blackouts. a rational
A stronger tariff
demand
Allowing markets to signal the need for new regulations,
response will ahelp
strong independent
mitigate regulator,
market5 power in and
investment
Define clearly in generation means
the government’s role inthat prices will
electricity viable and
electricity financially
markets andstable
provide distribution utilities.5
potential investors
go high on occasion. Governments
market reform and the terms of its involvement need to with more predictable energy (and ancillary service)
anticipate that
as precisely as possible. such fluctuations will occur and Although
prices the government
and therefore decrease is reportedly
investmentconsidering
risks.
ensure that consumers are aware of price risks invoking the emergency powers of the President
Attracting investment in power generation requires a
and have options to mitigate these risks. under the existing EPIRA
clear market design, with predictable changes and Be prepared to detect andlaw in order
to act upontowholesale
contract for
no interference into the market or into the operation additionalmarket
electricity power during possible low power reserve
manipulation.
Develop demand response within electricity
of the independent institutions established to Insituations in 2015, concerns
order to address the basic about
industry structure that
wholesale
markets. has beenmarket
put in place under thegovernments
EPIRA law: must open
implement the market reform. The government’s electricity manipulation,
Fluctuating spot electricity prices offer rewards
role mustasbewell
clearly set out accessthat
competitive
electricitymerchant power plants in the
as risks. Theboth as the
low price agent of
elasticity ofthe ensure markets have monitoring
reforms and in its energy policy involvement once generation sector,
mechanisms a monopoly
that cannot only detectin themanipulation
national gridas
electricity demand, especially for small
the market opens. is at least partly due to the inability
customers,
operated by a private concessionaire,
it is occurring but also take prompt action andtoa regulated
to reward consumers for adjusting their distribution
mitigate utilities This
its impacts. will continue
will reduce to pressure
be the regulatory
on the
Recognize that electricity
consumption whenprice
pricesfluctuations are
are high. Greater framework under which the power sector will
intrinsic demand
to well-functioning electricity markets.
response in electricity markets is develop and expand to meet electricity demand in
Allowing needed
marketstotohelp
signal the that
ensure needelectricity
for new markets the future. This framework has been proven in other
investmentarein generation
always able tomeans that
clear, i.e. byprices will go
rationing countries to work in attracting sufficient investments
electricityGovernments
high on occasion. supply according needto price rather than
to anticipate in merchant power capacity as long as there is an
that suchthrough brownouts
fluctuations or blackouts.
will occur and ensure A stronger
that independent tariff regulator and transparent market
consumers demand response
are aware will help
of price risksmitigate
and have market
options based pricing.
power in electricity markets and provide potential
For further information, please contact:
to mitigate these risks.
investors with more predictable energy (and
Develop ancillary
demandservice)
response prices and therefore
within decrease
electricity Roberto G. Manabat
markets.investment risks. Chairman & CEO
Fluctuating spot electricity prices offer rewards as KPMG in the Philippines
Be prepared to detect and to act upon
well as risks. The low price elasticity of electricity
wholesale electricity market manipulation.
T: +63
For 2 885
further 7000
information, please contact:
demand, especially for small customers, is at least E: rgmanabat@kpmg.com
In order to address concerns about wholesale
partly due to the inability to reward consumers for
electricity market manipulation, governments Henry D. Antonio
adjustingmust
their ensure
consumption when prices
that electricity arehave
markets high.
Head of Advisory
monitoring mechanisms that cannot only detect
manipulation as it is occurring but also take KPMG in the Philippines
prompt action to mitigate its impacts. This will T: +63 2 885 7000 ext. 387
reduce pressure on the government to respond, E: hantonio@kpmg.com
4
5 International Energy Agency, Power Generation Investment in Electricity Markets
Anoop
5 Singh, Private Investment in Power Sector in Developing Countries: Lessons from Reforms in Asian and Latin American Countries
Anoop Singh, Private Investment in Power Sector in Developing Countries: Lessons from Reforms in Asian and Latin American Countries
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 52
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
TTaxation
axation
Taxationof
ofof
Infr
Infr
Infr
astr
astr
astr
uct
uct
uctur
ur
ureePr
ePrPr
ojects
ojects
ojects
Cristina
Cristina
R
Ro
oxas,
Roxas,
Advisory
Advisory
Par
artner
tner
Partner
, KPMG
, KPMG
in the
in Philippines
the Philippines
Mary Karen Quizon-Sakkam,Tax Director, KPMG in the Philippines
Infrastr
Infrastruct
Infrastr Infrastruct
uct uct
ureure projects
ure projects
projects areare granted
are granted
granted fiscal
fiscal fiscal
and and non-fiscal
and non-fiscal
non-fiscal incentiv
incentiv incentiv
eses under
under esthe
under
the Omnibus
the Omnibus
Omnibus Investments
Investments
Investments Code.Code
To qualify
Code. TToo qualify
qualify,
, the ,project
the project
the project
mustmust
must
be registered
be registered
be registered
with with
with
the Bthe
the
oard
BBoard
oard
of Invof
of
estments
Invvestments
In estments
(BOI).(BOI).
Registration
(BOI). RRegistration
egistration
requires
requires
that that
the minimum
requires the minimum
that theequit equit
y of the
minimum yequit
ofoperating
the operating
y of thecompan compan
operatingy must
y must
companat least
y at
mustleast
be at
twbeent
enty
twenty
leasty fiv
five
beetwenty
(25%)
five (25%)
of
fivetheofproject
the project
percent cost cost
unless
(25%) unless
of e
exxempted
the exempted
project under
costunder
any of
unless any
theofffollo
exemptedollowing:
the wing:
following:
under any of the following:
1. Projects of applicants with good track record payments thereto are subject to two percent (2%)
1
in. implementing
Projects
1. Projects of applicants
of applicants
registered withprojects;
good
with trac good k record
track record
in banks,banks,
in creditable interestinterest
withholding payments
taxpaifyments
thereto
the thereto
operatingare subject
are subject
company to tis
woto two
implementing
2. Projects implementing registered
of publicly-listed registered
projects;
companies; projects; or percent
classified percent
and (2%) credit
(2%) as
notified credit
ablea topwithholding
able
twentywithholding tax if tthe
thousand ax ifoperating
the operating
2. P Projects
3. Projects 2. Pnot rojects
ofentitled
publicly
of publicly
-listed
to Income-listed
companies; companies;
Tax or
Holiday or compan
company
(20,000) company
y is classifi
corporation is by
classifi
edthe and ednotifi
tax and ed
notifi
authorities.as eda topas
Onatw top
theenttwent
y thousand
y thousan
3.
(ITH) P
Projects
3. Projects not entitlednot entitled
to Income to Income Tax Holida
Holiday
Tax Holiday
y (I
(ITH)
TH) (ITH) other (20,0
(20,00 0(20,000)
hand, 0) loans
corporation
corporation
obtained bbyy by
theby tt
ax
the the authorities.
tax authorities.
operating On the
company Onother
the other
from hand, hand,
OffshoreloansBanking
loans
obtainedobtained
b
byy the
Units byoperating
(OBUs) the or operating
compan
company
from the
company
y from from
Infusion
Infusion Infusion
of equit
of equit equityyofcapital
yequity
capitthrough
alcapit
through
al throughsubscription
subscription subscription
of of shares of shares
of Foreign
of
Of
Offshore
fshore
Offshore
Currency Banking Banking
UnitsUnits
Deposit Units
(OBUs) (OBUs)
(FCDU)or from oforbanks
the
fromForeign
the
in Foreign
stoc
stocks
shares ks
ofstocks
at
attracts
tracts
stocks attracts
st
stamp
ampstdut
attracts duty
amp
st y tduty
amp axdut ofytax
.5tax percent,
ofof.50.5 percent,
basedbased on theonthe theCur
rency
CurrencyCurrency
Philippines Deposit
are Deposit
Unit (FCDU)
generally Unit (FCDU)
subject of to
banks of banks
ten in theinPhilippines
percent the Philippines
tot
total
al par
total v alue
par vof
aluethe of originally
the
percent, based on the total par value of the originally originally
issued issued
shares. shares.
Should Should
a a
(10%)arefinal
generally
arewithholding
generally
subject subject
to tentopercent
tax. ten percent (10%)(10%) final withholding
final withholdin
foreign
issued foreign
shares.in
invvestor investor
Should opt to aoptbuytothe
foreign buinvestor
yshares
the shares of
optantoofebuy
xisting
an existing tax. tax.
theoperating
shares operating
ofcompan
company company,
an existing y, theoperating
st the
ampstamp
stamp dut
duty y tduty
company, ax rate tax
theisrate
.375 is percent
.375 percent
In case of foreign loans, interest payments to the
based
stamp based
duty on taxtheon tot
total
rate the
alispar
total
0.375 value
par vof
alue
percent theof acquired
basedthe acquired
on shares.
the shares. offshore In case In ofcase
lenders foreign
of
areforeign
loans,loans,
subject interest
to twentyinterest
payments payments
percent to
(20%)thetoofthe
fshore offshore
total par value of the acquired shares. finallenders lenders
withholdingare subject
are
tax. subject
Theto twithholding
went
ent
to twent
y percent ytax
percent
(20%)
rate may (20%)
final final
In man
many Inymany
instances, instances,debt financing
debt financing is partisofpart theofpre-project
the pre-project withholding
be reduced withholding tax. isTtax.
if there he
an withholding
The withholding
applicable taxtaxtreaty
ratetaxmama
ratey bemareduced
y be reducedif
activities.
activities.
L ocal Local
t
tax
ax r ules
In many instances, debt financing is part of thetax and
rules regulations
and regulations allo w allow
the the
betweenthere there
is
theanPhilippines
applicable
is an applicable tax treat
and treaty
taxhome
the ytreaty
bet
betw w een
betw
country the
een
ofPhilippines
the Philippines
deduction
pre-project deduction of interest
activities. of interest
Localpayments
taxparules
yments
onand loanson loans
for purposes
regulations for purposes of lender.
of and the andhome the home
countrcountry
y of theoflenderlender.
the lender.
.
Philippine
Philippine
income income
t ax subject
t ax
allow the deduction of interest payments on loans for subject
to the tot ax
the arbitrage
t ax arbitrage
rule rule
wherein
purposes wherein
ofthe amount
Philippinethe amount of allo
income allow of
wtaxable
allow deduction
able deduction
subject to the fortaxinterest
for interest ThereThere
areTareherealso
also arecert
cert alsolenders
ain ain certlenders
ainthatlenders
that
enjoenjoythat y enjoy
pref
preferential
preferential erential
preferential
ttax
ax tax
expense
arbitrage erule
xpense
shall
whereinbe
shallreduced
be
thereduced by thirt
amount thirty
by
ofy allowable
thirty
three three percent percent
(33%)(33%) of taxoftreatmenttreatmentin theinPhilippines
the Philippines suc
such h assuch theasAsianthe Asian
De
Dev
velopment
Developme
the interest
deduction thefor interest
income
interest incomesubjected
expense subjectedto final
shall beto ttax.
final
ax. Similarly
reduced Similarly,
tax.by Similarly,
, Bank B
Development (ADB)
ank Bank
(ADB)
and (ADB)
the
andInternational
the
andInternational Finance
the International Finance
Corporation
Corporation (IFC). (IFC
document
documentar
documentary
ary y st
stamp
amp stamp
t
tax
ax
thirty three percent (33%) of the interest income (DStax T) (DS
paid T) on
paid debton instr
debt uments
instruments Finance
SinceCorporation
Since
thesetheseentitiesentities
(IFC).are Since
exare
empt ex empt
thesefromentities
Philippine
from Philippine
are income income
tax,
ax,
ta
(rate is
subjected (rate
.5
to percent),
is .5 tax.
final percent),
whose
Similarly,whose
object object
is located
documentary is located
or used
stamp or used
in theinexempt
theinterestinterest
from paPhilippine
yments
payments
toincome
theseto these
organizations
organizations
tax, interest are consequently
are consequently
taxPhilippines,
(DST)Philippines,
paid on is ttax
ax is
debt deductible.
tax deductible.
instruments (rate is 0.5 exempt
payments exto empt
from
thesewithholding
from withholding
organizations tax. are tax.
consequently
percent), whose object is located or used in the exempt from withholding tax.
