You are on page 1of 14

THE SPECIAL MAINTENANCE OF ROAD P23/1 BETWEEN KROONSTAD AND STEYNSRUS:

SECTION 1300
CONTRACTORS ESTABLISHMENT ON SITE AND GENERAL REQUIREMENTS

ITEM No DESCRIPTION UNIT QTY RATE AMOUNT

B13.01 Contractor's general obligations

(a) Fixed obligations Lump sum Rate Only

(b) Value-related obligations Lump sum Rate Only

(c) Time-related obligations Month Rate Only

B13.02 Health and Safety obligations

Fixed obligations for the preparation of risk assessments safe work procedures, the project Health and Safety file the
(a) Lump sum Rate Only
Health and Safety plan and any other Health and Safety matters that are legally required

Time-related obligations for updating and amending the risk assessments, the safe work procedures, the project Health and
(c) Safety file and the Health and Safety plan, and for full compliance with all Health and Safety legislation during the Month Rate Only
construction of the Works under the Contract

SECTION TOTAL CARRIED FORWARD TO SUMMARY

C2.6
THE SPECIAL MAINTENANCE OF ROAD P23/1 BETWEEN KROONSTAD AND STEYNSRUS:
SECTION 1500
ACCOMMODATION OF TRAFFIC

ITEM No DESCRIPTION UNIT QTY RATE AMOUNT

B15.03 Temporary traffic-control facilities -


-
(a) Flagmen man-day Rate Only
-
(b) Portable STOP and GO-RY signs No Rate Only
-
(d) Amber flicker lights No Rate Only
-
(e) Road signs, R- and TR- series: -
-
(ii) 1200mm diameter -
-
-
2. Mounted on stand No Rate Only
-
(f) Road signs, TW-series: -
-
(ii) 1500mm diameter -
-
-
2. Mounted on stand No Rate Only
-
(g) Road signs, STW-, DTG-, TGS- AND TG-series (excluding delineators and barricades) -
-
-
(ii) Mounted on stand m² Rate Only
-
(h) Delineators TW401 or TW402: -
-
(i) Single -
-
1. 1000mm x 250mm No Rate Only
-
2. 800mm x 250mm No Rate Only
-
(ii) Mounted back to back -
-
1. 1000mm x 250mm No Rate Only

2. 800mm x 250mm No Rate Only


-
-
(j) Traffic cones (750mm high) No Rate Only
-
(k) Single guardrails attached to posts m Rate Only
-
-
-
-
-
PAGE TOTAL CARRIED FORWARD

C2.7
THE SPECIAL MAINTENANCE OF ROAD P23/1 BETWEEN KROONSTAD AND STEYNSRUS:
SECTION 1500
ACCOMMODATION OF TRAFFIC

PAGE TOTAL BROUGHT FORWARD

ITEM No DESCRIPTION UNIT QTY RATE AMOUNT

15.10 Accomodation of traffic where the road is constructed in half-widths


-
-
(a) Single carriageway km Rate Only
-
B15.11 Traffic control devices (set) -
-
-
(b) Operating signalised traffic control devices month-sets Rate Only
-
B15.14 Amber flashing lights mounted on signs No Rate Only
-
B15.15 Provision of traffic safety equipment for use by the -
Engineer: -
-
(a) Emergency mini lightbar for mobile use No Rate Only
-
(b) Road Inspection Vehicle sticker for vehicles with 100mm -
high lettering No Rate Only
-
(c) Safety jackets No Rate Only
-
B15.16 Provision of traffic safety -
-
Traffic safety officer month Rate Only
-
-
-
B15.19 Flashing illuminated arrow board No Rate Only
-
OVERHAUL -
(Section 1600) -
-
15/B16.02 Overhaul on material hauled in excess of
1,0 km (ordinary overhaul) m³-km Rate only

