Professional Documents
Culture Documents
Supplied by:
Consisting of:
Design and Operation Manual
Maintenance Manuals
Proprietary Notice:
PART 1 - INTRODUCTION
TABLE OF CONTENTS
TITLE SECTION
1-0-1
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
1-1-i
CFB BOILER DESIGN AND OPERATION MANUAL
INSTRUCTIONS TO USER
GENERAL
NOTICE
This instruction manual has been prepared to serve as a
guide in operating and maintaining the specific equip-
ment for which it was issued. It is not intended to cover
all possible variations in equipment, nor to provide solu-
tions to specific problems which may arise. Should addi-
tional information be required, Formosa Heavy Industries,
or its field representatives should be contacted.
1-1-1
CFB BOILER DESIGN AND OPERATION MANUAL
INSTRUCTIONS TO USER
USE OF
WARNINGS,
CAUTIONS,
AND NOTES
This publication includes WARNINGS, CAUTIONS and
NOTES at appropriate locations to point out safety relat-
ed or other important information.
1-1-2
CFB BOILER DESIGN OPERATION MANUAL
INSTRUCTIONS TO USER
MANUAL
ORGANIZATION
Design and
Operation
Manual
This manual covers the design and operation of the For-
mosa Heavy Industries manufactured products. When
necessary, reference has been made to the general op-
eration of specific vendor supplied auxiliary equipment.
Information in the Design and Operation Manual is bro-
ken down into sections covering the general systems
which make up the steam generator. Each section is then
divided into tabs covering specific pieces of equipment or
subsystems.
Maintenance
and Vendor
Manual
This manual covers the maintenance of the Formosa
Heavy Industries manufactured products as well as de-
sign, operation and maintenance information supplied by
the vendors for their equipment. Information in this man-
ual is broken down into sections covering the general
systems which make up the steam generator. Each sec-
tion is then divided into tabs covering specific pieces of
equipment or subsystems. Every attempt has been
made to make these sections and tabs correspond to
those in the Design and Operation Manual.
1-1-3
CFB BOILER DESIGN AND OPERATION MANUAL
INSTRUCTIONS TO USER
CONVERSION
FACTORS
The following conversions factors, which generally apply
to the design, operation, and maintenance of steam gen-
erating equipment have been provided as a convenience
to the users of this manual.
Length
1 ft = 0.3048 m 1 m = 3.281 ft
1 in. = 25.4 mm 1 mm = 0.03937 in.
1 µm = 39.37 x 10-6 in.
Area
1 ft2 = 0.0929 m2 1 m2 = 10.76 ft2
Volume
1 ft3 = 0.0283 m3 1 m3 = 35.314 ft3
1 ft3 = 28.32 L 1 L = 0.0351 ft3
1 gal = 3.785 L 1 L = 0.2642 gal
1 in3 =16.39 cm3 1 cm3 = 0.0610 in3
Temperature
t°F = 1.8 t°C + 32 t°C = 5/9 (t°F - 32)
Weight
1 lb = 0.4536 kg 1 kg = 2.2046 lb
1 lb = 4.536 x 10-4 metric ton 1 metric ton = 2204.6 lb
1 U.S. ton = 1 metric ton =
0.9072 metric ton 1.1023 U.S. ton
1-1-4
CFB BOILER DESIGN OPERATION MANUAL
INSTRUCTIONS TO USER
Density
1 lb/ft3 = 16.02 kg/m3 1 kg/m3 = 0.0624 lb/ft3
1 ft3/lb = 0.0624 m3/kg 1 m3/kg = 16.02 ft3/lb
1 ft3/lb = 62.43 L/kg 1 L/kg = 0.01602 ft3/lb
Pressure
1 psi = 0.0703 kg/cm2 1 kg/cm2 = 14.223 psi
1 lb/ft2 = 4.882 kg/m2 1 kg/m2 = 0.2048 lb/ft2
1 atm = 14.696 psi 1 psi = 0.0680 atm
1 atm = 406.8 in. w.g.
1 psi = 6.895 kPa 1 kPa = 0.145 psi
1 MPa = 145 psi
1 in. w.g. = 0.249 kPa 1 kPa = 4.016 in. w.g.
1 in. Hg = 3.377 kPa 1 kPa = 0.296 in. Hg
1 mm Hg = 0.1333 kPa 1 kPa = 7.502 mm Hg
1 psi = 0.0689 bar 1 bar = 14.50 psi
1 bar = 401.4 in. w.g.
Flow Rates
1 lb/hr = 1 metric ton/hr =
4.536 x l0-4 metric tons/hr 2205 lb/hr
1 lb/hr = 0.4536 kg/hr 1 kg/hr = 2.205 lb/hr
1 lb/hr-ft2 = 1 kg/sec-m2 =
0.00136 kg/sec-m2 737 lb/hr-ft2
1 ft3/min = 1 m3/sec =
4.72 x l0-4 m3/sec 2119 ft3/min
1 ft3/sec = 0.0283 m3/sec 1m3/sec = 35.314 ft3/sec
1 gal/min = 0.227 m3/hr 1 m3/hr = 4.40 gal/min
Concentration
1 lb/(106 Btu) = 1 kg/(106 kcal) =
1.8 kg/(106 kcal) 0.556 lb/(106 Btu)
1 grain/ft3 = 2.29 g/m3 1 g/m3 = 0.437 grain/ft3
1-1-5
CFB BOILER DESIGN AND OPERATION MANUAL
INSTRUCTIONS TO USER
Velocity
1 ft/sec = 0.3048 m/sec 1 m/sec = 3.28 ft/sec
1 ft/min = 0.00508 m/sec 1 m/sec = 196.85 ft/min
Heat
1 Btu = 0.252 kcal 1 kcal = 3.97 Btu
1 Btu/lb = 0.556 kcal/kg 1 kcal/kg = 1.80 Btu/lb
1 Btu/lb-°F = 1 kcal/kg-°C 1 kcal/kg-°C = 1 Btu/lb-°F
1 Btu/hr = 0.252 kcal/hr 1 kcal/hr = 3.97 Btu/hr
1 Btu/hr-ft2 = 1 kcal/hr-m2 =
2.712 kcal/hr-m2 0.369 Btu/hr-ft2
1 Btu/hr-ft3 = 1 kcal/hr-m3 =
8.89 kcal/hr-m3 0.112 Btu/hr-ft3
1 Btu/hr-ft2-°F = 1 kcal/hr-m2-°C =
4.89 kcal/hr-m2-°C 0.204 Btu/hr-ft2-°F
1 Btu = 1.055 kJ 1 kJ = 0.948 Btu
1 Btu/lb = 2.326 kJ/kg 1 kJ/kg = 0.430 Btu/lb
1 Btu/lb-°F = 1 kJ/kg-°C =
4.19 kJ/kg-°C 0.239 Btu/lb-°F
1 Btu/hr-ft2 = 3.154 W/m2 1 W/m2 = 0.317 Btu/hr-ft2
1 Btu/hr-ft3 = 1 W/m3 =
10.353 W/m3-ft3 0.0966 Btu/hr-ft3
1 Btu/hr-ft2-°F = 1 W/m2-°C =
5.678 W/m2-°C 0.176 Btu/hr-ft2-°F
Power
1 hp = 0.746 kW 1 kW = 1.341 hp
1 Btu/hr = 0.293 W 1 W = 3.413 Btu/hr
Torque
1 ft-lb = 0.138255 kgf-m 1 kg-m = 7.233011 ft-lb
1 ft-lb = 1.355818 N-m 1 N-m = 0.737562 ft-lb
Miscellaneous
1 ft2/1000 cfm = 1 m2/m3/sec =
0.197 m2/m3/sec 5.08 ft2/1000 cfm
1-1-6
CFB BOILER DESIGN OPERATION MANUAL
INSTRUCTIONS TO USER
AMENDMENT
RECORD
SHEET
The Instruction Manual Amendment Record Sheet locat-
ed in Part 1, Section 3 of the Design and Operation con-
tains a complete listing of those items that have been
added to, or have replaced information in the respective
manual. Upon initial issue of these manuals, the lists
may contain items which were not included because they
were not available at the time of delivery. However, their
delivery is anticipated and appropriate locations have
been provided for them in the manual as indicated in the
index. When they are shipped, the shipment date will be
added to the amendment record sheet, and a new sheet
will accompany the delivery.
1-1-7
CFB BOILER DESIGN AND OPERATION MANUAL
PART 1- INTRODUCTION
1-2-1
CFB BOILER DESIGN AND OPERATION MANUAL
AMENDMENT
RECORD SHEET
The following Instruction Manual Amendment Record Sheet contains
a complete listing of those items that have been added to, or have
replaced information in this manual. Upon initial issue of this manual,
this list may contain items which were not included because they
were not available at the time of delivery. However, their delivery is
anticipated and appropriate locations have been provided for them in
the manual as indicated in the index. When they are shipped, the
shipment date will be added to the amendment record sheet, and a
new sheet accompany the delivery.
1-3-1
CFB BOILER DESIGN AND OPERATION MANUAL
10
11
12
13
14
15
1-3-2
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
TITLE SECTION
FOREWORD ................................................................................................................... 1
2-0-1
CFB BOILER DESIGN AND OPERATION MANUAL
SECTION 1 - FOREWORD
TABLE OF CONTENTS
2-1-i
CFB BOILER DESIGN AND OPERATION MANUAL
FOREWORD
FOREWORD
GENERAL
OVERVIEW
A circulating fluidized bed boiler and its auxiliaries contain all the
fundamental parts found in any fossil fired steam generation system.
The are circuits for:
Fuel – Prepared coal is carefully metered into the preheated furnace
where it begins conversion to oxides of carbon, hydrogen, sulfur and
nitrogen. Start-up and supplemental fuel firing is also provided for.
Air – Several air circuits are used for combustion transport, and fluid-
ization of fuel and combustion products.
Water – Furnace with a steam drum, water cooled wall tubing and
an economizer.
Steam – Superheated steam is produced in circuits at both the top
of the furnace (Radiant) and in the superheater backpass (Convec-
tive) section. Reheated steam is produced in circuits located in the
reheater backpass (Convective) section.
2-1-1
CFB BOILER DESIGN AND OPERATION MANUAL
2-1-2
CFB BOILER DESIGN AND OPERATION MANUAL
2-1-3
CFB BOILER DESIGN AND OPERATION MANUAL
BOILER AND
RELATED
EQUIPMENT
ESP (1)
Induced Draft Fan (1)
Stack (1)
Safety Valves Sec. I and Sec. VIII
2-1-5
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
2-2-i
CFB BOILER DESIGN AND OPERATION MANUAL
EQUIPMENT ARRANGEMENT
EQUIPMENT
ARRANGEMENT
The General Arrangement drawings of boiler provided for client
show the equipment arrangement within the CFB boiler island.
The components shown on the General Arrangement Drawings from
north to south are:
1. The solid fuel feeding system, which includes (per boiler):
a. Three solid fuel silos, each with an isolation valve.
b. Three gravimetric feeders with inlet chutes and outlet hop-
pers.
c. Three fuel feed isolation valves.
d. Six fuel nozzles.
The gravimetric feeders charge the fuel from the fuel silos
through the isolation valves into the furnace front wall openings.
2. The furnace with the steam drum, the furnace waterwalls and
furnace plenum.
3. The start-up over-bed burners are located in the east and west
side walls of the furnace and are accessible from the FL+8,800
mm elevation platform.
4. The water cooled screw ash coolers are located off the floor of
the furnace.
5. Two parallel recycle cyclones.
6. The siphon seals are directly attached to the recycle cyclone sol-
ids outlets and are located on the FL+15,200 mm elevation plat-
form, discharging the recycle ash into the combustion chamber.
7. Two fluidizing air blowers located below the siphon seals at
ground level.
8. The convective backpass which contains heat absorbing surfac-
es, superheater, reheater and economizer.
9. The Ljungstrom rotary air preheater.
10. The sorbent (limestone) silo and feeding system is located in
east side of boiler island for unit 1 and in west side of boiler is-
land for unit 2.
11. The inert (sand) feeding system is located in the last bay of boil-
er structure. The primary and secondary air fans are below the
Ljungstrom air heater on the ground level.
2-2-1
CFB BOILER DESIGN AND OPERATION MANUAL
12. The flue gas cleaning equipment, the ID fan and the stack are at
the south side of the unit on the ground level.
2-2-2
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
2-3-i
CFB BOILER DESIGN AND OPERATION MANUAL
Heat for steam generation is removed from the system in three areas:
1. In the primary loop, where heat is removed from the solids circu-
lating in the CFB system. Heat removal is achieved by:
a. Heat absorbing surface in the water walls of the furnace;
b. Pendant superheater and evaporator heat absorbing surfac-
es located in the upper furnace region.
2. In the convective pass (backpass), where heat is removed from
the flue gas exiting the recycle cyclones. Heat removal is
achieved by superheater, reheater and economizer surfaces.
After the convective pass, the gases are further cooled in an air heater.
From the air heater, the flue gases are cleaned in the flue gas cleaning
equipment and vented via an induced draft fan to the stack.
2-3-2
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
TITLE PAGE NO.
FUEL SYSTEM ................................................................................................................. 2-4-1
Coal Storage and Feed System Description ............................................................. 2-4-1
Component Description .............................................................................................. 2-4-1
Coal Silos................................................................................................................. 2-4-1
Coal Silo Isolation Valves ........................................................................................ 2-4-1
Acoustic Flow Monitors ............................................................................................ 2-4-1
Coal Gravimetric Feeders ........................................................................................ 2-4-2
Furnace Isolation Slide Gate Valves ........................................................................ 2-4-2
SORBENT (LIMESTONE) INJECTION SYSTEM DESCRIPTION ................................... 2-4-2
Component Descriptions ............................................................................................ 2-4-3
Sorbent (Limestone) Silo ......................................................................................... 2-4-3
Sorbent (Limestone) Silo Outlet Fluidizing Device ................................................... 2-4-3
Sorbent (Limestone) Silo Isolation Gate .................................................................. 2-4-3
The "RotoFeed" Machine System ............................................................................ 2-4-3
Flow Proportioner (Splitter) ...................................................................................... 2-4-5
Line Isolation Valve and Injection Feed Nozzles ..................................................... 2-4-5
INERT (SAND) INJECTION SYSTEM DESCRIPTION ..................................................... 2-4-5
Component Descriptions ............................................................................................ 2-4-5
Inert (Sand) Silo ....................................................................................................... 2-4-5
Inert (Sand) Silo Isolation Gate ................................................................................ 2-4-6
DensPhase Pneumatic Conveying System ............................................................. 2-4-6
Isolation Valve and Injection Feed Nozzles ............................................................. 2-4-6
CIRCULATING FLUIDIZED BED FURNACE ................................................................... 2-4-7
Circulating Fluidized Bed System Description ......................................................... 2-4-7
Component Description .............................................................................................. 2-4-8
Lower Refractory Lined Furnace Section/Plenum and Grate .................................. 2-4-8
Upper Waterwall Furnace Section ........................................................................... 2-4-9
In-Furnace Pendant Evaporator Panels................................................................... 2-4-9
SOLIDS RECYCLE SYSTEM ........................................................................................... 2-4-9
Solids Recycle System Description ........................................................................... 2-4-9
Component Description ............................................................................................ 2-4-10
Recycle Cyclones .................................................................................................. 2-4-10
Standpipes (Siphon Seal Inlet Duct) ...................................................................... 2-4-10
Siphon Seal Pots ................................................................................................... 2-4-10
Solids Return Ducts to Furnace ............................................................................. 2-4-10
AIR/GAS SYSTEM .......................................................................................................... 2-4-10
Air/Gas System Description ..................................................................................... 2-4-10
Component Description ............................................................................................ 2-4-11
Primary Air Fan ...................................................................................................... 2-4-11
2-4-i
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
2-4-ii
CFB BOILER DESIGN AND OPERATION MANUAL
FUEL SYSTEM
Component
Description
Coal Silos
The solid fuel preparation and feed system empties into three (3)
coal silos. Each coal silo has one hopper and isolation valve which
discharges coal into the associated gravimetric feeder.
Acoustic Flow
Monitors
An acoustic flow monitor is mounted in each of the downspouts be-
low the coal silo isolation valve outlets to detect material flow or
flow interruption in the downspouts.
The flow monitor unit consists of two subassemblies; a detector
probe which mounts on the downspout, and a control unit suitable
for wall mounting in a convenient location. The detector probe in-
cludes a stainless steel alloy tip, which protrudes through the
downspout wall into direct contact with the moving material. The
control unit includes the required electronics, alarm relay, compara-
2-4-1
CFB BOILER DESIGN AND OPERATION MANUAL
Coal Gravimetric
Feeders
The coal silo hoppers discharge the solid fuel into the three (3) en-
closed pressurized gravimetric feeders. One feeder is provided for
each of the three fuel feed trains. The feeders are furnished with a
variable speed ac drive and controller, to regulate the fuel feed to
the furnace by varying the belt linear speed.
The feeders each have a 1,150 mm wide belt. The center feeder is
6,201 mm and the outboard feeders are 7,061 mm inlet to dis-
charge length. They are designed for 0.21 kg/cm2(g) internal pres-
sure and are provided with drag chain scavengers driven with sepa-
rate ac motors to recover any fuel spillage at the bottom of the
feeder housing.
Other features furnished with the fuel feeders include: Access
doors at each end of the feeders, glass observation ports, internal
lights, provisions for coal sampling, and switches for sensing (zero
speed, starvation, belt tracking and discharge pluggage).
Furnace Isolation
Slide Gate Valves
Three (3) pneumatically operated slide gate valves (one per train)
are furnished to isolate each fuel train from the furnace for mainte-
nance shutdowns and to protect the feeder from hot furnace gas-
ses should the pressurization of the feeder become inadequate for
any reason. The valve gate is provided with a single cylinder ac-
tuator.
As a safety feature, three fail-safe packages (one per valve) are
supplied to automatically shut down the valve in the event of a
power failure. Each fail-safe package includes an air accumulator,
air filter/regulator/lubricator, open/close limit switches, pressure
switches, air feed control valve, and solenoid and check valves.
SORBENT
(LIMESTONE)
INJECTION SYSTEM
DESCRIPTION
One (1) sorbent (limestone) feed system is provided for each boiler.
The sorbent (limestone) material from the sorbent (limestone) daily
silo is injected into the furnace at eight (8) points, to control the SO2
emissions at the stack outlet.
Prepared sorbent (limestone) material from the sorbent (limestone)
daily silo flows through the sorbent (limestone) silo hopper with flu-
idizing devices to the “Rotofeed” system. The “Rotofeed” system
dispenses limestone through conveying pipework to the boiler unit
2-4-2
CFB BOILER DESIGN AND OPERATION MANUAL
via one 4-way splitter and four 2-way splitters, providing 8 injection
points at the boiler.