Interest
Philippines, Interest
paisyments,
taxpadeductible.
yments,
howehowever,ver
er,, ma
mayy be may subject
be subject
to withholding
to withholding A similar
A similar
preferential
preferential
ttax
ax treatment
tax treatment is accorded
is accordedto to
taxes tax and esthe andlaw thedesignates
law designates the operating
the operating compan
company company
y is is similar
A infrastr
infrastruct
infrastruct
ucture projects
preferential uretaxprojects
funded
treatment funded
byisthe byOf
Official
accordedthe
ficialOfficial
toDe
Devvelopment
Development
designated
Interest designated
payments, to acthowever,
toasact theaswithholding
the
maywithholding
be subject agent.to agent.
The rates The rates
of infrastructure
of Assist
ssistance
Assistance
anceprojects
(ODA), (ODInternational
A), International
funded by theFinance officialFinance
Institutions
Institutions
(IFI), (IFI),
withholding
withholding t
tax
ax v
var
ary
tax
y .
withholding taxes and the law designates the vary.
Thus, Thus,
for loans
f or loans
obt ained
obt ained
from local
from local and international
development and international
assistanceaid throughaid through
(ODA), a Development
vaelopment
International Development Cooperation
Finance Cooperation
operating company is designated to act as the Institutions (IFI), and international aid through a
withholding agent. The rates of withholding tax vary. Development Cooperation Agreement with the
Thus, for loans obtained from local banks, interest Philippines, such as the Canadian International
53 | 2Infrastructure
| Infrastr
InfrastructIn-depth:
2 | Infrastruct
ucture ure Philippines
Guide:Guide:
Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Development Development
Agreement
Agreement
Agencywith the Agency
with
(CIDA), Philippines,(CIDA),States
theUnited
Philippines, sucUnited
h assucAgencyStates
the
h asCanadian
theAgency
for Canadian authorities
Transf Transf
early
Ter
ransf erer
inpricing
pricing 2013
pricing
guidelinesguidelines
although
guidelines wereaswof were
issued
ere issued
date, bthe
issuedy thebybyPhilippine
the
the Philippinetax tax
for International
International
International International
DevelopmentDevelopment Development
Development
(USAID), Agency (USAID),
Agency
Japan (CID A), (CIDA),
International Japan
United United
StatesStates implementing Philippine
authorities rules
authorities early tax
and inauthorities
early 2013early
regulations
20 1in
3 although have
althoughasinnot
2013
of as been
date, and
of date,
the are the
issued. largely
Agency
Cooperation International
Agencyfor International
Agency Cooperation
for(JICA),
International andDeWorld Agency
velopment
DevBank’s
elopment(JICA),
(US AID), andJapan
(USAID),
International World Japan Nonetheless, based
implementing theonPhilippine
implementing the
rules arm'sand
rules length
tax
regulations
and methodologies
authority
regulations has
ha vethe havpower
not as
ebeennotset tooutissued.
been
issued.
Bank’s
BankInternational
International
for Reconstruction International
Cooperation Cooperation Bank
Agency
and Development. for Reconstruction
Agency(JICA), (JICA),
and World and and World
Bank’s Bank’s
allocate under
income
Nonetheless, the
Nonetheless,andthe Organisation
expenses
Philippine
the Philippine for
taxEconomic
between authorit
tax orauthorit
among Cooperation
y has related
ythehaspothe werpower
to to
Development.
International
International Bank Bank for Reconstr
for Reconstr uctionuction and De and velopment.
Development. parties, inand
allocate orderDevelopment
allocate
incometo income
prevent
and eand (OECD)
the
xpenses evasion
e Transfer
xpensesbetw ofeen Pricing
taxes
betw or
oreen
among Guidelines.
to
or clearly
amongrelatedrelated
Project Operations reflect the
parties,Although
income
parties,
in order the
among
in toimplementing
order prerelated
to
ventprevent
the rules
parties.
evasion and
The
the evasion regulations
of“arm’s
taxes of taxes
or to clearly
or to clearly
An operatingP
Project r oject
Projectcompany Operations
Operations Operations
in the Philippines is subject to the length”refl have
test
ect refl is
the not
ectused been
income
the to issued
evaluate
incomeamong as
among of
related the
transactions
relatedtime
parties. of
between
parties.
Thewriting,
“arm’s
The the
“arm’s
regular AnAnoperating
Ancorporate
operating operatingincome
compan compan tax ythe
y in(RCIT)
company ininPhilippines
theof Philippines
the thirty
Philippinespercent isissubject
is subject (30%)
subject
to the totorelated Philippine
taxpayers
thelength” length”
test is tax
following
test
used authority
to OECD
is used toisev
evaluate empowered
guidelines.
aluate
transactions by bet
transactions lawweentobetween
onthe
basedregular net regular
regularincome.
corporate corporate
corporate However,
income incomeincome taxtax
taxbeginning
(RCIT) of(RCI
(RCI the
thirt
T) of T)fourth
y of
thirt thirt
percent y (30%)(30%)
y percent related allocate
taxpayers
related income
taxpayers follo andwing expenses
follo wing
OECDOECD between
guidelines. or among
guidelines.
taxable percent
year
based based
on (30%)
immediately
neton net based
income. following
income. on However
However net , income.
the year
beginning in which
, beginning However,
the fthe ourth
the fourth related parties, in order to prevent the evasion of
Project Incentives
operating beginning
taxable company
taxable the
commenced
year immediately
year fourth taxable
immediately year
its business
following followingtheimmediately
year operations,
thein year which in which the Project
the Infrastructure taxes
Project or toIncentives
Incentiv
projects clearly
es reflect water,
(transport, the income logistics, among waste related
following
the corporate
operating income
operating compan the year
tax
compan iny which
shall
y commenced be thethe
commenced higher
its operating thecompany
itsofbusiness
business 30 operations,
operations, parties.
Infrastruct
management Infrastruct
ure projects
facilities, uretollways,
projects
(transport,(transport,
railways, waterwater , logistics,
, logistics,
wastewaste
percent commenced
the RCITthe or
corporate theincome
corporate two itsincome
business
percent
tax shall (2%)
tax operations,
be
shallminimum
thebehigher the the corporate
corporate
higher
of theof30the 30
management
telecommunicationmanagement facilities, facilities,
facilities, tollw ays,
tollways,
Public-Private railways, railways,
Partnership
income income
tax
percent RCITtax
(MCIT)
percent or shall
which
RCIT theortwo be
isthe the
based
percent
two higher
on gross
percent
(2%)of the income.
minimum
(2%) 30minimum
percent RCIT
corporate corporate Project
telecommunication
projects, Incentives
telecommunication
and disaster facilities,
prevention, Public-Private
facilities,
mitigation andPartnership
Public-Private recovery Partnership
incomeorincome
thetaxtwo (MCIT)
tax percent
(MCIT)
which (2%)
which minimum
is based is based
on gross corporate
on gross income. income
income.projects), Infrastructure
projects, projects,
as wellandas disaster
and projects
projectsdisaster
pre on (transport,
vention,
prevention,
ecological water,
mitigation mitigation
solid logistics,
and reco
waste andveryrecovery
Value Added tax (MCIT)
Tax (VAT) whichat the is rate
based of on grosspercent
twelve income. (12%)Value is management waste
projects),projects), management
as
and w ell
asas
renewable well projects facilities,
asenergy
projects
on (RE) tollways,
ecological
ondevelopment,
ecological railways,
solid w
solid
aste
arewaste
generally
Value Aimposed
dded
Value
Added TAdded
axTax (V(VA
on Asale
T)
Tax atof
T) the
(VA
at T)rate
goods
the atrate ofof
and
the trate
welv
services
twelv ofe twelve
percent
e in, and
percent (12%)
on2%)
percent
(1 isincluded
(12%) is telecommunication
is managementinmanagement
the 2013 and rene
andwrenew
Investment facilities, ablePublic-Private
ablePriority
energy energy
(RE)(IPP)
Plan de
(RE)velopment,
asdevelopment, are are
importation generally
generally of imposed
generally goods imposed
to on
imposed thesale on onsale
Philippines.
ofsale ofofgoods
goods and and
goods serand ser
vicesser vices
vices
in, and in,in,on on Partnership
and included
preferred included
or in thein20
mandatory [PPP]
the
13 projects,
Investment
2013
investment and
Investment disaster
Priorit
areas. APriorit
ysPlansuch,yprevention,
(IPP)
Plan
these as
(IPP) as
and
importation
import on import
ation
of goods ofation to of
goods the goods the to
toPhilippines. the Philippines.
Philippines. prefer
projects, mitigation
prefer
red or
when red and
mandator recovery
or mandatory
registered y invthe
with projects),
estment
inv estment
BOI, asenjoy
areas.
can wellAs as
areas. projects
such,
the Astaxsuch,
thesethese
Operating losses incurred in a tax year may be carried over incentives onprojects,
projects, ecological
provided
whenwhen for solid
under
registered waste
the
registeredwith management
Omnibus
the
withBOI, theInvestment
can
BOI, and
enjocany enjoy
the taxthe tax
Operating
as a deduction
Operating
Operating from
losses losses incurincur
gross
losses income
red
incur red
in afor
red ininathree
tax atax
yeartaxymay ear
yearma
consecutive be
ma ycarried
ybe becar ried
carried
over Codeover renewable
incentives
of the incentives provided
Philippines. energy
provided for(RE) fordevelopment,
under under
the Omnibusthe Omnibus are included
Investment in
Investment
yearsas a over
as aas
immediately
deduction a deduction
following
deduction from gross from from
the year
gross
incomegrossof fsuch
income income
or three floss, for
or three three
provided
consecutiv consecutive
e Code theof2013
Code Investment
theofPhilippines.
the Philippines. Priority Plan (IPP) as preferred
that there
years consecutive
yis no substantial
immediately
ears immediatelyyears immediately
change
following followingthein year
thethe following
ownership
of
year such the
of loss,
such ofyearthe ofprovided
provided
loss, or mandatory
The tax incentives under investment
the Omnibus areas. As such, Code
Investment theseare
that such
business or
there
that loss,
is noprovided
enterprise.
there subst
is no Such that
losses,
substantial
antial there
change isinno
however,
change thesubstantial
inoshall
the not
wnership ownershipbeof the The projects,
offollows:
as the tax
The tax when
incentiv incentiv
es under registered
es under with
the Omnibus the In
the Omnibus BOI, canestment
vestment
Inv enjoy
Code Code
are are
allowed aschange
business a deduction
business or in the
enterprise. ownership
in a taxable
or enterprise. Such Suc ofyear
the
losses, business
during
h losses,however which ,orshall
however the , not
shallbenot be the
as tax
as follows: incentives provided for under the Omnibus
follows:
operating enterprise.
allowed company
allowed
as a deduction
as Such
was losses,
exempt
a deduction however,
from
in a taxable income
in a taxable y
ear shall ytax.
during
ear notduring
be hwhich
whic the the 1. ITH Investment
of six (6) years Codefor of projects
the Philippines. with pioneer status
allowed
The Philippines
operating
operating as
has no
compan a deduction
ycontrolled
company was ex was in
empt a taxable
foreign
exempt
from year
corporation
income
from income during
tax.(CFC) which
projects;
equipment,
taxednot capitalization
as allowed
a not
separate
allowed rules
entity.
as each as compan
each although
compan for
y within BOI-registered
y within
a corporate a corporate groupgroup is is spare 2. Duty 2.Developed
parts ex
Duty emption
and ex Area
emption (LDA);
on imported
accessories; on imported four
capit(4)alcapit
years alfor
equipment, new
equipment,
Transfer
taxed enterprises,
pricing
tax
as ed guidelines
a separate a
as a separate debt-to-equity
were
entit ratio
issued by the
y.entity. of 3:1 must betax
Philippine 3. Exemption spare projects
spare
parts
from parts withaccessories;
and
wharfage non-pioneer
and dues andstatus;
accessories; any export and threetax, (3)
maintained. Tax consolidation is also not allowed as years for expansion/modernization projects;
each company within a corporate group is taxed as a 2. Duty exemption on imported capital
separate entity. equipment, spare parts and accessories;
Infrastructure
Infrastruct
Infrastruct
ure In-depth:
Infrastruct
Guide:
ure Guide:
ure Philippines
Philippines
Guide: | 3 || 54
Philippines
Philippines
3 |3
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
duty,
3. 3.Ex3.
impost
Ex
emption
emption
Exemption
andfrom fees;
from wharf
from
wharf wharf
age age dues
age
dues dues
andand
anand
an
y export
yany export
tax, tax,
7. Cash6.7. VAT-z
incentiv
6. ero
Cash VAT-z erate
for
eromissionar
incentive on
ratesale
for on of
sale
yfuel
electrification;
missionar oforfuel
y po w
orerpowgenerated;
electrification;er generated;
4. Tax exemption
duty
export
, duty
imposttax,
,onimpost
breeding
and
duty,fees;and
impoststocks
fees;
andand fees;
genetic 8. Tax 7.8.
exemption
Cash7. Cash
Tax incentiv
exemptionofincentive
carbon
e for
ofmissionar
credits;
for missionar
carbon yand
electrification;
credits; yand
electrification;
materials;
4. 4.
