Hitung STR Lengkap
Hitung STR Lengkap
02 * R. SERBAGUNA Finishing 90
* R. OLAH RAGA Plafond 20
* HALL 110
* R. PERTEMUAN Plat beton t=120 mm 288
Beban Mati = 398 398.0 398.0 398.0
Beban Hidup = 400 400.0 360.0 200.0
798.0 758.0 598.0
03 * LOBBY Finishing 90
* KORIDOR Plafond 20
* TANGGA 110
Plat beton t=120 mm 288
Beban Mati = 398 398.0 398.0 398.0
Beban Hidup = 300 300.0 270.0 150.0
698.0 668.0 548.0
6 * GUDANG Finishing 90
Plafond 20
110
Plat beton t=120 mm 288
Beban Mati = 398 398.0 398.0 398.0
Beban Hidup = 400 400.0 360.0 200.0
798.0 758.0 598.0
1 2.2 2.8 227.9 4.5 3600 2 600 4427.9 1.4 1.4 2259.143
2 4.3 2.8 445.5 5.8 4640 5 1500 6585.5 1.4 1.4 3359.939
TRIBUTARY AREA
(cooling tower)
1 3.5 1 3430.0 0.0 0.0 0 0.0 0.0 0.0 4.5 9720 2 4320 17470.0
2 3.5 2 6860.0 0.0 0.0 0 0.0 0.0 0.0 5.8 12528 5 10800 30188.0
cooling tower
Type Size L (m) q (kg/m') M=1/8ql2 Mu=1.5M
(cmxcm) kgm kgm
add - office
Code q Dimensions p q-seg q-trp
of lx ly ly/lx
slab (kg/m2) (m) (m) (kg/m') (kg/m')
bm
A 510.00 2.50 8.00 3.20 637.50 425.00 616.75
EQUIVALEN LOAD
add - office
Code q Dimensions p q-seg q-trp
of lx ly
slab (kg/m2) (m) (m) ly/lx (kg/m') (kg/m')
bh
A 300.00 2.50 8.00 3.20 375.00 250.00 362.79
0.3
192.9
0.3
216.9
0.3
244.5
0.3
259.5
0.3
259.5
0.3
415.5
0.3
744
0.3
1560
0.3
162.9
Beban Total
kg/m2
Gempa
0.3
267
0.3
423
0.3
274.5
0.3
274.5
0.3
423
U24 BRC U50 PILE(cm) L (m) P (ton)
= 2.53 cm2
= 1.89 cm2
TENSION LOAD
Location Area n-pile Uplift Found Slab 2nd - Base 1st- Base 1st- Floor Ret. Wall Pilecap Pile Tension
m2 kg/m2 kg/m2 kg/m2 kg/m2 kg/m2 kg kg kg
(11,C) 64 1f 100 8500 1200 1500 1000 1000 0 12902 43353 186945
( 13,A) 32 1f 80 8500 1200 1500 1000 1000 51840 9878 15680 44202
Tension 1Pile
kg
186945
44202
54512
PERENCANAAN PELAT DASAR
Pada perencanaan ini beban bergerak ( forklift ) lebih menentukan karena adanya beban terpusat
yang besar pada suatu titik yang menyebabkan terjadinya konsentrasi tegangan pada titik tersebut
yang dapat menimbulkan terjadinya pumping pada pelat lantai.