PAGE TOTAL CARRIED FORWARD

C2.8
THE SPECIAL MAINTENANCE OF ROAD P23/1 BETWEEN KROONSTAD AND STEYNSRUS:
SECTION 1700
CLEARING AND GRUBBING

ITEM No DESCRIPTION UNIT QTY RATE AMOUNT

1700 CLEARING AND GRUBBING

17,01 Clearing and grubbing of: ha Rate Only

(a) Normal areas

(i) Within the road reserve

17,02 Removal and grubbing of large trees and tree stumps

(a) Girth exceeding 1m up to and including 2m

(b) Girth exceeding 2m up to and including 3m

Clearing and grubbing at inlets and outlets of


17,04
hydraulic structures m² Rate Only

17,05 Cleaning out of hydraulic structures:

(a) Pipes with an internal diameter up to and including m³ Rate Only


750mm

(b) Pipes with an internal diameter m³ Rate Only


exceeding 750mm

(c) Box culverts up to and including 1.5m vertical dimension m³ Rate Only

(d) Box culverts exceeding 1.5m vertical dimension m³ Rate Only

SECTION TOTAL CARRIED FORWARD TO SUMMARY

C2.9
THE SPECIAL MAINTENANCE OF ROAD P23/1 BETWEEN KROONSTAD AND STEYNSRUS:
SECTION 1800
DAYWORKS

ITEM No DESCRIPTION UNIT QTY RATE AMOUNT

B18.01 Personnel

(a) Unskilled labour hr Rate Olny

(b) Semi-skilled labour hr Rate Olny

(c) Skilled labour hr Rate Olny

(d) Ganger hr Rate Olny

(e) Foreman hr Rate Olny

B18.02 Equipment

(b) Compressor, 7,0m 3 per min hr Rate Olny

(c) Self propelled vibratory roller, 9-12 tons hr Rate Olny

(d) Pneumatic tyred roller, gross mass to range from approx. 4,5 tons unloaded to 18 tons loaded hr Rate Olny

(e) Hand propelled vibratory roller, 0,5 ton mass hr Rate Olny

(f) Tractor for towing, 105 kW power hr Rate Olny

(g) Crawler excavator minimum power 105 kW hr Rate Olny

(h) Front-end loader minimum power 90 kW hr Rate Olny

(i) Vibrating plate compactor minimum power 2 kW hr Rate Olny

(j) Platform truck minimum load mass 10 tons hr Rate Olny

(k) Tip truck minimum load capacity 10 tons hr Rate Olny

(l) Water tank truck minimum capacity 10 kl hr Rate Olny

(m) Self-propelled motor grader mass not less than 9 tons, power approx. 100 kW hr Rate Olny

(n) Gridroller, 15 tons mass hr Rate Olny

(o) Mobile crane with lifting capacity of 5 tons hr Rate Olny

(p) Low bed trailer with mechanical horse hr Rate Olny

(q) Flat steel wheeled roller, 9-12 tons mass hr Rate Olny

(r) Track-type bulldozer, 200kW power hr Rate Olny

(s) Traxcavator 80 kW power hr Rate Olny

(t) 900 CFM Compressor hr Rate Olny

PAGE TOTAL CARRIED FORWARD

C2.10
THE SPECIAL MAINTENANCE OF ROAD P23/1 BETWEEN KROONSTAD AND STEYNSRUS:
SECTION 1800
DAYWORKS

PAGE TOTAL BROUGHT FORWARD

ITEM No DESCRIPTION UNIT QTY RATE AMOUNT

(u) AC Drilling Rig hr Rate Only

B18.04 Transport

(a) LDV (2000cc) km Rate Only

(b) Flatbed truck (5 Ton) km Rate Only

SECTION TOTAL CARRIED FORWARD TO SUMMARY

C2.11
THE SPECIAL MAINTENANCE OF ROAD P23/1 BETWEEN KROONSTAD AND STEYNSRUS:
SECTION 2100
DRAINS

ITEM No DESCRIPTION UNIT QTY RATE AMOUNT

B21.01 Excavation for open drains

(a) Excavating soft material situated within the


following depth ranges below the surface
level:

(i) 0 m and up to 1,5 m m³ Rate Only


-
(ii) Exceeding 1,5 m and up to 3,0 m m³ Rate Only
-
(b) Extra over subitem B21.01(a) for excavation in hard material, irrespective of depth m³ Rate Only
-
B21.03 Cleaning and shaping existing open drains m³ Rate Only
-
B21.03 Excavation for subsoil drainage systems: -
-
(a) Excavating soft material situated within the -
following depth ranges below the surface -
level: -
-
(i) 0 m and up to 1,5 m m³ Rate Only
-
(ii) Exceeding 1,5 m and up to 3,0 m m³ Rate Only
-
(b) Extra over subitem B21.03(a) for excavation in hard material, irrespective of depth Rate Only