TaxTax
4.exTaxex
emption
emption
exemption onon breeding
breeding
on breeding stoc
stocksstocks
ks
andandgenetic
and genetic 9. Tax 8.9.
credit
Tax 8.exon
Tax Tax
emption
creditdomestic
exonemption
of carbon
capit
domestic of alcarbon
credits;
equipment
capit alcredits;
andand
equipment and
and
5. Tax credits
materials;
genetic
materials;
on imported
materials; raw materials; services.
9. Tax 9.credit
Tax credit
services. on domestic
on domestic capitalcapit
equipment
al equipment and and
6. Tax 5.and
5.
TaxT5.
ax
duty-fee
credits
Tcredits
ax credits
onimportation
onimported
imported
on imported ra
ofwra
consigned
w
materials;
ramaterials;
w materials; services.
services.
equipment;
6. 6.
TaxT6.
ax
andTand
axdut
anddut
y-fy-f
duty-f
eeee import
import
ee import
ation
ation ation
of ofconsigned
consigned
of consigned Tax and duty
Tax andexemptions
duty exemptions are also areprovided for infrastructure
also provided for
7. Additional
equipment;
equipment;
equipment;
deduction for labor expense; projects
Tax funded
and
Taxduty
and
infrastructurebyexduty
Development
emptions
exemptions
projects areCooperation
funded also
are
byproalsovided
provided
Agreements
Development for infrastructure
for infrastructure
8. Employment
7. 7.Additional
A
7.dditional
Additional
of deduction
foreign
deduction
deduction
nationals;
forfor
labor
flabor
or labor
expense;
expense;
expense; (e.g. projects
AusAid).
projects
funded
CooperationExemptions
funded
by Dev
Agreements by
commonly
elopment
Dev elopment
(e.g. Cooperation
provided
AusAid). Cooperation
are Agreements
for: Agreements
Exemptions
9. Simplification
8. 8.Emplo
Emplo
8. Employment
yment
of customs
yment
of offoreign
fof
oreign
procedures;
foreign
nationals;
nationals;
nationals;
and (e.g. AusAid).
(e.g. AusAid).
commonly Exemptions
provided Exare
emptions
commonly
for: commonlyprovided provided
are for:
are for:
10. Access
9. 9.Simplification
Simplification
9.to Simplification
bonded of manufacturing
ofcustoms
customs
of customs
procedures;
procedures;
warehouse.
procedures;
andandand 1. Taxes on income received by the personnel of the
10.
10.Access
10.
A ccessAccess
toto bonded
to bonded
bonded manuf manuf
acturing
manufact acturing
uring wawrehouse.
warehouse.
arehouse. cooperating
1.1.Tax1.
Taxeses
Taxes
ononforeign
income
on income
income country
receiv
receiv received
ed
for
edbactivities
ybythe bypersonnel
the theperformed
personnel
personnel ofoftheof the
For entities engaged in RE development projects, they have in thecooperating
Philippines;
the cooperating foreign countrcountr
foreign y for activities
y ffor performed
or activities performed
the option
ForFor
entities
Fto
entities
orelect
entities
engaged
engaged
theengaged
incentives
in inRERE in
degranted
RE
de
velopment
velopment
development
by theprojects,
projects,
Omnibus
projects,
they have
they have
2. Taxesinand theduties
inPhilippines;
performed the Philippines;
on project
in the supplies and for
Philippines;
Incentive
thethey
option
Code
thehaveoption
or
tothethe
electto
option
incentives
elect
the incentiv
totheelect
under
incentiv
es
thegranted
the
incentives
esRenewable
granted
by the granted
byOmnibus
the Omnibus professional
2.2.Tax 2.
Taxeses
Tax
andand
esduties
and and
technical
dutiesduties
ononproject
materials
on project
project supplies
imported
supplies
supplies and
andfinto
or
and
for for
EnergyIncentiv
by
Actthe
Incentiv
ofeOmnibus
2008
Code e which
Code
or theIncentive
or
are
incentiv
the
as incentiv
follows:
Code
es under orestheunder
the
incentives
Renewable
the Renewable the Philippines;
prof essional
profprof
essionalessional
and
and
andtec and
hnical
tec technical
hnical materialsmaterials
materials importedimported
imported into into
Energy
under
Energy
Act
theofRenewable
Act
2008 of 2008
which Energy
which
are asAct
are
follows:
as
of 2008
follows:which are 3. Taxesthe and Philippines;
into duties
the
the Philippines;
on personal
and and
Philippines; andand household effects,
1. ITH
as follows:
of seven (7) years and
3.3.motor
Taxes
3. Taxes
Taxes vehicles
andandduties
and for
dutiesduties
on
personal
onpersonal
on personal
personal use andimported
and household
and household
householdandeffects, effects,
2. Duty-free
1. ITH1.ofimportation
ITHseven
of seven
(7) yearsof(7)REyears
machinery, equipment exported
and motor
into
andthe
effects, motor
andvehicles
Philippines
vehicles
motor for personal
by
forthe
vehicles personal
forpersonnel
use imported
personaluse ofimported
usetheand and
and
2. 1.
materials;
Duty
ITH
2. -free
Duty
of seven
import
-free (7) import
ation
years ation
of REof mac REhinery
machinery
, equipment
, equipment cooperatingexportedexported
imported foreign
intoandthe
into
country.
Philippines
the Philippines
exported into b y the
the bypersonnel
the personnel
Philippines byof theof the
3. Net 2. Operating
and Duty-free
materials;
and materials;
Lossimportation
Carry-Over of (NOLCO);
RE machinery, cooperating
cooperating
the personnel foreign
offthe
oreign
countr country.
y.
cooperating foreign
4. Corporate
3. Net equipment
3.Operating
Net
tax rateOperating
and
ofLoss10%
materials;
Carry-Ov
Loss
afterCarry-Ov
ITH;er (NOLCO);
er (NOLCO); country.
5. Accelerated
4. 3.Corporate
Net
4. Corporate
Operating
depreciation;
tax rate taxLoss
ofrate
1Carry-Over
0%of after
10% ITH; after
(NOLCO);
ITH;
6. VAT-zero
5. 4.Accelerated
Corporate
5.rate
Accelerated
on saledepreciation;
tax of rate
depreciation;
fuel
of or
(10%)
power after
generated;
ITH; Note that the details of the Development
5. Accelerated depreciation; Cooperation Agreement should be carefully and
6. VAT-zero rate on sale of fuel or power thoroughly analyzed to determine the coverage and
generated; duration of the tax exemption. Further, there must
55 | Infrastruct
| Infrastructure
2 | Infrastruct
2 2 |ure In-depth:
Infrastruct
Guide:
ure Guide:
ure Philippines
Philippines
Guide:
Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Notebe that the detailswith
compliance of the theDevelopment
formalities orCooperation
reportorial obligations
Agreement
Note
imposed that bethecompliance
should
on details
be carefully
BOI-registered with
of the and the formalities
Development
thoroughly
entities to ensure orthereportorial
Cooperation
analyzed to percent.
continued Sale
asset, of
Onreal
there istheproperty also
othergains
capital hand, triggers
gains
tax (CGT) DST
theat
realized
at theof
from
rate rate
sale6 of shares
determine
Agreement
availmenttheobligations
coverage
ofshould beimposed
and
tax incentives. carefully
duration onand
BOI-registered
of the
thoroughly
tax exemption.entities of
analyzed to 1.5percent.
to percent, Sale
regardless
are of real of
subject to whether
property
CGT atalso thetriggers
the realof
rate property atisthe rate
DSTpercent
five
Further, there ensure
determine must bethe
the coverage continued
compliance availment
and duration
with of tax
theofformalities
the tax incentives.
exemption.
or treatedof 1.5
as an
percent,
ordinaryregardless
(5%)/ten asset or of
a capital
whether
percent(10%). asset.
Theretheisreal
alsoproperty is
DST implication
eportorial
Further,obligations
Repatriation there must imposed
be compliance
on BOI-registered
with the formalities
entities or treated asofan0.375
ordinary assetbased
percent, or a capital
on theasset.
total par value of the
o ensure the Repatriation
reportorial
Dividends continued
obligations
paid by a availment
imposedof
domestic ontaxBOI-registered
incentives.
corporation entities
to non-resident shares sold. Lastly, the selling price of the shares
to ensure Dividends
the continued paid by a domestic
availment
corporate shareholders are subject to 30 percent final of corporation
tax incentives. to must not be lower than its book value, otherwise, a
Repatriation non-resident corporate shareholders
withholding tax. The tax rate may be reduced when there are subject to donor’s tax of thirty percent (30%) shall be imposed
Repatriation
Dividends thirty percent
paid by a domestic
is an applicable (30%)
tax treatycorporation final
between the withholding
to Philippines
non-residenttax. The
and the tax on the difference.
corporate rate
homeshareholders
Dividends country paidmay bythe
of abe
are reduced when
subject corporation
domestic
shareholder, to 30 there
or percent
whento is
theanhome
final applicable tax
non-resident
withholding
countrytax.
corporate treaty
of The between
shareholders
the tax rateare
shareholder the
may Philippines
allowsbe reduced
subject a to 30and
credit forthe
when
percent home
there
taxesfinalpaidcountry
in
s an withholding
applicable
the oftax
Philippines. the
tax. shareholder,
treaty
ForThe tax rateormay
between
repatriation when
the bethe
Philippines
of capital, home
reduced
foreignandcountry
whenthethere
investors of the
homeis
cancountry
aneither shareholder
of
applicable thethe
sell allows
shareholder,
tax treaty
assets aorcredit
between
or sell when
thethe forthe
shares taxes of paid
home
Philippines in
and the
the operatingthe
country
home of the
company. Philippines.
shareholder
country allows a credit
of the shareholder, for taxes
or when the paid
home in
he Philippines.
country of the For shareholder
repatriation of capital,
allows foreign
a credit forinvestors
taxes paid in For further
For further
information,
information, please please
contcont
contact:
act: act:
can either
the
Gains sell For
therepatriation
Philippines.
derived assets
For sale
from of assets
or sell
repatriation
of capital,
the sharesforeign
of are
capital,of theinvestors
operating
foreign
subject to 30 can either
investors
percent
company.
can or 2sell
RCITeither sellthe
percent theassets
assetsor
MCIT, orsell
sellthe
whichever theshares
isshares ofofthe
applicable. theoperating
operating
In case
the assetcompany.
company. sold is real property and treated as a capital
RobertoRober
Robert G.toManabat
G. Manabat
Gainsasset,
derivedtherefrom is sale
capital of gains
assetstax are(CGT)
subject to 30
at the rate percent
of 6 Chairman
Chairman& CEO& CEO
CEO
RCIT Gains
or 2 percent
percent. Gains
SaleMCIT,
derived derived
from from
whichever
of realsale sale
of assets
property of assets
is applicable.
also are subject
triggers are subject
Intocase
DST 30the
at to
percent
ratethirty KPMG KPMG
Forinfurther
thein Philippines
the Philippines
Philippines
please contact:
information,
he asset
of 1.5sold
RCIT or 2percent
is (30%)
MCIT,RCIT
realregardless
percent
percent, property and or twoispercent
treated
whichever
of whether as
thea real (2%)
capital
applicable. InMCIT,
property case
is T: +63 T: +63
2 885 2 885
700070 700 0 0
asset,the
there
asset
treated aswhichever
is capital
sold
an ordinarygains
is real isproperty
applicable.
tax (CGT)
asset a at
orand Inthecase
treated
capital the
rate asofaasset
asset. 6capitalsold is real E: rgmanabat@kpmg
E: rgmanabat@kpmg
rgmanabat@kpmg.com
Mary .com
Sale of real property also triggers DST at the rate of KPMG in the Philippines
1.5 percent, regardless of whether the real property T: +63 2 885 7000 ext. 351
is treated as an ordinary asset or a capital asset. E: mquizon@kpmg.com
Infrastructure
Infrastructure
Infrastr
Infrastruct
ucture
Guide: In-depth:
ure Guide:
Philippines Philippines
| 3 | 3 | 56
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Project Risk
Funding of
Management
Infrastructure Projects
Geno Armstrong, Advisory Principal, KPMG LLP (U.S.)