Data Perencanaan :
RUMUS WESTERGAARD
s = 4.3P / h2 . ( 1- aV2/L).1.2
300
750
Mutu Bahan :
Beton : K 250 ----> s'bk = 250 kg/cm2
Tulangan :U 50 ----> sa = 2900 kg/cm2
s*au = 4350 kg/cm2
Dimensi Plat:
Bentang Plat ( lo ) = 300 cm
Tebal plat ( h ) = 10 cm ( tebal efektif)
Penulangan Plat:
Diameter tulangan = 0.6 cm
Jarak tulangan = 15 cm
Lendutan f = fe g'.k1.k2+p'
g+p
k1 = 2 ( balok persegi )
k2 = 1 --------> A'/A = 1
1 + A'/A
k2 = 0.5
x = 2.5.A.s*au = 0.02732
b.h.s'bk
Berat urugan :
urugan atas tandon 0.000
84 128
166.65 177.875
Tanah :
1.546875 ton-m Tebal dinding = 25 cm
Air
=3,5*1*0,5*3,5*1/3*3,5 2.6041666667 CU =
4.1510416667 q =
A =
dipakai D-13 jarak =
q = 0.09583 q = 0.049
A = 15.901 A = 6.504425
dia 13 8.345389 dia 13 20.4015
Gaya keatas tekanan air :
=3,6*1*4,5*8,75
3.801868 CU = 4.752335
0.075 q = 0.13125
9.955752 A = 21.77821
13.32898 d13 6.093247
Dia 16 9.183492
900
400
480
1780
PERENCANAAN DINDING STRUKTURAL
Data Perencanaan :
Panjang ( B ) = 350 mm
tebal ( h ) = 6700 mm
fc' = 30 Mpa
fy = 420 Mpa
Tulangan Horisontal
Geser Rencana
Vu = 4148.95 > 1/6.Acv.fc'^2
2140.68 kN
Sehingga diperlukan 2 lapis tulangan
Dipakai : f Tulangan = 12 mm
Jarak = 100 mm
rn = 0.00646
Tulangan Vertikal
Tulangan vertikal DS harus---------------> r v > 0.0025
Dipakai : f Tulangan = 12 mm
Jarak = 250 mm
W1 3606 54.09 20 0.154 3 3.4 1.13 42.00 37.00 20.45 18.01 1.08 1.14 0.0171 0.0028 0.0029 4.30
0.141 42.00 37.00 20.45 18.01 1.08 1.14 0.0018 0.0028 0.0029 4.30
X- direc. reinforcement Y- direc. reinforcement
Dia(mm) jrk(cm) At-y(cm2) Dia(mm) jrk(cm)
Dia(mm) jrk(cm) Al-y(cm2) Dia(mm) jrk(cm)
Type balok : B9
T = 79128 N
Cs = 76245 N
Cc = 1657.5 a
a = 1.73907692 mm
Mn = 10674291 Nmm
1067 kgm
Type balok : B2
T = 226080 N
Cs = 130287 N
Cc = 3162 a
a = 30.2952205 mm
Mn = 76711153 Nmm
7671 kgm
LENDUTAN TIE BEAM
tinggi dinding :9 m
q : 2250 kg/m
E beton : 210000 kg/cm2
f = 5/384*(q.L^4)/EI
fy = 4000 Kg/cm2
fc' = 210 kg/cm2
TYPE Dimensi Mu As required As min Dia Tul jumlah As design a M cap M cap > Mu
B (cm) D(cm) kgm cm2 cm2 mm mm cm2 cm kgm kgm
Material properties :
Fc = 200 kg/cm2 swy 2400 kg/cm2 As 1-D19 = 2.84 cm2
sy = 4000 kg/cm2 dc 4 cm As 2f10 = 1.57 cm2
Qsu={ 0.053 x Pt0.23(Fc+180) / ( M/Q x d + 0.12) + 2.7VPw x swy } x b x j ( JCI - 1982 Appendix 2.14 )
Pt = At/b.d
Pw = Aw/b.x
PERHITUNGAN TULANGAN BALOK
fc' = 21 Mpa
fy = 400 Mpa
Lokasi : Lt1
Type Mu B D d r min Rn m r perlu
balok kgm cm cm cm
P1 = 38 ton
P2 = 76 ton
P3 = 114 ton
TYPE q dinding q sloof q total L koef Mu 10% P1 10% P2 10% P3
kg/m2 kg/m kg/m kgm kg kg kg
Selanjutnya perencanaan ground beam dilakukan dengan menggunakan diagram interaksi M-N
PERHITUNGAN GESER BALOK
Beban Mati
* Plat : 288 kg/m2
* plafond : 20 kg/m2
* finishing : 100 kg/m2
408 kg/m2
Beban Hidup
* B. Hidup : 400 kg/m2
Vu = 290.54 kN
Vs = Vu/f =Vu/0.75 = 387.39 kN
Vs = Av x fy x d
S
S perlu = Av x fy x d = 165.96 mm
Vs
Kontrol S max
S max1 = d/4 = 160.25 mm
S max2 = 8.db tul = 152 mm
S max3 =24 db hoop = 240 mm
S max 4 = 300 mm
Sehingga S pakai = 150 mm
Kontrol Vs max
Vs max1 = 2/3xbwxd.fc'^0.5 = 1170.3 kN
Vs max2 = 1/3xbwxd.fc'^0.5 = 585.2 kN
Vs ada = 422.68 kN < Vs Max1,2……. (OK)
