Professional Documents
Culture Documents
Vol. 15/No. 2
1996
Case Study
125
Journal of Manufacturing Systems
Vol.15/No.2
1996
The pipe shop can produce pipes in all size ranges and obsolete machines. The pipe shop layout is
in both ferrous and. nonferrous materials for the shown in Figure 2.
shipyard; however, its production rate of 150 pipes From the executive manager's point of view, the
per day cannot meet the requirements of the ship- situation is clear: Is it possible to increase the pro-
yard, and overtime or subcontracting is necessary, duction rate of the pipe shop with a smaller work-
resulting in increases in cost. A flowchart, shown in force? Two types of approaches--kaizen and
Figure 1, demonstrates the manufacturing process of automation--were proposed by consultants from
the pipe shop. Williams and Oglesby6 present a more Japanese shipyards and Western countries' ship-
detailed description of the piping design, fabrica- yards, respectively. The concepts and practices of
tion, and installation in commercial shipbuilding these two approaches are briefly explained in the
practices. following sections.
There are 67 workers currently in the pipe shop,
and the production rate per worker per day is much Automation Approach
lower at competitive companies. Among the reasons Automation is one of the most competitive tools
for the low labor productivity, based on the observa- available to manufacturers. A company may take
tions of the managers, are inadequate plant layout advantage of the new technologies so that its manu-
facturing process and operations can outperform
those of other companies. The contents of automa-
tion technologies involve not only computer-aided
Incomingrawpipes I
design (CAD), computer-aided manufacturing
(CAM), robotics, computer numerical control
(CNC), and many hardware/software products, but
Cutting also include concepts and techniques such as design
t
126
Journal q/ Mamf/acturing System~'
gol. 15/No. 2
1996
Inspected pipes
Welding Grinding
Cutting zone zone zone
Bending zone
Figure 2
Original Layout of Pipe Shop
reduce the number of fixture changes during the Consultants from Japan strongly discouraged the
bending process. managers of CSBC from adopting the automation
The capacity of the welding zone is inadequate, approach. They felt that the productivity of the pipe
and many pipes are waiting to be welded on the shop could be further improved using kaizen. Some
shop floor. Automated welding machines should examples proposed by the Japanese consultants are
be purchased in the near future. as follows:
127
Journal of Manufacturing Systems
Vol. 15/No. 2
1996
Unified Framework
Advice from different approaches sometimes
Envision future of company
causes confusion for managers regarding the priori-
ty of the actions and the subsequent performance
measurement. A unified framework depicted in
I L
Figure 3 demonstrates how the kaizen approach and Organizeteam and set goal [
128
Journal qf Manufacturmg Systems
Vol. 15/No. 2
1996
one of the concepts from the kaizen team result- Standardize the new process. Before beginning a
ed in a dramatic redesign of the manufacturing new process reengineering project, it is neces-
process. This concept provides an opportunity sary to standardize the new process if the orga-
for performance breakthrough, which project nization tries to keep the performance as good as
team decides to work on. expected. Availability of qualified human
• Design the newprocess. With input from previous resources, adequate equipment, and related doc-
stages, the project team can design a new process. uments are all important elements in standardiz-
Persons involved in process reengineering should ing the new process. In general, educating and
constantly question which processes or tasks training personnel in the new process environ-
could be shut down, reengineered, or improved. ment is critical to maintain the same, if not bet-
In the case study, the project team adopted the ter, performance.
idea of "bending pipes after pipes welded"
instead of the existing "welding pipes after pipes There are many books and papers that discuss
bent" concept in redesigning the manufacturing process reengineering. For example, Hammer and
processes of the pipe shop. The team members Champy ~° and Roberts" are good sources to use to
have discussed the new design from different gain a better understanding of how to undertake a
aspects--management (impact of human radical reinvention of the process. Because the new
resource), equipment (feasibility of hardware and process is so dramatically different from the original
software), and facilities (accompanied layout of process, it is common practice that top managers
the new manufacturing process) to refine the new may feel that it is too risky to perform such a "revo-
manufacturing process. For example, managers lutionary" change. During the interim of the case
from the design division had calculated the per- project, top managers hesitated regarding imple-
centage of pipes that could fit well in the new mentation of the new process, and project team
design process, based on drawings of some exist- members had difficulties agreeing on the possible
ing ships, and convinced every team member that performance improvement. With the use of an ani-
the new concept was feasible. mated simulation model, the new layout could be
• Implement the n e w p r o c e s s and modify the infra- justified. The next section discusses the simulation
structure. This stage is regarding the implemen- model development.
tation of the new process. Note that the reengi-
neered process should be fine-tuned as problems Simulation Model
surface before and after installation. There is Simulation is well recognized as a very useful
always a tradeoff in the implementation stage technique for the design and evaluation of complex
with cost, technology, and other issues. That is manufacturing facilities. !~ As computer hardware
why the framework proposed has an iterative technology keeps advancing and more animated
nature. During the case study period, the project simulation software becomes commercially avail-
team found that the animated simulation model, able, several studies have been conducted regarding
which will be discussed in the following section, the visual interactive simulation of a manufacturing
is an important tool for effective communication system during the past decade.~3,14These studies, in
among the team members and for the prediction general, have shown that the inclusion of animation
of possible bottlenecks and expected perfor- as a simulation tool can enhance the presentation to
mance of the new process. users and improve the communication between man-
• Measure the performance. Finally, one must agers and system programmers. With the addition of
determine the level of success of the reengineer- interactive control ability, users can halt the simula-
ing project in terms of the goal set in the previ- tion experiment at any moment to view the statistics
ous stage. As shown in many reports, an and/or change some parameters; insights into the
improvement of 50-60% in cost and productivi- system's behavior are then understood.