Reid Tucker, Advisory Director, KPMG LLP (U.S.)
Singapore
TheProject
worldRisk
todayManagement
is faced withismultitude
frequently overlooked
challenges yet is one
pursuant of the more
to population critical(global
growth elements to successful
project deliveries.
population to reach 9 Generally, delivering
billion by 2050), a project’s
urbanization defined
(more thanscope on time
50 percent of and withinpopulation
the world budget are
characteristics
lives of project
in urban centers), success.
ageing Unfortunately,
infrastructure, theseimperatives
low carbon success factors are often
and need not achieved, especially
for poverty
for large complex
alleviation. The needprojects whereinfrastructure
is to develop both externalatinfluences
a pace thatand internal
can project
support strong requirements
economic may change
significantly
growth overcater
to not only time.to the growing population but also to help lift masses of people now
below the poverty line. Of the about 945 million people below poverty line globally, close to 21
percent lives in Southeast Asia.1
The challenge today is not the lack of infrastructure launched multiple social and economic
projects or financing. It is the availability of funding to infrastructure projects, Indonesia has a list of
the projects being made available to the market. The key PPP projects to be implemented as PPPs
quality of the regulatory framework, market 5. Financing Institutions – Clifford capital has been
attractiveness, commercial sustainability and set up in Singapore to fund infrastructure
transparency as well as lack of successful projects in the region
precedence for smooth implementation of the 6. Project preparation support – Asian
Development Bank (ADB) and International
infrastructure projects in various developing countries
Enterprise (IE) Singapore have set up a center of
pose major impediments. A few commendable
excellence in Singapore to help identify and
steps have been taken by the governments in the
prepare infrastructure opportunities for potential
region including – PPP
1. Setting up of Public-Private Partnership (PPP)
Given the need of infrastructure investments in the
Center – The Philippines reorganized the
Build-Operate-Transfer Center into the PPP
region (US$60 billion is needed per year until 2022 to
Center in 2010 to facilitate the implementation meet infrastructure needs in ASEAN 4 ) and the
PPP programs and projects current private financing quantum (US$18 billion
2. PPP regulatory and contractual framework – worth of financing was arranged by the top 10 banks
State Enterprise Policy Office (SEPO) in Thailand in ASEAN between 2009-2013 5 ), we are surely
has set up comprehensive framework for PPPs looking at a huge gap. The private participation is very
3. Supporting Institutional framework – Indonesia low compared to the target of at least 50 percent of
3
has set up IIF 2 and IIGF infrastructure projects to be implemented as PPPs in
4. Pipeline of pilot projects – Philippines has the region. So the question is what is required for us
1
Source: UNESCAP Statistical Yearbook for Asia and the Pacific 2011
2
Indonesia Infrastructure Fund
3 Indonesia Infrastructure Guarantee Fund
4
World Economic Outlook, S&P, and KPMG Analysis
57 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
to make the ASEAN infrastructure PPP financing a Given the size of Philippine GDP (~US$250 billion+),
US$30 billion per annum market? if the government can target to divest assets worth 1
percent of the GDP per year, that not only means a
While the regulatory and institutional constraints are ready pipeline of US$2.5 billion per year of operating
well understood and are also being addressed infrastructure assets that could benefit from better
comprehensively through intervention by multilateral technology and management practices brought in by
agencies like the World Bank and the Asian the private sector, but also a source of capital for
Development Bank, perhaps we need further government to reinvest in new greenfield
innovation and out of the box thinking by the industry infrastructure projects.
stakeholders to realise the vision. Also some simple
course correction measures by the government and This will not only potentially increased the
tapping on the most underused source of public infrastructure spend in the country from current
capital may be a solution. levels (potentially by one percent point increasing
from 2.5 percent to 3.5 percent for Philippines) but
Monetization of government infrastructure assets also provide an opportunity to set up successful
One alternative worth considering is to bolster the precedence for infrastructure project developers and
ability of states to raise financing through financiers. This in turn also helps strengthen
monetization of the infrastructure assets and reinvest institutional capability at the public sector and
in greenfield infrastructure development. Privatization enhanced performance for infrastructure assets.
of government assets has been undertaken by
various countries in the region. For the ASEAN region of over 620 million people and
combined GDP of US$2.2 trillion, a one percent
The Philippines, for example, has carried out privatization target can generate US$22 billion of
privatization of assets across sectors – oil and gas revenue per year which can go a long way in meeting
(O&G), water, power, airports, etc. The aggregate the projected annual infrastructure investment
infrastructure spend in Philippines has been between requirement in ASEAN of US$60 billion. The funding
2.0 percent to 2.5 percent of the gross domestic raised thus could be potentially also be used to
product (GDP) over the last few years leading to a provide viability gap funding for infrastructure
strong infrastructure asset ownership. projects structured as PPPs. (See box in the next
page for the concept)
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 58
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
register and develop efficient response plans that focus impact on the project.
attention
Upfront on capital
items with higher priority.
contribution It is important
/ Viability Gap Funding to – Many infrastructure
Acceptanceprojects– fail
proceeding as planned and
the commercial
identify all potential
viability test althoughrisksthe
that will require
economic follow-up
rationale for thebyproject
the may be very strong. accepting
This isthe outcome
mainly of a risk.
on account of
project
poorteam.
payment ability, underdeveloped tariff models, regulatory constraints Finalizing and documenting
and political will. Until thethe time various
we risk
are able to graduate to full cost recovery models on infrastructure utility responses identified
service pricing, by each
a good optionresponsible
is for party. The
Stepgovernment to provide
2 – Quantitative upfront grant / low cost debt / zero-rated bondsplan
Analysis to defray
should the high tariff
clearly define expectations
the agreed upon response
For for making theanalysis,
quantitative project viable in the team
the project light ofassigns
lower traffic
a most forecasts. Indonesia has set
for a risk, the up a VGF facility
responsible andresults
party, this from both
could
likely costbevalue
a goodto precedence
each identifiedfor other ASEAN
risk. This countries
value to follow. The the
takes into challenge is, of course,
quantitative availabilityanalysis,
and qualitative of and a
financing with
consideration boththe state
the exchequer
probability andinpotential
the regionimpact
and the ofstrain the state budget.
budget and Role of multilaterals
timeframe for the(like
risk responses.
theADB, Worldoccurrence.
risk event Bank, etc.) could be effective,
Determining wherein,and
probability they could structure a framework and a time bound
roadmap
impact for moving
can result from towards
a varietycost reflective model
of exercises, for utility services
including: to make
Monitoring andthis more sustainable while
Control
state governments find avenues for raising funding.
Interviews – gathering impact and probability data The final step of risk management is monitoring and
for a range of scenarios (e.g. optimistic, most likely, control. This process should be set up to track potential
and pessimistic). risks, oversee the implementation of risk plans, and
Governments
Decisionsmust,Trees
however, carefullythe
– comparing evaluate assets
probability of most
risks attractive
evaluateto the
private investors, of
effectiveness and consider
risk management procedures.
regulatoryand oversight to ensure service affordability
rewards between various decisions. and consumer protection, since these assets
Monitoring and control should occur are primarily
throughout the project
public utilities.
ModelUnderstanding sovereign cash
simulations – conducting flowssimulation
a project would also help establish
lifecycle a practical
and help improve timeline
and guide for greenfield
the overall risk
development.
in order Learning from potential
to quantify the Philippines,
impactspower to theprivatization
project. has to be reflected
management process. so that
Thisthestepend customer also
should:
feels the benefits of privatization by way of improved performance of the utility and competitive tariffs. We also
need to see how to effectively use the proceeds for the developmentofEquip greenfield projects and
management rather thethan onlyteam to make
project
extinguishing
Response Planningthe debt obligations and leases. (Power sector privatization informed decisions regarding risk. largely
proceeds in the Philippines were
used to service debt and lease obligations.)
Response planning is the phase where the project team Evaluate the effectiveness of risk response actions.
develops response actions and
Infrastructure andalternative options
Other Capital to
Outlay Identify risk characteristics
PSALM: that Proceeds
Use of Privatization appear to have
reduce project risks. Project teams use response planning changed from what was documented in earlier
to200,000
decide ahead of time how they will address possible risk 3.0 %identification and
1 analysis stages.
Regular Debt Service
occurrences and how they will avoid, transfer, mitigate, or
millions
2.0 %
consideration
100,000 available resources and potential Project25Risk Audits 24
– a seriesOthers
of audits that examine
repercussions of the response plans. The goal of response the effectiveness of risk response strategies and
PERCENTAGE
2004
2005
2006
2007
2008
2009
2010
2011
2012
Assigning responsibility for identified risks to Project Risk Report – a summary report or
appropriate project team members or stakeholders. dashboard that communicates the risk status for a
Source: Department of Budget and
It is imperative Management
that the assignment take into Source: Power
project. ThisSector Assets
tool can beandcustomized
Liabilities Management
to update
consideration
Capital Markets Solutionthe individual’s capability to address management on current project risks.
specificsource,
Other financing risk areas.
whichAssigning
has largely a risk to someone
remained untapped in Asian markets, is the local capital markets. The
nominal average savings rate in Asian countries isarea
who has little or no knowledge of a risk 37.5ispercent
not and Monitoring
is expectedandtocontrol
remainisconstant
essentialfor forthemaintaining
next 20 effective
years. Not much of this savings go into capital markets. The ASEAN market capitalization is at US$1.1 trillion – for
6 an effective risk planning approach. and efficient risk management. It is a barometer
of
only half Developing
the region’s a response
GDP – in plan
local to addressbonds
currency the by end 2013. determining
7
Nearly 80how well of
percent your risk is
which management
from more plan is
developedidentified
Malaysia,risk. This process
Singapore should be
and Thailand. iterative
Such and
underutilized designed.combined
financing, If monitoring
withand
the control
high savingsreveals that certain
rate,
indicate ainclude
significantall stakeholders affected
source for further by the risk.capital.
infrastructure risks are not being mitigated or avoided as planned, then an
Common options for a response include: adjustment can be made to the response plan. Likewise, if
Avoidance – modifying the project plan
A few initiatives are being undertaken in the region to channel more to avoid monitoring and control
of the savings reveals
into the thatmarkets.
capital an identified
The risk is
the potential condition or occurrence. unlikely to materialize, the
Credit Guarantee and Investment Facility (CGIF) is a commendable initiative to encourage corporate sector to raise plan can be adjusted to
Transference – shifting the consequences and reprioritize the risk to a lower
local currency bonds in their capital markets with improved credit rating. The inaugural guarantee of Thai Baht and level.