Vu = 204.97 kN
Vn = Vu/f = 273.29 kN
Data Perencanaan :
fc = 21 MPa
fy = 240 MPa
dc = 4 cm ( selimut beton )
Lokasi Vu bw h d Vc 0.5Vc Vs Tulangan Geser s max ( d/2 ) s pakai
kN mm mm mm kN kN kN dia s ( mm ) (mm) ( mm )
Tumpuan 114 200 600 542 82.79 41.40 107.21 10 182.87 271 100
Keterangan :
Vc = ( fc'^2/6).bw*d
Vs = Vu/f - Vc
keterangan :
selanjutnya dilakukan analisa dengan diagram M-N
PERHITUNGAN TULANGAN GESER BALOK
A. TUMPUAN
Mutu Bahan :
fc' = 21 Mpa
fy = 400 Mpa
Tulangan Balok :
tulangan utama = 16 mm
sengkang = 10 mm
cover = 30 mm
Dimensi Balok :
bw = 300 mm
H= 700 mm
d= 652 mm
Hasil Analisa :
Vu = 120 kN
Vs = 125.30 kN
Vs = Av x fy x d
S
S perlu = Av x fy x d = 326.77 mm
Vs
Kontrol S max
S max1 = d/4 = 163 mm
S max2 = 8.db tul = 128 mm
S max3 =24 db hoop = 240 mm
S max 4 = 300 mm
Tulangan Balok :
tulangan utama = 16 mm
sengkang = 10 mm
cover = 30 mm
Dimensi Balok :
bw = 300 mm
H= 700 mm
d= 652 mm
Hasil Analisa :
Vu = 120 kN
Vs = Vu/f -Vc
Vs = 120 - 149.39
0.6
Vs = 50.61 kN
Vs = Av x fy x d
S
S perlu = Av x fy x d = 809.07 mm
Vs
Kontrol S max
S max1 = d/2 = 326 mm
S max 4 = 600 mm
TABEL PERHITUNGAN GESER & TORSI BALOK
======== = ========= = ========== = ===== = =
GRAVITY STATIC LOAD : 1.5 x ( M + H )
SEISMIC LOADING : 1.05 x (M+Hr+Ex)
: 1.05 x (M+Hr+Ey)
kg/cm2
kg/cm2
kg/cm2
======= = ====== = ====== = ===== = ====== =
Tbsum | Tbu'' | Ts | STRIRRUPS |
| | | |
kg/cm2 | kg/cm2 | kg/cm2 | d(mm) | as(cm) |
======= = ====== = ====== = ===== = ====== =
| | | | |
8.61 | 0.00 | 8.61 | 10 | 12.6 | 30 ||| 50 20
11.51 | 0.00 | 11.51 | 12 | 13.6 | 30 ||| 50 20
21.09 | 4.73 | 11.73 | 10 | 15.0 | 30 ||| 50
======= = ====== = ====== = ===== = ====== =
| 50
| 50
PERENCANAAN SLOOF
keterangan : -N adalah aksial tarik yang diperoleh dari 10% aksial kolom
akibat kombinasi beban gempa
cooling tower
Type Size L (m) q (kg/m') M=1/8ql2 Mu=1.5M
(cmxcm) kgm kgm
Mu = 1500 kN
Mn = 1875000000 Nmm
Rn = 1875000000
600 x 949 2
Rn = 3.469905
m = fy/ (0.85*fc')
m = 400
0.85 x 21
m = 22.40896
r = 1/m( 1- (1-2.m.Rn/fy)^0.5
r = 0.0097
r pakai = 0.009737
As perlu= r.bw.d
= 5544.284 mm2
Tulangan Pakai = 8 D 22
TABEL PENULANGAN LENTUR BALOK
Balok Mu fc' fy B H Rn m r r min r pakai rb r maks As perlu f tul Jumlah Tul r ada
kgm kg/cm2 kg/cm2 cm cm 0.75 rb mm2 mm pakai
220000 210 4000 70 100 4.1753 22.41 0.0121 0.0035 0.0121 0.0228 0.0171 8196.1 25 16.7 14 0.0101
a fMn
kNm
0.0090 2132.05
Perencanaan Penulangan Lentur Balok
Data Perencanaan :
fy = 400 MPa
fc = 21 MPa
dc = 4 cm ( selimut beton )
Letak Mu bw h d m Rn r perlu r min r max r pakai As perlu Penulangan As ada
kgm cm cm cm cm2 dia ( mm ) jumlah cm2
Tumpuan kiri - 13259.00 20 60 54.2 22.41 2.655 0.00722 0.00350 0.01707 0.00722 7.83 16 4 8.04
Lapangan + 6879.00 20 60 54.2 22.41 1.377 0.00359 0.00350 0.01707 0.00359 3.89 16 4 8.04
Tumpuan kanan - 13500.00 20 60 54.2 22.41 2.703 0.00737 0.00350 0.01707 0.00737 7.98 16 4 8.04
Keterangan :
m = fy / 0.85.fc'
Rn = Mu/f.bw.d2
r min = 1.4/ fy
As perlu = r.bw.d
Mutu Bahan :
Beton : 15 Mpa
Baja : 240 Mpa
Tul utama 13 mm
Sengkang 8 mm
B10 ------ - D16 ------ - D16 ------ - D16 - Dia 10- . Dia 10- . Dia 10- .
