Professional Documents
Culture Documents
Geothermal Power Generation
Geothermal Power Generation
CONTENTS
Cover Photo:
Geothermal energy is receiving
Hachijo-jima Geothermal Power Plant 113
widespread attention as a source of
clean and renewable energy. Geo-
thermal power plants are being con-
structed throughout the world in
those countries which have geother-
mal resources.
Fuji Electric has supplied geo-
thermal power units capable of pro-
Geothermal Steam Turbines for Various Purposes 120
ducing a cumulative output of
1,700MW, ranging from small ca-
pacity units such as for a hotel to
large-capacity 110MW units, de-
pending on customer needs. The
units supplied by Fuji Electric are
favorably regarded for their high
reliability.
The photograph on the front
Recent Technology of Geothermal Steam Turbines 124
cover shows a complete view of the
Wayang Windu Geothermal Power
Plant in Indonesia and its 110MW
geothermal steam turbine. The tur-
bine is the world’s largest single-
casing-type geothermal turbine.
Shigeto Yamada
Iceland
36 MW
China
3 MW
Japan
4 MW
USA
666 MW
Philippines
428 MW
El Salvador
96 MW
Indonesia
385 MW
New Zealand
Total 1,673MW 55 MW
Table 1 Worldwide capacity of geothermal power plants toward total plant engineering. In the recent construc-
(Source : IGA NEWS, July to September 2000) tion of Malitbog Geothermal Project in Leyte, Philip-
Capacity (MW) pines, Fuji Electric (along with a trading company as
Countries Year 2005 the main contractor) worked on the project to provide a
Year 1995 Year 2000
(forecast) full turnkey solution, including construction, civil
* USA 2,817 2,228 2,376 engineering work, manufacturing, procurement, instal-
* Philippines 1,227 1,909 2,637 lation and commissioning of the plant which consists of
Mexico 753 755 1,080 three 77.5MW units. In this case, the only data
632 785 946
supplied to Fuji Electric was given were the steam
Italy
conditions at the plant boundary, the site meteorology,
* Japan 414 547 567
and the customer’s required net plant output. Fuji
* Indonesia 310 589 1,987
started the engineering work by determining the
* New Zealand 286 437 437
design wet bulb temperature, which has a large
* El Salvador 105 161 200
influence on the plant economy and performance.
Nicaragua 70 70 145 Then, design conditions were determined for the main
Costa Rica 55 142 161 equipment and each sub-system. The ultimate goal of
* Iceland 50 170 170 plant engineering is to realize a geothermal power
Kenya 45 45 173 plant which is reliable, highly efficient, economical,
* China 29 29 NA and at the same time has a minimum influence on the
Turkey 20 20 250 environment.
Russia 11 23 125 More recently in 1999, Fuji Electric provided
Portugal 5 16 45 equipment to the Wayang Windu Geothermal Power
France 4 4 20 Plant located in West Java, Indonesia also under an
0.7 0 NA
EPC contract. The power plant is equipped with a
Argentina
110MW geothermal steam turbine, the world’s largest
Thailand 0.3 0.3 0.3
single casing turbine for geothermal service.
Australia 0.2 0.2 NA
Another recent example, in contrast to Wayang
Ethiopia 0 9 9
Windu in terms of its size, is the Hachijo-jima
Guatemala 0 33 33
Geothermal Power Plant also inaugurated in 1999.
Total 6,833 7,974 11,398 The power plant, whose output is 3.3MW replaced
Note : * shows the countries where Fuji Electric supplied distributed diesel power plants in Hachijo-jima island
geothermal power plants. which is a remote volcanic island in eastern Japan
Hiroshi Murakami
SUNDA STRAIT
power plants has been promoted to utilize clean and SERANG JAKARTA
renewable energy with low carbon dioxide emissions. PANDEGELANG
TANGERANG BEKASI
KARAWANG
RANGKASBITUNG INDRAMAYU
P.PANAITAN
The country of Indonesia has the fifth largest PURWAKARTA
SUBANG
BOGOR
development of geothermal energy, following the USA, SEM.
