Professional Documents
Culture Documents
ABSTRACT
The latest generation of Shell-designed C3MR-based LNG trains, that are under
construction or in operation, have a design capacity of around 4.2-4.5 Mtpa, which is the
largest train capacity built so far. The introduction of Shell’s DMR technology,
particularly in combination with the GameChangerTM concept, has significantly increased
the potential for capacity growth and has resulted in very cost competitive designs in the
5-6 Mtpa range. Current market growth and the availability of large gas reserves,
however, is pushing designers to look at even larger capacity trains since lowest unit cost
continues to be a key value driver.
Against this background, Shell has developed a further enhancement of a large LNG
TM
train concept based on its efficient DMR technology: the Parallel Mixed Refrigerant
(PMR) process. The process consists of a single pre-cool cycle followed by two parallel
liquefaction cycles, the compressors of which are driven by three GE Frame 7 gas
turbines. The resultant LNG train production capacity is up to 8 Mtpa, and the associated
specific cost will be significantly lower than current benchmark values. Added benefits of
the process are the high availability, and the potential for phased implementation.
This paper describes the concept as developed, covering process and compressor line-
ups and performance in terms of cost and efficiency. Further, it includes a comparison
with alternative designs in the 4-6 Mtpa range, highlighting the strengths and weaknesses
of the various options.
RESUME
La toute dernière génération des modules de production de GNL basés sur le procédé
C3MR conçus par Shell, en cours de construction ou déjà en service, ont une capacité
théorique de 4.2-4.5 million tonnes métriques par an (Mtpa). Ce sont les modules de plus
grande capacité construites à ce jour dans le monde. L'introduction de la technologie
TM
DMR de Shell, combinée notamment au concept GameChanger , a permis d'augmenter
considérablement la capacité potentielle et a abouti à des conceptions d'ouvrage très
économiques dans la gamme 5-6 Mtpa. L'expansion actuelle du marché et la disponibilité
de vastes réserves de gaz, cependant, poussent les concepteurs à envisager des trains de
capacité encore plus grande car un coût unitaire aussi faible que possible demeure un
motif de décision clé.
PS5-3.1
SESSIONS CONTENTS
Paper PS5-3
INTRODUCTION
Economy of scale has always been an important driver to lowering the cost of base-
load LNG production. This has resulted in an increase in LNG train capacity (Figure 1)
from steam driven LNG trains of 1 Mtpa (such as facilities in Algeria, Brunei and Lybia)
to large gasturbine driven LNG trains of around 4 Mtpa using the C3MR process (such as
facilities in Malaysia and currently under construction in Australia and Nigeria).
Shell developers have made a considerable contribution to the capacity
improvements, for example by introducing 80 MW gasturbine drivers, highly efficient
axial compressors in the MR cycle and a large four stage propane compressor. The most
recent LNG Train designs have been based on the application of two GE-F7 gas turbines
for both the propane and MR compression service, with an endflash system to maximise
production capacity. Air cooling is becoming the standard, but water cooling can still be
an attractive option if the specific local conditions favour this.
At the same time, the transport and production of Liquefied Natural Gas (LNG) has
grown at a rate of 6% per annum over the past five years to about 110 million tons per
annum (Mtpa) of LNG traded in 2002. This trend is expected to continue and global LNG
trade is expected to reach around 190 Mtpa in 2010. This market growth, together with
the availability of large gas reserves, pushes designers to look at even larger capacity
trains to maximize the benefits from economy of scale [1,2].
Shell has increased the capacity of designs employing two GE-F7 gasturbines to 5.5
Mtpa. Furthermore, it has developed an electrically driven design which is especially
attractive between 5 and 6 Mtpa, more recently followed by the Parallel Mixed
Refrigerant (PMR) design utilizing three GE-F7 gasturbines for capacities up to 8 Mtpa.
PS5-3.2
SESSIONS CONTENTS
Paper PS5-3
7 Existing Existing
Under Construction Under Construction
6
Train capacity (Mtpa)
Proposed Proposed
5
0
1960 1970 1980 1990 2000 2010
Start up Year
Figure 1: LNG train size evolution showing existing plants, plants under
construction and proposed plants
PS5-3.3
SESSIONS CONTENTS
Paper PS5-3
8
M F7
SplitPropane
Line-up
LP MP HP HHP
8
M F7
Traditional
Line-up
LP MP HP HHP
For the same compression duty, this split arrangement results in a lower volumetric
flow per wheel, because the HP section does not see the MP flow anymore, etc. This
offers the freedom to enlarge the C3 compression duty in combination with deeper
precooling, and to better load the gasturbines. A train capacity of 5+ Mtpa becomes
possible, whilst maintaining the operational benefit of separate compressor cycles.