B11 ------ - D16 ------ - D16 ------ - D16 - Dia 10- . Dia 10- . Dia 10- .
B18 ------ - D16 ------ - D16 ------ - D16 - Dia 10- . Dia 10- . Dia 10- .
PERHITUNGAN GROUND BEAM
GB 1
Data Bahan :
fc' = 21 Mpa
fy = 400 Mpa
Ukuran Penampang :
B = 30 cm
H = 90 cm
d = 88 cm
r min = 1.4/fy
= 0.0035
Rn = 0.783023
m = 22.40896
r = 1/m(1-V(1-2mRn/fy)
= 0.002002
r pakai = 0.0035
As pakai---> dia = 16 mm
jumlah = 5 mm
As ada = 10.048 cm2
PERHITUNGAN TULANGAN GESER KOLOM
A. TUMPUAN
Mutu Bahan :
fc' = 21 Mpa
fy = 400 Mpa
Tulangan Balok :
tulangan utama = 16 mm
sengkang = 10 mm
cover = 30 mm
Dimensi kolom :
B= 400 mm 1/2 b = 200
H= 500 mm 1/2h = 250
d= 452 mm
Ag = 200000 mm2
Hasil Analisa :
Vu = 120 kN
Nu = 200 kN
Perhitungan Tulangan Geser Kolom :
Vc = (1+Nu/14.Ag)*(1/6*Vfc'*bw*d
(1+Nu/14Ag) = 1.0714285714
1/6*Vfc'.B.d = 138088.28 N
1/6*Vfc'.B.d = 138.09 kN
Vc = 147951.73 N
Vc = 147.95 kN
Vc pakai = 0.5 Vc
= 73.98 kN
Vs = Vu/f -Vc
Vs = 120 - 73.98
0.6
Vs = 126.02 kN
Vs = Av x fy x d
S
Tulangan Balok :
tulangan utama = 16 mm
sengkang = 10 mm
cover = 30 mm
Dimensi kolom :
B= 400 mm 1/2 b = 200
H= 500 mm 1/2h = 250
d= 452 mm
Ag = 200000 mm2
Hasil Analisa :
Vu = 120 kN
Nu = 200 kN
Perhitungan Tulangan Geser Kolom :
Vc = (1+Nu/14.Ag)*(1/6*Vfc'*bw*d
(1+Nu/14Ag) = 1.0714285714
1/6*Vfc'.B.d = 138088.28 N
1/6*Vfc'.B.d = 138.09 kN
Vc = 147951.73 N
Vc = 147.95 kN
Vs = Vu/f -Vc
Vs = 120 - 147.95
0.6
Vs = 52.05 kN
Vs = Av x fy x d
S
DATA PERENCANAAN :
Mutu Bahan :
fy = 400 Mpa
fc' = 21 Mpa
Dimensi Balok :
B = 600 mm
H = 600 mm
d = 549
Tulangan :
Tul. Utama = 22 mm
Sengkang = 10 mm
As = 379.94 mm2
Hasil Analisa :
Mu = 1500 kN
Nu = 1500 kN
office area
axis C1 DIM
storey LUAS Q MATI Q HIDUP L1 DIND.1 L2 DIND.2 H KOL Q KOL L BAL Q BAL Q LT - i Q KUM KOLOM
B3F 20.76 560 800 5.5 600 4.5 1100 4 1940 15 700 44778.8 139541 34.1
B2F 20.76 560 800 5.5 600 4.5 1100 4 1940 15 700 44778.8 94762 28.1
PH 20.76 560 800 5.5 600 4.5 1100 5 600 15 700 49983.6 49984 20.4
axis C2 DIM
storey LUAS Q MATI Q HIDUP L1 DIND.1 L2 DIND.2 H KOL Q KOL L BAL Q BAL Q LT - i Q KUM KOLOM
B3F 34.7 560 800 0 600 8 1100 4 1940 12 700 55496 178384 38.6
B2F 34.7 560 800 0 600 8 1100 4 1940 12 700 55496 122888 32.0
PH 34.7 560 800 0 600 8 1100 5 600 12 700 67392 67392 23.7
project :Slipimas-Project
location :Jakarta - Indonesia
Project : Sakura Residence - Myanmar
C2 500 x 500 500 x 500 450 x 450 450 x 450 400 x 400 400 x 400 -
P3 23712 4000 210 160 70 9.96 20.16 16 150 21.44 3.00 52860 23712
ok
ok
ok
Calculation sheet : Foundation Pile
Reaction Force :
Data : Fx = 1500 kg
Fy = 5000 kg
Fz = 30500 kg
