Professional Documents
Culture Documents
HARVEY W. GERSHMAN
National Center for Resource Recovery, Inc. (NCRR)
Washington, D.C.
1
commitments are oftentimes open-ended and not case when a bargain can be struck. Put differently,
guaranteed to "take-or-pay," even if produced to an undertaking to produce and utilize RDF would
the agreed upon specification. This is because of then be mutually beneficial.
uncertainty about its long run suitability as a fuel.
Even so, many jurisdictions are quite seriously DESCR IPT ION OF THE FACIL ITY
looking at the prospects and constructing plants to
produce RDF. [9] The experience with full-scope A "full-scope" facility designed to process ac
materials recovery is more limited. cording to the flowsheet depicted in Figure I, is
Materials revenues can be shown in two ways. used as the example. The characteristics of the full
First, at the current market levels, determined by scope processing is shown in Table L The different
calculating the pricing structure that is tied to types of output products to be recovered are listed
varying commodity quotations. Secondly, certain in Table 11. The capital and gross operating cost
materials revenues can be expressed in terms of estimates (August 1974 dollars) are listed in Table
their minimum floor price level. Floor prices III. These estimates represent considerable pre
become important in determining a "worst-case" liminary engineering detail based on work per
materials revenue level. formed in support of a New Orleans resource
The approach discussed here takes the view recovery program. [I I] Expected mate rials reve
point that an RDF energy product is the chosen nues for the various output materials products are
.
energy option. This certainly does not exclude provided in Table IV. All of these assumptions,
other energy options such as steam, pyrolysis gas cost estimates and revenue projections are in a
or oil, or electricity from being considered. But, for 1974 timeframe. Proper updating and adjustment
the purposes of presentation, the RDF energy out would be required to bring these projections to
put is used. Along with the RDF product, other future timeframes.
materials products are also recovered. Certain The facility produces RDF (57 percent by
materials products may not be applicable to a given weight) [12] which is hauled via transfer trailers to
•
location because of such factors as (a) variability in a utility user 20 miles away. Waste newspapers and
the waste stream, (b) availability of markets, or corrugated are handpicked prior to processing. The
(c) capital budgeting constraints. remainder of the solid waste (36.6 percent by
H can be said that resource recovery will have a weight), i.e., the shredded, air classified heavy
good chance of being implemented where its costs fraction, is magnetically separated for recovering
will be at least equal to or less than present or im ferrous metals (9.65 percent by weight). An air
mediate future costs for the disposal alternative. knife divides the ferrous fraction into two prod ucts
With this in mind and the fact that materials reve - light and heavy. Dump trailers transport these
nues can be predicted with a higher degree of ferrous fractions to market. A rising-current sepa
certainty, it becomes necessary to determine what rator removes heavy organics while concentrating
revenues will be required from the sale of the RDF the noncombustible materials. A two-stage heavy
product in order that the projected economics can media system next concentrates a mixed nonferrous
at least be the same as the alternative disposal prac fraction (0.27 percent by weight) and a glass and
tice. The use of such a technique developed here aluminum rich stream. After the aluminum has
will assist the decision-maker in evaluating the eco been separated by the electrostatic separators, flint
nomic feasibility of the proposed project. and color-mixed glass cullet (6.3 percent by weight)
This approach provides the decision-maker on are separated by a color-sorting system. Glass fines
the processing side a manner in which to establish (2.5 percent by weight) are recovered from the
his minimum RDF floor price. The RDF user - in various screening underflows by a froth flotation
most cases the local utility - will probably do a circuit. These recovered materials are transported
similar calculation taking into account the cost of to market via dump trailers. The remaining residue
an equivalent amount of fossil fuel the RDF is to (I7 percent by weight) is transported via dump
replace minus the incremental costs of firing RDF. trailer to adjacent landfill operations.
[10] Neddless to say, such values will vary and
need to be determined on a site-specific basis. Hope ANALYSIS APPROACH
fully, the "bargain" struck will be above the pro
ducer's calculated minimum and below the user's This analysis determines the minimum value
calculated maximum. This is likely to be the only Refuse-Derived Fuel (RDF) would need to take in
2
TAB LE I. C HARACTERIST ICS OF FU L L-SCOPE FACI LITY
Input: Primarily raw municipal solid waste and some bulky waste
as well as commercial.
