Project Title : Construction of the Bar - Boljare Highway, V.O. Ref No : V.O. #3
Section: Smokovac - Uvač - Mateševo issued on: : 25-April-19
Contract Ref. No. : 01-827/1 Engineer's approval of offer ref. letter : IG/10999/JLO
Signed on: : 26-February-14
the Employer : The Government of Montenegro
Ministry of Transport and Maritime Affairs (MTMA)
the Contractor : China Road and Bridge Coorporation (CRBC)
the Engineer (FIDIC : INGEROP CONSEIL &INGENIERIE - GEODATA Engineering S.p.A
dasdsfds
Effect of variation Order on Contract comments (if any) Cost of Variation Order
Is there an Overall Cost effect √ Accepted Contract price : 809,577,356.14
*Cost offect of Variation to Work √ Contract price before this VO : 809,577,356.14
*Is there an Extension of Time √ Value of VO. #3 works : 30,456,569.00
*Cost Effect of Extension of time □ Cost of Extension of Time [(-)]/[(+ : Nill