The more flexible Shell Dual Mixed Refrigerant (DMR) process [4] was developed as
the key to the future for medium and large train sizes. The use of a mixed refrigerant
instead of propane in the precooling cycle overcomes the inherent limitations of the
C3MR design; the additional degree of freedom resulting from the use of two mixed
refrigerant cycles allows full utilization of power in a design driven by two GE-F7
gasturbines. Further, it allows keeping the compressors at their best efficiency points over
a very wide range (up to 50 ºC) of ambient temperature variations and changes in feed
gas composition. This design has been selected for the Sakhalin LNG project [5]
currently under construction, with an annualized design capacity of 10 Mtpa (two trains).
Developments of the DMR process have further improved process efficiency.
Examples are the application of a three stage pre-cooling cycle and the use of a more
efficient axial compressor in the pre-cooling cycle. As a result, this concept enables a
production of 5.5 Mtpa LNG under tropical conditions, using 2 GE-F7 machines; The
DMR process efficiency calculated for typical conditions is 11.7 kW/tpd compared to
12.4 kW/tpd for C3MR, clearly confirming the efficiency potential of the DMR process
[12,13,14].
Building on the inherent flexibility of the DMR process, the electrically-driven DMR
(LNG GameChanger) design was developed, offering competitive unit costs and a faster
PS5-3.4
SESSIONS CONTENTS
Paper PS5-3
schedule [7,8,9]. This is the selected process for the Mariscal Sucre LNG project in
Venezuela, and for a project in the Middle East [9]. Electrically-driven LNG trains can
compete with mechanically-driven trains because the increase in cost (on a like for like
basis) is compensated for by the increased availability. Other benefits of the electric
option are the variable size and speed of the driver, the increased vendor base, and the
potential to make a step change in overall plant efficiency by choosing combined cycle
for electric power generation. The current electrically-driven DMR design is particularly
attractive in the 5-6 Mtpa capacity range.
Condensate
stabilisation Fractionation
Liquefaction
Gas Gas Precooling End LNG
Receiving Treating flash tank
Liquefaction
The PMR design can be based on either the C3MR line-up or the DMR line-up.
However, the DMR process was selected because of its inherent flexibility and because it
offers an improved efficiency compared to the C3MR process. This is particularly
relevant as the power delivered into the process by the three gasturbines is limited and the
DMR process enables for a higher throughput to be achieved.
PS5-3.5
SESSIONS CONTENTS
Paper PS5-3
To match the power balance of 1:2 between pre-cooling and liquefaction, the
resulting pre-cooling outlet temperature is about –25 ºC in this design. The natural gas is
cooled to about –150 ºC in the liquefaction exchanger, and an endflash system [13] is
used to produce fuel gas and LNG, whilst maximizing LNG production.
Other technology providers are proposing large train LNG plants using three (serial)
cooling cycles (precooling, liquefaction and subcooling) [1,2,10] in combination with
larger drivers. The advantages the PMR design offers are:
• Robustness, through the application of proven equipment, the use of spiralwound
tubular exchangers, and independent cooling cycles (each cycle has its own
driver). The use of tubular exchangers also underpins an excellent reliability. The
parallel line-up ensures that the liquefaction refrigerant flows are within
acceptable limits, and acceptable line sizes.
• High efficiency, through the use of the DMR process, which is in addition more
robust against changes in ambient conditions and feedgas composition than any
other process. Optimal efficiency is realized through the use of a precooling cycle
with three pressure levels and the use of axial/centrifugal compressors in
combination with each driver.
• High reliability and on-stream time, through the choice of the parallel
independent line-up of the two liquefaction cycles. In case of a trip of one of the
liquefaction cycles, continued LNG production is possible (at a level of some
60%), resulting in the following benefits:
- The effective plant reliability (on a throughput basis) is equal to a
mechanically driven Shell design driven by two GE-F7 gasturbines, and
higher than for processes based on three serial cycles.
- Possibility for maintenance on one of the liquefaction cycles whilst
continuing production.
- A more continuous gas off-take from upstream.
- A more continuous LNG production profile.