Paper 43.8%
Ferrous 10.2%
Aluminum 0.7%
Other Nonferrous 0.3%
Glass 10.5%
Yard Waste 9.7%
,Food Wast
. e 9.9%
Rags and ''lood 5.1% 1 ton = .9072 Mg
Rock and Ash 9.8% 1 mile -
- 1. 069 km
100.0%
3
TABLE I I. OUTPUT PR ODUCTS F OR T HE RECOVERY FAC I L IT Y
waste Corrugated 3 .. 20 .
Aluminum 0.50
RESIDUE 17.00
TOTAL 100.00
4
TABLE III. CAPITAL AND OPERAT I NG COSTS F OR T HE REC O VER Y
FAC I L IT Y
Capital cost*
Processing $ 6,659,000
Materials and Residue
Transportation 156,000
RDF Transportation 125,000
$ 6,940,000
Operating Cost
$ 2,584,000
,
Processing
Materials and Residue
Transportation 358,000
RDF Transportation 228,000
$ 3,170,000
Contingency 10.0%
Total 10.0% •
5
'!
TABLE IV, R E VE NUES FROM FULL SCOPE MATER IA LS REC O VERY FAC I L ITY
•
I
Percentaqe Dec. 2 Revenue Floor Revenue
Mat erials Recover ed Decembe r 2 Price Floor Price ($ r in ut ton) ($ er in ut ton"
Liqht Ferrous 8.80 in excess of $20/lonq ton $4.32 $1. 57
$55/lonq ton2
-
Heavy Ferrous 0.85 in excess of None $ .55
$72/lonq ton
j
,
Other Nonferrous 4 -
0.27 in excess of None $ .95
,
$350/ton I
,
I
I
Flint Glass 2.50 $ 1 6/to n : $16/ton I $ .40 $ .40
•
I ,
0\ Color-Mixed
I
Glass Finas 2.80 $lS/ton $15/ton $ .42 $ .42
, ,
Waste Corruqated 3.20 $20/ton '$20/ton $ .64 $ .64
!
Waste News 3.20
I,
$lO/ton $lO/ton
I $ .32 $ .32
l
These are qross revenues, not including transportation.
21 Long Ton equals 2,240 lbs.
3
The aluminum bid price increases each year from in excess of $300/ton in the first
year to in excess of $400/ton in the fifth year.
48&sis for revenues only. Aotual output is 0.35% which inclUdes non-metallics, upon
which no revenue is received.
Item ($/year)
lFrom Table IV
1 lb. = .4536 kg
1 ton = .9072 kg
1 BTU = 1. 055 kJ
7
REFUSE
Fines Belt
Impactor
Surge Bin (2.3%) Bucket Elevators (2)
Air Classifiers and Cyclones (2 sets) IDUE--. Screen
Dual Push Pits (2) Pump and Pump Tank
RDF Transfer Packers (2) Hydrocyclones
Transfer Trailers (5) Wash Tank
Tractors (4) 57% Conditioning Tank
00 Material Reagent Feeder
Flotation Cells
HEAVY Thickener
MATERIAL Tailings Tank (2.8%)
(34.3%) Water Treatment & Lagoon S FINE�_�
Tailings Pond (5.2%)
Glass Fines Silo IDUE- ...
-3/16 inch
1 inch = 2.54 cm Fines
(7.1%)
+3/16 inch Nonferrous & Mixed Glass (7.7)
650 Ton-Per-Day
Full-Scope
Sanitary Landfill Resource Recovery
$ per year
Gross Operating 3,170,000
Materials Revenues
($9.67 per input ton) (1,961,000)
Landfill Expenses
($4.00 per ton x 17 percent) 138,000
Operating Costs:
RDF Revenue Needed ($0.46
$4. 00 per-ton x 650 toris per-million BTU x 10 million
per-day x 312 days-per BTU per-ton RDF, 57 percent
year output) (536,000)
1 ton - • 9072 Mg
1 BTU - 1. 055 kJ
9
order that a facility be competitive with alternative The equation then means simply that ROF
costs for disposal - here a landfill example is used sales must produce a certain revenue if the sited
as the alternative. This value for RDF is called here facility is to be competitive with the alternative
the RDF "Indifference Value" (IV). [13] The disposal charge.
analysis is carried out for a facility processing 650 In actual practice and as mentioned above, the
tons-per-day (589.68 Mg-per-day) and recovering equation is solved for "0" the RDF revenue
-
RDF plus other materials. A credit of $4.00 per needed to produce the same annual cost as for land
,
ton ($4.41 per-Mg) is assigned for refuse diverted fill. This is done by transposing "0" to the right side
from the landfill operations. This is discussed fur of the equation and moving "E".to the' left side.