A isolation valve is provided at each nozzle ( each injection points ),
to isolate the feed system from the furnace for maintenance pur-
poses.
Component
Descriptions
Sorbent (Limestone)
Silo
The prepared sorbent (limestone) silo, one per boiler, stores pre-
pared sorbent (limestone) material. The silo has one (1) outlet, hav-
ing a maintenance slide gate located at the silo hopper outlet, for si-
lo isolation and maintenance of equipment below.
Sorbent (Limestone)
Silo Outlet Fluidizing
Device
Silo hopper fluidizing device are provided at the hopper of the
sorbent (limestone) silo for the purpose of ensuring steady sorbent
(limestone) flow from the silo to the vertical downspout. The source
of fluidizing air is from one air receiver near silo. Action of fluidizing
device will be an interlock with “Rotofeed” system.
Sorbent (Limestone)
Silo Isolation Gate
A manually operated isolation gate (one per system) is provided in
the piping between the sorbent (limestone) silo and the “Rotofeed”
system for the purpose of isolating the conveying system from the
storage silo. Actuation of the gate is through a rotary screw shaft by
a manual wheel.
The “Rotofeed”
machine system
The “Rotofeed” machine consists of two pressure vessels, a volu-
metric feeder and a compressed air distribution manifold. The volu-
metric feeder will be driven through a gearbox by a standard induc-
tion motor. The electrical supply to the motor will be from a variable
frequency / voltage inverter drive (VFD), which will enable the “Ro-
tofeed” feeder speed and hence material output of the “Rotofeed” to
be controlled. The “Rotofeed” feeder speed is measured and used
to calculate material output. Thermal switches incorporated into the
feeder motor will provide an indication of motor overheating and pro-
tection within the VFD will stop the motor in the event of an overload.
The pressure vessels are arranged vertically with the dispensing
vessel located beneath the lock vessel. The inlet to each vessel is
provided with a Materials Handling air operated Dome Valve. These
2-4-3
CFB BOILER DESIGN AND OPERATION MANUAL
2-4-4
CFB BOILER DESIGN AND OPERATION MANUAL
Flow Proportioner
(Splitter)
Each flow proportioner (splitter) (five per system) is provided with
abrasion-resistant contact surfaces and an balancing shoe, for sys-
tem balancing.
INERT (SAND)
INJECTION SYSTEM
DESCRIPTION
One (1) inert (sand) feed system is provided for each boiler. The
material from the inert (sand) silo is injected into the furnace at two
(2) points when needed.
Sized inert material from the inert (sand) silo flows through the inert
(sand) silo outlet maintenance gate, will be discharged by gravity to
the DensPhase transport vessel of inert (sand) feed system. The
material will then be pneumatically conveyed through steel pipework
to the boiler.
A compressed air from dry plant air system provides conveying air
which transports the inert material/air mixture through conveying
pipe, and then injected into the return line of each seal pot. A isola-
tion valve is provided at end of injection line, to isolate the feed sys-
tem from the seal pot for isolation and maintenance purposes.
Component
Descriptions
DensPhase
Pneumatic Conveying
System
The DensPhase pneumatic conveying system consists of inlet dome
valve, DensPhase vessel, vent valve, air bypass valve and outlet ball
valve density stabilisers and associated valves.
Inert (sand) will fall under gravity from silo into the DensPhase vessel.
During filling the vent will remain open to allow displaced air to be re-
leased from the vessel. After a time delay or when the level switch in
the DensPhase vessel indicates that the vessel has filled, the vent will
be closed. After a short timed delay to allow the vessel to completely
fill, the inlet dome valve will be closed. When the inlet dome valve and
vent valve have both closed and sealed, the outlet ball valve will be
opened and air will be introduced into the vessel and the material will
be discharged into the pipeline and conveyed to the furnace.
During material transfer, the bypass air will be closed. Air will also be
introduced at points along the conveying pipe via the density stabi-
lisers to ensure smooth conveying. When the material has been
discharged into the boiler, signalled by a drop in conveying pressure,
the conveying air valves and outlet Dome valve will be closed and
the bypass air will be opened. The vent will be re opened and the
cycle is complete.
2-4-6
CFB BOILER DESIGN AND OPERATION MANUAL
CIRCULATING
FLUIDIZED BED
FURNACE
Circulating Fluidized
Bed System
Description
Fuel combustion in the Circulating Fluidized Bed (CFB) system takes
place in the vertical combustion chamber. Properly sized fuel and fi-
ne grained sorbent (limestone) are fed into the furnace and burned
1 at a relatively low temperature (850°C~900°C). The fine grained
limestone captures the sulfur dioxide released when the fuel is
burned. The bed material in the furnace consists primarily of coal
ash, gypsum, excess calcined limestone and inerts. The mean par-
ticle size of the bed material is in the range of 100 to 300 microns.
The bed material is fluidized by primary air introduced through a
nozzle grate at the bottom of the bed, and by the gas generated dur-
ing combustion. The gases flow upward with a relatively high veloci-
ty filling the entire furnace with suspended solids. They have high
concentration at the fluidizing bed but decrease continuously to-
wards the top of the furnace. The combustion gas entrains a con-
siderable portion of the solids in the furnace and carries them over to
recycle cyclones where the entrained solids are separated from the
gases. Some solids are continuously returned to the bed by a recy-
cle loop.
Because of the high slip velocity between the gas and solids, the sol-
ids proceed through the furnace at a much lower velocity than the
gas. Solids residence times on the order of minutes are obtained for
each cycle of solids circulation. The long residence and contact
times, coupled with the small particle sizes and efficient heat and
mass transfer rates, produce a high combustion efficiency. These
aforementioned effects in combination with temperature allow both
the decomposition of limestone and the subsequent formation of
gypsum.
Combustion air is introduced into the furnace at two levels. About
sixty percent of the combustion air is passed as primary fluidizing air.
Preheated to approximately 287°C, it enters the furnace through a
grate assembly and plenum located at the bottom of the furnace.
The balance of the air is admitted as secondary air, also preheated
to approximately 302°C, entering the furnace via multiple ports lo-
cated in the front and rear walls of the furnace. The combustion pro-
ceeds in two zones: a primary reducing zone in the lower section of
the furnace, and complete combustion using 20% excess air in the
upper section. This staged combustion, at controlled low tempera-
tures, effectively suppresses NOx formation.
Flue gas resulting from the combustion of the fuel, and the entrained
solids, exit the furnace at essentially the furnace temperature via two
outlets located in the upper portion of the rear wall and is ducted into
the two parallel recycle cyclones designed to remove about 99% of
the solids entrained by the gas from the combustion chamber. The
2-4-7
CFB BOILER DESIGN AND OPERATION MANUAL
Component
Description
The CFB combustion chamber is of rectangular single grate design
(15,506.7 mm wide x 7,683.5 mm deep) and consists of two sec-
tions:
Lower Refractory
Lined Furnace
Section/Plenum and
Grate
Fuel combustion proceeds in two furnace zones: a primary reducing
zone in the lower section, and final combustion at 20% excess air in
the middle and upper section. Primary fluidizing air, representing
roughly 60% of the total air to the furnace, is supplied under pres-
sure from the primary air fan through the plenum and grate assem-
bly at the bottom of the furnace.
The plenum is located in the lower most portion of the furnace. Pri-
mary air is injected into the plenum. The plenum consists of un-
cooled duct plate on two sides and the floor. The roof of the plenum
is made of finned waterwall tubes with holes in the fins to accommo-
date fluidizing air nozzles.
The fluidizing grate consists of:
1. The roof of the plenum described above.
2-4-8
CFB BOILER DESIGN AND OPERATION MANUAL
Upper Waterwall
Furnace Section
The upper section is rectangular in design and is made up of evap-
orative waterwalls, maintained in place by a grid of buckstays. This
upper waterwall section, combined with the lower furnace section.
Water is supplied to the waterwalls by use of a lower ring header.
The solids density gradient decreases as the stream moves up
through the upper furnace. At the top of the furnace section, the
stream exits through two openings in the rear wall and proceeds to
the recycle cyclones.
In-Furnace Pendant
Evaporator Panels
The In-Furnace evaporator panels (C-23) are located in the upper
furnace front wall area opposite to the cyclone inlet openings. They
consist of six (6) 63.5 mm O.D. tube fin-welded assemblies.
SOLIDS RECYCLE
SYSTEM
Solids Recycle
System Description
Flue gas with entrained solids enter the two parallel recycle cy-
clones where about 99% of the solids are captured. The collected
solids flow downward into a standpipe, ending in two refractory
lined, air fluidized siphon seal pots. The siphon seal pot arrange-
2-4-9
CFB BOILER DESIGN AND OPERATION MANUAL
Component
Description
Recycle Cyclones
Two (2) recycle cyclones are provided for this system. The cy-
clones are fabricated from 10 mm thick carbon steel and are refrac-
tory lined. The cyclones have an inside diameter of 7,900 mm and
an overall height of approximately 24,542, including the domes. An
expansion joint is provided between the cyclone top and the dome.
At this same elevation, a vortex finder made of abrasion and heat
resistant alloy steel is supported by twelve (12) equally spaced lugs
around the vortex finder perimeter.
Standpipes (Siphon
Seal Inlet Duct)
Two (2) standpipes are provided. Each pipe is refractory lined,
1,450 mm diameter inside the refractory lining, and is provided with
an expansion joint.
AIR/GAS SYSTEM
Air/Gas System
Description
The combustion air is supplied to the CFB furnace in two main
streams: primary fluidizing air and secondary air.
Primary fluidizing air is introduced through a plenum and grate as-
sembly located at the bottom of the lower refractory furnace section.
The balance is admitted as secondary air through various ports in
the front and rear walls of the furnace, as vented fluidizing air for the
siphon seals and as transport air for the limestone feed. Various
purges, pressurization and other fluidizing air flows also contribute to
the combustion air. The flow of air into the furnace is integrated and
recorded and is automatically proportioned to the fuel rate to main-
tain the required excess air ratio for combustion. The gas flow
2-4-10
CFB BOILER DESIGN AND OPERATION MANUAL
through the system is generated by the induced draft fan. The in-
duced draft fan, located downstream of the ESP and upstream of
the stack, pulls the gas through the system and forces the resulting
clean gases into the stack for dispersal into the air.
Component
Description
2-4-11
CFB BOILER DESIGN AND OPERATION MANUAL
BURNER SYSTEM
Burner System
Description
The CFB burner system is composed of start-up burners.
The start-up burners are used for preheating the unit. These burn-
ers operate with air supplied from the secondary air fan and are re-
tracted when the temperature in the furnace reaches approximately
700°C.
Component
Description
Start-up Burners
The start-up burner system consists of four (4) automatically re-
tractable start-up burners for firing diesel oil, with a high energy arc
igniter and a burner management system. The burners are located
on the east and west side walls of the furnace. Start-up and shut
down is independent for each burner. The minimum turndown of
each burner is approximately 20% of its maximum rated capacity.
Combustion air is supplied from the secondary air system and the
fuel/air ratio is controlled for each burner.
HEAT TRANSFER
SYSTEMS
Heat Transfer
System Description
The heat transfer systems are of two kinds. The first is those parts of
the process where heat is introduced into the system. This type of
process is provided by the Burner & Fuel Feeder System (see
“Burner & Fuel Feeder System” section).
The second kind is where heat is removed from the system. These
types of processes are:
1. Furnace Waterwalls (see “Furnace” section).
2. Furnace Pendant Superheater and Evaporator (see “Super-
heater” and “Furnace” sections).
3. Convective Backpass/Superheater/Reheater/Economizer.
4. Air Preheater.
Component
Description
Convective Backpass
Flue gas enters the convective split backpass after exiting from the
recycle cyclones which reduce the solids carry-over to the convec-
2-4-12
CFB BOILER DESIGN AND OPERATION MANUAL
tive section. Heat is transferred from the flue gas to the steam and
water circuits which are made up of superheater, reheater and
economizer surfaces.
The hot gases pass through a steam cooled superheater enclosure
and division wall, and across the horizontal reheater section and the
horizontal finishing superheater section in each pass of split back-
pass respectively. The hot gases then pass across the horizontal
plain tube economizer sections located in RH pass and SH pass. Fi-
nally, the hot gases leaving each pass merge back one stream and
then across horizontal plain tube economizer located in common
duct. Heat is recovered from the flue gas before entering the Ljung-
strom air preheater, where remaining heat is transferred to the pri-
mary and secondary air systems.
Ljungstrom Air
Preheater
Primary and secondary air leaving the PA Fan and SA Fan respec-
tively are heated by the Ljungstrom Air Preheater. Flue gas leaving
the Ljungstrom Air Preheater is cooled to 135°C.
The Ljungstrom regenerative air preheater design is a highly efficient,
rotating modular element, compact heat exchanger. The design has
three sections: one for flue gas, one for primary air, and one for sec-
ondary air.
The Ljungstrom Air Preheater is located below the convective back-
pass, and consists of a rotor drive unit electrically driven geared as-
sembly mounted to the rotor hub drive shaft. This drive assembly
provides the facility of main AC electric drive and standby air drive
(used for maintenance and loss of power), two (2) retractable soot-
blowers (one on the air preheater gas inlet side and one on the air
preheater gas outlet side), stationary washing devices, fire detection
device and rotor support bearing/ steady bearing with oil bath.
AIR POLLUTION
CONTROL SYSTEM
2-4-13
CFB BOILER DESIGN AND OPERATION MANUAL
Component
Description
Convective Backpass
/Ljungstrom Air
Preheater
Gases from the CFB pass through the recycle cyclones where the
majority of particulates in the gas are removed. The gases then en-
ter and pass through the various sections of the convective split
backpass. Convective split backpass is split to two gas passages by
steam cooled division wall which is parallel to front steam cooled wall
and rear steam cooled wall of backpass. The two gas passages, one
is RH pass located closest to the cyclone outlet ducts and all reheat-
er sections are located in the pass. The other is SH (superheater)
pass located near rear steam cooled wall and finish superheater
sections and economizer sections are located in the pass. As a re-
sult of the low velocity design of the backpass, additional particulate
recovery occurs at the bottom of the Ljungstrom air preheater which
has four (4) hopper outlets.
Electrostatic
Precipitator
For cleaning the flue gas the electrostatic precipitator will be used to
meet the particulate emission requirement 50 mg/Nm3 at 6% O2 vd.
An electrostatic precipitator has one inlet duct through which the
gases pass uniformly at a velocity of 1~1.5 m/s. The duct is formed
by parallel rows of vertically mounted collecting plates and a number
of discharge electrodes vertically suspended between the collecting
plates. Five cells and two ash hopper per cell are designed. Every
ash hopper will be connected to the transmitter vessel of fly ash re-
moval system.
The high negative voltage applied to the electrically insulated dis-
charge electrodes creates a strong electrical field between the dis-
charge electrodes and the earthed collecting plates. As the voltage
is raised, electrical breakdown of the gas which close to the elec-
trode surface take place. This breakdown, called “corona”, produces
large numbers of gas ions. The negative gas ions produced charge
the dust particles suspended in the gas, then the negatively charged
particles migrate towards the collecting plate where they are depos-
ited.
These particles build up a layer of dust on the collecting-plate sur-
face which is dislodged by rapping.
The inlet dust loading – 23.8 g/Nm3 as dry base will be introduced to
ESP chamber, the outlet dust concentration shall be less than 50
mg/Nm3. Over 99.7% high collecting efficiency will be reached base
on above operation condition.
2-4-14
CFB BOILER DESIGN AND OPERATION MANUAL
ASH REMOVAL
SYSTEM
Ash Removal
System Description
One of the many reasons for a CFB being very efficient is because it
effectively utilizes ash and ash recirculation for added heat transfer.
Fluidized ash is circulated up through the combustor giving off heat
to the combustor waterwalls. Heavier, more coarse ash is recirculat-
ed through the cyclones and seal pot and back into the bottom of the
combustor. Fluidizing air and the injection of inert sand helps this
heavier ash return to the combustor and plenum. A majority of the
ash will follow this recirculating path before eventually exiting the
CFB through a bottom ash removal path (ash screw coolers). A
smaller portion of the ash is expected to be so fine that it remains in
laminar flow streams in the flue gas to travel out through the back-
pass with the flue gas.
Ash is removed from the system in three places: the water-cooled
screw ash coolers, Ljungstrom air preheater gas outlet hoppers, and
the ESP hoppers.
Fly Ash : Ash entrained within the flue gas passing through the
backpass is considered to be fly ash. Some of the fly ash will attach
to the superheater, reheater and economizer tubes. Long and par-
tial retract sootblowers will dislodge this sintered material. Some of
the fly ash will attach to the Ljungstrorm Air heater plate surfaces.
Retract AH sootblowers will dislodge this dust and any sulfate based
compounds. Ash hoppers located below air heater will collect any fly
ash that drops out of the flue gas flow. Ash collected in air heater
hoppers is removed by the ash handling system.
Bottom Ash : While the CFB uses ash recirculation as a basis for
heat transfer. The ash be circulated is derived from the combustion
of the solid fuel plus limestone and sand. The ash will be removed
from the bottom ash system will be chemical compounds based on
the sorbent and sulfate compounds plus a small amount of the inert
sand and fuel ash
Component
Description
Bottom ash is removed through four(4) bed drains located in the bot-
tom of the combustor. Each bed drain is connected to a single screw,
water cooled screw conveyor that continuously removes the bottom
ash from the combustor to bottom ash removal system. The ash re-
moval system will deliver bottom ash to bottom ash silo.
2-4-15
CFB BOILER DESIGN AND OPERATION MANUAL
Bottom Ash
Combustor Bed Drain
Valves
The 304.8 mm inlet slide gate valve is located in the plenum exit
above the water cooled screw conveyors. The inlet valve is either
pneumatically or manually operated (hand wheel) knife gate valve.
They provide isolation of the water cooled screw conveyor from the
combustor bed when the screw conveyor requires servicing. Special
material is used to survive the high inlet temperatures
Water-cooled Screw
Ash Cooler Ash
Removal
Bottom ash is removed from boiler bottom with four water cooled
single screw conveyors per boiler. Each water cooled single screw
conveyor is equipped with one infeed chute.
The operation and capacity of all water cooled single screw convey-
ors are controlled from bottom ash handling automation system. The
capacities must be checked and adjusted during commissioning with
actual material.
Water cooled screw conveyor is equipped with single screw and mo-
tor. The meaning of the water cooled screw is to cool the ash coming
from the boiler. Water circulations must be always on, when bottom
ash is removed.
