You are on page 1of 3

Doc.No.

: PRJ 200
Daily Progress Report REV.No.: 00
Eff.Date: 01.02.2018

Client : Adani Gas Ltd Pipe Dia & Thickness :12" & 7.9mm Date: 03-11-2019
Contractor : Tolani Projects Pvt Ltd Pipe Specification :API 5L Gr-X-42M
TPIA : TUV India Location :Riico road to Hindustan zinc Puliya, chittorgarh
PROGRESS Qty Executed
Weekly Last
Sr Total Qty
No
Activity UOM
(Scope)
Planing Week
Today’s Previous Cumulat. Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Total
Progress

1 Pipe Received ( Steel) Mtr. 4690 0 29130.99 29130.99 0 0 0 0 0 0 0 0 0


MDPE 125mm
2 Mtr. 0 0 0 0 0 0 0 0 0 0 0
Received ( PE)
MDPE 90mm Received
3 Mtr. 0 0 0 0 0 0 0 0 0 0 0
( PE)
4 Pipe Stringing Mtr. 4690 0 4754.510 4754.51 475.00 0 0 0 0 254.14 217.96 0 472.10 0

Main line Welding Nos. 460 7.00 246 253 15 0 0 0 3 4 0 7 14 5

5 Tie in welding Nos. 0 26 26 7 0 0 2 1 1 2 0 6 9

Total Welding Nos. 460 7.00 272 279 22 0 0 2 4 5 2.00 7 20 14

Radiography taken Nos. 460 0.00 269 269 20 0 1 2 10 0 4.00 0 17 13

Reviewed Nos. 0 265 265 0 0 0 0 0 13 0 13 21

Accepted Nos. 0 265 265 0 0 0 0 0 13 0 13 21

Retake / Reshoot Segment - 39 39 0 0 0 0 0 0 0 0 0


6
RT/RS Attended Segment - 39 39 0 0 0 0 0 0 0 0 0

Repair Segment - 16 16 0 0 0 0 0 0 0 0 0

Repair Attended Segment 0 16 16 0 0 0 0 0 0 0 0 0

Total Accepted Nos. 0 265 265 0 0 0 0 0 13 0 13 13

7 Joint Coating Nos. 460 0 261 261 40 0 1 1 15 13 8 0 38 18

8 Trenching Mtr. 4690 154.39 1981.07 2135.46 530.00 0 0 0 140.00 235.22 0 154.39 529.61 326.85

9 Lowering Mtr. 4690 154.39 ### 2117.37 530.00 0 0 0 0 375.22 0 154.39 529.61 325.34

10 MDPE 125 Lowering Mtr. 0 0 0.00 0 0 0 0 0 0 0 0 0

11 MDPE 90 Lowering Mtr. 0 0 0.00 0 0 0 0 0 0 0 0 0

12 MDPE 125 Joints Nos. 0 0 0.00 0 0 0 0 0 0 0 0 0

13 MDPE 90 Joints Nos. 0 0 0.00 0 0 0 0 0 0 0 0 0

14 Backfilling Nos. 0.00 1,824.54 1824.54 415.00 0 36.32 0 0 181.63 193.59 0 411.85 295

15 HDD Mtr. 0 0 0.00 0 0 0 0 0 0 0 0 0

Manpower Machinery

Type Nos. Type Name Qty.

Welders 2 Project Manager Hydra 2

Fitters & Grinder 3 Q.A./Q.C Engineer MANORANJAN SHARMA JCB 2

Riggers 5 Site In-charge (Steel) Shajahan P I Welding M/c Set 3

Helpers 4 Project Co-ordinator Ganesh sharma Coating Equipment Set 1

Excavation Labours 3 safety officer Rajan verma Grinding M/c 12

Insulator 2 Foreman Submercible Pump 1

sand blaster 1 Electrician /Mechanic Ajeet Prajapati Power Generator 1

operator & Drivers 6 Store Keeper Dinesh Sharma Trailor / Tractor/LMV 6

Supervisor 1 Planning Engineer

Store Keeper 1 Trenching Supervisor Sugata Dutta

Welding Supervisor Sadam Hussain

Coating Supervisor Pramod kumar

RCM Ramneek singh

Q.A./Q.C Engineer Nitin Kumar

Contractor's Stock Sheet Welder Performance

Qty. Welder Name Jt. Done Repair % of Repair Remarks

Welding Electrode - 6010 625 KG Mukesh Mahato 252

Welding Electrode - 7010P1 1450 KG Balinder Mahato 252

Coating Sleeves 2 KM(280 NOS)Jagannath 27

Warning Mat 20 KM

ANY PROBLEMS :

Contractor TPIA AGL


Sign:
Name:
Date:
GA-Chittorgarh

DPR as on 03.11.2019

Sr.No Activity UOM Todays Previous Cumulative


1 Stringing M 0 ### 4754.51
Nos 7 272 279
2 Welding
M 133.21 4283.88 4417.09
3 Lowering M 154.39 1962.98 2117.37
4 Backfilling M 0.00 1824.54 1824.54
Next Day Program As On Date 04.11.2019

S.No. Activity Location Supervisor Name/Engineer Contact No.


1 Mainline Welding KM-03 Manoranjan Sharma 9337814987
2 RT Taken KM-02 & KM-03 Manoranjan Sharma 9337814987
3 Joint Coating KM-02 & KM-03 Pramod Kumar 9048316176
4 Trenching KM-02 & KM-03 Sugata Dutta 9330539235
5 Lowering KM-02 & KM-03 Pramod Kumar 9048316176
6 Tie in joint KM-02 & KM-03 Manoranjan Sharma 9337814987
7 Backfilling KM-02 & KM-03 Sugata Dutta 9330539235
8 RT Review Dark Room Manoranjan Sharma 9337814987

FOR TOLANI PROJECTS PVT LTD

You might also like