Daily Progress Report: Mtr. 4690 Mtr. Mtr. 4690
Daily Progress Report: Mtr. 4690 Mtr. Mtr. 4690
: PRJ 200
Daily Progress Report REV.No.: 00
Eff.Date: 01.02.2018
Client : Adani Gas Ltd Pipe Dia & Thickness :12" & 7.9mm Date: 03-11-2019
Contractor : Tolani Projects Pvt Ltd Pipe Specification :API 5L Gr-X-42M
TPIA : TUV India Location :Riico road to Hindustan zinc Puliya, chittorgarh
PROGRESS Qty Executed
Weekly Last
Sr Total Qty
No
Activity UOM
(Scope)
Planing Week
Today’s Previous Cumulat. Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Total
Progress
Repair Segment - 16 16 0 0 0 0 0 0 0 0 0
8 Trenching Mtr. 4690 154.39 1981.07 2135.46 530.00 0 0 0 140.00 235.22 0 154.39 529.61 326.85
9 Lowering Mtr. 4690 154.39 ### 2117.37 530.00 0 0 0 0 375.22 0 154.39 529.61 325.34
14 Backfilling Nos. 0.00 1,824.54 1824.54 415.00 0 36.32 0 0 181.63 193.59 0 411.85 295
Manpower Machinery
Warning Mat 20 KM
ANY PROBLEMS :
DPR as on 03.11.2019