Water circulation must be closed (manually) within approx. 15
minutes after screw conveyor is stopped to avoid the condensation
inside the screw. This time can be reduced to 5 minutes in situations
when the conveyor is empty. The capacity of screw conveyor can be
regulated with frequency converter. Both screws are equipped with
independence frequency converters.
Furnace ash passes through the water-cooled screw ash coolers to
the ash handling system.
2-4-16
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
2-5-1
CFB BOILER DESIGN AND OPERATION MANUAL
INTRODUCTION
The following description and instructions cover in a general way the
upper furnace wall design used. Specific information on wall con-
struction and furnace setting can be found in the contract pressure
part arrangement and the insulation and refractory drawings.
WELDED WALL
CONSTRUCTION
The furnace walls are composed of 63.5 mm O.D. tubes on 88.9 mm
centers. The space between the tubes is fin welded to form a com-
plete gas tight seal.
The convective split pass (backpass) steam cooled side walls are
composed of 44.45 mm O.D. fin welded tubes on 114.3 mm centers.
The backpass front wall, roof wall and rear wall are composed of
50.8 mm O.D. fin welded tubes on 114.3 mm centers. The division
wall runs parallel to front and rear backpass walls and is composed
of 50.8 mm O.D. fin welded tubes on 114.3 mm centers. Screen
tubes come from division steam cooled wall tube and bare type with-
out fin welded at upper cavity of the convective split backpass. The
purpose is gas stream be able to across division wall and enter SH
pass.
Where tubes are spread out to permit passage of superheater, re-
heater and economizer elements, screen tubes, sootblowers, etc.,
the spaces between the tubes and openings are closed with fin ma-
terial so a completely metallic surface is exposed to the hot furnace
gases.
All finned tubes are backed with a plastic refractory and skin casing
which is seal welded to form a gas tight envelope.
Poured insulation and plastic refractory are used at each horizontal
buckstay to form a continuous band around the furnace thereby pre-
venting flue action of gases between the casing and waterwalls. At
2-5-2
CFB BOILER DESIGN AND OPERATION MANUAL
Hot air or gas over 177°C should not be allowed to enter ducts sud-
denly during the initial start-ups. Dampers should be open to allow
the duct temperatures to increase with the furnace temperature.
Loss of the organic binder as smoke does not affect the insulating
qualities of the mineral fiber batts, blankets and blocks. The incre-
mental temperature increase less than 55.6°C/hr is required only the
2-5-3
CFB BOILER DESIGN AND OPERATION MANUAL
2-5-4
CFB BOILER DESIGN AND OPERATION MANUAL
2-5-5
CFB BOILER DESIGN AND OPERATION MANUAL
Tube Repairs
A tube section that has failed, or which must be replaced because of
danger of failure, can in most cases easily be replaced. After remov-
ing the furnace wall insulation behind the failed area, the tube sec-
tion is removed by cutting across the tube, sufficiently above and be-
low the failure and carefully cutting the web alongside the tube (See
Note). Before inserting and rewelding a new tube section the tube
ends should be properly prepared for welding.
NOTE: The longitudinal cuts must extend beyond
the perpendicular cuts sufficiently to permit welding
completely around the periphery of the tube when
installing the new tube section. Webs between
tubes must be replaced and made gastight.
It must be recognized that it is impossible to include repair proce-
dures (methods, welding techniques, etc.) to cover all pressure parts
and associated structural components of a complex modern steam
generator. It is recommended that Formosa Heavy Industries’ ser-
vice or construction representative be consulted for assistance in
evaluating and repairing damaged pressure parts and/or failures.
All repairs should be done by competent and qualified personnel and
all welding should be in accordance with the Recommended Rules
for Repairs of Power Boilers by the National Board of Boiler and
Pressure Vessel Inspectors.
NOTE: If repaired tube is located in boiler furnace
grinding of welding region to make a smooth and
vertical furnace water wall with an angle of impact
approximating zero is necessary to prevent wearing
on welded zone due to high particle loads in the
furnace. The criteria of grinding and vertical angle is
shown on the drawing of pressure parts.
GUIDELINES FOR
HANDLING OF
SILICA DUST
Introduction
These guidelines are provided to alert our customers to the potential-
ly harmful health effects and the risk of serious disease caused by
2-5-6
CFB BOILER DESIGN AND OPERATION MANUAL
2-5-7
CFB BOILER DESIGN AND OPERATION MANUAL
2-5-8
CFB BOILER DESIGN AND OPERATION MANUAL
the progress of the disease will be slower without continued dust ex-
posure. Breathing may become severely labored. The worker is far
below normal physically and is susceptible to respiratory diseases.
Chest x-ray may show an enlarged heart as a result of the body's at-
tempts to overcome the resistance of restricted blood vessels in the
lungs. Pulmonary tuberculosis and emphysema are frequent com-
plications.
Other Diseases
In addition to causing silicosis, the inhalation of silica dust can oth-
erwise weaken the lungs and their natural cleansing process. As a
result, the inhalation of silica dust may be a contribution factor lead-
ing to other respiratory diseases. Medical and scientific analysis is
continuing, and the total effect of silica inhalation is not known.
What is known strongly indicates that silica inhalation is hazardous to
health.
Threshold Limit
Value (TLV)
TLV's or Threshold Limit Values of mineral dusts are time weighted
average concentrations considered permissible for exposures of
eight hours per day, five days per week that are published by the
American Conference of Governmental Industrial Hygienists (ACGIH)
and have been promulgated as standards of OSHA.
2-5-9
CFB BOILER DESIGN AND OPERATION MANUAL
Medical
Requirements
An effective medical control program for exposed personnel will help
prevent occupational diseases. Such a program can also serve as a
check on engineering controls because symptoms of exposure in a
group of workers could indicate inadequate controls.
Examinations should be performed by or under the supervision of a
licensed physician and should be given to all personnel prior to their
assignments to areas in which airborne concentrations of dust may
exceed the permissible exposure limits.
These examinations should include as a minimum the following:
2-5-10
CFB BOILER DESIGN AND OPERATION MANUAL
Protective
Equipment
Respiratory protection should be used by personnel working in dust
environments where the ventilation system is inadequate or non-
operational. A combination of both proper ventilation and respiratory
protection would tend to eliminate most risks.
For details on use of respirators refer to the ANSI standard, Z88.2-
1969 "Practices for Respiratory Protection".
2-5-11
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
2-6- i
CFB BOILER DESIGN AND OPERATION MANUAL
PROCESS DESCRIPTION
Fuel is withdrawn from the coal silo, via coal silo shutoff valves, di-
rectly to the Gravimetric Feeders. The feeders are controlled by
the boiler capacity control system and according to the preselected
ratio. The fuel is then fed via pneumatically operated knife gate
valves and fuel feeding chutes to furnace front wall openings. The
fuel gravimetric feeders are also pressurized with cold primary air
via 6” diameter piping connections. Each pressurizing system con-
tains valves and instrumentation. Cold primary air also provides
purge air below each furnace isolation slide gate valve.
Sorbent (Limestone)
Injection System
There is one sorbent (limestone) silo which services one boiler. The
sorbent (limestone) silo is located in east side of boiler island for
unit 1 and in west side of boiler island for unit 2. One silo has one
(1) outlet. Silo hopper is equipped with a fluidizing device, isolation
gate valve and “rotofeed” continuous sorbent injection system.
Prepared sorbent (limestone) from the silo flows through the silo
outlet maintenance gate, fluidizing device, silo isolation gate, inlet
Dome Valves, lock vessel and dispensing vessel to variable speed
of volumetric feeder. Conveying air from dry plant air system pro-
vides high pressure conveying air which transports the sorbent
(limestone)/air mixture to the flow proportioners (splitters). The flow
proportioners divide the mixture into eight(8) streams which are
then injected into the furnace through injection feed nozzles. A iso-
lation valve is provided at each nozzle to isolate the feed system
from the furnace for isolation and maintenance purposes.
2-6-1
CFB BOILER DESIGN AND OPERATION MANUAL
Sized inert material from the inert (sand) silo flows through the in-
ert (sand) silo outlet maintenance gate, through the inlet dome
valve (pneumatic), and the Densphase transport vessel of feed
system. An compressed air from dry plant air system provides
conveying air which transports the inert material/air mixture into
the return duct of each seal pot nozzles. A isolation valve is pro-
vided at each nozzle to isolate the feed system from the seal pot
for isolation and maintenance purposes.
CFB COMBUSTION
(HEAT GENERATION)
The furnace chamber design is of the single grate arrangement.
2-6-2
CFB BOILER DESIGN AND OPERATION MANUAL
solids are separated from the gas in the recycle cyclones. Some
solids are continuously returned to the bed by a recycle loop. The
very high internal and external circulating rates of solids, character-
istic of a circulating fluid bed, result in consistently uniform temper-
atures throughout the furnace and the solids recycle system.
Because of the high slip velocity between gas and solids, the solids
proceed through the furnace at a slower velocity than the gas. Sol-
ids residence times in the order of minutes are obtained for each
cycle of solids circulation. The long residence and contact times,
coupled with the small particle sizes and efficient heat and mass
transfer rates, produce a high combustion efficiency. The afore-
mentioned effects in combination with temperature allow both the
decomposition of limestone and subsequent formation of gypsum.
2-6-3
CFB BOILER DESIGN AND OPERATION MANUAL
the fluidizing air blower is used for fluidization of the cyclone solids
outlet cones, seal pots, and seal pot return ducts.
COMBUSTION AND
FLUIDIZING AIR SUPPLY
Combustion air is supplied to the CFB furnace in two main streams.
Air is passed through the bottom grate as primary fluidizing air.
The balance is admitted as secondary air through various ports in
the front and rear walls of the furnace, as fluidizing air for the si-
phon seals (seal pots) and as transport air for the limestone feed.
Various purges and fluidizing airflows also contribute to the com-
bustion air.
1. Primary air fan in operation - Air to the furnace grate via the
Ljungstrom air preheater, cold and hot purge air for solids feed-
ing. Flow inlet vane controlled by combustion air flow control
(60%).
2-6-4
CFB BOILER DESIGN AND OPERATION MANUAL
Solids are removed from the circulating fluid bed system as follows:
1. Fine fly ash at the Ljungstrom air preheater and flue gas clean-
ing equipment hopper outlets.
2. Coarse bottom ash from the furnace grate via ash screw cooler
outlets.
Ash is discharged from the furnace grate via 8.625” OD pipes and
ash discharge gate valves into four trains of single screw, water-
cooled ash coolers. Each ash cooler train is arranged at a slight
incline to horizontal.
Special ash drains are provided on the furnace windbox and are in-
tended for use only when the unit is essentially cooled down. Dur-
ing normal operation the ash temperatures will range up to 900°C.
Start-up burners are located on the east and west side walls of the
furnace. Each of the start-up burners has a firing capacity of
35.8x106 kcal/hr. Start-up and shutdown is independent for each
2-6-5
CFB BOILER DESIGN AND OPERATION MANUAL
burner. The minimum turndown for each burner is 20% of its rated
capacity.
Combustion air for the start-up burners is supplied from the sec-
ondary air fan via the Ljungstrom air preheater.
UTILITY SYSTEMS
The diesel oil firing rate for each of the start-up burners is set by
the operator via hand indicating controller in conjunction with the
burner total diesel oil and total air summer (totalizer) control system.
Air Supply
Combustion air is supplied by the the secondary air fan to the start-
up burners. Protective purge air is also supplied by the secondary
air fan to cool burners when not in use.
Combustion air to the furnace is supplied by the primary air fan and
the secondary air fan via the furnace bed (via the Ljungstrom air
preheater).
Fluidizing air and grease air for cyclone and seal pot is supplied by
fluidizing air blower
Cooling Water
Cooling water coming from closed circuit cooling system is supplied
at a temperature of 37°C and a pressure of 4 kg/cm2(g), and is
used for services such as generator air cooler, T/G oil cooler, ash
screw coolers, F.A. blower, compressors, dryers, boiler feed water
pump, air heater and fans etc.
2-6-6
CFB BOILER DESIGN AND OPERATION MANUAL
Service Air
Service air from plant air system (compressor station) is provided at
ambient air temperature and a pressure of 4~7 kg/cm2(g), dry, at a
2°C dew point temperature. The service air system is provided to
supply the various consumers within the plant, which are not sup-
plied from the instrument air system.
The transportation air for fly ash, limestone, sand and bottom ash
recycle system will also be integrated to the service air system,
surely buffer tanks are necessary for separate system.
- Start-up burner
- Ash cooler
Instrument Air
Instrument air is provided for controls at ambient air temperature, a
pressure of 4~7 kg/cm2(g), dry-oil and dust free, at a 2°C dew point
temperature.
2-6-7
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
2-7-1
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
LIST OF TABLES
2-7-TAB_1-1
CFB BOILER DESIGN AND OPERATION MANUAL
DESIGN DATA
INTRODUCTION
The steam generator is designed to produce superheated steam at
specified temperatures and pressures, when supplied with feedwa-
ter at a specific temperature. Operation of the steam generator at
any condition that exceeds the design limitations will shorten the
life of the boiler and its auxiliary equipment. Specific design param-
eters are outlined on the Predicted Performance sheet (Tab 3).
When the equipment is new, specific operating parameters should
be established which will serve as a standard for satisfactory boiler
operation. Then, if this specific “standard” or “normal” operating
condition is exceeded, steps can be taken to correct any devia-
tion(s) which may result in unsatisfactory boiler operation.
Emergency conditions may result in unnecessary boiler outages,
repairs or injuries. Plant personnel must be trained in safe boiler
operation and to make diligent recordings in the appropriate boiler
operation data logs.
Plant operation and maintenance standards should be followed by
plant personnel for both the boiler and the auxiliary equipment.
Plant personnel should become thoroughly familiar with the specific
design characteristics of the boiler and the associated auxiliary
equipment. This can only be accomplished if plant personnel dili-
gently observe, record, check and verify all pertinent data obtained
during normal boiler operation.
DESIGN CONCEPT
At maximum continuous rating (MCR), the Formosa Heavy Indus-
tries two CFB Type Reheat Boiler (steam generators) are each de-
signed for an evaporation rate of 460,000 kg/hr at a superheater
outlet pressure of 129 kg/cm2(g) and temperature of 541°C. The
design feedwater temperature is 245.4°C.
2-7-TAB_1-2
Table 1. Boiler Pressure Parts
CIRCUIT
NUMBER REQ'D DESCRIPTION
NUMBER
C-1 1 1676.4 I.D. STEAM DRUM
C-2 4 355.6 O.D. FURNACE DOWNCOMER
C-3 1 406.4 O.D. FURNACE LOWER FRONT INLET HEADER
C-4 174 TBS 63.5 O.D. FURNACE FRONT/ROOF FIN WELD PANELS
C-5 1 273.1 O.D. FURN FRONT/REAR UPP OUTLET HDR
C-6 26 168.3 O.D. FURN FRONT/REAR/ROOF RISERS
C-7 86 TBS 63.5 O.D. FURN FLOOR FIN WELD PANELS
C-8 1 406.4 O.D. FURNACE LWR REAR INLET HDR
C-9 174 TBS 63.5 O.D. FURN REAR FIN WLD PNLS
C-10 2 219.1 O.D. FURN OUTLET RING HDR
C-11 2 406.4 O.D. FURN LWR SIDE INLET HDR
C-12 172 TBS 63.5 O.D. FURN SIDE FIN WLD PNLS
C-13 2 273.1 O.D. FURN UPP SIDE OUTLET HDR
C-14 14 168.3 O.D. FURN SIDE RISERS
C-21 6 219.1 O.D. EVP. DOWNCOMER
C-22 6 273.1 O.D. EVP. INLET HDR
C-23 6 PNLS 63.5 O.D. EVP. FIN WLD PNLS
C-24 6 273.1 O.D. EVP. OUTLET HDR
C-25 12 168.3 O.D. EVP. RISERS
E-1 1 273.1 O.D. ECONOMIZER #1 INLET HEADER
E-2 115 TBS 50.8 O.D. ECON. #1 PLAIN TUBE ASSY
E-3 1 273.1 O.D. ECON. #1 OUTLET HEADER
E-4 1 273.1 O.D. COMMON LINK FROM ECON. #1
E-5 1 273.1 O.D. LINK TO ECON. #2-S IN SH PASS
E-6 1 273.1 O.D. ECON. #2-S INLET HDR
E-7 106 TBS 50.8 O.D. ECON. #2-S PLAIN TUBE ASSY
E-8 1 273.1 O.D. LINK TO ECON. #2-R IN RH PASS
E-9 1 273.1 O.D. ECON. #2-R INLET HDR
E-10 106 TBS 57.2 O.D. ECON. #2-R PLAIN TUBE ASSY
E-11 1 323.9 O.D. ECON. #2 JUNCT HDR
E-12 1 273.1 O.D. LINK TO ECON. #3 IN SH PASS
E-13 1 273.1 O.D. ECON. #3 INLET HEADER
E-14 106 TBS 50.8 O.D. ECON. #3 PLAIN TUBE ASSY-LOWER
E-15 106 TBS 50.8 O.D. ECON. #3 PLAIN TUBE ASSY-UPPER
E-16 1 323.9 O.D. ECON. #3 OUTLET HEADER
E-17 1 219.1 O.D. ECON. #3 LINK TO STEAM DRUM
S-1 8 168.3 O.D. SATURATED LINKS FROM STEAM DRUM
S-2 2 273.1 O.D. BKPASS UPP SIDE INLET HDRS
S-3 116 TBS 44.5 O.D. BKPASS SIDE FIN WLD PNLS
S-4 2 323.9 O.D. BKPASS LWR SIDE OUTLET HDRS
2-7-TAB_1-3
Table 1. Boiler Pressure Parts
CIRCUIT
NUMBER REQ'D DESCRIPTION
NUMBER
S-5 1 323.9 O.D. BKPASS LWR FRT INLET HDR
S-6 107 TBS 50.8 O.D. BKPASS FRONT FIN WLD PNLS
S-7 2 273.1 O.D. BKPASS GAS INLET RING HDR
S-8 107 TBS 50.8 O.D. BKPASS ROOF FIN WLD PNLS
S-9 107 TBS 50.8 O.D. BKPASS REAR FIN WLD PNLS
S-10 1 323.9 O.D. BKPASS LWR REAR OUTLET HDR
S-11 5 168.3 O.D. LINKS TO DIVISION WALL
S-12 1 273.1 O.D. BKPASS DIVISION WALL INLET HDRS
S-13 107 TBS 50.8 O.D. BKPASS DIVISION WALL
S-13 53 TBS PER ROW 50.8 O.D. BKPASS SCREEN TUBES
S-15 1 273.1 O.D. BKPASS DIVISION WALL OUTLET HDR
S-16 2 273.1 O.D. LINKS TO IN-FURN SH PANEL
S-17 1 406.4 O.D. SH PNL #1 INLET HDR
S-18 7 PNLS 44.5 O.D. SH FIN WLD PNL #1 INLET
S-19 7 273.1 O.D. SH PNL #1 JUNCT HDRS
S-20 7 PNLS 44.5 O.D. SH FIN WLD PNL #1 OUTLET
S-21 1 355.6 O.D. SH PNL #1 OUTLET HDR
S-22 1 355.6 O.D. LINK TO SH DESUPERHEATER #1
S-23 1 355.6 O.D. SH DESUPERHEATER #1
S-24 1 355.6 O.D. LINK TO SH PNL #2
S-25 1 355.6 O.D. SH PNL #2 INLET HDR
S-26 7 PNLS 44.5 O.D. SH FIN WLD PNL #2 INLET
S-27 7 273.1 O.D. SH PNL #2 JUNCT HDRS
S-28 7 PNLS 44.5 O.D. SH FIN WLD PNL #2 OUTLET
S-29 1 406.4 O.D. SH PNL #2 OUTLET HDR
S-30 1 406.4 O.D. LINK TO SH DESUPERHEATER #2
S-31 1 406.4 O.D. SH DESUPERHEATER #2
S-32 1 406.4 O.D. LINK TO LINK S-33
S-33 2 355.6 O.D. LINKS TO BP FINISH SH
S-34 1 406.4 O.D. FINISH SH INLET HDR
S-35 212 TBS 50.8 O.D. FINISH SH ASSY-LOWER
S-36 212 TBS 50.8 O.D. FINISH SH ASSY-INTERM.
