You are on page 1of 2

CHAPTER 8- RESOURCE ALLOCATION Longer than expected durations, frequently Accept Perceived Quality

Project Crashing: Shortening(expediting) some missed deadlines, Increased costs more than -Do nothing due to below threshold or cost of is the quality attributed to a good or service
activities within a project to reduce overall project budget, substantially less deliverables than response based on in direct
completion time originally promised -If risk occur use backup plans or contingency measures.
Project Costs: -Goldratt’s focus in the Critical Chain is on a single Opportunities:
Direct Costs: Labor, materials, other costs related to project with multiple demands on a scarce resource Exploit:
activities -The logic extends to the multiproject case without -Eliminate uncertainty that may hinder
Indirect Costs: administration, depreciation, alteration opportunity to be realized
financial, other overhead costs that can be avoided Accept:
by reducing total project time CHAPTER 9- PROJECT RISK MANAGEMENT -Do nothing due to below threshold or
Penalty Costs: if project extends beyond some Project Risk: uncertain event, has a cost of response
specific date positive/negative effect on 1 project objective -If risks occurs use backup plans or
Cost to Crash contingency
Normal Time (NT): time necessary to complete an Share:
activity under normal conditions -Team up w. 3rd party who’s able to
Normal Cost (NC): activity cost associated w/ realize an opportunity and reap the
normal time benefit
Crash Time (CT): shortest time to complete an Enhance
activity -Increase probability and/or impact by
Crash Cost (CC): activity cost associated with the identifying and maximizing key drivers
crash of the risk to ensure it occurs
Resource Leveling Crystal Ball
-When the project is large and contains many Forecast Cells: cells that contain
resource over-allocations, resource leveling must be outcomes we are interested in
accomplished: -a cell that contains a parameter we
-A technique in which start and finish dates are Risk Management(RM) in Sub-processes make assumptions about is NOT
adjusted based on resource constraints with the Risk Management Planning: plan for RM activities called a forecast cell
goal of balancing demand for resources with the Risk Identification: finding those risks that will affect -Simulation: circumvent the
available supply project assumption of statistical
-Purpose: create a smoother distribution of Qualitative Risk Analysis: evaluating the seriousness independence by including the activity
resource usage of risk& likelihood it will affect project or path
-Resource leveling aims to min. the period-by- Risk Response Planning; ways to reduce negative
period variations in resource loading by shifting impact CHAPTER 10- PROJECT QUALITY
tasks within their slack allowances Risk Monitoring&Control: maintaining records MANAGEMENT
-Leveling is done by delaying or splitting tasks until &evaluating sub-processes to improve RM What is Quality?
the resources assigned to them are no longer over- Risk Management Planning Conformance to requirements:
allocated -Method to carry out step 2-5 The project’s processes and products
Allocating Scare Resources to Several Projects -Ensure necessary resources can be applied in meet written specifications
When the allocating scarce resources is extending timely/organized manner Fitness for use:
to where several projects are being carried out -Continuous Process: factors that cause uncertainty A product can be used as it was
concurrently, the size and complexity of the change over time intended. Fitness may be determined by
-Organizational Problem: planning on dealing the client, users or other key
problem increase
w/uncertainty stakeholders.
With several projects, we can link them together
Risk Identification- Failure Mode&Effect Analysis Eight Dimensions of Product Quality
with pseudoactivites Performance: refers to a product's
-Pseudoactivities have duration but require no (FEMA)
-Structured to help identify, prioritize & manage risk primary operating characteristics. This
resources dimension of quality involves measurable
-The use of pseudoactivites allows a set of projects 6 Steps:
attributes. Example: A car’s fuel
to be linked and dealt with as though it were a 1.List ways project might fail
economy, acceleration rate, top speed,
single project 2.List consequences and evaluate its severity
interior volume, seating capacity,
-Individual projects are interrelated by 3.List cause and likelihood etc. Example: Having the opinion that cars made in
specifying predecessor/successor 4.Estimate the ability to detect each failure Features Germany or Japan have higher quality
relationships, appear to be parts of 1 project 5. Calculate the Risk Priority # (RPN) are additional characteristics that enhance the Quality Concepts:
-Problem a PM faces: choosing between 6.Sort potential failures by their risk priority # appeal of the product or service to the user. 1.Zero Defects: is a management tool
different outcomes that result from diff. Delphi Technique Example: Availability of heated steering, AC,
-Group decision process about the likelihood that aimed at the reduction of defects through
priority rules, and leveling rule power brakes,
certain events will occur alloy wheels, GPS mapping, etc. prevention. Directed at motivating people
Criteria of Priority Rules
-Goal: obtain reliable response to problem from to prevent mistakes by developing a
There are many measurable criteria to help select a
experts Reliability constant and conscious desire to do their
priority rule
-Don’t interact with each other, responses are is the likelihood that a product will not fail within job right the first time.