ty is a realistic objective. 9 A detailed discussion The procedure to develop a visual interactive sim-
regarding the performance of the new process is ulation model, accompanied with the practices in the
shown in the following section. case project, is shown as follows:
129
Journal of Manufacturing Systems
Vol. 15/No. 2
1996
• Define the goal. A good simulation model is one was also a necessary input of the software to
that covers only the system of interest and can show how the parts move during the manufac-
provide answers for managers. An accurate def- turing process in the plant. Figure 4 shows a
inition of the goal is always required. The major revised plant layout input in the computer.
concern of this project was the estimated pro- Verification and validation. The computer simu-
duction rate and the necessary number of work- lation model needs to be verified if it is to work
ers on the shop floor for both the existing and as intended and reflect the operation of the real
new manufacturing process environment. The system. An animated simulation model is much
time to complete the simulation experiments easier to verify and validate because users can
also had to be as short as possible. monitor the results of each activity on the
• Collect and input data. Sufficient and correct screen. The output generated from the simula-
data must be available to formulate a simulation tion model, based on the existing process, pro-
model and to execute the computer experiments vides a benchmark to compare its "reality."
thereafter. Information such as demands, routing Results and analysis. Output, such as the aver-
files of the parts, processing time of the parts, age production rate or the utilization of each
moving time from location to location, and so on workcenter, can easily be found and collected by
is usually required. Traditional time and motion simulation packages. Users can also experiment
studies and statistical analysis were conducted in with alternative layouts to improve the perfor-
this project to find the necessary information. mance of the system. The project team used sim-
Performance data from the new facilities was ulation as a communication channel to examine
collected from vendors. the possible results of using different operating
• Draw layout andpartflow diagram. For an ani- parameters in the job shop.
mated simulation model, it is necessary to draw
the layout for the background during the execu- In this study, Promodel PC version 5.0 is selected
tion of the simulation model. During the project, as the simulation software package) 5 This package
the size of the pipe shop and the position of each provides an easy input/output interface, dynamic
machine were measured. Layouts for the new graphics presentation ability, and various analysis
process and for the existing process of manufac- tools at an affordable price. The simulation models
turing pipes were drawn. A part flow diagram were built and executed on an IBM-compatible 486
f Cuttinroom
g )
130
Journal qf Manu[hcturing Systems
Vol. 15/No. 2
1996
PC. Development of a simulation model for the pro- of this finding is that there is no need to purchase a
ject, including debug, took less than two weeks; new overhead crane, although this had been suggest-
however, it took more than three months to collect ed during the automation evaluation.
and verify the necessary input data. An interesting observation is that the managers
feel that the workers will have more pride and
Results and Analysis responsibility in the proposed new manufacturing
Two types of analyses, static and dynamic, were process. That is, after related activities are designed
conducted. Static analysis is well documented in and integrated into each workcenter in the new lay-
many plant layout textbooks. One can calculate the out, the job of each worker is enriched. Workers are
moving distance of a pipe during the production now involved in a larger portion of the manufactur-
process. The procedure is simply to put the layout on ing process and should be more motivated to
the table and go through the manufacturing process improve their own working environment. Therefore,
flowchart and part flow diagram to determine how a quality and productivity could be improved due to
pipe is manufactured in the factory and how much the human factor.
moving distance is required. For example, it was Because the pipe shop is a division of CSBC, a
found that the moving distance of a large straight nationally owned company, all the investments pro-
pipe could be reduced from 228.5 meters in the posed were presented to the government for
existing layout to 136 meters in the new layout. approval, which was granted. Currently, the pipe
Various similar calculations were done, and they all shop has started the purchasing process.
illustrated that the new layout was promising.
Compared to the static analysis, simulation then is Conclusions and Future Research
considered dynamic analysis. Most simulation mod- Although the automation approach and the kaizen
els approach the manufacturing system dynamically approach are quite different, this research shows that
so that arrival rates of demand and equipment uti- it is possible to combine both approaches for process
lization, for example, are all input as dynamic vari- reengineering. Based on the empirical results from
ables. Users examine the state of the simulation the pipe shop in the case study, the improvement is
model evolving over simulated time, such as watch- dramatic. The following points summarize the infor-
ing a conveyor system in a factory. mation resulting from this project:
Assuming the pipe shop operates 8 hours a day
and 260 days a year, the output of the experiments on 1. Think about the process instead of products and
the simulation model depicts that the average pro- departments.
duction rate can be increased from 150 pipes daily to 2. The proposed framework is effective and seems
195 pipes daily after the process is redesigned. The to be general enough to be applied to other types
number of workers required in the proposed layout of process redesign.
can be reduced from 67 to 60 workers. The labor pro- 3. A cross-department team is required, and good
ductivity can therefore increase from 2.24 (150/67) communication among team members is neces-
to 3.25 (195/60)--a nearly 50% improvement in pro- sary.
ductivity. This dramatic improvement is due in part to 4. Simulation is very important in process reengi-
the streamlined manufacturing process (kaizen neering.
approach) and to the use of some new facilities 5. In redesigning a manufacturing process, human
(automation approach). With the managers' knowl- factors should be carefully considered.
edge that 10 persons are planning to retire in the next 6. Improvement performance in process reengi-
two years, the proposed layout can also reduce the neering can be very dramatic.
pressure of recruiting workers.
Another important simulation output shows that As discussed above, use of a simulation technique
use of the overhead cranes can be reduced from 96 is important in process reengineering. Although
to 70 times daily in the new manufacturing process most simulation packages have a much better inter-
environment. This result is consistent with the top face compared to that used in the past decade, man-
manager's ideal plant layout vision. The implication agers and engineers in the case pipe shop felt that
131
Journal of Manufacturing Systems
Vol. 15/No. 2
1996
132