ther later on. The RDF revenues needed can be "E" is the target net operating cost for processing,
deterlllir.ed by the following equation: while "C" is the cost of land filling the residual from
the recovery facility. Merged together one con
A -
-
B + C D = E, where,
- structs a variable "F" [16] which is the credit
A -
-
Gross operating cost; obtained from not having to landfill the recovered
B -
-
Expected materials revenues; products. Hence, the equation becomes:
C -
-
Landfill cost for residue disposal;
. O=A-B-F
D -
-
Revenue needed from RDF;
E -
-
Target net operating cost; "0" is the product of the exchange price (IV)
times the energy content in the RDF delivered to
Values for "A" come from the operating cost the user, multiplied times the quantity of RDF
for the particular facility configuration as given in produced and used. This is the approach used to
Table III. "B" comes from the expected materials compute the "IV" values.
revenue described in Table IV while "c" is assumed A somewhat uncertain area in determining net
to be $4.00 per-ton ($4.41 per-Mg) multiplied by costs is the credit used for "F" in the equation
the quantity of residue annually landfilled. "D" is given above. The figure of $4.00 was assigned for
calculated so that "E" equals $4.00 per-ton ($4.41 refuse diverted from landfill operations. This has
per-Mg) times the total annual facility throughput, been used only as an example. This value should be
such that the target net operating cost for the determined on a case-by-case basis and evaluated
facility is equivalent to the operating cost for land in such a way that actual savings attributed to not
filling the entire facility input directly. Table VI il having to landfill portions of the facility input are
lustrates this concept from a budgetary perspective. estimated. If the processing facility were added to
On the right side of Table VI, gross operating costs an existing landfill operation, marginal costs for
of the facility are shown as $3,170,000 annually. not landfilling the recovered products should be
December2, 1974 exchange prices are assumed for forecasted. Additionally, one may want to consider
the sale of recovered materials at $9.67 per ton the cost benefit for extending the life of a landfill.
($10.66 per-Mg), or $1,961,000 annually. An ad This latter factor may be almost impossible to
ditional expense of $138,000 is shown for land calculate.
filling the process residue. The analysis assumes
that 57 percent by weight of the input refuse ANALYSIS AND RESULTS
emerges as RDF. The RDF is assumed to have a
heat value of 5000 BTUs-per-pound (11.63 kJ -per The RDF "IV" 's for the facility have been
g) and a moisture content of27.5 percent. [14] determined for both the December 2, 1974 and
The recovery facility has to bear the cost of its the floor price materials revenue levels (see Table
residue disposal (17 percent of the input) and then V). At the December 2, 1974 materials revenue
sell its RDF. The resulting operating costs come out level, the RDF "IV" is calculated to be $0.46
to be $4.00 per ton ($4.41 per Mg), or on a yearly per-million-BUT's ($.44 per-Gj). When materials
basis, $811,000. This is the same as not having a revenues are at the floor price level, the ROF "IV"
recovery facility and simply landfilling the waste. is $1.26 per-million-BTUs ($1.19 per-Gj).
This is shown on the left. In order to obtain this The outputs of this analysis provide a gauge for
net operating cost of $811,000, RDF would have to judging the feasibility of the processing described.
account for $536,000 annually in revenues, or be These outputs should represent to the municipal
worth approximately $0.46 per-million-BTUs decision-maker target RDF minimum "bargains".
($.44 per-Gj). [15] They say what that facility configuration would
10
need such that the operating budget for disposal RE FERENCES
of the same quantity does not change. An RDF
value above the "IV" will generate benefits to the [ 1] "Resource Recovery Engineering and Economic
annual budget while an RDF value below will Feasibility Study for the 1-95 Complex, Lorton, Virginia,"
bring about operating budget increases. NCRR, 1975, for the Washington Metropolitan Waste
Management Agency.
The "site·specific" RDF value will natually
[2] City of Alexandria, Virginia; Arlington County,
fluctuate. The price the RDF user pays for the Virginia; Washington, District of Columbia; Fairfax
alternative fossil fuel must be taken into account. County, Virginia.
These costs vary significantly geographically. [17] [3] "1-95 Center Markets for Recoverable Resources
The location of the RDF user with respect to the from Mixed Municipal Solid Waste," September 5, 1974
and Draft of No. 1 above, January 7, 1975, NCRR, for
processing facility, the materials recovery revenues,
the Washington Metropolitan Waste Management Agency.
the ability to produce the materials to specification [4) Op.Cit. No. 1,
for the expected revenues, also will bear upon the [5] Materials such as ferrous, aluminum and other
RDF "IV". nonferrous metals; glass cui let and fines; and waste papers.