S-37 212 TBS 50.8 O.D. FINISH SH ASSY-UPPER
S-38 1 406.4 O.D. FINISH SH OUTLET HDR
R-2 1 406.4 O.D. REHEATER INLET HDR
R-3 318 TBS 57.2 O.D. RH ASSY-LOWER
R-4 318 TBS 57.2 O.D. RH ASSY-LOWER INTERM.
R-5 318 TBS 57.2 O.D. RH ASSY-UPPER INTERM.
R-6 318 TBS 57.2 O.D. RH ASSY-UPPER
R-7 1 508 O.D. REHEATER OUTLET HDR
2-7-TAB_1-4
CONTRACT DATA SHEET
FORMOSA HEAVY INDUSTRIES
Contract No. MPP-130108-01/02/03
Project Description
SUPPLIER Formosa Heavy Industries Corporation.
USER San Miguel Consolidated Power Corporation, Malita, Davao Del Sur, Philippines
FUEL BURNING EQUIPMENT Description CFB Furnace w/Gravimetric Coal Feeders, Diesel Oil Start-up Burners
Operating Conditions
MCR
2-7-TAB_2-1
Formosa Heavy Industries Corp.
CFB Type Reheat Boiler
Unit 1 and Unit 2
San Miguel Consolidated Power Corporation
Malita, Davao Del Sur, Philippines
FHI Contract no. : MPP-130108-01/02/03
Predicted Performance
Load MCR
Fuel Coal
Evaporation kg/hr 460,000
Feedwater Temperature °C 245.4
Feedwater Temperature Leaving Economizer °C 303
Superheater Outlet Temperature °C 541
Superheater Outlet Pressure kg/cm2(g) 129
Superheater Pressure Drop kg/cm2(g) 16
Reheating Steam kg/hr 181,867
Reheater Inlet Temperature °C 370
Reheater Inlet Pressure kg/cm2(g) 36.6
Reheater Outlet Temperature °C 541
Reheater Outlet Pressure kg/cm2(g) 35.1
Reheater Pressure Drop kg/cm2(g) 1.5
Economizer Pressure Drop kg/cm2(g) 3.5
2-7-TAB_3-1
TAB 3 - PREDICTED PERFORMANCE
*NOTES:
These performance figures are predicted only and are not to be construed as being
guaranteed except where the points coincide with the guarantees.
Operation of this unit in excess of the above specified Maximum Continuous Rating (MCR)
may result in damage to the equipment and/or increased maintenance.
The fuel specifications on which the guarantees are based are as follows:
Type: Coal
% Passing
Size Distribution Enter Boiler Size(mm) By Weight
6.0 – 9.0 Top Size (99% passing)
0.7 – 1.5 D - 50
Less Than 0.1 5% (max.) fines
Carbon 42.97
Hydrogen 2.75
Nitrogen 0.59
Sulfur 1.49
Ash 6.82
Oxygen 11.42
Water 33.96
100.00
2-7-TAB_3-2
TAB 3 - PREDICTED PERFORMANCE
Limestone Specification
Type: Limestone
% Passing
Size Distribution Size(mm) By Weight
0.8 – 1.5 Top Size (99% passing)
0.3 – 0.5 D - 50
Less Than 0.1 5% (max.) fines
Sand Specification
Type: Sand
2-7-TAB_3-3
CFB BOILER DESIGN AND OPERATION MANUAL
LIST OF FIGURES
Maximum Allowable Rate of Pressure Change for Normal Startups & Shutdowns 1
2-7-TAB_4-1
MAXIMUM ALLOWABLE RATE OF PRESSURE CHANGE
FOR
NORMAL START-UPS AND SHUTDOWNS
(NATURAL CIRCULATION UNITS)
PSIG PSIG
[kPa (gauge)] [kPa (gauge)]
[20685]
[17238] [16548]
[13700]
[13790]
[13798]
[10343]
[10343]
[6895]
[6895]
[5516]
D
R
U [4137]
M
P [2758]
[3448]
R
E [2069]
S
S [83° C]
U [1379]
R
E
- [110° C]
P
S [689]
I
[552] [690]
G
[414]
[276] [345]
[207]
[138]
Figure 1
FORMOSA HEAVY INDUSTRIES CORPORATION
SMC-150MW RH-CFB BOILER
COLD STARTUP
900 110
Furn. Temp.
** : Period from turbine rolling to sychronize depends on turbine warm-up suitation 100
800
SUPERHAETER OUTLET PRESSURE,, Kg/Cm2 G
Boiler load 90
700
SH./ R.H OUTLET TEMPERATURE, °C
80
FURNACE TEMPERATURE, °C
600
70
BOILER LOAD, %
500 SH / RH Out.
60
Temp.
400 50
40
300
30
200
S.H. pressure 20
100
10
0 0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
TIME, HOURS
FORMOSA HEAVY INDUSTRIES CORPORATION
SMC-150MW RH-CFB BOILER
WARM STARTUP
900 110
Furn. Temp. Furn. Temp.
100
800 Boiler 8 - 56 HOUR
SHUTDOWN
Boiler Load
SUPERHEATER OUTLET PRESSURE, Kg/Cm2 G
Load
90
700
S.H. / R.H. OUTLET TEMPERATURE, °C
80
FURNACE TEMPERATURE, °C
LOAD, % MCR
500 60
400 50
40
300
30
200
SH Outl.
SH Out. Press. Press. 20
100
10
0 0
-3.00 -2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00
TIME, HOURS
900 110
Furnace Temp. Furnace Temp.
100
800
Boiler Load Boiler Load
90
700
< 8 HOUR
80
SUPERHEATER OUTLET PRESUE, Kg/Cm2 G
SHUTDOWN
600
SH/RH OUTLET TEMPERATURE, °C
70
SH/RH Out. Temp.
500 SH/RH Out. Temp.
60
400 50
40
300
30
200
20
SH. Out. Press. SH. Out. Press.
100
10
0 0
-3.00 -2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00
Start Fans, Start
Begin Blowers Oil
Reducing Shut off Fuel, Burnerl Turbine Full Load TIME, HOURS
Fuel Trip Turbine Turbine Syn & HP/LP Start Shutoff
Roll Coall
Transfer. Burner
FORMOSA HEAVY INDUSTRIES CORPORATION
SMC-150MW RH-CFB BOILER
900 120
Furnace Temp.
800
100
Boiler Load
700
SUPERHEATER OUTLET PRESSUR,(Kg/cm2 G)
600 80
SH/RH OUTLET TEMPERATURE (°C)
FURNACE TEMPERATURE (°C)
300 40
200
SH Outlet Press. 20
100
0 0
-2.00 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00
TIME, HOURS
Begin Shutdown, Start Shut off Shut off
Start Reducing Fuel Burners Solid Fuel Burners
FORMOSA HEAVY INDUSTRIES CORPORATION
SMC-150MW RH-CFB BOILER
542
540
538
536
STEAM TEMPERATURE, °C
534
532
530
528
526
524
522
20 30 40 50 60 70 80 90 100
BOILER MCR STEAM FLOW, %
FORMOSA HEAVY INDUSTRIES CORPORATION
SMC-150MW RH-CFB BOILER
14
12
FLUE GAS VOLUME OXYGEN LEVEL DRY BASE, % O2
10
0
30 40 50 60 70 80 90 100
BOILER MCR STEAM FLOW, %
FORMOSA HEAVY INDUSTRIES CORPORATION
SMC-150MW RH-CFB BOILER
900
850
FURNACE FLUE GAS OUTLET TEMPERATURE, °C
800
750
700
650
600
550
30 40 50 60 70 80 90 100
BOILER MCR STEAM FLOW, %
FORMOSA HEAVY INDUSTRIES CORPORATION
SMC-150MW RH-CFB BOILER
OVERALL FURNACE PRESSURE DROP VERSUS BOILER LOAD
2300
HIGH LIMIT
2100
OVERALL FURNACE PRESSURE DROP MMH2O
1900
1700
NORMAL
1500
OPERATION
1300
LOW LIMIT
1100
900
700
500
0 10 20 30 40 50 60 70 80 90 100
BOILER MCR STEAM FLOW, %
FORMOSA HEAVY INDUSTRIES CORPORATION
SMC-150MW RH-CFB BOILER
3.00
2.50
SUPERHEATER SPRAY, % MAIN STEAM FLOW
2.00
1.50
1.00
0.50
0.00
30 40 50 60 70 80 90 100
BOILER MCR STEAM FLOW, %
FORMOSA HEAVY INDUSTRIES CORPORATION
SMC-150MW RH-CFB BOILER
150.0
140.0
SUPERHEATER OUTLET PRESSURE, Kg/cm2G
130.0
120.0
110.0
100.0
90.0
80.0
70.0
60.0
0 10 20 30 40 50 60 70 80 90 100
BOILER MCR STEAM FLOW, %
FORMOSA HEAVY INDUSTRIES CORPORATION
SMC-150MW RH-CFB BOILER
700
600
AIR FLOW RATE TO FURNAC TONS/HR
500
400
TOTAL AIR TO BOILER
300
200
0
0 10 20 30 40 50 60 70 80 90 100
BOILER MCR STEAM FLOW, %
FORMOSA HEAVY INDUSTRIES CORPORATION
SMC-150 MW RH-CFB BOILER
100
90
COAL FLOW
80
FUEL & SORBENT FLOW, T/HR
70
60
50
40
30
20
10
LIMESTONE FLOW
0
30 40 50 60 70 80 90 100
TABLE OF CONTENTS
SAFETY PRECAUTION
FEEDWATER TREATMENT.......................................................................................... 3
2-8-1
CFB BOILER DESIGN AND OPERATION MANUAL
SAFETY
PRECAUTION
a. When the water level in the drum is lowered below the lowest
visible point of the gage glass, all water should drain out of the
glass. Any time a repair or change is made to the gage glass,
this should be checked.
2-8-2
CFB BOILER DESIGN AND OPERATION MANUAL
d. Air and gas passages must be free from obstruction and unit
capable of being thoroughly purged by the circulation of air
through the unit.
2-8-3
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
PRELIMINARY.................................................................................................. 2-8-TAB_1-1
2-8-TAB_1-i
CFB BOILER DESIGN AND OPERATION MANUAL
INTRODUCTION
After installation of all pressure parts, except those omitted during
chemical cleaning (see Chemical Cleaning Procedures), the unit is
subjected to the required initial hydrostatic test of 1-1/2 times the
unit design pressure. Depending on insurance requirements, hy-
drostatic test of pressure parts repairs are commonly made at the
normal operating pressure or the design pressure.
2-8-TAB_1-1
CFB BOILER DESIGN AND OPERATION MANUAL
FILLING
1. Fill the superheater (See Fill Water Below) through a suitable
outlet connection (such as the final superheater outlet header
drain or vent) until all elements are filled and the water over-
flows into the steam drum.
2. Cease filling through the superheater outlet connection when
the water overflows into the steam drum. Close superheater fill
and vent connections.
3. Proceed filling the boiler (See Fill Water, below) through the
normal filling connections. Keep filling until water overflows
from the drum vents. Then close all vents.
FILL WATER
It is the responsibility of the customer to provide properly treated
water, as specified below, at ambient temperature but in no case
less than 21°C and max. 50°C. If the proper type of water is not
available, the Formosa Heavy Industries Co-Generation depart-
ment should be contacted for further information. Once the super-
heater has been filled, take water samples from each available su-
perheater vent or drain and analyze them to verify the absence of
contamination.
Type of water to be used:
1. Superheater and Reheater (drainable and nondrainable sec-
tions): Fill with treated condensate or treated demineralized wa-
ter (See Note). The treatment shall include 10 ppm ammonia.
This treated water will have a pH value of approximately 10.
2-8-TAB_1-2
CFB BOILER DESIGN AND OPERATION MANUAL
EXTERNAL
INSPECTION
2-8-TAB_1-5
CFB BOILER DESIGN AND OPERATION MANUAL
NOTE :
For Boiler plus Superheater
Design Pressure : 153.5 kg/cm2(g)
Hydrotest Pressure : 230.25 kg/cm2(g)
Hold Points and Check :
1st : 10 kg/cm2(g), hold and field check
nd
2 : 50 kg/cm2(g), hold and quick field check
3rd : 153.5 kg/cm2(g), hold 1~2 hr for thorough check
th
4 : 230.25 kg/cm2(g), hold 15 min. no field check
5th : 153.5 kg/cm2(g), hold 1~2 hr for thorough
check
For Reheater
Design Pressure : 45 kg/cm2(g)
Hydrotest Pressure : 67.5 kg/cm2(g)
Hold Points and Check :
1st : 10 kg/cm2(g), hold and field check
2nd : 45 kg/cm2(g), hold 1~2 hr for thorough check
3rd : 67.5 kg/cm2(g), hold 15 min. no field check
4th : 45 kg/cm2(g), hold 1~2 hr for thorough check
POST
HYDROSTATIC
TEST
PROCEDURES
1. Introduce nitrogen through the drum vent to pressurize the unit
to approximately 0.35 kg/cm2(g).
2. Remove all hydrostatic test plugs and gags from the safety
valves prior to starting up the unit.
NOTE: Since there is generally some time delay
between the hydrostatic test and the initial boiling
out of the boiler, the unit should remain full of water,
air should not be allowed to enter.
2-8-TAB_1-6
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_1-7
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
2-8-TAB_2-i
CFB BOILER DESIGN AND OPERATION MANUAL
WATER WEIGHTS
kgs at 15.5°C
Economizer: 55,379
[Includes water in all Economizer
Components, starting at the econo-
mizer inlet and ending at the drum
end of the economizer outlet links]
Furnace: 74,477
(Includes water in all Furnace Com-
ponents, starting at the inlet end of
the downcomers and ending at the
drum end of the riser tubes)
Evaporator: 13,994
(Includes water in all Evaporator
Components, starting at the drum end
of the evaporator downcomers and
ending at the drum end of the evapo-
rator risers)
Superheater:
[Includes water in all Superheater
Components, starting at the drum end 75,760
of the superheater connection tubes
and ending at the superheater outlet]
Reheater:
[Includes water in all Reheater Com- 60,068
ponents, starting at the reheater inlet
header and ending at the reheater
outlet header]
Total 311,462
2-8-TAB_2-1
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
LIST OF FIGURES
2-8-TAB_3- i
CFB BOILER DESIGN AND OPERATION MANUAL
WATER TREATMENT
WATER
TREATMENT
The treatment of feedwater and the conditioning of boiler water are
beyond the control of this company. This company does not as-
sume the responsibility for water treatment and does not make spe-
cific recommendations for control purposes. This is in accordance
with the practice established by the American Boiler and Affiliated
Industries Standards Committee. However, reference should be
made to the company’s Proposal, which warns against exceeding
maximum limits of hardness in the feedwater for certain boiler types
and of total solids, alkalinity and suspended solids concentrations in
the boiler water. These limits are absolute maximums and should
not be exceeded. In addition, the boiler water silica content should
be limited for the particular operating pressure involved by reference
to standard silica vaporization curves.
The successful operation of steam generating equipment depends
upon a rigid control of feedwater and operating variables to assure
freedom from scale formation and corrosion of water and steam con-
tacted surfaces of the boiler. This control is very important in lower
pressure boilers and becomes increasingly magnified at intermediate
and higher pressure operation.
Scale formation in boilers is prevented by providing a good makeup
water to the feedwater system and by avoiding condensate contami-
nation. At lower pressures, a suitable makeup may be attained by
cold or hot lime-soda process softeners or by zeolite combinations.
At higher pressure, the makeup must be of condensate quality such
as provided by evaporation or by demineralization.
Corrosion of metal surfaces in contact with water and steam consti-
tutes the major maintenance expense to the power industry. The
condensate and feedwater must be free of dissolved corrosive gas-
2-8-TAB_3- 1
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_3- 2
CFB BOILER DESIGN AND OPERATION MANUAL
over. The only disadvantage of this treatment is the fact that the
boiler water is unbuffered and subject to relatively rapid changes in
boiler water pH values if contamination should occur. Where the
advantages of volatile control are to be pursued, special emphasis
must be placed on quick detection of condenser leaks, and alarms
must be available etc, alert the operators that such condition exists.
Volatile control should be used only when the dissolved solids con-
tent in the boiler is less than that shown in the attached table. If a
significant concentration of solids is present as a result of condenser
leakage, solid treating chemicals such as trisodium phosphate
should be available for immediate injection of pH adjustment of the
boiler water. Under no circumstances should a boiler be operated
with a pH value below 7.0. If the boiler water pH cannot be main-
tained above this value with chemical feed and blowdown, the unit
should be removed from service in an orderly fashion.
Close control of solids in the boiler water must be established to pre-
vent carry-over of boiler water into the steam. The presence of oil,
grease, high alkalinity, or other foam inducing solids cannot be toler-
ated.
It is evident that stringent control of operation and feedwater treat-
ment must be applied to prevent trouble from scaling, corrosion and
foaming. While caustic embrittlement is no longer a serious problem
in the industry, care should be taken in the operation of lower pres-
2
sure boilers [below 63.3 kg/cm ] to prevent its occurrence by
maintenance of proper alkalinity-to-nitrate ratios. The necessity for
its application can be determined by means of a Bureau of Mines
Embrittlement Detector.
