BILL OF QUANTITY MECHANICAL & PIPING WORKS FL1 UPGRADE

# PACKAGE 2 : EVAPORATOR, ECRP, METHANOL

NO DESCRIPTION UNIT Q'TY REMARK

E TANK (Fabrication & Erection)


1 CS Kg 45,100.0
2 SS 304 Kg 416,750.0
3 SS 316 Kg -
4 Duplex Kg -
5 Non Metalic Kg -
6 Steel Structure (Roofing, Ladder & Platform) Kg 137,950.0
7 CS (Assembling & Erection, material from vendor in roll section) Kg -
8 Duplex (Assembling & Erection, material from vendor in roll section) Kg 130,000.0

Subtotal E 729,800.0