Indonesian Rupiah responsibilities
bonds in 2013 associated
bodes wellwithfor
thethe
risk to a and we believe it can gain momentum in the years
concept
ahead. The success,third party
plus (often accomplished
the pipeline of guaranteeby contractual Benefits
offers this year, promptedof Risk
CGIF Management
contributors to raise the
guarantee capacity agreement).
to US$1.75 billion. 8 This paves the way to guaranteeingAlthough aproject
well-designed and executed
bonds, thereby helpingrisk management
support
Mitigation
regional infrastructure – taking preventative action to
development. process can significantly reduce the risk of failure, the
reduce the probability of a risk occurrence or Identify risk characteristics that appear to have changed
6
NBER Working Paper No. 17581 (The National Bureau of Economic Research)
7
Asia Bond Monitor June 2014, ADB
8 CGIF Progress Report 2013, ASEAN
59 2
| Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
2013 LCY Bond Market
800
Billions
600
US$(%)
400
PERCENTAGE
200
400
Billions
300
US$(%)
200
PERCENTAGE
100
Government Corporate
Source: Asian Bond Monitor
Others such as the ASEAN Infrastructure Fund (AIF) capital markets solution (bonds, infrastructure funds,
and Climate Investment Fund (CIF) also offer an etc.) in the short to medium term, that could make
alternative investment for country reserves and US$20 billion per annum available to infrastructure
pension funds. These funds have started to have an project financing in ASEAN.
impact on several countries – the Philippines, for
instance, is drawing US$250 million from CIF’s Clean Conclusion
Technology Fund for small, solar-powered vehicles, The above two sources of financing, viz.
industrial energy efficiency, and renewable energy. monetization of assets and the capital markets
solution, could cumulatively bring up to about US$ 40
These are good initial steps and clearly much needs billion per annum thereby significantly helping meet
to be done by the central banks and regulators of the target spend of US$60 billion per annum for
each country to help develop a thriving debt capital whole of ASEAN in the infrastructure space.
market solution that one day could match the
success achieve in Northern America and Europe.
Education and comfort relating to understanding of
the nature of risks in a capital market bond issuance
are critical for its success. If we can get even 25
percent of savings moving to infrastructure through
For further information, please contact:
Sharad Somani
Partner and ASPAC Head for Power & Utilities
KPMG in Singapore
E: sharadsomani@kpmg.com.sg
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 60
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Pr
Prooject
ject Risk
Risk
Manag
Management
ement
Project
Project Risk
Risk Management
Management is frequently
is frequently overlooked
overlooked yetyet is one
is one of of
thethe more
more critical
critical elements
elements to to successful
project deliveries.
successful Generally,Generally,
project deliveries. deliveringdelivering
a project’s defined scope
a project’s definedonscope
time and within
on time budget
and withinare
characteristics
budget of projectofsuccess.
are characteristics Unfortunately,
project success. these success
Unfortunately, these factors
successare often are
factors notoften
achieved,
not especially
for largeespecially
achieved, complex projects
for large where
complex both external
projects influences
where and internal
both external project
influences andrequirements may change
internal project
significantlymay
requirements overchange
time. significantly over time.
Project
Project riskrisk management
management is aiscontinuous
a continuous process
process of of project teams
as tracking potentialmay express
change the view
orders, that “everything we do
and project
identifying, analyzing, prioritizing, and mitigating
identifying, analyzing, prioritizing, and mitigating risks risks that is risk management. ” While
teams may express the view that “everythingall of these activities
we do help to
threaten a project’s likelihood of success
that threaten a project’s likelihood of success in in terms of cost, is risk management.” While all of these activities helprisk, they
identify and manage discrete elements of project
schedule, quality, safety, and technical
terms of cost, schedule, quality, safety, and technical performance. do not fully
to identify describediscrete
and manage a comprehensive
elements approach
of projectto project
Organizations and owners often
performance. Organizations and owners often consider project risk risk, they do not fully describe a comprehensive risk
risk management. A comprehensive project
management activities as “nice to
consider project risk management activities as “nicehave” on a project rather management
approach to projectapproach should haveAthe following
risk management.
than as a core component of
to have” on a project rather than as a core project controls. Additionally, components, which should
comprehensive project risk management be scalableapproach
to the specific
there is some
component confusion
of project between
controls. organizations
Additionally, there is and projectshould project’s
have size and type:components, which should
the following
someteams as to what
confusion exactly
between constitutes and
organizations risk management
project be scalable to the specific project’s size and type:
activities.
teams as to what exactly constitutes risk 1. Strategy and Planning
management activities. 2. Risk Identification
1. Strategy and Planning
Defining Project Risk Management 3. Analysis
2. Risk (Quantitative & Qualitative)
Identification
The objective of project
Defining Project Risk Management risk management is to understand 4. Response Planning& Qualitative)
3. Analysis (Quantitative
project and program level risks,
The objective of project risk management is to minimize the likelihood of 5. Monitoring
4. Response Planning and Control
negative events,
understand and program
project and maximizelevel the risks,
likelihood of positive
minimize 5. Monitoring and Control
theevents on project
likelihood and program
of negative events, and outcomes.
maximize Project
the risk Strategy and Planning
management is a continuous process
likelihood of positive events on project and program that begins during Strategy and planning activities set the foundation for a risk
The power industry is one in which project risk management is
the planning phase and ends once
outcomes. Project risk management is a continuous the project is management program and ultimately determine whether
particularly ill-defined. Where a utility has both a regulated and
successfully commissioned and
process that begins during the planning phase andturned over to operations. an the initiative
unregulated is successful.
business Duringside
unit, the regulated theoften
strategy and
focuses
ends once the project is successfully commissioned its planning
risk managementphase, an organization
procedures around will
cost define
recovery. how
In risks are
Construction owners,
and turned over to operations. project teams, and contractors often addressed
contrast, and managed.
the unregulated Strategy
side typically and
has a more planning
traditional should
define and apply risk management activities differently on arisk take management approach.
into consideration:
project. Owners
Construction owners, may practice
project informal
teams, or ad hoc practices,
and contractors
often define and apply risk management activities as risk
such as stage gate approval, that they interpret Strategy and Corporate
Planningor enterprise wide risk management
management activities, contractors
differently on a project. Owners may practice may define risk Strategy and planning(including
guidelines activities tolerance levels for for
set the foundation risk)
management as tracking potential
informal or ad hoc practices, such as stage gate change orders, and a risk management program and ultimately,
approval, that they interpret as risk management determine whether the initiative is successful.
activities, contractors may define risk management During the strategy and planning phase, an
61 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
organization will define how risks are addressed and
managed.organization
Strategy and willplanning
define how should
riskstake
areinto
addressed and process to solicit input from all project stakeholders
consideration:
managed. Strategy and planning should take into including those outside of the core project team.
consideration: prject
Potential team membersto(planners,
contributors engineers,
risk identification include:
Corporate or enterprise - wide risk management architects, contractors, etc.)
guidelines (includingortolerance
Corporate enterprise levels forrisk
- wide risk)
ris management
project team team members
members (planners, engineers,
Available management
resources (staffing, budgets)
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 62
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Analysis
register and develop efficient response plans that focus impact on the
feasibility considerations. Riskproject.
response planning
Theattention
analysison phase
itemsdetermines
with higherthe priority.
likelihood It is and
important to includes: Acceptance – proceeding as planned and
impact
identifyof each
all potential
identified risksriskthat
andwillprioritizes
require follow-up
risks for by the accepting the outcome of a risk.
management
project team. attention. Successful risk analysis Assigning
Finalizing responsibility
and documenting for identified risks risk
the various to
requires objective thinking and input from those most appropriate
responses project
identifiedteambymembers or
each responsible party. The
familiar
Step 2with– Quantitative
the area affected Analysis by the possible risk. stakeholders.
plan should It is imperative
clearly define the that the upon response
agreed
Analysis
For quantitative
is typicallyanalysis,
a two-step the approach:
project team 1) assigns a most assignment
for a risk, take into consideration
the responsible the from both
party, results
qualitative
likely costanalysis,
value toand each 2) identified
quantitative risk. analysis.
This value takes into individual’s capability
the quantitative and toqualitative
address specific analysis, risk
and a
consideration both the probability and potential impact of areas.
budget Assigning a risk to for
and timeframe someone
the riskwho has
responses.
Step
the1risk
– Qualitative
event occurrence.Analysis Determining probability and little or no knowledge of a risk area is not an
Forimpact
the qualitative
can resultanalysis,
from a variety the project
of exercises,
team assigns including: effective
Monitoring andrisk planning approach.
Control
a priority
level
Interviews
(e.g. high,
– gathering
medium, impact
low) to andeach
probability
risk. data Developing
The final step ofarisk response
management plan to is address
monitoring the and
level, and
Decisions
other organizational
Trees – comparing objectives. the Theprobability
priority of risks by the
evaluate therisk. Common options
effectiveness for a response
focus attention
in order ontoitems
quantify withpotential
higher priority.
impactsIttoisthe project. management avoidprocess.
the potential This condition
step should: or
63 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Tools used for monitoring and control include: Benefits of Risk Management
Tools used for monitoring and control include: Although a well-designed and executed risk
Project Risk Audits – a series of audits that Benefitsmanagement
of Risk Management
process can significantly reduce the
Project Risk Auditsthe
examine – aeffectiveness
series of audits thatresponse
of risk examine Althoughrisk
a well-designed
of failure, the and
benefitexecuted risk management
of performing a
the effectiveness
strategiesofand
riskproject
responseriskstrategies
assessments.and process comprehensive
can significantlyriskreduce
analysis mayofbefailure,
the risk costlythe
and
project risk assessments.
These audits can beThese
used audits can be used
to stimulate benefit of performing for
burdensome a comprehensive
smaller projects risk analysis
with limitedmay be
to stimulate process
process improv
improv ement
ement andandmakemake costly and burdensome
complexity. for smaller
As noted earlier,projects with limited
risk management
recommendations regardingregarding
recommendations the risk management
the risk
complexity. As noted
processes earlier,
should berisk management
scalable to the sizeprocesses
and
procesAs.management process.
should be scalable to
complexity ofthe size and complexity
an organization’s program of or
an project. To
Project Risk Report
Project Risk– Report
a summary report or
report or
– a summary organization’s
achieve program
this, anororganization
project. To achieve this, an defining
should consider
dashboard that communicates
dashboard the risk status
that communicates forstatus
the risk a organization should consider defining a baseline
a baseline set of procedures to apply to all setprojects
of
project. This
for atool can be
project. customized
This tool can be tocustomized
update to procedures to apply to all projects along with a more
along with a more rigorous set of procedures for high
managementupdateonmanagement
current project onrisks.
current project risks. rigorousvalue,
set of complex
procedures for high value, complex projects.
projects.
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 64
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
CaseIn both
Studythe 1 case studies, the risks were well-known to the integrating project lifecycle
risk management
and project intocontrol
their project
activities. By
project
Project teams and New
Description: could medical
have likely beenbuilding,
office avoided or the protocols
integrating
and controls.
risk management
Primary considerations
steps into the approval for an
mitigated
US$30+ if a risk management process would have been inorganization
million process, stage to establish
gates,an and effective
project plan reporting,
include: the importance
place. Having a risk management process would have of risk management is emphasized and it becomes a
Riskallowed the organizations
Description: In order toto commission
track, quantify, the plan and Allottingelement
mandatory appropriateof the resources to perform
project control risk
environment.
building
communicate
at the completion
the risks to of individuals
construction, with thetheutilities
capability to management activities.
needhelptomitigate
be connected
or avoid to the
the risk.
public utility system (gas Creatingadherence
Monitoring an environment to riskthat embraces procedures
management and
and electric). Throughout the project the team could promotes risk
An organization management
should and actively
perform regular monitoring and
notEmbedding
get a commitmentRisk Management
from the utility into Day-to-Day
company for Activities encourages
auditing of their andrisk pursues
management risk management
process. As at previously
whenEffective
they would
risk management
complete the is connection.
typically achievedThis riskwhen an all levelsthis
mentioned of the
can organization.
be accomplished through the use of a
was organization
never communicated
undertakesbeyond an active thecommitment
project teamto Clearly
risk defining and
report/dashboard andtraining personnel
risk audits.
on risk
andintegrating
there wasrisk no analysis
management of theinto impact
theirforproject
a delay protocols
or management controls.
an and
alternative
controls. planPrimary
developed considerations
to address for thean risk.
organization to Risk Reporting – reporting should be evaluated by
teamcontrol
responsible
of risk management
for managingfunctions the construction
include: independent
Identify any evaluation
processmore appropriate?
improvement opportunities.
phase of the project. Identify any trends in overall program risk.