The control of boiler water is a prime requisite for good operation. A
good chemical staff should be employed. The services of a compe-
tent consultant can be of value to supplement necessary technical
data and information.
2-8-TAB_3- 3
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_3- 4
Figure 2-8-TAB_3-1
Figure 2-8-TAB_3-2
Figure 2-8-TAB_3-3
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
2-8-TAB_4- i
CFB BOILER DESIGN AND OPERATION MANUAL
LAY-UP PROCEDURES
PRE-
OPERATIONAL
PERIOD
When the boiler is ready for the hydrostatic test, proceed as follows:
1. Fill the superheater with condensate or demineralized water
containing 10 ppm (10 mg/kg) of ammonia and 200 ppm (200
mg/kg) of hydrazine. The pH value of the solution should be
approximately 10.0. The condensate is added at the super-
heater outlet to overflow into the boiler drum.
2. When the condensate overflows from the superheater into the
boiler drum, the addition of condensate at the superheater can
be stopped and the unit filled as described in step 3.
3. Fill the boiler through the normal filling connections with hydra-
zine treated water. Close boiler drains and open boiler vents as
during normal filling procedures.
4. At the conclusion of the hydrostatic test, with the boiler and su-
perheater filled to overflowing, pressurize the unit to 0.2 to 0.35
2
kg/cm (g) gage with nitrogen.
a. If freezing is a problem, the water in the drainable circuits
can be displaced with nitrogen and the unit is layed up un-
der nitrogen pressure. Auxiliary heat may be applied to
keep the non-drainable sections from freezing.
b. With drainable superheaters all surfaces can be laid up un-
der nitrogen pressure.
5. Boilers without stop valves in the main steam line should have
the outlet isolated by means of a blank flange, or equivalent, so
that a small positive pressure can be applied.
2-8-TAB_4-1
CFB BOILER DESIGN AND OPERATION MANUAL
POST BOIL-OUT
PERIOD
If the operation of the boiler is delayed after boiling out it should be
filled as follows:
Introduce condensate containing about 10 ppm (10 mg/kg) of am-
monia and 200 ppm (200 mg/kg) of hydrazine to the boiler and su-
perheater and pressurize the unit with nitrogen.
SHORT OUTAGE
PERIOD
No draining. If the boiler is shut down for a period of three to four
days, and the boiler pressure will drop to atmospheric pressure:
Introduce nitrogen through the boiler drum vent and superheater
outlet header drain/vent, as the unit is cooled, when the steam
pressure drops below 0.35 kg/cm2(g). Maintain a total pressure
0.35 kg/cm2(g) due to nitrogen. Admission of air through atmos-
pheric vents should be avoided.
LONG OUTAGE
Boiler not opened for repair work. Where the boiler is removed
from service for a prolonged shutdown, as a seasonal outage of a
month or longer:
1. Fill the superheater, adding the condensate to the outlet of the
nondrainable sections. Then proceed with filling the boiler with
a condensate 10 ppm (10 mg/kg) of ammonia and 200 ppm
(200 mg/kg) of hydrazine.
The treated condensate can be displaced with nitrogen or the entire
unit can be laid up wet under nitrogen pressure depending upon the
temperature of the surrounding area. Maintain a nitrogen pressure
of 0.2 to 0.35 kg/cm2(g) gage on the undrained sections of the unit,
where possible. If the main steam line is not equipped with a stop
valve, steps should be taken to blank off the line so that the boiler
can be pressurized.
2. If freezing weather conditions arise during the outage, means
must be provided to keep the elements above freezing temper-
ature.
2-8-TAB_4- 2
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_4- 3
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
2-8-TAB_5-i
CFB BOILER DESIGN AND OPERATION MANUAL
FOREWORD
Boiling out is the process of chemical cleaning for the removal of oil
and grease, and the solvent usually consists of a strong aqueous al-
kaline solution. Oils and greases previously introduced in manufac-
turing and for the purpose of providing protection during the storage
of tubes and other pressure parts for extended periods of time must
be removed prior to unit operation.
The presence of even very thin films of oil or grease or their decom-
position products on the boiler heating surfaces will seriously retard
heat transfer. The resultant increase in metal temperature may be
sufficient to cause overheating and blistering of boiler tubes, and ul-
timate failure at high loads.
During the boiling out process, the gage glass may become badly
discolored and permanently etched. FHI suggests that the customer
have, on hand at the job site, replacement kits for all gage glasses. If
not applicable, enough drain for gauge glass be necessary. The
gage glass manufacturer's instruction also should be consulted.
The chemicals should be dissolved in water before being added to
the boiler and should never be added to the boiler in solid form. In
handling caustic materials, care should be exercised to avoid contact
with the eyes, skin or clothing. When mixing this material, it is rec-
ommended that goggles, rubber gloves and cotton clothing be em-
ployed.
The chemical solutions should not be added to the boiler
through the regular chemical feed system since these high
concentrations may plug the chemical feed piping and valves.
Chemical solutions should always be added by means of an external
blend/fill pumping system or feed from manhole of drum.
PREPARATION
FOR BOILING OUT
Prior to boiling out a boiler, the items previously outlined under
"safety precautions" and "drying out" should be consulted and fol-
2-8-TAB_5-1
CFB BOILER DESIGN AND OPERATION MANUAL
lowed. Generally, "drying out" and "boiling out" are combined as one
continuous operation.
A careful cleaning and inspection of the interior and exterior surface
of the boiler and auxiliaries should be made for the purpose of re-
moving all scrap metal, borings, wood, tools, rags and other miscel-
laneous materials. It is very important that these materials be re-
moved before boiling out, otherwise foreign material in the interior
boiler sections is likely to interfere with the operation of blowdown
valves and future operation of the boiler.
It is considered undesirable to attempt to set safety valves when the
boiler contains water of high chemical concentration such as that
used for boiling out purposes. The safety valves should be set when
the boiler contains water of approximately normal concentration for
steam generation.
The boiler should be filled to a point about 300 mm below the bottom
of the steam drum manhole(See Note Below). The unit should be
filled through the passage normally used during operation. Water
should be supplied from the condensate storage tank, through de-
aerator feedwater pump, boiler feed pump, and connecting piping
through the feedwater heaters, to the economizer through the main
feedwater pipe, through the economizer and into the boiler drum. If
this filling procedure is followed, it will flush all the piping and auxilia-
ries ahead of the boiler, and eliminate fouling of the boiler surfaces
with contaminants after the boiler has been properly cleaned. Flush-
ing the feedwater supply system also reduces the quantity of silica
found in boiler water during the initial period of operation.
All superheater drains and vents and boiler steam drum vents
should be opened wide after filling the boiler. Close all access and
observation doors. Check the firing equipment and the feedwater
system to be sure they are in correct operating condition. Pressure
gages, correctly calibrated, should be mounted in locations readily
visible to the operator.
One (1) pressure gage should be located at the boiler steam drum
and another located at the firing aisle, each indicating "steam drum
pressure".
When using oil for boiling out, the oil piping should first be checked
for leaks. Fans should be operated for several hours during which
2-8-TAB_5-2
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_5-3
CFB BOILER DESIGN AND OPERATION MANUAL
BOILING OUT
PROCEDURE
The boiler should be lit off in accordance with the start-up procedure
contained in the operation and maintenance section of this manual.
After furnace purge, RH pass damper close at min. opening and SH
pass damper open at full opening.
Fire at minimum capacity until steam issues forcibly from the steam
drum vent. At this time, close the drum vent and all superheater
vents and drains except those on the superheater outlet header.
Slowly raise the pressure on the unit as attached figure as possible
and always keeping furnace exit temp. below 535℃. To protect re-
heater tube, the proper boiling out pressure based upon the design
pressure of the unit is 30~35 kg/cm2(g).
After the hold time of 4 hours shut down all start up oil burners that are in
service and blow down the lower headers and Evaporator headers via
drain valves on header. Blowdown until the drum pressure drops to 25
kg/cm2(g) or when the drum level drops to low level of -445mm.
2-8-TAB_5-4
CFB BOILER DESIGN AND OPERATION MANUAL
Repeat the above procedure every four hours until all signals of oil
have disappeared from a cooled boiler water sample.
After each blowdown period, a cooled sampled should be checked
for PH and phosphate concentration if possible and shall test for oil
and silica concentration.
The times of each blowdown, valve cycles and chemistry data
should be recorded on a blowdown data sheet until the concentra-
tion of tested blow down water is :
Oil <= 3ppm
Silica<= 5 ppm
DRAINING & RINSE
Draining
- Once the Oil and Silica are with-in the acceptable limits allow the
unit to cool down slowly and once the drum reached 1.5
kg/cm2(g) open its vents.
- Open all drains on the lower header point and drains on the
evaporator panel point and allow to drain completely.
- Open all low point drain valves on the steam circuits point.
Rinse -
- Fill boiler to top of drum level gauge.
- Following complete draining of the alkaline solution, the boilers is
to be filled to the top of the gauge glass with rinse water via
normal boiler filling.
- Backfill the Superheater
- Backfill the superheater via the bypass valve of secondary super-
heater desuperheater spray station until the superheater spills
over into the drum and the drum level increases approximately 1”
(25mm).
- Draining the Boiler.
- Drain the rinse water through,
Lower header drain valves
Economizer drain valves
2-8-TAB_5-5
CFB BOILER DESIGN AND OPERATION MANUAL
After the boiling out period, when the boiler has been cooled and
drained, the steam drum should be inspected and any sediment
removed by hand. If the quantity warrants, inspect lower furnace
headers, through inspection nipples.
If any foreign material is found in a lower furnace header, it can be
removed by hand or flushed with a high pressure water hose, In
addition to checking for sediment, inspection should assure that the
metal internal surfaces are free from oil adherence.
After the drum and headers have all been cleaned and inspected,
the unit can be closed. New manhole gaskets should be installed
on the drum and any inspection nipple caps or tubes cut for clean-
ing and inspection should be replaced. The unit should be filled
with either demineralized water or condensate and subjected to a
hydrotest pressure approximately that of normal operating pressure.
The unit should then be drained to normal operating drum level.
The superheater should also be drained thru headers drain system.
2-8-TAB_5-6
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_5-7
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
2-8-TAB_6-i
CFB BOILER DESIGN AND OPERATION MANUAL
INTRODUCTION
The following "General Principles of Boiler Operation" are prepared
to acquaint operators with the basic operation and care of large
natural circulation steam generating units. Specific and detailed in-
formation regarding operation and maintenance of the boiler com-
ponents and auxiliary equipment supplied at this installation will be
found in other sections of this manual.
Basic rules must be followed in the operation and maintenance of
boilers and secondary equipment; the operator should familiarize
himself with the characteristics of this particular installation. This
can only be accomplished by diligently observing, recording, check-
ing and comparing data and details. Emergency conditions, result-
ing in unnecessary outages and repairs, can be avoided by a prop-
er working knowledge and attention on the part of the operator.
PERFORMANCE
1. All steam generating equipment is designed for a specific pur-
pose. When supplied with feedwater at a specific temperature,
the unit will deliver a definite quantity of steam at the design
pressure and temperature. Operating at conditions which ex-
ceed the design limitations will shorten the life of the boiler and
its components.
2. The concentration of solids entrained in the steam leaving the
steam drum will depend to a great extent upon the quality of the
feedwater. Suitable make-up water treatment and an adequate
blowdown program should be employed to control the boiler
water alkalinity, silica and concentration of dissolved and sus-
pended solids in the boiler water. Adequate mechanical deaera-
tion of the feedwater should be provided and steps taken to
control the level of metallic oxides entering the boiler in the
feedwater. Refer to the "Feedwater Treatment” section of the
manual.
3. The quantity of fuel consumed is generally measured and rec-
orded. The means employed will depend upon the nature of
the fuel and the equipment available for measuring. A repre-
2-8-TAB_6-1
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_6-2
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_6-3
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_6-4
CFB BOILER DESIGN AND OPERATION MANUAL
ter in the gage is sluggish when the drain valve is opened or closed,
investigate the cause and correct the condition immediately. To
protect the gage glass, blow downs should be kept to a minimum,
during normal operation.
During normal operation the water level in the gage glass should be
observed periodically even though the boiler may be equipped with
a reliable feedwater regulator and/or remote water level indicator.
While steaming, the boiler should be protected from rapid changes
in feedwater temperature. The feedwater flow to the boiler should
correspond fairly closely to the steaming rate and should not be
shut off completely while the furnace is being fired.
The recommended water level and operating range is indicated in
the section "Drum lnternals”. Unless there is information to the con-
trary, the water level should be carried near the center of the gage
glass. The gauge glass center line is normally set to indicate nor-
mal level inside the drum at full pressure conditions. If the unit is
operated at significantly reduced pressure the level indicated at the
gauge glass center line will correspond to a lower than normal ac-
tual level inside the drum, due to the difference in temperature be-
tween the water in the glass and the water inside the drum. Any
adjustment of the water level should be gradual. If the water level
is too high, carryover or even priming may occur, especially if the
steam demand is large and rapidly fluctuating.
Perhaps the most serious emergency that may be encountered is
low water. As mentioned in previous paragraphs, the water level
must be watched continuously and the water gauges should be
checked periodically to ensure proper operation. Protection of wa-
ter level transmission lines should be provided to avoid freezing or
other damages to these lines. Do not rely solely on high and low
level alarms.
If the water level falls out of sight in the water gauge, due to failure
of the feedwater supply or neglect of the operator, except in the
case of momentary fluctuations that might occur with extraordinary
changes in load, appropriate action should be taken at once to dis-
continue fuel firing. Any decision to continue to operate, even if on-
ly for a short time at a reduced rating, would have to be made by
someone in authority, thoroughly familiar with the circumstances
2-8-TAB_6-5
CFB BOILER DESIGN AND OPERATION MANUAL
that led to the emergency and positively certain that the water level
can be restored immediately without damaging the unit.
WARMING UP AND
EXPANSION
While the unit is being brought up to pressure, provision should be
made for gradually heating and adequately draining all cold steam
piping from the beginning by opening all drain valves and bypasses
(if stop valves are provided).
During initial firing, periodically check the expansion movements of
the unit and make sure the casing, headers, piping, etc., move
freely in respect to the structural steel. Expansion markers should
be installed at suitable locations to facilitate inspection (refer to
Pressure Parts Arrangement drawings and/or Expansion Movement
Diagrams for this installation). Periodic checks should be made
during the life of the unit to determine that expansion movement
continues to occur in a normal, uniform manner. All hangers on the
unit and related piping should be checked periodically for proper
settings and functioning.
AIR HEATERS
An abnormal increase in draft loss across the gas and/or air side of
an air heater indicates that deposits are building up. Every precau-
tion should be taken to keep the gas swept surfaces of the air heat-
er clean. Operate the air heater soot blowers as frequently as nec-
essary.
If oil is being fired make certain the fuel is being burned completely.
Watch the temperature of the gas leaving the air heater, particularly
when starting up the unit. Use air heater cleaning device to remove
accumulations of combustible deposits. A sudden and abnormal in-
crease in the gas outlet temperature would indicate that a fire has
developed. In this event, the unit should be shut down immediately
and steps be taken to quench the fire.
The exit gas temperature will rise with increasing load and fall with
decreasing load. If a log is kept of the load, the exit gas tempera-
ture and soot blowing schedule, the operator will soon be able to
recognize an abnormally high or low exit gas temperature.
If the exit gas temperature is below normal for the load at which the
unit is being operated, look for very low excess air (very high CO2,
maybe some CO, and smoke).
2-8-TAB_6-6
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_6-7
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_6-8
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_6-9
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_6-10
CFB BOILER DESIGN AND OPERATION MANUAL
service until it is more convenient to take it off the line and make
the necessary repairs. While it is possible to operate for a consid-
erable period of time under such conditions, there is always a
chance of cutting other tubes. As long as the failure does not be-
come one which involves the loss of water level in the gauge glass,
the unit should be shut down in the normal manner, in order that no
equipment may be subject to sudden temperature changes.
If failure is such that the water level cannot be maintained in the
gauge glass, then the unit should be shut down immediately. After
a shutdown because of low water, every effort should be made to
keep the water as near normal as possible until the boiler is cool
enough to drain.
A leak in a superheater element should be investigated at the earli-
est possible time, and the unit should be shut down in a normal
manner.
These are recommendations only and are not intended to supplant
the judgment of the operators responsible for the operation of the
equipment. lt must be borne in mind that prolonged operation with
leaking tubes may cut other tubes and make a major repair job out
of what was a relatively simple and short one, but the time selected
to take the unit off the line is solely the responsibility of the opera-
tors as they are the only ones who know all the circumstances, the
advantages and disadvantages of keeping the unit on the line.
FURNACE
EXPLOSIONS
Furnace explosions are generally a result of the following conditions:
1. The accumulation of unburned fuel in the furnace due to in-
complete combustion.
2. The mixture of this unburned fuel with air in explosive propor-
tions.
3. The application of sufficient heat to raise the temperature of a
portion of this mixture to the ignition point.
Unburned fuel may accumulate in the furnace in a number of ways,
for instance:
4. Through leaky auxiliary fuel inlet valves on idle fuel firing
equipment.
5. If the fires are extinguished and the fuel is not shut off promptly.
6. If the fuel is not burning as rapidly as it is entering the furnace.
2-8-TAB_6-11
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_6-12
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_6-13
CFB BOILER DESIGN AND OPERATION MANUAL
INSPECTION
Whenever the unit is shut down, and cool enough to enter, make
an external inspection of the unit, waterwalls, cyclone, superheater,
economizer, air heater and baghouse or ESP. Clean the firesides
where necessary and examine all tubes for evidence of corrosion,
erosion, swelling, warping, blistering, burning and cracking.
Swelling of superheater tubes indicates overheating which may
have been caused by bringing the unit up to pressure too quickly,
failure to vent the superheater sufficiently while the unit is being
brought up to pressure, or scale on the internal surfaces due to car-
ryover of water from the steam drum. Slight warping is not serious
if steps are taken at once to determine and eliminate the cause.
Check the condition of the unit setting and check the casing and
doors for leaks.
Periodic inspections should be made to examine the watersides of
the furnace. When draining the boiler for internal inspection during
freezing weather conditions, care must be taken that no water re-
mains trapped in piping or above valve seats. Especially gate
valves in vertical piping should remain open during the outage to
prevent damage to the valve seats due to freezing. Some conden-
sate will remain in non-drainable superheater loops. Means (some
source of heat) must be provided to prevent freezing.
