PROJECT LRT LINE 3

TECHNICAL & METHOD STATEMENT PRESENTATION


FOR
REVERSE CIRCULATION DRILL (RCD) PILE

Piling Contractor : GEOFORCE EAST SDN BHD


1.0 INTRODUCTION

What is Reverse Circulation Drill (RCD) method?


Benefit of RCD Pile
1.0 Introduction
What Is RCD Pile?

RCD method provides a continuity drilling with extension 3.0m drill rod at every
stage of drilling work
Soilslurry will be sucked up through the rod where the suction force being
produce by the suction pump mounted on the RCD rig
Slurry is then discharge into siltation tank provided on site for segregation of
the soil and water
Water is then discharged back into the bored shaft and drilling work shall carry
on by circulation of the water
1.0 Introduction (con’t)
✓ Benefit of RCD Pile

 Good for limitation of construction space


 High water table level would potentially delay if using caisson method
 No vibration compared to other drilling method
 Free of sound disturbance
 Better control of excavated soil within the siltation pond
 Better choice for big diameter and deep boring pile
 Less disturbance to bored pile wall and provide better skin friction
 Better pile verticality can be obtained
2.0 Plant & Equipment

 List of Plant & Equipment for the project


 Reverse Circulation Drill (RCD) Rig Specification
2.0 Plant and Equipment

-List of Plant and Equipment for the project

No. Plant & Equipment Description


1 Reverse Circulation Drilling Rig For bored pile drilling works
2 Service Crane (mobile crane) For hoisting of equipment / materials (RCD rig,
reinforcement cage, boring tools and etc)
3 Temporary Casing (3000mm diameter) Temporary support for bored hole
4 Excavator For site platform preparation for drilling rig
5 Tremie Set For concreting of bored pile in wet condition
6 Water Pump For pumping of water
7 Generator Set Power supply for RCD Rig and equipment
3.0 METHOD STATEMENT FOR RCD PILE
3.0 Method Statement for RCD Pile

 Platform preparation
 Surveying and setting out
 Installation of Steel Casing
 Setting up of RCD Machine and detention tank
 Drilling of the bored pile shaft
 Steel cage installation
 Installation of Tremie Pipes
 Concreting
 Removal of temporary casing & backfill of empty bored shaft
4.0 Consequence of Works
for RCD PILE
4.1 Drilling Process
– Plan view during drilling process
4.2 Drilling Process
– Sectional view during drilling process
4.3 Steel Cage Installation Process
– Plan view during steel cage installation
4.4 Steel Cage Installation Process
– Sectional view during steel cage installation
4.5 Concrete Process
– Plan view during concreting process
4.6 Concrete Process
– Section view during concreting process
5.0 Past Completed Project with RCD Method
5.1 Past Completed Project with RCD Method

Project :
Road Widening at LDP, Sri
Damansara, Kuala Lumpur
Pile Size : 1500mm Dia
Drill Depth : 18.0m
5.2 Past Completed Project with RCD Method

Project :
V-Resident, Gurney, Penang

Pile Size : 750mm Dia


Drill Depth : 60.0m
5.3 Past Completed Project with RCD Method

Project :
MRT V3-Pier 27&28,
Bandar Utama

Pile Size : 2800mm Dia


Drill Depth : 35.0m
5.4 Past Completed Project with RCD Method

Project :
MASS RAPID TRANSIT LEMBAH
KELANG, JAJARAN SUNGAI
BULOH - KAJANG (PACKAGE V1)

Pile Size : 600mm Dia


Drill Depth : 40.0m
5.5 Past Completed Project with RCD Method

Project :
Kajang Bridge 2

Pile Size : 1800mm Dia


Drill Depth : 40.0m
5.6 Past Completed Project with RCD Method

Project :
Tanjung Bin

Pile Size : 1800mm Dia


Drill Depth : 40.0m
5.7 Past Completed Project with RCD Method

Project :
Next Success, Hotel, Penang

Pile Size : 1200mm Dia


Drill Depth : 80.0m
5.8 Past Completed Project with RCD Method

Project :
Loji Rawatan Kumbahan
Serantau, Penang
Pile Size : 1000mm Dia
Drill Depth : 76.0m
6.0 Current Project with RCD Method

Project : Pile Size : 3.0m Dia.


MRT LINE 2 Package V208, Pile Length : 38.0m
Seri Kembangan
THANK YOU