PS5-3.6
SESSIONS CONTENTS
Paper PS5-3
Liquefaction
circuit A
Liquefaction Fuel
refrigerant
Pre-cooling
circuit
GE-7
3-stage a,b,c
LNG
Pre-cool
Natural
GE-7 gas
Liquefaction circuit B
Pre-cool
Natural gas
Ex treating Scrub
GE-7
column
Pre-cool
To Fractionation
The introduction of the PMR concept leads to a continuation of the cost reduction
trend (see Figure 5). Compared to the current Shell designs using 2 GE-F7 gas turbines or
the all electric DMR design at 5 Mtpa capacity (which have similar unit costs around 5
Mtpa), the PMR design shows a cost reduction of 10%.
250
ME: Middle East
AM: America
NLNG: Nigeria LNG
200
OLNG: Oman LNG
Relative specific cost (%)
150
100
50
0
ME NLNG ME AM OLNG DMR 2F7 or PMR 3F7
1995 1993 1996 1995 1995 DMR electric 2003
2003
PS5-3.7
SESSIONS CONTENTS
Paper PS5-3
FURTHER DEVELOPMENTS
Larger LNG trains are possible, but it is realized that economy of scale is flattening
off, unless larger compressor/driver combinations (such as GE-F9 turbines) are
introduced. However, one should carefully address the risks associated with step outs in
driver and compressor size. Whilst options for larger mechanical drives are considered, it
is noted that the electric drive route also has potential, as the economy of scale is gained
in the power plant by using larger gasturbine generators.
As indicated, for a 5 Mtpa plant based on the Shell DMR process, the unit costs of a
gasturbine driven design (using two GE-F7 gasturbines) and an electric motor driven
design (using four motors of 47 MW) are similar. Application of larger motors (up to 80-
90 MW) however could make the electric driven DMR design very competitive to the
PMR design. Further, there are other inherent benefits of the electric drive, including the
potential to increase the overall power generation efficiency to levels around 50% in the
case of combined cycle power generation (compared to just 30% for gas turbine driven
designs). The efficiency increase is offset however, by an increase in power generation
costs.
The key issue, however, is to develop experience with larger electric motors. Electric
motors of 65 MW have already been constructed for LNG service, and 80-90 MW motors
are considered feasible, but to date the industry has little experience with these large
drives.
It should be noted that large trains may not always be the best value solution for a
project. A pre-requisite is a large reserve base and the ambition to develop a large
liquefaction complex based on multiple large trains, delivering to an expected large
market that allows a fast ramp-up. Despite the benefits, the application of large trains
makes a liquefaction complex more vulnerable (in value terms) to ramp-up. With an
increase in LNG trade however, market ramp-up will be less of an issue, as the spare
capacity can be sold on a spot basis. As illustrated in the picture below, the ramp-up
needs to be sufficiently steep to secure the value increase that results from the decreased
unit costs.
PS5-3.8
SESSIONS CONTENTS
Paper PS5-3
Wedge
Market demand
Market demand Wedge
Wedge
Time Time
When the climate is right for a large train, for today’s immediate projects, the Shell
PMR design based on three GE-F7’s is an attractive option, as it clearly remains within
the boundaries of well-proven designs and uses existing proven equipment.
REFERENCES CITED
[1] Large Capacity Single Train AP-XTM hybrid LNG process. Mark J Roberts, James
C Bronfenbrenner, Yu-Nan Liu, Joseph M Petrowski. Gastech 2002 Qatar.
[2] Study evaluates design considerations of larger, more efficient liquefaction plants.
Amos Avidan, Wayne Varnell (Bechtel Corp. Houston) and Bobby Martinez
(ConocoPhillips Houston). Oil and Gas Journal, August 18, 2003.
[3] Propane compressor line-up for an LNG plant. USA patent specification 6637238.
[4] Double mixed refrigerant process for liquefying natural gas. USA Patent
specification 6370910.
[5] Engineering design challenges for the Sakhalin LNG project. Wim Dam, Siew-
Mung Ho. GPSA Conference San Antonio, March 2001, Texas.
[6] Electric motor driven LNG plant. International patent application publication No.
WO 01/40725
[7] Changing the LNG Game. Cas Groothuis, Dave Fletcher, Rob Klein Nagelvoort.
LNG13, 2001, Seoul, Korea.
[8] The LNG GameChangerTM Technology. Eva Heyman, Alan Bliault, Barend Pek,
GASEX 2002.
[9] Persian LNG – A Giant Awakes. Ate Visser, Colin Bowkley. World Gas
Conference Tokyo 2003.
[10] Developments in the Mixed Fluid Cascade Process (MFCP) for LNG Baseload
Plants. Wilfried A. Bach (Linde), München. Reports on science and technology
63/2002.
PS5-3.9
SESSIONS CONTENTS
Paper PS5-3
PS5-3.10
SESSIONS CONTENTS