Before entering the drum, make sure that all valves in drum con-
necting piping (feedwater, auxiliary steam, chemical feed, blow-
down, drains, sampling, gauge glass drains, etc.) are closed tightly
and properly tagged so that they will not be opened inadvertently.
Remove the manhole covers and check the drum internals for
tightness and cleanliness.
Check the drum for corrosion and pitting. Oxygen pitting is a com-
mon form of corrosion that can be found in boilers, usually in the
steam drum above the normal water level, but also in tubes and
headers.
Remove a sufficient amount of inspection plugs from each boiler
and waterwall header for boroscope inspection of the internal tube
surfaces. Wash down the unit to remove any sludge.
Inspect and if necessary clean the external heating surface of the
economizer.
2-8-TAB_6-14
CFB BOILER DESIGN AND OPERATION MANUAL
See that the heating surfaces of the air heater are clean. Corrosion,
if present, would appear in the cooler portion of the heater, particu-
larly where soot and dirt are allowed to accumulate.
Make a thorough inspection of the furnace and clean as required.
Check fuel burning equipment (ignitors, oil guns, scanners, linkage,
dampers, etc.) for cleanliness and proper operation. If a fluidized
bed supervisory system is provided, check out and exercise, where
practicable, control valves, relays, interlocks, etc.
Annual inspection should be complete and include an internal and
external examination of the entire unit.
LAY-UPS
When the Unit is shut down for stand-by purposes and draining of
the boiler is not required for maintenance or repairs, the boiler met-
als must be protected against corrosion. Refer to Lay Up Proce-
dures in this manual.
2-8-TAB_6-15
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
RESPONSIBILITY............................................................................................ 2-8-TAB_7-1
PRECAUTIONS................................................................................................ 2-8-TAB_7-3
2-8-TAB_7-i
CFB BOILER DESIGN AND OPERATION MANUAL
PURPOSE
The purpose of blowing the main steam lines and reheater steam
lines prior to starting up a new unit is to remove any foreign material
remaining in the superheater, reheater and steam piping after erec-
tion is completed. Considerable damage could result if such for-
eign material was allowed to enter the plant steam system or tur-
bine during initial operation.
On older units the need for steam line blowing should be consid-
ered following major pressure parts repairs, where the possibility of
introduction of foreign material into the system exists.
RESPONSIBILITY
Since prevention of damage to the plant steam system or turbine is
the prime concern, the responsibility for determining the effective-
ness of the steam line blowing operation rests with the purchaser.
During the steam line blowing process the unit should be operated
in accordance with Formosa Heavy Industries recommended pro-
cedures, with all control systems and protective interlocks function-
ing.
The responsibility for the design, fabrication and installation of any
temporary piping system used for the purpose of steam line blowing,
as well as its protection against overpressure or overtemperature
rests with the purchaser.
GENERAL
Ideally, to obtain optimum cleaning, the flow conditions in the sys-
tem during steam line blowing should equal those during normal
operation at maximum load. Since it is impossible to exactly dupli-
cate these conditions when blowing through the piping to atmos-
phere, it is desirable to produce equivalent conditions by using low-
er pressure steam with a flow rate such that the product of steam
flow times velocity will equal that under normal full conditions. The
determination of the total obtainable flow quantity must be based on
flow resistances in the entire system, including the temporary piping.
2-8-TAB_7-1
CFB BOILER DESIGN AND OPERATION MANUAL
When more than one steam line is provided in any section, consid-
eration should be given to arranging the temporary piping so that
each line may be blown separately. lf this is done, the piping sys-
tem should be investigated to insure that flow unbalances and ex-
pansion stresses at connections do not become a problem.
An indication of the cleanliness is obtained by impact specimens,
installed in the blowoff piping during the final blows. Suitably
mounted and supported, polished square bar stock has been used
effectively for this purpose. The degree of pitting of the specimen
surface following a blow is used to determine the end point of the
blowing cycle for the particular section.
2-8-TAB_7-2
CFB BOILER DESIGN AND OPERATION MANUAL
PRECAUTIONS
1. The process of steam line blowing imposes abnormal and se-
vere conditions upon the boiler and steam piping. Large, rapid
temperature changes occur during each blowing cycle. This
cycling of temperature is far more severe than is incurred in
normal operation. Thermal stresses may be excessive in the
heavy wall portions of the system such as drums, headers and
piping. It is prudent to consider this fact when performing the
blowing procedure and to limit the number of blowing cycles
(“blows”) to the minimum consistent with cleaning the system.
2. Before starting the steam blowing process, the start-up burners
should be turned off. The P.A. fan should remain in service.
This will minimize the extreme fluctuations in refractory face
temperatures, and a repurge of the unit may not be necessary.
3. Since the temporary steam line blowing piping may be de-
signed for lower pressure than the boiler, care must be used to
prevent overpressuring this piping during the entire steam line
blowing operation. The pressure in the temporary piping should
be monitored continuously and operators be alert to prevent
overpressure.
It is recommended that a means of overpressure protection be
provided in the temporary piping, such as, safety valves set at
the design pressure of the temporary piping.
4. It is difficult to avoid carryover from the steam drum to the su-
perheater during the steam line blowing operation. Therefore,
boiler water should not be treated with non-volatile chemicals
during this process, to avoid deposits of solid materials into the
superheater.
5. Ash drain shut-off valves to the ash screw coolers should be
closed, and the drains should be filled with ash or sand.
6. Main fuel and limestone slide gates should be closed and seal-
ing air provided downstream of slide gates.
7. The seal pot nozzles should be completely covered with ash or
sand in order to protect them from localized hot gases, when
F.A. blower is not in service.
2-8-TAB_7-3
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_7-4
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_7-6
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
2-8-TAB_8-i
CFB BOILER DESIGN AND OPERATION MANUAL
BOILER
MECHANICAL
Drum Internals
Inspect the drum internals for correct assembly and cleanliness. In-
sure that those internals are installed correctly.
Drum Centerline
Transfer the drum centerline to structural steel and to the gauge
glasses.
Drum Gauge Glass Check
Check the drum gauge glass installations and forward a detailed
sketch of same to FHI office. Verify the drum centerline. Insure that
the drum internal connections to the gauge glass are clear.
Drum Level Alarms & Trips
Set up the drum level alarms and trips.
Inspect Anti-Erosion Protection
Inspect all refractory and/or baffles to prevent erosion, to insure cor-
rect installation.
Vibration Baffles
Inspect the anti-vibration baffles for correct locations and support, if
installed.
Inspect Dead Air Spaces
Inspect the dead air spaces for tube interferences, sag support in-
stallations and cleanliness.
Furnace Inspection
Inspect the furnace to insure refractory and fluidizing nozzles correct-
ly installed, all fin welding is complete, and site welding is grinding to
meet requirement of design, and construction materials have been
removed.
Inspect Bottom Ash drain
Insure that bottom ash drain is installed correctly and will not inter-
fere with boiler expansion.
Refractory Inspection
2-8-TAB_8-1
CFB BOILER DESIGN AND OPERATION MANUAL
Check to insure that the proper refractory has been correctly poured
at lower furnace, bottom of S/H panel, all ports, access doors, soot-
blower openings and seals.
Burner Throats & Seals
Check that the refractory for the burners has been correctly poured,
both the burner throats and the seal cans behind each burner.
Expansion Interferences & Measurements
Walk down the unit looking for expansion interferences. Insure that
all interferences are corrected prior to initial firing. Mark all bumpers
and guides for future measurement of boiler expansion during opera-
tion.
Check Boiler Seals
Ascertain that all boiler seals are correctly installed and have the cor-
rect refractory where applicable.
Feed Stop & Check Valves
Insure that the valves are clean and in proper operating condition.
Stroke each valve and set up the open and closed positions. Verify
that the valves are installed for the proper direction of flow of the
feedwater.
Drain & Vent Inspection
Trace all boiler drain and vent piping for proper routing an interfer-
ences. Insure that all valves are stroked and are operable.
Chemical Feed System
Check that the pump set is in operating condition. Stroke all valves in
the system and set limit switches as supplied. Insure piping is routed
correctly, supported adequately, and will not interfere with boiler ex-
pansion. Verify that chemical feed discharge pipe in the economizer
outlet is correctly installed. Operate the system with water only to
check for leaks and proper operation.
Ash Removal System
Check that ash removal system is correctly installed. Verify that sys-
tem is sized to handle the expected ash loading for the fuel burned.
Insure that the ash removal system will not interfere with boiler ex-
pansion.
Spring Hanger Settings & Stops
Check all spring hangers for correct installation, remove all spring
stops and record cold set point of each hanger. Adjust those hangers
which are not at the correct initial cold set point.
2-8-TAB_8-2
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_8-3
CFB BOILER DESIGN AND OPERATION MANUAL
Expansion Joints
Check that all expansion joints are installed correctly, that movement
limits have correct clearances, and that all shipping bolts/straps have
been removed.
Damper Checkout
Check all flue and duct dampers for correct installation. Operate all
dampers normally to insure free and easy movement, prior to operat-
ing with the actuator.
Mark Damper Blade Shaft Ends
Insure that all damper blade shaft ends are clearly marked to indi-
cate their actual position externally to the unit.
Adjust Damper Limit Switches
Adjust the open and closed limit switches for each damper, insuring
that the correct open and closed position of the damper blades is
achieved.
Control Room Indication
Connect damper actuators and operate locally and from the control
room. Verify that the open and closed positions indicate properly in
the control room.
Damper Operation During Trip
Check the correct operation (full open, full close or stop) of all damp-
ers following a trip.
Flues & Ducts Available
The flues and ducts are available for air flow tests and subsequent opera-
tion.
FANS & BLOWERS
The majority of the work on the fans will be performed under the di-
rection of a service representative of the fan manufacturer.
Check Foundations
Insure that all foundations for fans & blowers and bearings are built
according to manufacturer's specifications.
Internal Inspections
Inspect the interior of each fan & blower for correct installation. In-
sure rotor is installed for correct rotation.
Inlet Screens and Silencer
Insure that fan inlet screens are installed correctly. Insure that blower
inlet filter and silencer are installed correctly.
2-8-TAB_8-4
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_8-5
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_8-6
CFB BOILER DESIGN AND OPERATION MANUAL
Check Voltages
Insure that the correct voltage is supplied to the system prior to en-
ergizing.
Check Oil Pump Station
Verify that the oil pump station is installed correctly and are ready for
operation.
Check Physical Installation
Check physical installation of each burner. Insure that the burners
are installed correctly.
Burner Centering
Insure that each burner is centered in its burner throat.
Check Ignitor and oil gun Installation
Check the physical installation of each burner ignitor and oil gun. In-
sure that the ignitor and oil gun are in the correct position when ex-
tended and retracted. Check and adjust the control valves.
Set Limit Switches
Adjust the limit switches for the extended and retracted position of
each ignitor and oil gun. Insure control room indication corresponds
to actual ignitor and oil gun positions. Adjust the limit switches on the
control valves.
Check-Out Dampers
Stroke all burner dampers and mark open and closed positions. Es-
tablish initial settings for all dampers based on contract specification.
Operate each damper locally and from the control room to insure
proper control and indication.
Check & Set Scanners
Insure that the flame detectors are installed correctly and the initial
sighting position has been set.
Check Shut-down & Light-Off Interlocks
Insure that the interlocks for the unit shut-down and for ignitor light-
off are installed and armed.
Control Room Indication
Verify that the control room indication of all ignition system functions
is complete and operable.
2-8-TAB_8-7
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_8-8
CFB BOILER DESIGN AND OPERATION MANUAL
Inspect the feeder both internally and externally and remove any
construction debris at this time.
Block Belt Scraper
Block the belt scraper in a position so that it does not contact the belt,
prior to bumping the feeder motors.
Adjust Belt Tension
Check the feeder belt tension and make any initial adjustments re-
quired.
Adjust Cleanout Chain
Adjust the cleanout conveyor chain tension.
Check Idler Rollers
Insure that the feeder idler rollers are free to rotate.
Bump Motors
Bump all motors to insure that all are operational and rotating in the
proper direction.
Adjust Discharge Limit Switch
Adjust the discharge limit switch of each feeder to actuate at the rec-
ommended distance from the feeder end plate.
Preset Controls
Preset and calibrate the feeder controls prior to the initial run-in. In-
sure that manufacturer's recommendations are followed strictly.
Run Feeder
Place each feeder in service and insure it operates correctly. Insure
that coal cannot enter the feeder for these initial run-ins.
Set Up Speed Controller
Adjust the feeder speed controller and calibrate the load cell accord-
ing to manufacturer's recommendations.
Check Belt Tracing
Insure that the belt tracks correctly.
Re-adjust Belt Tension
During the initial test runs, the feeder belt tension may require ad-
justment.
Shutdown Feeder & Close Doors
Following the recommended run-in time, remove the feeder from
service and close all access doors.
Check Feeder Calibration
2-8-TAB_8-9
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_8-10
CFB BOILER DESIGN AND OPERATION MANUAL
BURNER
CONTROLS &
FUEL SAFETY
Check Local Cabinets
Check all local cabinets for correct installation, material supply, and
weather tightness.
Check Wiring
Insure that the wiring from the control room to each burner is correct.
Insure Proper Voltages
Check that all supply voltages are correct prior to energizing the sys-
tems.
Alarms, Trips & Interlocks
Check and verify that all alarms, trips and system interlocks are con-
nected and are operable.
Simulate Control Functions
Simulate all of the system control functions, including alarms, trips
and interlocks.
Simulate Light-Off
Simulate a boiler light-off to insure all permissive, alarms, trips, and
interlocks operate correctly.
Simulate Oil Firing
Simulate boiler normal operation on oil firing and test all permissive,
alarms, trips, and interlocks.
SOOTBLOWER
The majority of the work on the sootblowers will be performed under
the direction of a service representative of the sootblower manufac-
turer.
Check Wiring & Voltages
Check the system wiring from the control room to each sootblower
and insure that supply voltages are correct prior to energizing the
system. Check motor grounds.
Check Local Control Boxes
Ascertain that all local control boxes are installed and wired correctly
and are weather tight.
Check Control Room Panel
Ascertain that the control room panel is correctly installed and wired.
Check Piping Installation
Verify that the physical layout of all sootblower piping is correct.
2-8-TAB_8-11
CFB BOILER DESIGN AND OPERATION MANUAL
2-8-TAB_8-12
CFB BOILER DESIGN AND OPERATION MANUAL
SPRAY SYSTEMS
Check Piping & Supports
Check that the spray system physical piping layout is correctly in-
stalled and supported.
Leak Test
Perform a leak test on the system. Also, perform a hydrostatic test as
required.
Clean Piping
Insure that all spray water piping has been cleaned.
Inspect Spray Control & Stop Valves
Insure that all spray control and stop valves function well.
Stroke Valves & Set Limit Switches
Stroke all of the valves manually and from the control room. Adjust
the open and closed limit switches. Insure proper control room oper-
ation and indication.
Check & Calibrate Thermocouples
Check that thermocouples are installed at appropriate points in the
system, that they are connected correctly, calibrated, and indicate in
the control room.
SAFETY VALVES
The majority of the work on the safety valves will be performed under
the direction of a service representative of the safety valve manufac-
turer.
Remove Hydro Plugs
Remove the hydrostatic test plugs.
2-8-TAB_8-13
CFB BOILER DESIGN AND OPERATION MANUAL
Clean Internals
Clean all valve internals per recommendations of the service repre-
sentative.
Lap Seats
Lap the seat of each safety valve as directed by the manufacturer's
representative, if necessary.
Assemble Valves
Assemble each valve following the inspections. Use molikote or
equivalent on all bolts to each future maintenance.
Remove Shipping Stops
Remove the shipping blocks from the safety valve springs.
Discharge Clearances
Insure that the expansion clearances between the discharge and ex-
haust piping are adequate. Also, check that exhaust piping supports
are installed correctly to allow for differential expansion.
Drains
Insure that the proper safety valve drains are installed and routed to
a safe location.
Set Safety Valves
Set the safety valve lift pressures.
Real Lift Pressures & Blow-down Tests
Raise boiler pressure and check the actual lift pressure of each safe-
ty valve. Also, check that the blow-down is correct.
ALARMS, TRIPS &
INTERLOCKS
Boiler Purge
Insure that all interlocks for a boiler purge are armed and operating.
Also, check that the proper unit trips hinder a successful boiler purge.
Drum Level
Check that drum level high and low level alarms and trips are set cor-
rectly and annunciate in the control room.
Start-up Burner System
Ascertain that all burner system alarms, trips and interlocks are func-
tioning, Especially check light-off permissive.
Furnace Draft
Check that the furnace draft alarms and trips are correctly calibrated
and armed.
2-8-TAB_8-14
CFB BOILER DESIGN AND OPERATION MANUAL
Damper Operation
Insure that all damper interlocks are correctly connected.
Fans and Blowers
Insure that all fan and blower start-up permissive are armed to pre-
vent improper operation of the fans and blower. Verify all fan and
blower alarms and trips.
Fuel Safety
Ascertain that the fuel safety system is properly designed for the in-
tended service and that all system alarms, trip and interlocks are
functioning correctly.
Manual Trip
Test the manual emergency boiler trip to insure it operates correctly.
INSTRUMENTATION
& CONTROL
Metals Temperatures
If applied, insure that all metal temperature thermocouples are cor-
rectly located and installed. Check each thermocouple for correct
operation prior to final terminations are made. Also, check that each
thermocouple indicates properly in the control room. Insure that
alarm points for high metal temperatures are set correctly and an-
nunciate.
Air & Gas Temperatures
Verify that all air and gas temperature thermocouples are correctly
installed and connected to indicate in the control room.
Furnace Temperature
Insure that the furnace temperature probes are available and indi-
cated in the control room.
Air & Gas Pressures
Check that all points of measurement of air and gas pressures
throughout the unit are connected to indicate in the control room and
are calibrated correctly.
Fans and Blower
Verify that all pertinent instrumentation on fan operation is correctly
installed and indicating in the control room. Insure that the fan and
blower controls function correctly in both the manual and automatic
modes.
2-8-TAB_8-15
CFB BOILER DESIGN AND OPERATION MANUAL
Air Flow
Insure that an indication of primary and secondary air flow is correct-
ly calibrated to indicate in the control room.
Cooling Water
Check that the instrumentation and control of cooling water is cor-
rectly installed and the correct alarms annunciate on loss of cooling
water.
Auxiliary & Atomizing Air
Both the local and control room instrumentation for auxiliary and at-
omizing air should be checked for correct installation. Insure that
controls for both systems function from the control system.
Drum Pressure & Level
Insure proper indication of the drum pressure and drum level in the
control room and locally at the drum. Verify the calibration of the var-
ious instruments. Check that the drum level controls are functioning.