1.Schedule Slippage: Amount project or set of a specific time period. This is a key element for
anonymous Zero Defects= no tolerance for errors
projects delayed by application of a leveling rule & users who need the product to work without fail.
-Questionnaires result in median answer, process within system
The PM must trade off penalty cost or displeasure Example: The reliability of cars is often
guides the group to a consensus 6 Sigma: data driven
of clients against the cost of adding resources measured by how many problems the owner
RISK SCORE= Probability x Impact approach&methodlogy for eliminating
2.Resource utilization: extent to which resources has with
are over or underworked a particular product and how severe the defects
3.In-process inventory: amount of unfinished work problems are. 2.Quality Throughout impact in- Product,
in the system Conformance process, and organization. Requires TQM,
is the precision with which the product or
-The minimum slack rule is probably the best which all members participate in improving
service meets the
overall priority rule according to research. the process, product, service, culture
specified standards. Example: Emission control
-It gives best combination of minimum project Risk Response Strategies- Threats in Canada is a predetermined standard that Quality Planning
slippage, minimum resource idle time, and Avoid: needs to be implemented regardless of where -Process for identifying quality standards and
minimum in process inventory. -Eliminate a specific threat, usually by eliminating the car was manufactured and bough requirements for overall project and for tracking,
Problems with Traditional Project Management its causes Durability monitoring and managing the expectations of
-When planning, estimates for task durations are -Change project plan to eliminate the risk condition measures the length of a product’s life.
required. or protect project objectives from the impact When the product can be
-To increase the probability and high confidence repaired, estimating durability is more
Example: remove new technology from the project
complicated.
that the task completing on time consider scope
Example: Durability of tires in terms of
additional safety time beyond work content time Transfer: kilometres until they require replacement
required to be embedded within the task duration Transfer: the impact of a risk and ownership of its Serviceability
-The more safety in a task the more there is a response to a third party is the speed with which the product can
tendency to behave in the following ways: -Gives another party responsibility, but doesn’t be put into service when it breaks down,
-Not starting the task until the last moment eliminate it as well as the competence and the
(Student Syndrome) -Use of insurance, performance bonds, warranties, behavior of the service person.
-Delaying (or pacing) completion of the task guarantees Example: How accessible are battery,
(Parkinson’s Law) -Use of a contract spark plugs, and other easily
As a result, the safety which was included at the Mitigate maintainable parts
-Reduce the consequences of a risk event by Aesthetics planned quality.
planning stage is wasted and tasks over run
reducing its probability and/or its impact to an is the subjective dimension indicating the kind -Inputs for quality planning include:
Goldratt’s Critical Chain of response a user has to a product. It ISO 9000- fundamentals of quality management
acceptable threshold
-CPM was created by Eli Goldratt in response to by represents the individual’s personal preference. systems
-Taking early action is more effective than repair
poor performance manifested in: Example: Style and look of the exterior and ISO 9002- model for quality assurance in
the consequences if risk occurred Example: add 2
interior of cars; overall image production, installation and servicing
weeks to schedule to allow for permit approval
ISO 9003- for quality assurance in final inspection -Project Procurement Management is typically CHAPTER 12: EVALUATING THE PROJECT &
& testing discussed from the perspective of the project TERMINATION
ISO 9004- emphasis quality assurance team as the buyer in the buyer-seller relationship, Evaluation Criteria
Scope document, requirement from stakeholders, project team could also be selling project -There are many different measures that may be
risk register, project schedule deliverables to an external client applied in a project
Quality Planning- Tools and Techniques Tendering: make a formal written offer for a fixed evaluation:
price 1.Criteria set by senior management for future
Procurement Categories: not all projects are planning and decisions
created equal, some are big or small, carry high/low 2.Original criteria for selecting and funding project
risks Fixed Price Incentive Fee (FPIF) such as
Major Complexity Procurement -Profitability
Major (high risk) complexity procurement: -Acquiring new competencies for the organization
purchasing something which doesn’t exist, tailored -Getting a foothold in a new market segment
to projects unique specifications. -Any special reasons for selection should also play a
-Represent high risks, to projects technical, quality, role:
costs, schedule -Was this project someone’s sacred cow?
-Require creation of something new by seller -Did a scoring model identify quantitative and
Minor Complexity Procurement qualitative reasons to select this project?
Minor (low risk) complexity procurements: 3.Success to date: evaluating four important
represent large monetary values, but the dimensions of project success
commodities exit and will conform to existing a. Efficiency in meeting the budget and schedule
sellers Fixed Price w/ Economic Price Adjustment (FP- b. Customer impact/satisfaction