[6] Op.Cit. No. 3; "EPA/Specifications For
There is roughly a factor of "three" between the
Materials Recovered From Municipal Refuse," Dr. Harvey
December "IV" and the floor price "IV". The
Alter and W, R. Reeves, NCRR, May, 1975; "Solid Waste
higher RDF "IV" at the materials floor price may Resource Recovery Market Survey and Analysis," Black,
in some cases be higher than the "bargain" that Crow and Eidsness, Inc.Study, Altoona, Pennsylvania,
may be obtainable. July, 1975; "Markets and Technology For Recovering
Energy From Solid Waste," EPA by Steven Levy,
A caveat concerning the recovery of glass and
Washington, D. C. 1974.
aluminum is in order. What is presented here re
[7] ASTM E. 38 Resource Recovery Committee,
presents, at best, preliminary process design con Chairman, Dr. Harvey Alter, NCRR.
figuration and cost estimates. Refinement in such [8] Organizations such as the Environmental
numbers will certainly affect the "bottom line" as Protection Agency, United States Bureau of Mines,
to the economic feasibility of their recovery. As Garrett R&D, Raytheon Service, Combustion Power
Company, Black Clawson, and NCRR.
such, the relative values presented here are thought
[9] For example: Chicago, Illinois; Milwaukee,
to be subject to change. Wisconsin; Monroe County, New York; Bridgeport,
Connecticut; and the 1-95 Complex in Lorton, Virginia,
COMMENTS [10) Some of the factors affecting this cost are: the
capital costs of the auxiliary equipment for storing,
handling and firing RDF, operating and maintenance
The analyses and methodology presented use as
costs, economic dispatch penalty, etc.
a working example what is termed a "full-scope" [11] "Cost Analysis for the New Orleans Resou rce
resource recovery system which produces a certain Recovery and Disposal Program," NCRR, 1974; "Bid
type RDF and other materials outputs. Certainly Specifications for Facilities and Operation of the
one must recognize the wide range of system types Resource Recovery and Disposal Program in New
Orleans, Louisiana," NCRR and the City of New
that are being developed, marketed, procured, and
Orleans, 1974; and "Materials Recovery System
operated. Oftentimes these systems have very dif-
• Engineering Feasibility Study," NCRR; December
ferent types of outputs. While this methodology 1972.
can be adapted to serve other types of systems, [ 12] The RDF output (57 percent) has been
naturally one would have to take into account chosen this low in order that higher quality fuel would
be obtained in terms of energy and ash content versus
different ca'pital costs, operating costs, materials
attempting to maximize organic content.
revenues, and alternative'disposal credits. Knowing [ 13] Op. Cit. NO. 1.
these, this methodology could be used to deter [ 14] Based on 380 samples taken November 9, 1973
mine what value the energy product from the sys through December 10, 1974 at the Union Electric
competitive.
As Fired Basis
If the value for the energy value can be deter
mined in the same time frame as the matefials Moisture Ash BTU/Pound (JIg)
all the better. This naturally would be preferable, Average 27.5 18.5 5,006 ( 11,643)
but unfortunately not always attainable. If this Maximum 63.0 53,8 7,593 ( 17,660)
Minimum 3.0 7.6 2,293 ( 5,333)
were the case, the net economics could be deter
mined and be compared directly to the alter [ 15) 650 tons-per-day (589.7 Mg-per-day) x 312 days
native without using an "Indifference" approach. per year x 0.57 RDF output x 10 million BTU-per-ton
11
11.63 k J/g RDF x $0.46 (approximately) per-million per-ton ($3.66 per-Mg) credit.
BTU $.44 (approximately) per-GJ equals $536,000 [17] See "Monthly Fuel Cost and Quality Informa
per year. tion," Federal Power Commission, Washington, D.C.
[16] "F" equals "E" minus "C" or $4.00 per-ton 20426.
($4.41 per-Mg) less 17 percent x $4.00 equals $3.32
Key Words
Cost Estimates
Economic Feasibility
Energy Recovery
Equipment
Full Scope Facility
I ndifference Value
Markets
Materials Recovery
Municipal Solid Waste
Refuse-Derived Fuel
Resource Recovery
12