Feedwater
Ascertain that an indication of feedwater is available in the control
room and that controls of feedwater flow and quality are functioning.
Advise your Regional Manager as to whether or not the feedwater
flow measurement includes spray water flow.
Flow, Pressure, Spray Temp.-SH/RH
Check for the proper installation and calibration of the indications of
flow, pressure, and spray water temperature for both the superheater
and reheater.
Start-Up Burner
Insure that there is proper indication in the control room and locally
of all burner system functions and pertinent operating data, such as
nature gas pressure, air pressure, etc.
Oxygen Analyzer
Verify that the oxygen analyzer is connected, calibrated and availa-
ble for service.
Steam Temperature Controls
Check that the attemperation valve and biasing damper controls are
connected and function correctly both in the hand and automatic
modes. Insure that there is control room indication of steam tem-
peratures before and after each spray station.
Sootblowers
2-8-TAB_8-16
CFB BOILER DESIGN AND OPERATION MANUAL
Verify that the controls and instrumentation for the sootblower sys-
tem are available for service.
Coal Feeders
Insure that there is control room indication of coal feeder operating
conditions and that all controls are connected and are available for
service.
Controls Automated
As unit operation permits, test the boiler controls in the automatic
mode of operation.
2-8-TAB_8-17
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
2-8 -TAB_9-i
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-ii
CFB BOILER DESIGN AND OPERATION MANUAL
INTRODUCTION
The procedures outlined in this section of the manual are intended
to serve as a guideline for manual and automatic operation. The
procedures include precautions which should be observed and the
proper operating sequences of the unit.
The procedures contained in this section of the manual describe
the proper operating sequences to ensure a safe and orderly start-
up and shutdown of the boiler. These procedures will also provide
temperature values to serve as a guideline to protect the refractory
as well as the boiler proper. As operating experience is gained and
controls are fine-tuned, the unit characteristics and actual operating
requirements will become evident to the operator.
Reference should be made to the controls description located
elsewhere in this manual for further operating details.
Reference should be made to the detailed manufacturers’ instruc-
tions found elsewhere in this manual for auxiliary equipment sup-
plied by them regarding operational and pre-operational procedures.
UNIT DESCRIPTION
The unit is a balanced draft, natural circulation, circulating fluid bed
(CFB) boiler.
The furnace is of a water - wall design with the lower portion refrac-
tory lined. Convective pass flue gas biasing dampers are provided
for reheat steam temperature control. There are six(6) coal feed
openings located on the furnace front wall. There are four (4) start-
up burners - two (2) located on each side wall. There are eight (8)
limestone feed points, six (6) on the furnace front wall and one (1)
in each seal pot return duct.
2-8 -TAB_9-1
CFB BOILER DESIGN AND OPERATION MANUAL
PRE-OPERATIONAL
PROCEDURES
Cleanup
Before initial firing and prior to each subsequent cold start-up, after
maintenance has been done on the unit, the furnace and auxiliary
equipment should be inspected and cleaned both internally and ex-
ternally. Any foreign material should be removed from the pressure
parts. Any grating, pipe lines, electric conduit, etc., that might re-
strict normal expansion of the unit should be cleared. All personnel
should be clear and access doors closed. A complete check list
should be prepared by operating personnel.
Chemical Cleaning
Specific procedures for boiling out elsewhere in this manual. Firing
procedures as outlined under “Lighting Off-Cold / Warm Startup”
should be used as a guide when operating the fuel firing equipment.
Blowing Steam
Lines
Prior to starting up a new unit or following major pressure parts re-
pairs on an older unit, the main steam lines and the reheater steam
lines should be blown out to remove scale and foreign matter,
thereby preventing damage to the turbine. This should be done af-
ter chemical cleaning and prior to setting boiler and superheater
safety valves. Consideration should be given to setting the reheater
safety valves before removing the temporary blow out piping.
Refer to “Steam Line Blowing Procedures” elsewhere in this manual
for recommended operating procedures and precautions.
Setting Safety
Valves
Setting of the safety valves on the drum and superheater should be
done prior to turbine rolling. Refer to the safety valve manufactur-
er’s instructions for setting procedures. A conservative firing rate
should be maintained, limiting the cyclone exit gas temperature to a
maximum of 535°C in order to protect the superheater pressure
parts and associated equipment, including the safety valves, during
setting of the safety valves. The reheater safety valves may be set
after reheater steam line blowing or while the turbine is carrying a
light load, by closing down on the intercept valves until a reheat
2-8 -TAB_9-2
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-3
CFB BOILER DESIGN AND OPERATION MANUAL
CURVE NO. 1
2-8 -TAB_9-4
CFB BOILER DESIGN AND OPERATION MANUAL
COLD / WARM
START-UP
A cold or warm start is considered to be when the temperature of
the fluidized bed at the startup burner elevation is below 700°C and
a purge cycle must therefore be included. The temperature of the
slumped bed prior to fluidization at the lowest thermocouple eleva-
tion provides an indication only (not a permissive) whether or not a
purge cycle may be required. Cold or warm start-up includes purg-
ing the unit, heating up the furnace with the startup burners above
550°C, introducing solid fuel with the start-up burners operating,
and final heat-up solely with solid fuel, above 700°C on solid fuel
only.
NOTE: Permissive temperature for coal burning
depends on coal property. Above permissive tem-
perature is according to design coal property. Any
burning coal is different from design coal, permis-
sive temperature must be tested during commis-
sioning or start-up.
Preparation for
Lighting-Off and
Purging
It is assumed that at this time the following preparatory work has
been completed:
1. The unit has been chemically cleaned, that the steam lines
have been blown, that the safety valves have been set, that the
unit has sufficient bed material, and that the unit has been filled
to slightly above the normal operating level with properly treated
feedwater.
CAUTION: The differential temperature between
economizer water outlet temperature and drum
metal temperature must never exceed 110°C. This
is to avoid thermal shocking the drum.
2. All control systems have been checked out and are available
for service.
2-8 -TAB_9-5
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-6
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-7
CFB BOILER DESIGN AND OPERATION MANUAL
11. The soot blowing equipment has been checked for proper op-
eration and the system is in the startup condition (all blowers
retracted, main steam supply valves isolation open.)
12. All Desuperheater Spray Water Control Valves are closed.
13. All Boiler, Superheater and Reheater drain and vent valves are
in the start-up position. Feedwater regulating valves closed
(manual control). All boiler drain and blowdown valves closed.
Main steam stop valve and/or turbine throttle valve closed.
Drum vent open. Water gauge valves open (locked open). Su-
perheater and Reheater header drains and vents and main
steam line drains open (see Note below).
2-8 -TAB_9-8
CFB BOILER DESIGN AND OPERATION MANUAL
14. The furnace and seal pots should be pre-charged with bed ma-
terial in order to maintain proper bed differential pressures.
Sized sand as bed material is highly recommended.
15. The turbine - generator is available for service and has been
prepared for service as described in the manufacturer’s instruc-
tions.
Initial Firing
Precautions
During start-up, warming up the unit to solid fuel firing conditions is
accomplished with the start-up burners.
When bringing the unit up to steam pressure and temperature, the
saturated steam temperature rise must be limited to 110°C, per
hour (see Note). The “Maximum Allowable Rate of Pressure
Change for Normal Startups and Shutdowns” curve shows the cor-
responding rate of drum pressure increase.
NOTE: It is recommended that during initial start of
a new unit a relatively slow rate of pressure in-
crease be followed, in order to allow sufficient time
for checking expansion movements and to permit
the operators to become familiar with the character-
istics of the unit and auxiliaries.
2-8 -TAB_9-9
CFB BOILER DESIGN AND OPERATION MANUAL
During all start-ups the firing rate should be controlled to keep the
maximum cyclone exit gas temperature below 535°C until the tur-
bine is synchronized. After rolling the turbine, the steam tempera-
ture and pressure rise at the turbine throttle should at all times be in
accordance with the limits prescribed by the turbine manufacturer.
NOTE: For the first few start-ups, until the refracto-
ry has seasoned, the furnace heat-up rates should
be limited to 65°C per hour. Once the unit has sea-
soned, the furnace heat-up rates can be increased
to follow the startup curves.
STEAM
TEMPERATURE AND
PRESSURE
CONTROL (PRIOR
TO UNIT
SYNCHRONIZATION)
During start-up of this unit, the HP and LP turbine steam bypass
system can be used to control steam temperature and pressure as
required to the turbine, and convective pass flue gas biasing damp-
ers can also put in service to assist steam temperature control if
necessary. Refer to the turbine supplier’s operating procedures for
this system’s details. Once the turbine/generator has been syn-
chronized and reheat flow has been established to the boiler re-
heater, the convective pass flue gas biasing dampers can be put in
service to control reheat steam temperature to the turbine as re-
quired.
AIR PREHEATER
PROTECTION
DURING UNIT
START-UPS ON OIL
It is strong recommendation to have the air preheater soot blowing
system continuously in service when firing oil to start up a boiler.
This measure is intended to help avoid air preheater fires due to
accumulation of oil vapor on heat transfer surfaces or ash particles
in the air preheater baskets. Retractable soot blowers are installed
at the cold end and hot end of the air preheater on the gas side.
2-8 -TAB_9-10
CFB BOILER DESIGN AND OPERATION MANUAL
For unit loads below 10% MCR steam flow, unnecessary high fluc-
tua-tions in furnace draft [more than ± 6.35mm w.g. (± 0.25" w.g.)]
should be avoided. Also, any steam that is available can and
should be used for air preheater soot blowing as long as sufficient
steam pressure is available (per sootblower instruction manual).
When this minimum steam pressure has been reached, continuous
cold end and hot end blowing should be initiated and continued un-
til 10% MCR steam flow is reached. After that air preheater soot
blowing can be reduced to intermittent operation, once every four to
eight hours or as required, depending on the fuel being fired.
Lighting-Off - Cold /
Warm Start
Before a cold or warm unit can be fired, a purge cycle is required to
obtain start-up burner ignition permit.
2-8 -TAB_9-11
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-12
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-13
CFB BOILER DESIGN AND OPERATION MANUAL
20. Before raising a vacuum in the condenser, make sure that all
the appropriate vents or drains including all reheater vents or
drains that are open to atmosphere are closed. Leave drains or
vents connected to the condenser open until the turbine is car-
rying a light load.
21. Start rolling the turbine as soon as the minimum permissible
start-up pressure and temperature, specified by the turbine
manufacturer, are reached. Refer to turbine manufacturer’s in-
structions.
22. When bringing the turbine up to speed, the firing rate should be
controlled to prevent the cyclone exit gas temperature from ex-
ceeding 535°C to protect the boiler superheater and reheater.
When the turbine is up to speed, it may be synchronized and
the 535°C cyclone exit gas temperature limit may be discontin-
ued. In no case should the firing rate exceed that which is nec-
essary to satisfy steam demand.
NOTE: If the unit is put on the line before operating
pressure is reached, further increase of firing rate
should be in accordance with the start-up rates.
2-8 -TAB_9-14
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-15
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-16
CFB BOILER DESIGN AND OPERATION MANUAL
NORMAL
OPERATION - UNIT
LOAD CHANGE
During normal operation the unit will be controlled automatically.
The operator will have to pay special attention to the unit’s opera-
tion to ensure that the flue gas emissions limits are not exceeded,
and that the superheater and reheater steam flow, temperature,
and pressure are maintained.
Decreasing Load
To reduce load, reduce the steam flow to the turbine. This is ac-
complished by decreasing the fuel flow to the furnace. Adjust the
solid fuel rate and/or take out of service an operating fuel feeder.
Increasing Load
To increase load, increase the steam flow to the turbine. This is ac-
complished by increasing the solid fuel flow to the furnace. Adjust
the fuel rate and/or place another fuel feeder in operation.
CAUTION: Some backsifting of bed material from
the furnace into the air plenum beneath the furnace
may occur during startup or periods of operation
below 50% load where primary air flow is signifi-
cantly reduced below the full load value. If the ple-
num is not periodically drained of this material,
amounts sufficient to impact PA fan performance
and possibly damage the plenum support structure
may accumulate. It is therefore recommended that
the plenum drains be operated once per shift during
these periods of low primary air flow operation.
Draining of the plenum is not normally required dur-
ing periods of operation above 50% load.
NORMAL
SHUTDOWN TO
COLD
The following procedures for normal shutdown to cold are based on
the assumption that the unit is operating at full load on automatic
control and that it is the intention to reduce the pressure to zero and
cool the boiler completely.
2-8 -TAB_9-17
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-18
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-19
CFB BOILER DESIGN AND OPERATION MANUAL
NORMAL
SHUTDOWN TO
HOT STANDBY
It is assumed that the boiler will be shut down for a relatively short
period of time (8 hours or less) and existing pressure and tempera-
ture conditions will be substantially maintained. The intention of this
procedure is to keep the furnace bed temperature as much above
the solid fuel firing permissive as possible. The superheater and
reheater circuits should be depressurized to a desired pressure at
which the boiler is to be held via the HP and LP turbine steam by-
pass system and should have some flow at all times.
A procedure similar to that for normal shutdown to cold should be
followed except:
1. Do not reduce drum pressure in line with unit load reduction.
The rate of pressure drop should be much smaller than the rate
followed during normal shutdown. Refer to the turbine manufac-
turer’s instructions.
2-8 -TAB_9-20
CFB BOILER DESIGN AND OPERATION MANUAL
2. Keep the water level in sight in the gage glass. As the unit
cools and the water shrinks, make up should be added intermit-
tently to prevent the water from dropping out of sight in the
gage glass.
NOTE: The operator should observe the gage
glass periodically to always be aware of the actual
drum level so that he can take the appropriate ac-
tion to reestablish water level when the unit is being
restarted.
3. Trip the main fuel. Keep the ID fan, SA fan, PA fan and fluidiz-
ing blower operating to remove volatiles and burn the remaining
fuel in the bed. This typically is indicated by an increase in oxy-
gen level and a drop in bed temperature. Then shut off the PA
fan to maintain the highest possible bed temperature above sol-
id fuel firing permissive.
4. After the cyclone exit gas outlet temperature is cooled to 535°C
(in order to protect the backpass tubing) and air preheater gas
inlet temperature below 120°C, then the SA fan can be shut-off.
Run the FA blower for another 10 minutes to purge the seal
pots of combustible gases, and to remove solids from the cy-
clones, cyclone stand legs, and seal pots. After the fluidizing
2-8 -TAB_9-21
CFB BOILER DESIGN AND OPERATION MANUAL
blowers are shut off, then the induced draft fan should be shut
off and the secondary air nozzle dampers closed.
HOT RESTART
Assuming the boiler has been down for a comparatively short peri-
od of time (8 hours or less) and considerable drum pressure was
maintained, a hot restart may be possible. A hot restart is consid-
ered to be when the temperature of the fluidized bed at the startup
burner elevation is above the purge bypass permit temperature
700°C therefore eliminating the requirement for a purge cycle. The
following procedures should be used in restarting the unit :
1. Make a general inspection of the boiler and check the points as
mentioned under normal cold start-up.
2. If the air preheater is shut down, when restart the air preheater,
must refer to the air preheater instructions for restart require-
ment of operating details.
3. Start the air preheater if all required conditions in air preheater
instructions are satisfied.
4. Start the ID fan, FA blower, and SA fan.
5. Open wide all superheater drains to allow complete draining of
superheater headers and/or elements. After draining, close all
drains except the Superheater Backpass Lower Front Inlet
Header and Backpass Outlet Header Drains and the start-up
drains (Main Steam Line Vents and Drains). Keep the Back-
2-8 -TAB_9-22
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-23
CFB BOILER DESIGN AND OPERATION MANUAL
Turbine Valve
Closure
If a loss of load should cause the turbine valves to close, all fuel is
tripped automatically. If HP and LP bypass are available, PA flow
shall reduce instantaneously, then leave the fans and blower on to
reduce the gas and solid temperatures below the above mentioned
temperatures. If HP and LP bypass aren’t available to in service,
PA fan shall stop automatically. And the convective pass flue gas
biasing dampers can be closed on the reheater side and opened on
the superheater side to minimize the flow of hot flue gases over the
reheater. Leave SA fan and ID fan on to reduce gas temperature
below the above mentioned temperature.
If an immediate restart is possible, as the turbine is still rolling and
will be available to take steam as soon as the governor has the tur-
bine speed under control (See note below). If immediate turbine re-
start is not possible and the turbine is tripped, the reheater conden-
ser drains should be opened.
NOTE: Refer to turbine manufacturer’s instructions
for no-load operating procedures and limitations.
Turbine Trip
If a loss of load occurs in which the turbine is tripped, all fuel should
be automatically and instantaneously tripped.
Boiler operation procedure is as same as above described in tur-
bine valve closure.
The reheater safety valves will protect against over pressure in the
reheater. The reheater condenser drains should be opened to
evacuate the condensed steam in the reheater. Depressurize the
reheater circuit.
2-8 -TAB_9-24
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-25
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-26
CFB BOILER DESIGN AND OPERATION MANUAL
3. Keep ID fan, SA fan, and fluidizing air blower on. Shut-off fluid-
izing air blower when cyclone, cyclone stand leg and seal pots
are clear of solids.
WARNING: If the fans are shut down with an air
preheater gas inlet temperature above 120°C, the
air preheater must be kept rotating until the flue
gas temperature below 120°C to prevent the rotor
jamming due to excessive expansion and cause ro-
tor sitting stationary in high heat levels. (Refer to air
preheater instructions)
2-8 -TAB_9-27
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-28
CFB BOILER DESIGN AND OPERATION MANUAL
2-8 -TAB_9-29
CFB BOILER DESIGN AND OPERATION MANUAL
Loss of SA Fan
1. Trip fuel and limestone feed, PA Fan, and startup burners (if in
use).
2. Shut off the fluidizing air blower after purging the cyclones, cy-
clones stand legs, and seal pots.
3. Shut off the induced draft fan after the cyclone exit gas temper-
ature has been reduced to 535°C.
WARNING: If the fans are shut down with an air
preheater gas inlet temperature above 120°C, the
air preheater must be kept rotating until the flue
gas temperature below 120°C to prevent the rotor
jamming due to excessive expansion and cause ro-
tor sitting stationary in high heat levels. (Refer to air
preheater instructions)
2-8 -TAB_9-30
CFB BOILER DESIGN AND OPERATION MANUAL
Loss of Induced
Draft Fan
1. Trip turbine. Trip fuel and limestone. Shut-off PA fan, SA fan
and fluidizing air blower.
2. Depressurize the superheater and reheater circuits.
3. Maintain drum water level.
4. Open all dampers to remove heat from Furnace, Cyclone and
Backpass.