Capacity of project team - do they have the Many energy companies, especially power & utility companies, set
Risk Impact: time/resource
The bedrock toineffectively
the actualmanage locationthe of the
risk up separate project management
Developing risk managementorganizations (PMOs) to manage
training
the unique risk of major capital programs. This assists the
bridge foundations
process? was substantially different than Training is the keystone to any risk management plan.
organization in aligning dedicated resources with the specific skill
the geotechnical
Expertise report- who indicated.
has theThis most resulted
knowledge in a and sets team Without
structure a formal
to manage training effort, a riskprojects.
major construction management
complete experience
redesign of in therisk
foundations
management? and several approach will most likely not be embraced or followed. Not
monthsdelay Potential
on theconflicts
project.of The interest
financial– would
impacts there be a only should training occur at the inception of the policy, it
were greater potential
than US$30
incentive million.
for risks not to be accurately Once the ownership
should include:
of this process is determined,
reported by the project team; is an independent risk management activities are typically most
In both theevaluation
case studies, morethe appropriate?
risks were well-known effective (and adhered to)
On-boarding forwhen they are embedded
new hires.
to the project teams and could have likely been throughout the project
Regular “brownlifecycle
bag”and project control
or informational
sessions to
avoided
Once or thetheownership
mitigatedofif this a riskprocess
managementis determined, risk activities. review
By integrating
any lessonsrisk management
learned, updates steps tointo
the policy, or
process
management
would have activities
been are in place.
typicallyHaving
mosta effective
risk (and the approval process,leading
identified stage practices.
organizations to track, quantify, plan and emphasized and it becomes a mandatory element of
communicate the risks to individuals with the the project control environment.
Effective risk management is typically achieved when and auditing of their risk management process. As
65 | 2Infrastructure In-depth:
| Infrastructure Guide:Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
through the use of a risk report/dashboard and risk and procedures and to emphasize the
audits. organizations commitment to risk
management.
Risk Reporting – reporting should be evaluated by
management on a regular basis to ensure risks are Training is often a forgotten aspect of policy
being identified, tracked, and accounted for in project implementation; however, this is a particularly critical
planning. Management should be diligent in function to establish an effective risk management
reviewing risk reports and question reports that approach. Often overlooked, training is crucial for
appear stagnant. It is imperative for management to informing employees about the importance of risk
actively participate in risk management to reinforce management and its various elements.
the importance of the risk management process.
Conclusion
Risk Audits – Organizations should self perform or A well-defined risk management process can greatly
procure an independent audit of their risk increase project and program success. However, risk
management practices on an annual or semi-annual management has traditionally been overlooked and is
basis (independent risk audits should also be considered by many one of the more fuzzy areas of
considered for projects that pose a significant risk to project management. At a minimum, organizations
an organizations
through the objectives or financial
use of a risk report/dashboard stability).
and risk audits. The with significant capital expenditures should clearly
intent of the audit should be to: define their procedures and expectations for risk
For further
management, information,
communicate please contact:
its importance,
Risk Reporting – reporting should be evaluated by
management onValidate compliance
a regular with risk
basis to ensure risksmanagement
are being adequately train its personnel, and monitor high-risk
process.
identified, tracked, and accounted for in project planning. For
projects for more information,
compliance you may
with risk management
Identify any trends in overall program
Management Review
should be accuracy
diligent inand thoroughness
reviewing of data
risk reports contact:
procedures.
risk.
being entered into process.
and question reports that appear stagnant. It is imperative
Identify any process improvement
for management to actively participate in risk management Geno Armstrong
Developing risk management training
opportunities.
to reinforce the importance of the risk management For further
Principal,
Training the information,
keyystone to any
isAdvisor please
risk contact:
Identify any trends in overall program risk.
process. KPMG LLP (U.S.)
management plan. Without a formal training
E: garmstrong@kpmg.com
effort,
Geno a Armstrong
risk management approach will most
Risk AuditsDeveloping risk management
– Organizations should selftraining
perform or procure likely not be
Principal, embraced or followed. Not only
Advisory
an independent audit of their risk to
Training is the keystone any risk management
management plan.
practices on should
Reid training
Tucker occur at the inception of the
Without a formal training effort, a risk management KPMG LLP (U.S.)
Infrastructure
Infrastructure In-depth:
Guide: Philippines
Philippines | 3 | 66
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Appendix
Concourse to platform 10 10 5 5
Optimal capacity (train’s
standing with allowance to
consider passengers’ 4-8 4-8 4-8 4-7 Actual Operation DOTC, PNR,
comfort/space) in train data LRTA
systems achieved (per
sqm.)
PNR-Metro Commuter
(Optimal capacity = 6 7 6 6 6 Actual DOTC, PNR
passenger/sqm.
passengers per sqm.)
LRT 1
(Optimal capacity = 6 7-8 7-8 5-7 5-7 DOTC, LRTA
passengers per sqm.) Project status
LRT 2 report, operations-
(Optimal capacity = 4-5 4-5 4-5 4-5 4-5 related report, DOTC, LRTA
passengers per sqm.) accomplishment
MRT 3 report
(Optimal capacity = 6 8 8 8 6 DOTC
passengers per sqm.)
Annual / actual
Load transported via the survey / monitoring / DOTC, PPA,
Central RORO Spine 202 221 232 251 verification on port MARINA,
increased (in tons per ship- operation and DPWH and TRB
hour) performance
Davao 137 153 161 179
Cagayan de Oro 43 45 47 47 Monthly statistical PPA
reports
Batangas 22 23 24 25
Passengers transported Actual operation
via air increased per 46,340,236 49,334,076 53,153,098 56,084,528 data, DOTC report DOTC
annum
Coverage of cellular
mobile telephone service 99 100 100 100
with broadband coverage
increased (in % of total NTC annual report,
number of NTC monitoring / ICTO, NTC
cities/municipalities) evaluation of private
Cities and municipalities sector
with broadband coverage 60 70 80 100
increased (in % total
number of
cities/municipalities
Source: Philippine Development Plan 2011-2016
http://plans.neda.gov.ph/pdp/chapter-10-accelerating-infrastructure-development/
LRT 2 Committed/
East (to Antipolo)* 13.2 61,640
Proposed
West (to MM North Harbor) 4.7 30,840 Proposed
MRT 3 Ext. (to Malabon & MoA) 9.4 68,600 Proposed
MRT-7 (Recto-Comm.Av.-Banaba) 26.1 128,360 Committed
N-S Subway (Dasmariñas East-San Jose
68.6 514,160 Proposed
Delmonte)
Total Primary (Incl. Upgrade) 202.1 987,240
Total Main 422.2 1,230,440
Ortigas - Angono 13.7 31,720 Proposed
Paco - Pateros 11.3 33,800 Proposed
Secondary
Road/Expressway Projects
Project Length Cost Status
(km) (PhP mil.)
C3 Missing Link (Sanjuan - Makati)* 5.9 24,000 Proposed
C5 Missing Link Committed/
6.9 680
Proposed
Pasig River Bridge (BGC - Ortigas)* 1.2 8,120 Proposed
Skyway-FTI-C5 Connector* 3.0 17,880 Committed
Other Interchanges/Flyovers 6.7 8,040 Committed
Road
B. Ports
Amount
Name of Project Status
(PhP million)
1. Replacement of North Harbor 40,000 Proposed
2. Other regional ports 2,000 Proposed
3. Other Port Programs* 12,080 Proposed
Port Project Total 54,080 -
Notes:
Source: Japan International Cooperation Agency Presentation on Roadmap for Transport Infrastructure Development
for Metro Manila and Its Surrounding Areas (Region III and Region IV-A) Summary of the Outputs September 2013
ABC Approved Budget for the Contract LCBI Local Capacity Building Institutions
ADB Asian Development Bank LGU local government unit
ADR alternative dispute resolution LLED Laguna Lakeshore Expressway Dike
AIF ASEAN Infrastructure Fund LRT Light Rail Transit
ASEAN Association of Southeast Asian Nations LRTA Light Rail Transit Authority
BBWSP Bulacan Bulk Water Supply Project LWUA Local Water Utilities Administration
BLT build-lease-transfer MDG Millennium Development Goal
BFAR Bureau of Fisheries and Aquatic Resources MERALCO Manila Electric Light and Railroad Company
BOP balance of payments MLD million liters per day
BOT build-operate-transfer MRT Metro Rail Transit
BPO Business Process Outsourcing MW megawatt
BRICs Brazil, Russia, India, China MWCI Manila Water Company, Inc.
BRLC Bulacan, Rizal, Cavite, Laguna MWSI Maynilad Water Services, Inc.
CAAP Civil Aviation Authority of the Philippines MWSS Metropolitan Waterworks and Sewerage System
CAVITEx Manila-Cavite Expressway m3 cubic meter
CALABARZON Cavite, Laguna, Batangas, Rizal, Quezon NAIA Ninoy Aquino International Airport
CBO community-based organizations NCR National Capital Region
CCA climate change adaptation NCWSP New Centennial Water Source - Kaliwa Dam
CCGT Combined Cycle Gas Turbine Project
CGIF Credit Guarantee and Investment Facility NEDA National Economic and Development Authority
CIF Climate Investment Fund NEDA-ICC National Economic and Development Authority –
CL contingent liabilities Investment Coordination Committee
CLB Calamba – Los Baños Toll Expressway NGA national government agencies
CLEx Central Luzon Expressway NGCP National Grid Corporation of the Philippines
CSC Civil Service Commission NGO non-government organization
CSO civil society organizations NIA National Irrigation Administration
DA Department of Agriculture NLEx North Luzon Expressway
DAP Development Academy of the Philippines NPC National Power Corporation
DBM Department of Budget and Management NSCB National Statistical Coordination Board
DEO District Engineering Office NSO National Statistics Office
DENR Department of Environment and Natural NTDP National Tourism Development Plan
Resources NWRB National Water Resources Board
DepEd Department of Education N-11 Next Eleven
DILG Department of Interior and Local Government ODA official development assistance
DOE Department of Energy OECD Organisation for Economic Co-operation and
DOF Department of Finance Development
DOT Department of Tourism O&G oil and gas
DOTC Department of Transportation and O&M Operation and Maintenance
Communications PAP projects and programs
DPWH Department of Public Works and Highways PCA Philippine Contractors Association
DTI Department of Trade and Industry PDMF Project Development and Management Facility
DU distribution utility PINE Philippines, Indonesia, Nigeria, Ethiopia
EGAT Electricity Generating Authority of Thailand PIP Public Investment Program
EPIRA Electric Power Industry Reform Act PPICS Peru, Philippines, Indonesia, Colombia, Sri Lanka
ERC Energy Regulatory Commission PPP public-private partnership
FAP foreign assisted project PSALM Power Sector Asset Liability Management
GCR Greater Capital Region Corporation
GDP gross domestic product RA Republic Act
GGG Global Growth Generators REID Foundation Research, Education and Institutional
GOCC government-owned and controlled corporations Development Foundation
GVW gross vehicle weight RORO Roll-On/Roll-Off
GWh gigawatt-hour RM Results Matrix
HSH High Standard Highways SCMB Subic-Clark-Manila-Batangas
IA implementing agency SCP Strategic Convergence Program
ICC-CC Investment Coordination SEPO State Enterprise Policy Office
Committee – Cabinet Committee SLEx South Luzon Expressway
ICC-TWG Investment Coordination Committee – SWS Social Weather Stations
Technical Working Group S&P Standard & Poor’s
ICT information and communications technology TEU twenty-foot equivalent unit
IEA International Energy Agency TOR Terms of Reference
IE Singapore International Enterprise Singapore TransCo National Transmission Corporation
IPP Investment Priority Plan VAT Value-Added Tax
IPPA independent power producer administrators VfM Value for Money
IRR Implementing Rules and Regulations VGF Viability Gap Financing
ITS Integrated Transport System WB World Bank
IWRM Integrated Water Resources Management WEF World Economic Forum
JICA Japan International Cooperation Agency WESM Wholesale Electricity Spot Market
JMP Joint Monitoring Programme WRM Water Resource Management
KWH kilowatt-hour WSP water service providers
Philippines
Philippines
The Philippines officially became a republic in 1946.
The The Philippines
Philippines officially officially became a republic in 1946.
Benigno Aquino III is the currentbecame President a republic
of the in 1946.