CIANJUR SUMEDANG CIREBON
BANDUNG
Philippines, Italy and Mexico in the world. JUNGKULON
SUKABUMI MALANGBONG
In June 1997, Fuji Electric of Japan, together with INDONESIAN OCEAN GARUT CIAMIS
CENTRAL
JAVA
PROJECT
a trading company, entered into an engineering, LOCATION
TASIKMALAYA
N
procurement and construction (EPC) contract with
Magma Nusantara Limited (MNL) of Indonesia to 0 30 60 90 km
3.2 Construction and commissioning Figure 3 shows an overview of the power station.
Civil and construction work was delegated to local The area is almost square, having 230m E-W and
subcontractors. Proposals for that work were thor- 210m N-S. Civil and architecture for Units No.1 and 2
oughly evaluated in terms of technical, commercial and the power plant for Unit No.1 are completed at
and financial perspectives. Onsite work for power present.
station started in June 1997. The turbine is of the single flash and double flow
SAGS onsite works started in December 1997. A type. The cooling water system is a closed circuit
local engineering company, which is a subsidiary of a consisting of a direct contact condenser and wet cooling
New Zealand engineering company, has been hired for tower. The gas removal system is a hybrid system
managing and supervising such subcontractors. consisting of a steam ejector and vacuum pump.
Figure 4 shows a schematic diagram of the power
3.3 Preservation station and Fig. 5 shows the power station layout after
Because the transmission line constructed by PLN completion of Units 1 and 2.
was not completed in August 1999, the plant was put
on preservation for 8 months. 4.1 Steam turbine
Mechanical equipment such as the turbine and Major specifications are listed below.
hotwell pump were disassembled and anti-corrosive Type : single cylinder, double flow and condensing
measures were taken. Space heaters were put into type
operation for electrical equipment where necessary. Output : 110MW (MCR 115MW)
Control and instrument equipment such as DCS and Inlet steam press. : 1.02MPa
the monitoring system were operated normally. Inlet steam temp. : 181°C
SAGS pipelines were steam-capped at low pressure Exhaust press. : 0.012 MPa
At plant boundary
1.06P
1.02P
180.7T
Legend:
P : Pressure, MPa abs
T : Temperature, °C
: Steam G
: Water
: Gas 110,000kW
0.12P
Re-injection Condenser 4.08P
Evaporation & drift losses
44.8T 42.5T
Hot well pump
Steam header
Cooling tower
Administration
building
Unit 1
Unit 2
(future)
Turbine-generator
Production wellpads
Power station
Steam
T/G
Two-phase fluid
Separators
Rock muffler Condensate
Brine
(MWh)
90,000
80,000
70,000
60,000
50,000
40,000
30,000
20,000
10,000
0
June July Aug. Sept. Oct. Nov. Dec. Jan.
(2000) (2001)
resulted in the delay of work progress. Local subcon-
tractors faced difficulty in purchasing materials from
foreign countries because foreign companies did not No.1 has been successfully completed in cooperation
accept letters of credit issued by Indonesian banks. with MNL and local subcontractors. We sincerely hope
As a countermeasure, we offered improved terms of that the electricity generated at this plant will contrib-
payment to the subcontractors so as to assist in solving ute to the development and improvement of life for
their finance problem and we purchased necessary local people in this area.
materials from foreign companies and supplied them to
the subcontractors. References
(1) Esaki, Y., Murakami, H. : Topics of Geothermal Power
8. Conclusion Generation Abroad, Geothermal Energy, Vol.24, No.3
(1999)
The world’s largest capacity geothermal turbine (2) Kato,Y. et al. : Progress of geothermal steam turbine
was manufactured at Fuji Electric’s Kawasaki Factory technology, Fuji Electric Review, Vol.42, No.2 (1996)
in Japan, based on extensive experience in both the (3) Murakami, H. et al. : Construction of the Largest
geothermal and conventional power generation busi- Geothermal Power Plant for Wayang Windu Project,
nesses. Indonesia, WGC2000, p. 3239 - 3244 (2000)
The Wayang Windu Geothermal Power Plant unit
Tadao Horie
1980.