Early Identification: of items is important to EPA) c. Business/direct success
properly schedule lead-times for each item and -The level of commercial success for external
budget necessary funds for it. EXAMPLE: purchased projects
labor, services, raw materials, supplies equip, -Reduced throughput time for internal projects
services. d. Future Potential
Procurement Risks: -More difficult to assess
1.Risks associated with technical, quality, or -Potential to develop a new technology, or
performance presence in a new market
-Possibility that the item being developed or 4.Project’s contribution to the organization’s goals
procured will not perform to the levels needed by and objectives
the project 5.Project’s contribution to the objectives of project
2.Risks with Schedule Performance team members
-Possibility that critical item needed by project 2. Cost Plus Fixed Fee (CPFF) Project Auditing
will not be available in the time-frame needed -Special type of evaluation is a formal audit
-Technical risks may also cause adverse impact on -Requires thorough examination of management of
Cost of Quality: total cost of all efforts to achieve project schedule a project: methodology and procedures, records,
product quality 3.Risks with cost performance properties, inventories, budgets, expenditures and
Bad Costs: Cost of Internal & External Failure -Possibility that the costs of the critical items will progress
-Cost incurred by project before a product or exceed that which had been estimated at budgeted Timing and Value of Project Audits
service reaches client Project Procurement Management Processes -Timing of audits depends on its purpose
-Cost of repairs, rework, investigation, planning 1.Procurement Planning- what to procure & when -Project State: feasibility study->very useful, esp. in
-Costs incurred to rectify product or service after it 2. Solicitation Planning: documenting project technical audit
has reached or is used by client/customer requirements & identifying potential sources -Project State: initiation->very useful, takes place
-Replacement/repair costs, warranty claims and 3. Solicitation: obtaining quotations, bids, offers, or early
cost, cost of lost customers/opportunity, legal costs proposals Cost Plus Incentive Fee (CPIF) -Project State: Preliminary plan/schedule budget
4. Source Selection: choosing from among potential -Project State: Master schedule->less useful,
Good Costs: Cost of Appraisal sellers flexibility limited
-Costs associated w/ investigative effort to asses 5. Contract Administration: managing relationship -Evaluation of date by project team: marginally
and uncover quality issues related to the product w/ seller used, monitor/control
Cost of internal;/external audits, investigations, 6. Contract Close-out: Completion and settlement -Post State: Post-Project-> more/ less useful,
inspections, testing & test equip., models, of the contract depends on applicability
prototypes, mock-ups etc. Inputs to Procurement Planning Audit Report
Good Costs: Cost of Prevention 1.Intro, 2. Current Status, 3. Future Project Status,
-Cost associated with proactive measures to ensure 4. Critical Management Issues, 5. Risk Analysis and
conformance w/quality standards: Risk Management, 6. Final comments
-Cost of quality consultants, cost of quality Project Termination
management systems, cost of validation of design 3. Time & Materials Contracts -Referred to as Project Closure by PMBOK
and planning, training costs, maintenance -Project Closure Phase- last phase of Project Life
Quality Assurance: process used to evaluate cycle, completion of all Project objectives and
project performance periodically and ensure that acceptance of end product by client
project will satisfy quality standards -Project closure ensures that: outcomes match
-Inputs for quality assurance are quality planning, stated goals of project, client is happy w/results,
work performance info, quality control critical knowledge captured, team feel completion,
measurements and quality metrics project resources are released for new projects
-Outputs of the process are change requests, When to Terminate a Project
project management plan updates, project -Project met goals, customer satisfaction and use,
document updates contributing to firm’s future, inefficient support
4. Guaranteed Maximum Price (GMP) from senior manager (failure factor)
CHAPTER 11- PROCUREMENT & CONTRACTS Types of Project Termination:
Outsourcing Pros vs. Cons 1.Project Extinction, 2. Termination-by addition,
Pros: Termination by integration, Termination by
-Delivery failure or poor service by existing source starvation
-Allow client organization to focus on its core Project Final Report: history of project & lessons
THE CONTRACT
business learned
Contract= Offer + Acceptance+ Consideration
-Gain access to world class capabilities 1.Project performance, 2. Administrative
Include: technical/management/commercial
-Reduced capital requirements and staff costs performance, 3. Organizational Structure, 4. Project
requirements, specific description of
-Pressure to reduce costs Teamwork, 5. Project Management Technique
technical/management programs,
Cons:
proposed prices
-Long term commitment
Contract Type Selection Guaranteed Maximum Price (GMP) Incentive Fee
-Communication with suppliers
-Dependence on suppliers
-Lack of control over supplier & quality of work

Procurement: act of finding, acquiring, buying


goods, services or works from an external source,
often via a tendering or competitive bidding
process.
Project Procurement Management: process
required to acquire g&s, attain project scope, from
outside the performing organization
1.Firm Fixed Price (FFP)

You might also like