WARNING: If the fans are shut down with an air
preheater gas inlet temperature above 120°C, the
air preheater must be kept rotating until the flue
gas temperature below 120°C to prevent the rotor
jamming due to excessive expansion and cause ro-
tor sitting stationary in high heat levels. (Refer to air
preheater instructions)
2-8 -TAB_9-31
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
TITLE SECTION
ECONOMIZER .................................................................................................................... 3
3-0-1
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
3-1-i
CFB BOILER DESIGN AND OPERATION MANUAL
DESCRIPTION
The circulating fluidized bed boiler utilizes natural circulation in the
water cooled circuits of the furnace and pendant evaporative panels.
The water flow path can be followed on the referenced Flow Diagram
for the Water and Steam Circuits (Combustor Circuitry). The ele-
ments which make up the flow path are essentially numbered con-
secutively. Where parallel flow paths exist, first one and then the
other circuits are numbered.
Feedwater enters the unit through the economizer elements (E-1)
through (E-17) (Economizer Circuitry refers to Part 3, Section 3), and
is mixed with boiler water in the steam drum (C-1). Water flows from
the drum (C-1) through four(4) downcomers (C-2) to the lower ring
headers (C-3) (C-8) (C-11). The ring headers assure proper distribu-
tion of the water to the furnace waterwalls.
From the ring header the water rises through the upper furnace wa-
terwall tubes where it absorbs heat. The front wall tubes and roof
tubes (C-4), rear wall tubes (C-9), and side wall tubes (C-12) form
parallel flow paths. The resulting mixture of water and steam collects
in the waterwall outlet headers (C-5) (C-13) and is discharged into
the steam drum (C-1) through the riser tubes (C-6) (C-14).
A water flow path exists parallel to the furnace waterwalls. Six(6)
separate downcomers (C-21) supply water to the evaporative panel
inlet headers (C-22) located at the upper furnace front wall. The wa-
ter continues into the evaporative fin welded panels (C-23) where it
absorbs heat. The resulting mixture of water and steam collects in
the evaporative panel outlet headers (C-24) and is discharged into
the steam drum (C-1) via riser tubes (C-25). In the steam drum the
steam and water are separated (see "Drum lnternals”), the steam
goes to the superheater (see “Superheater”) and the water is re-
turned to the water side of the steam drum to be recirculated.
3-1-1
CFB BOILER DESIGN AND OPERATION MANUAL
3-1-2
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
3-2-i
CFB BOILER DESIGN AND OPERATION MANUAL
DESCRIPTION
The function of the steam drum internals is to separate the water
from the steam generated in the waterwalls of the furnace and to re-
duce the dissolved solids contents of the steam to below the pre-
scribed limit. Separation of steam from water in the drum is general-
ly performed in three stages, with the first two stages occurring in the
turbo-separators, and the final stage taking place at the top of the
drum just before the steam enters the connecting tubes.
The steam water mixture entering the drum (C-1) from the riser
tubes (C-6) (C-14) (C-25) is collected in the chamber formed by in-
ternal baffles (refer to the referenced flow diagrams of combustor for
element numbers). At the lower end of the baffles the steam water
mixture is forced upward through two rows (37 per row) of turbo sep-
arators (refer to Figure 1).
3-2-1
CFB BOILER DESIGN AND OPERATION MANUAL
3-2-2
CFB BOILER DESIGN AND OPERATION MANUAL
OPERATION
General
Operation of the steam drum is directly related to overall boiler oper-
ation. Therefore, operating procedures pertaining to the steam drum
are discussed in detail in the Unit Operating Procedures included in
this Manual.
3-2-3
CFB BOILER DESIGN AND OPERATION MANUAL
3-2-4
CFB BOILER DESIGN AND OPERATION MANUAL
3-2-5
CFB BOILER DESIGN AND OPERATION MANUAL
SECTION 3 - ECONOMIZER
TABLE OF CONTENTS
3-3-i
CFB BOILER DESIGN AND OPERATION MANUAL
ECONOMIZER
DESCRIPTION
The function of the economizer is to preheat the boiler feedwater be-
fore it is introduced into the steam drum, by recovering some of the
heat of the flue gases leaving the furnace. The economizer water
flow path can be followed on the referenced Flow Diagram for the
Water and Steam Circuits (Economizer Circuitry).
There are three economizer sections located in the convective back-
pass. First economizer section is a common economizer (as Eco.1)
located directly above the Ljungstrom rotary air preheater. It is com-
posed of one(1) bank of 115 parallel bare tube assembly (E-2) ar-
ranged in horizontal rows in such a manner that each row is in line in
relation to the row above and below.
Second economizer splits into two parallel economizers (as Eco.2-R
& Eco.2-S) located in each rear passes and above each flue gas bi-
asing dampers respectively. The Eco.2-R is located in reheater
backpass and composed of one(1) bank of 106 parallel bare tube
assembly (E-10) arranged in horizontal rows. The Eco.2-S is located
in superheater backpass and composed of one(1) bank of 106 paral-
lel bare tube assembly (E-7) arranged in horizontal rows.
Third economizer (as Eco.3) is located in superheater backpass and
below finish superheater banks. It is composed of two(2) banks of
106 parallel bare tube assemblies (E-14 & E-15) arranged in horizon-
tal rows.
Feedwater is supplied to the economizer inlet header (E-1) via feed
stop and check valves. The feedwater flow is upward through the
economizer, that is, counterflow to the hot flue gases. Most efficient
heat transfer is hereby accomplished, while the possibility of steam
generation within the economizer is minimized by the upward water
flow.
From the common economizer tube assembly (E-2), heated water
splits into two parallel paths and flows through each parallel econo-
3-3-1
CFB BOILER DESIGN AND OPERATION MANUAL
mizers (E-7 & E-10) in each backpass respectively, and then recom-
bines at junction header (E-11). The combined heated water flows
through Eco.3 assemblies (E-14 & E-15) via link E-12, with counter-
flow to the hot flue gases, and to the economizer outlet header (E-
16). The heated feedwater is then led to the steam drum (C-1) via
the economizer outlet link (E-17).
OPERATION
Operation of the economizer is not independent of the rest of the
boiler. Therefore, operating procedures for the economizer are dis-
cussed in detail under Unit Operating Procedures.
The frequency with which soot blowers are used depends entirely on
local conditions. When the economizer is first placed in operation,
the economizer soot blowers should be blown about once every shift.
Observation of the increase in draft loss between blowings will de-
termine how long an interval may be set as a standard. In many cas-
es, it has been found that blowing the economizer soot blowers once
a day or less is sufficient. For further details, refer to the Soot Blow-
ing Philosophy section located in Part 5, Section 2.
MAINTENANCE
Before starting up the furnace and at each extended outage the
economizer should be inspected externally and if necessary cleaned.
If the installation is new, accumulation of erection material (wood, in-
sulation, welding rods, etc.) is not unusual. Large debris should be
removed manually, followed by washing down the economizer banks
by means of a hose and water.
Any exposed insulation should be kept in good condition at all times.
3-3-2
CFB BOILER DESIGN AND OPERATION MANUAL
3-3-3
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
TITLE SECTION
SUPERHEATER.................................................................................................................. 1
REHEATER ......................................................................................................................... 3
4-0-1
CFB BOILER DESIGN AND OPERATION MANUAL
SECTION 1 - SUPERHEATER
TABLE OF CONTENTS
INSPECTION................................................................................................................. 4-1-5
4-1-i
CFB BOILER DESIGN AND OPERATION MANUAL
SUPERHEATER
DESCRIPTION
The arrangement, tube size and quantity of the Superheater ele-
ments are shown on the Pressure Part Arrangement drawings. The
steam flow path can be followed on the referenced Flow Diagram for
the Superheater Steam Circuits (refer to Fig. 1).
Superheater
The Superheater is composed of four basic stages or sections; Fin-
ishing Horizontal Sections (S-35), (S-36) and (S-37), #1 and #2 Fur-
nace Panel Sections (S-18), (S-20), (S-26) and (S-28) and the con-
vective pass (Backpass) Enclosure Wall, Division Wall and Roof
Sections (S-3), (S-6), (S-8), (S-9) and (S-13).
The Finishing Sections are located above No.3 Economizer Horizon-
tal Section (E-15) and consist of three(3) banks (S-35), (S-36) and
(S-37) of 106 [50.8mm O.D. tube] assemblies spaced on 114.3mm
centers.
#1 and #2 Furnace Superheater Panel Sections (S-18), (S-20), (S-26)
and (S-28) are located in the upper front furnace area opposite the
cyclone inlets. They consist of seven(7) [44.45mm O.D. tube] fin-
welded assemblies spaced on 622.3mm centers from the centerline
of the furnace for each sections.
The Convective Pass (Backpass) Enclosure Wall and Roof Sections
form the sidewall (S-3) constructed of fin welded panels of 44.45mm
O.D. tubes, front wall (S-6), roof (S-8) and rear wall (S-9) constructed
of fin welded panels of 50.8mm O.D. tubes. The division wall (S-13)
of the vertical gas pass splits convective pass into two parallel gas
passes and it is constructed of fin welded panels of 50.8mm O.D.
tubes.
Steam Flow
The course taken by steam from the steam drum to the superheater
finishing outlet header can be followed on the referenced Flow Dia-
gram for the Superheater Steam Circuits. The elements which make
4-1-1
CFB BOILER DESIGN AND OPERATION MANUAL
4-1-2
CFB BOILER DESIGN AND OPERATION MANUAL
4-1-3
CFB BOILER DESIGN AND OPERATION MANUAL
DESIGN DATA
Design information for the superheater is contained in Table 1 in Part
2, Section 7, Tab 1 of this manual.
OPERATION
Operation of the superheater is not independent of the rest of the
steam generator. Therefore, operating procedures for this compo-
nent are discussed in the section "Unit Operating Procedures", lo-
cated in Part 2, Section 8, Tab 9. However, basically the following
rules can always be followed:
General
Make sure the superheater convective pass walls and main steam
lines are completely drained (especially after a hydrostatic test), by
opening inlet and outlet header drains before lighting off. Close the
backpass lower header drains immediately after rolling the turbine,
see “Unit Operating Procedures” for exceptions.
The main steam line vents and drains serve as starting vents. They
are kept open until the turbine is under light load. These valves may
be throttled as drum pressure increases, providing a sufficient steam
flow through the superheater is assured at all times (refer to start-up
procedures in the section "Unit Operating Procedures"). The drain
valves near the turbine should be operated in conjunction with the
startup vents to provide additional steam flow and to drain and warm
the main steam line prior to turbine rolIing.
MAINTENANCE
It is essential that suitable arrangements are made to assure cleanli-
ness of the external and internal surfaces of the Superheater at all
times. Ash accumulations result in unequal gas distribution, ineffi-
cient heat transfer, and possible localized overheating. Suitably lo-
cated soot blowers operated in the proper cycle, normally provide
adequate means of keeping surfaces clean.
Proper feedwater treatment and control of steam quality and carry-
over are essential to assure cleanliness of interior surfaces of super-
heaters. Overloads, fluctuating load, high water level, foaming, high
solids concentrations, etc., all contribute to deposits on interior sur-
faces. Accumulation of these deposits inside the tubes will lead to
4-1-4
CFB BOILER DESIGN AND OPERATION MANUAL
4-1-5
CFB BOILER DESIGN AND OPERATION MANUAL
S-15
D/A #2
S-31
4-1-6
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
4-2-i
CFB BOILER DESIGN AND OPERATION MANUAL
SUPERHEATER DESUPERHEATERS
DESCRIPTION
Two (2) spray type superheater desuperheaters are provided on
each unit. One (S-23) is located in the connecting link between the
in-furnace superheater panel #1 outlet header (S-21) and the in-
furnace superheater panel #2 inlet header (S-25). The second su-
perheater desuperheater (S-31) is located in the connecting link be-
tween the in-furnace superheater panel #2 outlet header (S-29) and
the finishing superheater inlet header (S-34) to permit reduction of
steam temperature when necessary and to maintain the tempera-
tures at design values within the limits of the nozzle capacity.
Temperature reduction is accomplished by spraying water into the
path of the steam through a nozzle at the entering end of the desu-
perheater. The spray water comes from the boiler feedwater system.
It is essential that the spray water be chemically pure and free of
suspended and dissolved solids, containing only approved volatile
organic treatment material, in order to prevent chemical deposition in
the superheater and carry-over of solids to the turbine.
CAUTION: During start-up of the unit, if desuper-
heating is used to match the outlet steam tempera-
ture to the turbine metal temperatures, care must
be exercised so as not to spray down below a min-
imum of 11°C above the saturation temperature at
the existing operating pressure. Desuperheating
spray is not particularly effective at the low steam
flows of start-up. Spray water may not be complete-
ly evaporated but be carried through the heat ab-
sorbing sections to the turbine where it can be a
source of considerable damage. During start-up
alternate methods of steam temperature control
should be considered.
4-2-1
CFB BOILER DESIGN AND OPERATION MANUAL
4-2-2
CFB BOILER DESIGN AND OPERATION MANUAL
BLOWOUT
PROCEDURE FOR
DESUPERHEATER
SPRAY WATER
LINES
The spray water lines should be blown out before using the desuper-
heaters on a new unit and after repairs on the spray water lines have
been made. They may also be blown when there appears to be any
indication of plugging. Always have full pressure on the boiler when
blowing out the desuperheater.
Each desuperheater should be blown out in the following sequence:
1. With the isolating valves closed, open the valves in the blowoff
connection and then open the bypass valve for 1 minute.
2. With the bypass valve closed and the blowoff valves open, open
the isolating valves and then open the control valve for 1 minute
(from the control station). Close the isolating valves and the con-
trol valve but leave the blowoff valves open for another minute to
clear the waste line before restoring the system to its operating
status.
4-2-3
CFB BOILER DESIGN AND OPERATION MANUAL
4-2-4
CFB BOILER DESIGN AND OPERATION MANUAL
SECTION 3 - REHEATER
TABLE OF CONTENTS
INSPECTION................................................................................................................. 4-3-3
4-3-i
CFB BOILER DESIGN AND OPERATION MANUAL
REHEATER
DESCRIPTION
The arrangement, tube size and quantity of the Reheater elements
are shown on the Pressure Part Arrangement drawings. The steam
flow path can be followed on the referenced Flow Diagram for the
Reheater Steam Circuits (refer to Fig. 1).
Reheater
The Reheater is composed of one section located in front pass of the
convective split backpass and consists of four banks of 57.2 mm O.D.
tube assemblies spaced on 114.3mm centers.
Steam Flow
The course taken by steam from the cold RH inlet lead to the hot RH
outlet lead can be followed on the referenced Flow Diagram for the
Reheater Steam Circuits. The Reheater steam flow is as follows:
Reheater inlet desuperheater (R-1) - Reheater inlet header (R-2) -
Reheater horizontal spaced lower, lower intermediate, upper inter-
mediate and upper assemblies (R-3), (R-4), (R-5) and (R-6) - Re-
heater outlet header (R-7). Reheat steam from the Reheater outlet
header (R-7) goes to the turbine via the "hot" reheat line.
Protection and
Control
4-3-1
CFB BOILER DESIGN AND OPERATION MANUAL
4-3-2
CFB BOILER DESIGN AND OPERATION MANUAL
4-3-3
CFB BOILER DESIGN AND OPERATION MANUAL
4-3-4
CFB BOILER DESIGN AND OPERATION MANUAL
4-3-5
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
TITLE SECTION
5-0-1
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
5-1-1
CFB BOILER DESIGN AND OPERATION MANUAL
AIR FLOW
Air flow through each unit is handled by one primary air (PA) fan, one
secondary air (SA) fan, and two fluidizing air (FA) blowers (one oper-
ating continuously and one installed spare). The air is utilized for:
1. Combustion and bed fluidization - Primary air.
2. Combustion and bed fluidization - Secondary air.
3. Fluidization and grease air - Fluidizing air.
Primary Air
One (1) primary air (PA) fan supplies combustion air and fluidizing air
to the furnace grate, purge air to the gravimetric fuel feeders, sealing
air to the fuel chutes between the furnace isolation slide gate valve
and the furnace, and fuel chute sweep air. Primary air used for com-
bustion bed fluidization and fuel chute sweep air is preheated by
means of the Ljungstrom type air preheater. Primary air used for
purge and sealing air is taken from the cold air duct leaving the PA
fan.
Control of the primary air flow is obtained by positioning the PA fan
inlet guide vanes. These vanes are controlled by a control loop as-
sociated with the DCS.
Secondary Air
One (1) secondary air fan supplies combustion air and fluidizing air
to the furnace and combustion air to the start-up burners. The sec-
ondary air that is preheated by means of the Ljungstrom type air
preheater enters the furnace via multiple ports located in the front
and rear walls of the furnace and through the start-up burners.
Control of the secondary air flow is obtained by positioning the SA
fan inlet guide vanes. These vanes are controlled by a control loop
associated with the DCS.
5-1-2
CFB BOILER DESIGN AND OPERATION MANUAL
Fluidizing Air
Two (2) 100% capacity fluidizing air (FA) blowers are installed, with
one blower operating continuously and the other an installed spare.
Fluidizing air is used to fluidize the seal pots and to provide grease
air to the cyclone cones and seal pots.
A check valve is located at each blower discharge to prevent back-
flow of furnace gases and ash if the blower is out of service. During
normal operation the blower flow is determined by the system re-
sistance. When there are solids in the seal pots, the system re-
sistance due to the solids level will be constant over the load range.
FLUE GAS FLOW
Flue gases travel upward in the furnace, through the cyclones and
then downward through the backpass to the Ljungstrom type air pre-
heater. In the air preheater, the residual heat of the flue gases is utilized
to preheat the primary and secondary air streams. From the air preheater,
the flue gases are drawn by the one (1) induced draft (ID) fan
through the backend flue gas cleaning equipment and are dis-
charged to the stack.
5-1-3
CFB BOILER DESIGN AND OPERATION MANUAL
TABLE OF CONTENTS
5-2-I
CFB BOILER DESIGN AND OPERATION MANUAL
INTRODUCTION
The soot blowing system for this unit has been designed on the
basis of specific parameters. That is, in determining the number
and type of blowers, blower location and operating sequences, the
characteristics of the fuel to be burned, the configuration of the
heat-absorbing surfaces of the boiler and past experience with this
type of unit, were taken into account.
OPERATIONS
Soot blowers are provided to fulfill a need. Operating practices
should be modified as the needs change. For this reason, ample
flexibility is provided in the system to enable manual selective op-
eration in addition to fully automatic control.
Intelligent use of the soot blower system offers the following ad-
vantages:
5-2-1
CFB BOILER DESIGN AND OPERATION MANUAL
Superheater and
Reheater Area
5-2-2
CFB BOILER DESIGN AND OPERATION MANUAL
5-2-3