Berlín G.P.P
A turnkey contract was signed with the owner,
Comisión Ejecutiva Hidroeléctrica del Río Lempa San Miguel
(CEL) in November 1996. After overcoming some
Nueva San Salvador
natural obstructions, steam was successfully produced, (Santa Tecla)
Zacatecoluca
and continuous power generation began in April 1999, Usulután
San Salvador
The two units were officially put into commercial N
operation in November 1999. Pacific Ocean Epicenter (Mw7.6)
[Unit: mm]
201500
1.000
235800
N68-443-5 N68-443-11
Takashi Murakami
Silencer A Mesh B
B demist-
er
Genera- Gas
Production well tor removal
(HT-2) Steam system
turbine G
Steam Con-
separator denser
Flash
steam ejector
tank
2nd-stage
Production well B A
(HT-1) B A
After
1st-stage cooler
steam Inter
V6-136
cooler
15A
ejector
Re-injection M
pump S
A
Hot
water
pit
B Cooling U
P tower Hot well
pump
Drainage (100%¥1)
TP-7
pump M
Auxiliary
cooling
water
Raw A main oil pump Chemicals
water cooler (100%×1) feed tank
tank Raw water
pump
(100%×1) B main oil
cooler
Re-injection well
Air H2S
cooler abate-
ment
P system
98250
Cooling
H2S abatement system tower
47700
control room
Turbine
Electrical
Gas
removal
system
Condenser
Generator
19300
PR hall
2 × CT
Generator 64G 100/5A 50-51
circuit braker SYN3 40VA
Vo 1PS
59G 27G F
V
Auxiliary transformer
R6.9-F6.6-F6.3kV/460V
Pf A 600kVA
60G
67G PR DV DA
41
3 × CT 600/5A
40VA,1PS
Fig.13 Exterior view of the generator Fig.14 View of the package-type electrical control room
Shigeto Yamada
tion.
In cases where the resource temperature is not
high enough to generate steam efficiently above atmo- 1995
3,600
Reinjection SP brine, from 3,500
Units 3 and 4 3,400
Output ( kW )
SP(8k) steam, from Units 3 and 4 3,300 For 1,000t/h hot water
3,200 at 130 °C
3,100
3,000
Fig.5 Section of Salton Sea Unit 5 turbine 2,900
2,800
2,700
2,600
0.05 0.06 0.07 0.08 0.09 0.1 0.11 0.12
Flash pressure ( MPa abs )
0.05P 0.067P
88.6T
0.15P 2,658H
130T 73,750F-ST
1,000,000F 0F-NC
0.07P
G
3,500kW
920,250F
Legend 73,750F-ST
0F-NC
P : MPa abs
T : °C
H : kJ/kg 0.011P
29.0T 33.0T
F : kg/h 2,600,000F 0NC
54Air
65ST
66,849F 44.7T
2,673,950F 2,673,950F 265F
WBT domestic energy source, and continuous development is
20.0T 44,000F
Coolers
expected in all geothermal countries. In order to
44,200F 200F
6,901F utilize geothermal energy more effectively, it is antici-
Blowdown
pated that geothermal power plants having additional
functions, as introduced here, will be planned. Fuji
Electric’s geothermal steam turbines will contribute as
(5.5kW), cooling tower fans (110kW), vacuum pump key components to such plans for multi-purpose geo-
(15kW) and power for the control system (Ca. 10kW) thermal plants.
such as an air compressor; totaling approximately Low temperature geothermal resources are plenti-
250kW which is roughly 7% of the gross output. ful. In addition to low temperature geothermal
There may be a various other cases in addition to resources, hot water that is being re-injected can be a
the example described in the previous section. If resource for a VLP flash system, if lowering the re-
geothermal hot water contains some percentage of injection temperature is allowed. Nature characteris-
steam, the turbine inlet pressure can be raised, for tics of geothermal resources vary area to area, and site
example, to 0.09MPa abs, thereby increasing the gross conditions also differ. The important consideration is
output; however in such cases, more power must be to select the most suitable system under the given
consumed for gas extraction because non-condensable conditions. The VLP flash cycle will contribute to
gases are usually contained in steam. Condenser expanding the range of selections available for geother-
pressure plays a very important role in determining mal power generation with low temperature resources.