-
B21.04 Impermeable backfilling to subsoil drainage systems
-
-
(a) Unstabilised natural gravel m³ Rate Only
-
B21.06 Natural permeable material in subsoil -
drainage systems (washed crushed stone): -
-
(b)
Crushed stone obtained from commercial sources:
-
-
(ii) Coarse grade (19,0mm) m³ Rate Only
-
B21.07 Natural permeable material in subsoil drainage systems -
(washed sand): -
-
(b)
Sand from commercial sources (clean river sand)
-
-
(i) Medium grade < 2.00mm m³ Rate Only
-
21.08 Pipes in subsoil drainage systems: -
-
(b) Unplasticised PVC pipes and fittings, normal -
duty, complete with couplings: -
-
(i) Rate Only
110 mm internal dia, perforated or slotted m
-
(ii) 110 mm internal dia, not perforated m Rate Only
-
21,10 Synthetic-fibre filter fabric, non woven or woven -
(Grade 2) m² Rate Only
-
21,13 Concrete caps for subsoil drain pipes No Rate Only
-
21,18 Excavation for the clearing of existing drainage systems: -
-
(a) Manholes and inlet and outlet structures m³ Rate Only
-
(b) Culvert barrels m³ Rate Only
-
(c ) Concrete side drains m³ Rate Only
-
B21.20 Subsoil outlet marker board No Rate Only
-
-
SECTION TOTAL CARRIED FORWARD TO SUMMARY

C2.12
THE SPECIAL MAINTENANCE OF ROAD P23/1 BETWEEN KROONSTAD AND STEYNSRUS: PREFABRICATED CULVERTS SECTION 2200

ITEM No DESCRIPTION UNIT QTY RATE AMOUNT

22,01 Excavation

(a) Excavating soft material situated within the following depth ranges below the surface level:

(1) 0 m up to 1.5 m m³ Rate Only


-
(2) Exceeding 1,5 m and up to 3,0 m m³ Rate Only

(3) Exceeding 3,0 m and up to 4,5 m m³ Rate Only

22,02 Backfilling:

(a) Using the excavated material m³ Rate Only


-
(b) Using imported selected material m³ Rate Only
-
(c) Extra over subitems 22.02(a) and (b) for soil cement backfilling Rate Only
-
(2) with 5% Cement m³ Rate Only
-
22,03 Concrete pipe culverts: -
-
(b) On class B bedding -
-
(2) 450mm dia. Class 100D m Rate Only

(3) 600mm dia. Class 100D m Rate Only

(5) 900mm dia. Class 100D m Rate Only


-
22,05 Portal and rectangular culverts: -
-
(b) Without prefabricated floor slab size m Rate Only
58,62m long x 14,88m wide x 1,70m deep and -
type SATS Rectangular Portal - Class 1 Loading -
1,5m wide opening x 1,5m high opening x 1,22m -
long -
-
-
22,07 Cast in situ concrete and formwork -
-
(b) In 200mm thick floor slabs for portal or -
rectangular culverts, including formwork, joints -
and class U2 surface finish class 25MPa m³ Rate Only
compressive strength concrete and 19mm -
aggregate -
-
22.10 Steel reinforcement -
-
(b) High-tesile steel bars (catchpit and channel) t Rate Only
-
22,18 Brickwork -
-
(b) 230 mm thick (NFX 14MPa clay brick) m2 Rate Only
to build wing walls

SECTION TOTAL CARRIED FORWARD TO SUMMARY

C2.13
THE SPECIAL MAINTENANCE OF ROAD P23/1 BETWEEN KROONSTAD AND STEYNSRUS: CONCRETE KERBING, CONCRETE CHANNELS,
CHUTES AND DOWNPIPES, AND CONCRETE LININGS FOR OPEN DRAINS
SECTION 2300