The 1986 year 1986 wlandmark
as a landmark year in the country’s
Republic of the Philippines. His main platform is countr y’s
The year w as a y ear in the
eff orts effto
orts to become
become a self-goa self-governing,
verning, full-fledged
full-fledged
good governance and the elimination of corrupt
democratic
democratic countr country
y when when
President President FerdinandFerdinand
Marcos Marcos
practices in the government. Under his
w as was ousted
ousted from from
po wer power
and and President
President Corazon Corazon
administration, the overall financial strength of the
Aquino Aquino
assumed assumed theowing the presidency.
presidency .
government has improved, to a more efficient
Former FormerPresident PresidentGloria Gloria Macapagal-Arroyo’s
Macapagal-Arroyo’s
tax administration and responsible government
presidency
presidency (2001-201 (2001-2010) has0)made has made the economthe economyy the the
spending.
f ocus of her presidency
focus of her presidency. Economic growth in terms . Economic growth in terms
of of
The current Aquino regime posted a GDP growth of
GDP GDP
averaged averaged 4.6 4.6 percent
percent during during
the the Arroyo
Arroyo
7.6 percent in 2010 and slowed down to 3.6 percent
administration from 01 200 1 up thetoend the end of 2003, to 5.5
in 2011.administration
It then grew byfrom 6.8 20 percent up in to 2012 andof 2003, to 5.5
percent percent
in 2006. in 2006.
2007 2007
saw sawcountry’s
the the country’s GDP GDP growgrow by by
exceeded the government’s expectations when the
7.3 7.3 percent
percent as as continuing
continuing fiscal fiscal
ref orms reforms
allowed allowed
the the
Philippine economy expanded to 7.2 percent in 2013.
government
government to make to make
headway headway in its in its development
development
The country still remains as one of the strongest
initiatives.country’
initiatives. The country’ s economic growth for 2009 is
economies in the The Asian regionswith economic
infrastructuregrowth for 2009 is
4.6
4.6 percent. percent.
development encouraged to continue in the next
Benigno Benigno Aquino Aquino
III is theIII iscur
the current
rent PresidentPresidentof theof the
administration.
R epublicRepublic
of the ofPhilippines.
the Philippines. His His main
main platf platform
orm is good is good
Different rating agencies have also consistently
govthe gov
ernance ernance and the elimination of corr upt practices in
upgraded creditand ratingsthe of elimination
the Philippines. of corrupt Fitch practices in
the the government.
government. Under Under
his his administration,
administration, the the overall
overall
affirmed the country’s long-term foreign and local
financial financial
strength strength
of theof the government has improved,
currency issuer default ratings atgo‘BBB-’
vernment and has ‘BBB,’ improved,
owing to a more efficient tax administration and Average temperature: 27 degrees Celsius (81
respectively, in March 2014, followed by Standard &and
o wing to a more ef ficient tax administration
responsible
responsible go v government
ernment spending spending.. degrees Fahrenheit); Average Humidity: 78 percent
Poor’s stable outlook of BBB in May 2014. Another
Year-round average temperature range: 23-32
vote of confidence was also seen from Moody’s
Languages
Languages degrees Celsius
positive outlook of Baa3 in September 2014. Population
Ov er 87 languages
Over 87 languages and dialects belonging to the
and dialects belonging to the Population
Malayo-Polynesian linguistic family Population 92.34 92.34
millionmillion (National
(National Statistics
Statistics Office, Office, May 2010
May 2010
Languages Malayo-Polynesian linguistic family
T hree principal languages:
Three principal languages: Cebuano, Tagalog, and
Cebuano, Tagalog, and 92.34 million estimate)
estimate)
(National Statistics Office, May 2010
Over 87 languages and dialects belonging to the Population growth rate of percent
1.81 percent per (2014
year (20
Ilocano. Ilocano.
Filipino Filipino
is the isofthe
ficial official
language. language. estimate) Population growth rate of 1.81 per year
Malayo-Polynesian linguistic family estimate)
English English
is the islanguage
the language of of business
business and goand government.
vernment. Population estimate)
growth rate of 1.81 percent per year
Three principal languages: Cebuano, Tagalog, and Literacy
GlobalEnglish,
GlobalEnglish, an independent
an independent researc research
h group, group,
ranked ranked (2014 estimate) Literacy Rate:Rate: 97.5 percent
97.5 percent of totof total population
al population
Ilocano.
the Philippines number
the Philippines number 1 in the world in terms of 1 in the world in terms of Literacy Rate: 97.5 percent of total population
Filipino is the official language. Education
proficiency
proficiency in business
in business English English
for itsfor its 2012
2012 study.study. Education
English is the language of business and K-12: universal kindergarten, six years of elementa
Education K-12: universal kindergarten, six years of elementary
government. GlobalEnglish, an independent education (Grades 1-6), four years of junior high sch
Geography
Geography K-12: education
universal (Grades
kindergarten, 1
six-6), four
years years
of of junior high school
research group, ranked the Philippines number 1 in with additional two years for senior high school
L ocated
Located in Southeast Asia
in Southeast Asia elementary with additional
education two
(Grades years
1-6), for
four senior
years high
of sc hool
the world in terms of proficiency in business English (Grades
Area: Area:
300,000 300,000 sq. km. sq.(117km.,1(117 ,187 square
87 square miles)miles) junior high (Grades
school 11 to 11
(Grades 12)to 12)
7-10) with additional two
for its 2012 study. Public Elementar
T hree major geographical
Three major geographical areas: Luzon, Visayas,
areas: Luzon, Visayas, years for Public
senior Elementar
high school y andyHigh
(Grades and
11 High
to 12)School
School education
education
Mindanao Public Elementary subsidized
subsidized and by the
High by the government
government
School education
GeographyMindanao
Major Major
citiescities
(2010(201 0 estimate):
estimate): CapitCapit (pop. (pop. subsidized
al - Manila
al - Manila by theEnglish
English is partisof
government part
theofcurthe curriculum
riculum and isandtheismedium
the medium
of
Located in Southeast Asia instruction for most subjects
11 .85 11 .85 million
million in the inmetropolit
the metropolitan an area) area) instruction for most subjects
English is part of the curriculum and is the medium
Area: 300,000 sq. km. (117,187 square miles)
Other Other
citiescities
- Cebu - Cebu
City (0.87City (0.87
million); million);
DavaoDavao City (1.45
City (1.45 of instruction for most subjects
Three major geographical areas: Luzon, Visayas, Political
million) million) Political
Mindanao Type: Republic
Terrain:
Terrain: ArchipelagoArchipelago composed composed of 7,107 of 7islands,
,107 islands,
65 65 Political Type: Republic
Major cities (2010 estimate): Capital - Manila (pop. Independence:
percent percent
mount mount ainous,
ainous, with with narrow
narrow coastal lowlands coastal lowlands Type: Independence:
Republic 1946 1946
11.85 million in the metropolitan area) Current constitution: Ratified
Independence: Current 1946 constitution: Ratified on 11on 11 February
February 1987 1987
Other cities - Cebu City (0.87 million); Davao City Branches: Executive; Legislative - Bicameral
Climate Climate Branches:
Current constitution: Executive;
Ratified on Legislative
11 February - 1987
Bicameral
(1.45 million) legislature; Judiciary
Tropical,
Tropical, sittingsitastride
ting astridea typhoona typhoon belt belt legislature;
Branches: Executive; Judiciary
Legislative - Bicameral
Terrain: Archipelago composed of 7,107 islands, 65 Administrative Subdivisions: 17 regions including
Three seasons: Rainy (J
Three seasons: Rainy (June to October); Cool and Dr y
une to October); Cool and Dry l egislature;
Administrative
Judiciary Subdivisions: 17 regions including
percent mountainous, with narrow coastal lowlands Metro Manila
(November(November to Februar to Februar
y); Hot y);andHotDr and Dry (March-May) Administrative
y (March-May) Metro Manila
Subdivisions: 17(National
(National CapitCapital
regions al
including Region),
Region), 80 province
80 provinces,
Average temperature: 27 degrees Celsius (81 degrees 138 138
cities cities
Metro Manila (National Capital Region), 80
Climate Average temperature: 27 degrees Celsius (81 degrees Suffrage: Universal, butcompulsor
not compulsory,
Fahrenheit);
Fahrenheit); Av erageAverageHumidit Humidity:
y: 78 78 percent
percent provinces, Suffrage:
138 cities Universal, but not y, at ageat18age 18
Tropical, sitting astride a typhoon belt
Year-round
Year-round av erage average
temperat temperat
ure ure range:
range: 23-32 23-32
degrees degrees Suffrage: Universal, but not compulsory, at age 18
Three seasons: Rainy (June to October); Cool and Sources: National Statistics Office, CIA World Factbook
Celsius Celsius Sources: National Statistics Office, CIA World Factbook,
Dry (November to February); Hot and Dry Sources: National www.gov.ph
75 | Infrastructure In-depth:
2 | Infrastruct
2 | Infrastruct ure Philippines
Guide:
ure Guide: Philippines
Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Direct
Directory
Dir oryGo
of
ectory ofvernment
of Government
Go Agencies
encies
Agencies
vernment Ag
361Industry
Trade and Industry
361 Tradeitsmorefuninthephilippines.com
and Building, Building,
Sen. Sen. Gil
Gil J. Puyat J. Puyat Avenue,
Avenue, Website: ppp.gov.ph
Website: psalm.gov.ph
Infrastructure In-depth:Guide:
Infrastructure Philippines | 76 | 3
Philippines
Infrastructure Guide: Philippines |3
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
KPMG
KPMG
KPMG
About KPMG
locally locally
implementedimplemented with awith global global
mindset. mindset.
KPMG KPMG
reliability ofdisciplines,
information helps client-f acing teams coalesce around the issues that
prof
professional prof
essional essional
disciplines, disciplines, yused
industrindustr yby
industr
sectors investors
sectorsy and and
sectors
and national and other
nationalnational
borders. borders. helps client-f
acing teams
borders.helps client-facing teams coalesce around the issues that coalesce around the issues that
stakeholders. mat
KPMG
matter most mat
ter most
inwith ter support
the most
Philippines with
with support from supportfrom from
KPMG KPMG
Centers KPMG of Centers
Centers of Excellence
of Excellence
Excellence
KPMG KPMGis is
organiz organized
ed around around
the the
Audit, Audit,
Tax Tax
and and
AdvisoryAdvisory and and
our
R.G. andglobal
our
global
Manabat our & global
methodologiesCo. methodologies
methodologies
(RGM&Co.)and and
approacis and
approac
thehes. approaches.
hes.
KPMG
Philippine KPMG
Centers KPMGCentersCenters
KPMG is organized around the Audit, Tax and Advisory
Tax practices.
practices. of Ex cellence
member of
of Excellence Ex cellence
are small
firm ofare KPMG are
groups small
smallInternational.
groups groups
of mobile, of mobile, of
global mobile,
It is one global global
ofspecialists
specialists the specialists
practices.
who
who support oursupport our our
member member firms firms
in bringingin bringing high high quality
Attitudes to tax are changing. Organizations of all whofastest-growing
support member practicesfirms inin bringing
the high
Philippines andyqualit
qualit y
Audit Audit industryindustry
andindustryand
technical andexpertise
technicaltechnical
expertise expertise
Audit sizes are ever more exposed to new trends in tax among the KPMG practices in the Asia Pacific region.
Audit is Audit
is an is
Aregulation,
udit
an independent an independent
independent
not serlocally
just vice ser ser
vice
thatbut viceenhances
that
enhances
globally.
thattheenhances theofreliability
the reliabilit
reliability ofto
y ofto our
It ranksourtosecond
clients. our clients.
clients. in number of top 1000 Philippine
information information
information
used bused used by
by investors
y investors inv estors
and other and st and
other other stakeholders.
stakeholders.
akeholders.
corporations
KPMG audited.*It has also been recognized as
KPMG KPMG
in the in theinPhilippines
the Philippines
Advisory a Tier taxPhilippines
1R.G. practice** and a Tier 1 leading thetax
Tax Tax Tax R.G. Manabat
R.G. Manabat & Manabat
Co. & (RCo. &(RCo.