the output since the heat drop across the VLP turbine
is quite low compared to that of an ordinary geother- References
mal turbine. With a VLP flash system, compared to (1) Esaki, Y. : Very Low Pressure Flash Cycle Geothermal
ordinary geothermal power generation, it is more Power Generation, Proceedings of 20th Annual PNOC
effective to lower the design condenser pressure to EDC Geothermal Conference, Manila, Philippines,
increase the output under the same brine consump- March, 1999
tion. (2) Yamada, S. : Flash Cycle for Low Temperature Geo-
thermal Resources – Very Low Pressure (VLP) Flash
5. Conclusion Cycle, Proceedings of the World Geothermal Congress
2000
Geothermal energy is regarded as renewable and
Yoshifumi Kato
(3)
3.1 Wayang Windu 110MW geothermal steam turbine
Figure 5 shows the cross section of the steam
turbine for the Wayang Windu Geothermal Power
Plant in Indonesia, which was put into the commercial
operation in June 2000. The turbine is of a single
flash, dual exhaust flow and single casing type. Major
specifications of the geothermal turbine are as follows:
(1) Inlet steam pressure: 1.02MPa
(2) Inlet steam temperature: 181°C
Fig.4 Triple eccentric butterfly valve Fig.5 Cross section of 110MW geothermal steam turbine for
Wayang Windu Geothermal Power Plant (Indonesia)
Sheet
Disk
Seal ring
Fig.6 Cross section of 58.32MW geothermal steam turbine for Fig.7 Casing upper half of geothermal steam turbine for
Salton Sea U5 (USA) Salton Sea U5
- +
Steam flow
After removal of the 1st stage
∆P
plants. ∆G
Steam flow
The turbine inlet pressure of Okoy is higher than
that of the other two plants, and the turbine for Okoy
has 1 more stage than the other units. ∆P
The design philosophy is to maintain the generator
output of Okoy by removing the 1st stage blade row in
case there is a future decrease in production well (b) Pressure of production well
pressure (Fig. 8).
By removing (machining off) the 1st stage blade Steam generation vs. pressure of the original well
Steam generation vs. pressure of the declined well
row of the Okoy turbine, the turbine rotor will be Pressure characteristics of the original blade row
common among these three geothermal power plants. Pressure characteristics of the redesigned or original
blade row with removal of 1st stage
A spare rotor can be used in any of the four units.
ASIA
East Asia Southeast Asia
FUJI ELECTRIC CO., LTD. FUJI ELECTRIC CO., LTD.
Beijing Representative Office Bangkok Representative Office
, THAILAND
THE PEOPLE S REPUBLIC OF CHINA
Tel : +86-10-6505-1263 Fax : +86-10-6505-1851 Tel : +66-2-653-2020, 2021 Fax : +66-2-653-2022
FUJI ELECTRIC (SHANGHAI) CO., LTD. FUJI ELECTRIC (MALAYSIA) SDN. BHD.
, MALAYSIA
THE PEOPLE S REPUBLIC OF CHINA
Tel : +86-21-6466-2810 Fax : +86-21-6473-3292 Tel : +60-4-403-1111 Fax : +60-4-403-1491
FUJI ELECTRIC DALIAN CO., LTD. FUJI ELECTRIC PHILIPPINES, INC.
, PHILIPPINES
THE PEOPLE S REPUBLIC OF CHINA
Tel : +86-411-762-2000 Fax : +86-411-762-2030 Tel : +63-2-844-6183 Fax : +63-2-844-6196
SHANDONG, LUNENG FUJI ELECTRIC CO., LTD. P. T. BUKAKA FUJI ELECTRIC
THE PEOPLE S REPUBLIC OF CHINA INDONESIA
Tel : +86-531-723-1138 Fax : +86-531-726-1737 Tel : +62-21-572-4281 Fax : +62-21-572-4283
SHANGHAI ,FUJI ELECTRIC SWITCHGEAR CO., LTD. P. T. FUJI DHARMA ELECTRIC
THE PEOPLE S REPUBLIC OF CHINA INDONESIA
Tel : +86-21-5718-5741 Fax : +86-21-5718-1448 Tel : +62-21-4606247 Fax : +62-21-4610338
SHANGHAI ,FUJI ELECTRIC TRANSFORMER CO., LTD. FUJI ELECTRIC SINGAPORE PRIVATE LTD.
THE PEOPLE S REPUBLIC OF CHINA SINGAPORE
Tel : +86-21-5718-5746 Fax : +86-21-5718-5745 Tel : +65-479-5531 Fax : +65-479-5210
FUJI/GE PRIVATE LTD.
SINGAPORE
Tel : +65-533-0010 Fax : +65-533-0021
Printed on recycled paper