PLANNING This is the stage prior to the commencement of the project tasks. This
takes place at a date before the project start date.
34 To add a baseline go to the Project Tab and Set Baseline. There are options for
up to 11 Baselines and also Interim Plans. You can now resave the plan. As work
is undertaken it will be compared to the plan.
CONTROL This is the stage when the project gets underway and control is required
in order that the programme is achieved. The date when this is done is after the
project start date.
35 Re-examine the Tracking Gantt. Black relates to the original plan, blue and red
to the actual plan. As work gets under way actual data and progress may well be
different to plan. This requires control by management.
36 Double click on activity A. This provides a screen in which progress data can be
entered. Change the Start Date A by a delay of 2 days. If the Planning Wizard
asks you to select 3 choices, consider these and select the middle option – move
the task and keep the link.
37 Re-examine the Tracking Gantt and Project, Project Information, Statistics
noting changes. (Finish is now 18/02/2020 and Key Project Milestone is later).
38 Double click on activity C. In the Advanced tab change from Start as soon as
possible to as late as possible. Look at effect on Tracking Gantt (activity C is
now critical). This illustrates the effect of activity float. Note critical activities
have no float.
39 The percentage completion can be recorded for each activity as the project
proceeds.
PROJECT DATA
ACTIVITY MILESTONE DURATION DEPENDS ON FIXED
COST £
- START 0 - 10000
A - 20 START 5000
B - 8 START 600
C - 16 START 2000
D - 5 WATERTIGHT 3500
E - 8 WATERTIGHT 5500
F - 14 A 4500
- KEY PROJECT 0 B,F -
MILESTONE
- FINISH 0 C,D,E -