ITEM No DESCRIPTION UNIT QTY RATE AMOUNT

23.02 Concrete kerbing-channelling combination:

(a) Prefabricated barrier kerb, Type 4 SANS 927:2013 m Rate Only

-
23,05
Inlet, outlet, transition and similar structures (typical designs):
-

Rate Only
(a) Inlet structures, for concrete side drains as per typical details No

-
23,07
Trimming of excavations for concrete-lines open lined drains
-
-
2 Rate Only
(a) In soft material m
-
(b) In hard material m2 Rate Only
-
23,08 Concrete lining for open drains: -
-
Rate Only
Cast in situ concrete lining (Class 30/19 concrete, V-drain as specified on the Tender Drawings) 3
(a) m

-
(b) Class U2 surface finish to cast in situ concrete m2 Rate Only
-
23,09
Formwork to cast in situ concrete lining for open drains (class F2 surface finish):
-
-
(a) To sides with formwork on both internal and external faces (each face measured) Rate Only
m2
-
(c) To ends of slabs m2 Rate Only
-
23.10 Sealed joints in concrete linings of open drains: -
-
(a) 10 mm bitumen impregnated fibre board -
with silicon joint sealer m Rate Only
-
23,12 Steel reinforcement: -
-
(c) Welded steel fabric (Ref. no. 311) kg Rate Only
-
23,13 Polyethylene sheeting (0.15 mm thick) for concrete-lined -
open darins -
m2 Rate Only
23,15 Precast concrete blocks in outlet structures (class 30/19 concrete), complete as shown on the Drawings Rate Only
No

SECTION TOTAL CARRIED FORWARD TO SUMMARY

C2.14
THE SPECIAL MAINTENANCE OF ROAD P23/1 BETWEEN KROONSTAD AND STEYNSRUS: PATCHING AND
SECTION 3900
REPAIRING EDGE BREAKS

ITEM No DESCRIPTION UNIT QTY RATE AMOUNT

B39.01L Mechanical saw cutting for patching:

(a) Saw cutting a combination of bituminous surfacings and cemented pavement layers to an average depth:

(i) Not exceeding 50mm m² Rate Only

(ii) Exceeding 50mm but not exceeding 100mm m² Rate Only

(iii) Exceeding 100mm m² Rate Only

B39.02 Excavation in existing pavements for patching in :

L (1) By hand:

(a) Asphalt layers (30 - 50mm thickness) m³ Rate Only

(b) Cemented layers (150mm) m³ Rate Only

(c) Crushed stone or unstabilized natural gravel layers m³ Rate Only

(2) By milling machine:

(a) Asphalt layers (30mm) m³ Rate Only

39.03L Backfilling of excavations for patching with:

(b) Base material stabilized with 1,5% of nett 60% anionic stable grade bituminous emulsion and 1% cement using:

(1) Excavated material for a patch with a surface area:

(i) Not exceeding 5m² m³ Rate Only

(ii) Exceeding 5m² but not exceeding 100m² m³ Rate Only

(iii) Exceeding 100m² m³ Rate Only

39.04 Compacting the floor of excavations for patching m² Rate Only

39.05L Cutting back the edges of existing surfacing for the repairing of edgebreaks (50mm depth) m Rate Only

B39/B1600 Extra over item B39.02 for overhaul of material as measured in accordance with the provisions of clause B1600 m³km Rate Only

SECTION TOTAL CARRIED FORWARD TO SUMMARY

C2.15
THE SPECIAL MAINTENANCE OF ROAD P23/1 BETWEEN KROONSTAD AND STEYNSRUS: GUARDRAILS SECTION 5400

ITEM No DESCRIPTION UNIT QTY RATE AMOUNT

B54.01 Guardrails on 3.81m spaced posts

(a) Complete galvanised system on:

(i) Timber posts m Rate only


-
(b) Extra over 54.02(a) for the following: -
-
(i) End treatments where double guardrail sections are used (including additional posts) No Rate only
-
54,06 Reflective plates No Rate only
-
B54.14 Nailing of gang nail plates on top of timber guardrail posts No Rate only