GM&Co.) GM&Co.)(RisGM&Co.)
the is theisPhilippine
Philippine Philippine
member memberfirm memberfirm firm
Advisory works with the world’s leading transactional
of KPMG firm*** in
International. the Philippines
It is one of by
the thefastest-growing
Attitudes
Attitudes
Attitudes to tax to aretax to tax are
are changing
changing changing . Organizations
. Organizations
. Organizations ofes of
all are
of allsustainable
siz all
sizes
eversizes are
are ever ever of KPMG International. It
of KPMG International. It is one of the fastest-growing is one of the fastest-growing
organizations to create and protect tthe International Tax
theinReview.
moremore
more exposed exposedto exposed
new totrends
new to trends
new
in t trends
ax in taxinregulation,
regulation, ax regulation,
not just notlocally
notlocally
just just locally
practices inpractices
practices the in Philippines the Philippines
Philippines
and among and amongand
the among
KPMG the KPMG the KPMG
practices inpractices
practices in in
valuebut of globally.
their business or organization – focusing in the the
Asia Asia
P acific Pacific
region. region.
It ranks It ranks
second secondin in top
number number
of top of1000
top 1000
but globally.
but globally. the Asia P acific region. It ranks second in number of 1 000
the areas of Management Consulting, Risk RGM&Co.
Philippine
Philippine takes
Philippine
corporations pride
corporations inaudited.*It
corporations
audited.*It imparting
audited.*It
has also knowledge
has also
been alsothat
hasrecogniz
been been ed recognized
recogniz as ed as as
Consulting
Advisory
Advisory and Transactions & Restructuring. a adds
Tier a
1 Tier
t value
ax a 1Tier
t to
ax
practice**,1 its
t ax clients’
practice**,
practice**,
Tier 1 businesses.
Tier
leading 1Tier 1
leading
t ax The
leading
t ax diverse
t ax transactional
transactional
transactional firm*** firm*** firm***
Advisory
Advisory
Advisory w orks works
with with
the the
world’
world’
s leadings leading organizations
organizations to to
create public
create
and and
Tier 1 and
and1Tier
Tier private
transactional sector
1 transactional
transactional advisor backgrounds
advisor
y firmadvisor
y
in firm
the y in ofthe
firm the
Philippines**** partners
inPhilippines****
the Philippines****
by by by
Advisory works with the world’s leading organizations to create
Demonstrating
and
the protect
and protect
and protect sust the KPMG
theainable
theainable
sust sustainable
value of difference
value
their vof
aluetheirof business
business theirorbusiness or or and principals,
the
the International coupled
International
the International Tax Review. with
Tax
Tax Review.
their
Review. extensive training,
KPMG – professionals
organization
organization
organization focusing – fthe
– focusing
in understand
ocusing
in theinareas
areas ofthe what
areas clients
of
of Management
Management need to
*Business
*Business World World
Top TopCorporations
1000 10002013
Corporations 2013 edition
2013 edition
skills and skills
skillsthe
and and
the
right the e
eright right experience
xperience
xperience to helptomeet to their
help help unique
meet meet their unique *Business
their unique World Top
**Tax
1000 Corporations
International Tax Review’s
edition
World TaxGuide
2014 Guide
** International
** International Tax Review’s
Review’s World World
Tax 2014Tax 2014
Guide
requirements. requirements.
requirements. ***Tax
International
*** International
*** International Tax Review
Tax Review
Review 2014 2014 2014
****Tax
International
**** International
**** International Tax Review
Tax Review
Review 2013 2013 2013
77
2 || Infrastructure
Infrastructure In-depth:
2 | Infrastruct Philippines
ure Guide:
Guide: Philippines
Philippines
2 | Infrastructure Guide: Philippines
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
Direct
Direct ory
ory
Directof
oryof
ParPtners
ofartners
Par and
and
tners Principals
Principals
and Principals
Roberto Roberto
Roberto
G. G. Manabat
G. Manabat
Manabat
Chairman Chairman
Chairman Ex&ecutive
& Chief
& Chief Chief Executive
Executive Officer
Officer
Officer
rgmanabat@kpmg.com
rgmanabat@kpmg
rgmanabat@kpmg.com .com
Emmanuel Emmanuel
Emmanuel P. Bonoan
P. Bonoan
P. Bonoan
Vice Vice Chairman
Chairman
Vice Chairman of&
& Head
& Head TaxHead
of Taxof Tax
ebonoan@kpmg.com
ebonoan@kpmg
ebonoan@kpmg.com .com
Sharon G.Sharon
Sharon G. Dayoan
G. Dayoan
Dayoan
Head HeadHead of Audit
of Audit
of Audit
sdayoan@kpmg.com
sdayoan@kpmg.com
sdayoan@kpmg.com
HenryHenryHenry D. Antonio
D. Antonio
D. Antonio
Head Head Head of Advisory
of Advisory
of Advisory
hantonio@kpmg.com
hantonio@kpmg
hantonio@kpmg.com .com
Emerald Emerald
Anne C. Anne
BagnesC. Bagnes ArthurArthur Z. Machacon
Z. Machacon
ebagnes@kpmg.com
ebagnes@kpmg Emerald .com Anne C. Bagnes amachacon@kpmg.com
Tireso Randy F. Lapidez
amachacon@kpmg.com
ebagnes@kpmg.com tlapidez@kpmg.com
CarmelCarmel
Lynne LynneM. Balde M. Balde TomasTomas
G. MahinayG. Mahinay
cbalde@kpmg.com
cbalde@kpmg.com Noel A. Baladiang tmahinay@kpmg.com
tmahinay@kpmg.comRicardo G. Manabat
nbaladiang@kpmg.com rmanabat@kpmg.com
Enrico Enrico
E. BaluyutE. Baluyut Ricardo Ricardo
G. ManabatG. Manabat
ebaluyut@kpmg.com
Carmel Lynne M. Balde
ebaluyut@kpmg.com rmanabat@kpmg.com
Virgilio L. Manguilimotan
rmanabat@kpmg.com
cbalde@kpmg.com vmanguilimotan@kpmg.com
Oliver Oliver
C. Bucao C. Bucao VirgilioVirgilio L. Manguilimotan
L. Manguilimotan
obucao@kpmg.com
obucao@kpmg.com Enrico E. Baluyut vmanguilimotan@kpmg.com
Maria Myla S. Maralit
vmanguilimotan@kpmg.com
ebaluyut@kpmg.com mmaralit@kpmg.com
Joan C. Joan
Cariño C. Cariño MariaS.
Maria Myla Myla S. Maralit
Maralit
jcarino@kpmg.com
jcarino@kpmg.com Oliver C. Bucao mmaralit@kpmg.com
mmaralit@kpmg.com Ador C. Mejia
obucao@kpmg.com acmejia@kpmg.com
Pacifico Pacifico
Castañeda Castañeda Ador C. Ador
Mejia C. Mejia
pcastaneda@kpmg.com
pcastaneda@kpmg.com Joan S. Cariño acmejia@kpmg.com
acmejia@kpmg.com John Molina
jcarino@kpmg.com johnmolina@kpmg.com
Alicia S.Alicia S. Columbres
Columbres John Molina
John Molina
acolumbres@kpmg.com
acolumbres@kpmg Pacifico.comCastañeda johnmolina@kpmg.com
Herminigildo G. Murakami
johnmolina@kpmg.com
pcastaneda@kpmg.com hmurakami@kpmg.com
ImeldaImelda
H. Corros H. Corros Herminigildo
Herminigildo G. Murakami
G. Murakami
icorros@kpmg.com
icorros@kpmg.com Alicia S. Columbres hmurakami@kpmg.com
hmurakami@kpmg.com Aline A. Novilla
acolumbres@kpmg.com anovilla@kpmg.com
Dindo Dindo
MarcoMarco M. Dioso M. Dioso WilfredoWilfredo
Z. Palad Z. Palad
ddioso@kpmg.com
ddioso@kpmg.com Imelda H. Corros wpalad@kpmg.com
wpalad@kpmg.com Wilfredo Z. Palad
icorros@kpmg.com wpalad@kpmg.com
Yoshiaki Yoshiaki
Endo Endo Ma. Carmela
Ma. Carmela M. PeraltaM. Peralta
yendo1@kpmg.com
yendo1@kpmg.comDindo Marco M. Dioso mperalta@kpmg.com
Ma. Carmela M. Peralta
mperalta@kpmg.com
ddioso@kpmg.com mperalta@kpmg.com
Jerome Jerome
Andrew Andrew H. Garcia
H. Garcia JimmyJimmy S. Quiñones
S. Quiñones
jhgarcia@kpmg.com
jhgarcia@kpmg.com Yoshiaki Endo jquinones@kpmg.com
jquinones@kpmg.com Kathleen L. Saga
yendo1@kpmg.com ksaga@kpmg.com
MichaelMichael
Arcatomy Arcatomy H. Guarin
H. Guarin Manuel Manuel P. Salvador
P. Salvador III III
mguarin@kpmg.com
Jerome Andrew H. Garcia
mguarin@kpmg.com msalvadoriii@kpmg.com
Manuel P. Salvador III
msalvadoriii@kpmg.com
jhgarcia@kpmg.com msalvadoriii@kpmg.com
DennisDennis
I. Ilan I. Ilan Ma. Georgina
Ma. Georgina J. Soberano
J. Soberano
dilan@kpmg.com
Michael
dilan@kpmg.com Arcatomy H. Guarin gjsoberano@kpmg.com
Ma. Georgina J. Soberano
gjsoberano@kpmg.com
mguarin@kpmg.com gjsoberano@kpmg.com
Kristine Kristine
S. ImperialS. Imperial Roberto Roberto
L. Tan L. Tan
kimperial@kpmg.com
kimperial@kpmg Dennis
.com I. Ilan rltan@kpmg.com
rltan@kpmg.com Darwin P. Virocel
dilan@kpmg.com dvirocel@kpmg.com
Jose P.Jose
Javier P. Javier
Jr. Jr. DarwinDarwin
P. VirocelP. Virocel
jpjavier@kpmg.com
jpjavier@kpmg.com Jose P. Javier, Jr. dvirocel@kpmg.com
dvirocel@kpmg.com
jpjavier@kpmg.com
Infrastructure
Infrastructure In-depth: Philippines
| 3 | 78
Infrastructure Guide:Guide: Philippines
Philippines |3
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
R.G. Manabat & Co.
Our Values
We lead by example
We work together
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.
EmmanuelP. PBonoan
Emmanuel . Bonoan
Infrastructure In-depth: Paul Patrick R. Afable
Editor-in-Chief
Philippines Henry D. Antonio Editor-in-Chief
Emmanuel P. Bonoan
Sharad Somani Sharon Smith
The Infrastructure Issue
Jerome Andrew H. Garcia
Henry D. Antonio Vaughn F. Montes,
Associate Editor PhD
2015 Investment Guide Michael Arcatomy H. Guarin Editorial Consultant
Growth and Opportunities
by KPMG in the
in the Philippines Ma. Pia A. Urgello
Ma.John
Cynthia C.
Molina Hernandez Sachin Gohel
Philippine Infrastructure Sector
Mary KarenArcatomy
Michael Quizon-Sakkam
H. Guarin Mariel D. Javier
Editorial Consultant
Sharad Somani
Paul Patrick R. Afable Ma. Cristina Isabel L. Roxas
2014-2015 Edition Mariel D. Javier
Geno Armstrong
Emmanuel P. Bonoan Editorial Coordinators
Reid Tucker Ma. Cristina Isabel L. Roxas
Writers Editorial
Jonathan Jong John ErnestCoordinators
T. Tandoc
Writers Art Direction and Layout
John Ernest T. Tandoc
Art Direction and Layout
Emmanuel P. Bonoan
Vice Chairman & Head of Tax, Chief Operating Officer
Pacifico M. Castañeda
Chief Financial Officer
Sharon G. Dayoan
Head of Audit
Henry D. Antonio
Head of Advisory
Makati City 1226, Metro Manila Sta. Rita cor. Canal Road CBD area
Iloilo City 5000
E-mail: ph-inquiry@kpmg.com
Telefax: +63 (47) 252 2826
Cebu Office
Bacolod Office
Infrastructure In-depth: Philippines 2015 Investment Guide by KPMG in the Philippines is available for download at
www.kpmg.com/PH/en/PHConnect/ArticlesandPublications/ThoughtLeadershipPublications/Pages/InfrastructureIn-depthPhilippines.aspx
© 2015 R.G. Manabat & Co., a Philippine partnership and a member firm of the KPMG network of independent firms affiliated with KPMG International Cooperative ("KPMG International"), a Swiss entity. All rights reserved.