PROJECT NAME TYPE

Rehabilitation Renovation - Block D,E,F Alden


Healthcare Renovation
Estates Rehabilitation Center Naperville, IL

Renovation - Multistory Residential - MDUs


Re/Max Properties South Residential Renovation
Chicago Land

Virgin Airlines Satelite Infill Project


Comercial Extention
Hansen Yuncken Brisbane,
/ Renovation
Australia

Lady Cilento Childrens Hospital Lendlease Hospital Extension New


Brisbane, Australia Construction
Lady Cilento Childrens Hospital Lendlease Hospital Extension New
Brisbane, Australia Construction

Factory Phase-3 Extension Suntory


Factory Extension New
Pepsi Corporation
Construction
Can Tho, Vietnam

Slab and Drainage System


Vina Kyoei Steel Corporation Factory Renovation
Vung Tau City, Vietnam

New Beverage Factory Construction Suntory


Pepsi Factory New
Pepsi Corporation Quang Nam,
Construction
Vietnam

Power Plant Restoration EVN


Hai Duong Power Plant
State Owned Enterprise Hai
Renovation
Duong, Vietnam
SIZE CONSTRUCTION
Two-phae FEATURES
gut and renovation of a VALUE PROJECT DURATION
4-storey inpatient building and
adjacent two-story critical care
wing. The Project included 144
patient rooms, offices, conference
rooms, nurse station, etc. Work
was conducted on an occupied
campus ( Which included multiple
14 Months
85,000 SF areas with shared utilities and $ 12.5 Million
(2008-20009)
occupied floors above, below and
adjacent to our construction areas.
Work required intensive
coordination wtih Alden
construction department,
Rehabilitation Staff and Facilities
(Engineering) to plan and minimize
impact to ongoing operations.
Full renovation of multiple
forclosure MDU buildings.
Including stripping all interior
finishes, roof membrane, windows,
50,000 SF $ 3.7 - $ 4 Million 05/2009-09/2013
plumbing, electrical, heating/etc.
Fast pace short-term projects,
roughly 6 months to practical
completion.

Satelite Infill and renovation of


existing Virgin Australia Lounge.
Infill of old garden area, additional
lounge for passangers and Aero
14,000 SF $ 10 Million 08/2014-07/2015
Bridge installation. This project had
a tight schedule and continues
construction during airport work
hours and nights.

12 Story 160,000 SF Patient care


and medical office building with
160,000 SF adjacent 150,000SF 4 story $92 Million 07/2012-11/2014
parking garage. Parking garage
including post tension slabs and
steel/ glass façade. Extension
included a full service outpatient
surgery center with operating
rooms, CAT Scan, MRI and X-Ray
machine, offices and retail space.
and medical office building with
160,000 SF adjacent 150,000SF 4 story $92 Million 07/2012-11/2014
parking garage. Parking garage
including post tension slabs and
steel/ glass façade. Extension
included a full service outpatient
surgery center with operating
rooms, CAT Scan, MRI and X-Ray
machine, offices and retail space.

New extension including steel


structure wearhouse, concrete slab
83,000 SF with pile works, three processing $17 Million 02/2015 - 11/2015
lines, laboratory, clean room, new
driveway pavement.

Demolition works and a new


reinforced heavy duty slab with
42,000 SF integrated drainage system in $1.5 Million 11/2015-02/2016
areas of the factory that suffered
errosion and cavity formation.

15m steel structure warehouse and


loading dock attached to a new two
story concrete office building.
452,000 SF Separate utility building and Waste $36 Million 02/2016-07/2017
water treatment plant. Including all
finishing, excluding installation of
processing lines.

Steel structure storage warehouse,


columns and truss repairs, New
216,000 SF Roof, full office renovations, $11 Million 04/2018-08/2019
reinforced concrete repairs at
loading dock.