SECTION TOTAL CARRIED FORWARD TO SUMMARY

C2.16
THE SPECIAL MAINTENANCE OF ROAD P23/1 BETWEEN KROONSTAD AND STEYNSRUS: FENCING SECTION 5500

ITEM No DESCRIPTION UNIT QTY RATE AMOUNT

55.02 Supply and erect new fencing material for new fences and for supplementing material in existing fences which are being

(a) Zinc-coated barbed wire (3.2 x2.5mm OVAL HIGH TENSILE GRADE SINGLE STRAND) km Rate only
-
(g) Standards (1850 x2.5 kg/m "Y" SECTION No Rate only
COMPLETE WITH HOLES AT 50mm c/c) -
-
(h) Droppers (1400 x 0.56mm kg/m RIDGEBACK PATTERN) No Rate only
-
(i) Straining posts, stays and anchors: -
-
1. Inclined: -
-
(i) Steel stays and anchors (2130 x 60Ø x 3mm MILD STEEL TUBING)

No Rate only
-
-
-
-
-
-
-
SECTION TOTAL CARRIED FORWARD TO SUMMARY

C2.17
THE SPECIAL MAINTENANCE OF ROAD P23/1 BETWEEN KROONSTAD AND STEYNSRUS: ROAD SIGNS SECTION 5600

ITEM No DESCRIPTION UNIT QTY RATE AMOUNT

B56.01 Road sign boards with painted or coloured


semi-matt background. Symbols, lettering
and borders in semi-matt black or Class I
retro-reflective material, where the sign
board is constructed from:

(c) Prepainted galvanized steel plate


(chromadek or approved equivalent):

(i) Area not exceeding 2 m² m² Rate only


-
(ii) Area exceeding 2 m² but not 10 m² m² Rate only
-
56.02 Extra over item 56.01 for using: -
-
(a) Background of retro-reflective material: -
-
(i) Class I m² Rate only
-
(ii) Class III m² Rate only

-
(b) Lettering, symbols, numbers, arrows, -

emblems and borders of retro-reflective -


material: -
-

(i) Class III m² Rate only


-

56.03 Road sign supports (overhead road sign -


structures excluded): -
-
(b) Timber (creosoted support poles - 110 diameter) m Rate only
-
56.03 Kilometer posts (triangular concrete post (Class 25/13) embedded in 1200mm high x 450 mm diameter pipe (Class No Rate only
-
-
56,05 Excavation and backfilling for road sign supports (not applicable to kilometre posts) m³ Rate only
-
56,06 Extra over item 56.05 for cement-treated soil backfill m³ Rate only
-
56,08 Dismantling, storing and re-erecting road signs with : -
a surface area of: -
-
(a) Up to 2 m² No Rate only
-
(b) Exceeding 2 m² but not 10 m² No Rate only
-
-
-
-
-

-
-
-
-
-
-
-
-
SECTION TOTAL CARRIED FORWARD TO SUMMARY

C2.18
THE SPECIAL MAINTENANCE OF ROAD P23/1 BETWEEN KROONSTAD AND STEYNSRUS: ROAD MARKINGS SECTION 5700

ITEM No DESCRIPTION UNIT QTY RATE AMOUNT

57,01 Road marking paint:

(a) White lines (broken or unbroken):

(i) 100mm Wide km Rate only


-
(iv) 500mm Wide km Rate only
-
(b) Yellow lines (broken or unbroken, 150mm wide) km Rate only
-
(d) White lettering and symbols m² Rate only
-
(e) Yellow lettering and symbols m² Rate only
-
(f) Transverse lines, painted island and arrestor bed markings (any colour) m² Rate only

57,04 Variations in rate of application:

(a) White paint ℓ Rate only

(b) Yellow paint ℓ Rate only

57,05 Roadstuds ceramic with shank (SANS approved) No Rate only

B57.06 Setting out and premarking the lines


(excluding traffic-island markings, lettering
and symbols) km Rate only
-
57,07 Re-estabilishing the painting unit at the end of the maintenance period Lump Sum Rate only
-
57,08 Removal of existing, temporary or permanent road markings by: -
-
(a) Sandblasting m² Rate only

SECTION TOTAL CARRIED FORWARD TO SUMMARY