Mx = 27000 kgm
Mz = 7500 kgm
A. AXIAL LOAD
Fz = 30500 kg Mx = 27000 kgm
R/C column = 53460 kg My = 7500 kgm
Pilecap = 47376 kg x max = 1.585 m
V total = 131336 kg S x2 = ( 4X1.5852)
= 10.048 m2
y max = 1m
Sy 2
= (4x1^2)
= 4 m2
B. LATERAL LOAD
F allowable = 2200 kg ( Lateral Load Capacity = 2200 kg )for lateral displacement max = 1/4"
M = Factor*cr*D2
cr = 0.5*cu
= 50 kg/m2
e/L = 0m
Ho/cr*D = 1250/50*0.4 ^------------> from atached table M/cr*D2 = 150
= 62.5
M = 150*cr*D2
= 150*50*0.42
= 1200 kgm
Mu = 1.5*1200 kgm
1800 kgm < Pile Moment Capacity = 10600 kgm ( ok )
Type Pu Vu Mu Panjang Tinggi Tebal f'c fPnw (Mu/Vu-lw/2) Vc1 Vc2 Vc fVc
Newton Newton Newton mm lw hw h Mpa Newton mm Newton Newton Newton Newton
mm mm mm
S1 13412200 3656200 64152900000 9000 4000 250 29 21101850 13046 5105764 44337390 5105764 3063458
S1 13412200 3656200 64152900000 9000 4000 250 29 21101850 13046 5105764 44337390 5105764 3063458
S1 13412200 3656200 64152900000 9000 4000 250 29 21101850 13046 5105764 44337390 5105764 3063458
ok
not
fVs rh min Sh max Tul h pakai fVs ada rh rh min < rh rv min Sv max Tul v pakai rv
Newton lw/5 3h 500 Dia Jarak Newton lw/3 3h 500 Dia Jarak
mm mm mm mm mm mm mm mm mm mm
592741.5 0.0025 1800 750 500 12 200 1904498 0.0045 ok 0.004578 3000 750 500 16 150 0.010718
592741.5 0.0025 1800 750 500 12 200 1904498 0.0045 0 0.004578 3000 750 500 16 150 0.010718
592741.5 0.0025 1800 750 500 12 200 1904498 0.0045 #REF! 0.004578 3000 750 500 16 150 0.010718
ok
not
rv min < rv
ok
#REF!
PROYEK : SHOWROOM GRESIK
T = 643072 N
Cs = 308827 N
Cc = 12648 a
a = 26.4266849 mm
Mn = 371075269 Nmm
37108 kgm lebih besar dari M ultimate = 36000 kgm
T = 643072 N
Cs = 308827 N
Cc = 12648 a
a = 26.4266849 mm
Mn = 393709876 Nmm
39371 kgm lebih besar dari M ultimate = 38250 kgm
T = 803840 N
Cs = 308827 N
Cc = 12648 a
a = 39.1376273 mm
Mn = 454032898 Nmm
45403 kgm lebih besar dari M ultimate = 44625 kgm
M = (22525*0.35)-(1/8*(780*4.7)*2.7^2-(0.5*(0.5*0.2*2400)*0.55^2
M = 6552 - 3340 - 36.3 = 3175.7 kgm
Mu = 1.5*3175.7 kgm
Mu = 4763.55 kgm
Rn = Mu/fb.d2 r min = 1.4/fy
Rn = 47635500/(0.8*500*3002) r min = 1.4/400
Rn = 1.32 r min = 0.0035 (menentukan)
m = fy/(0.85*fc')
m = 400/(0.85*18.6)
m = 25.3
r = 1/m(1-V(1-2mRn/fy)
r = 1/25.3(1-V(1-2.25.3*1.32/400)
r = 0.00345
As perlu = 0.0035*500*300
As perlu = 525 mm2
SF = 2.1
Keterangan :
D : dimensi tiang
S : jarak antar tiang
m : jumlah baris tiang arah - x
n : jumlah baris tiang arah - y
EFFISIENSI PILE GROUP
Type n - pile D(m) S(m) m n Eff
P2 2 0.2 0.8 2 1 1
P3 3 0.2 0.8 - - 1
P6 6 0.2 0.8 3 2 1
Eff = 2(m+n-2)S + 4D
m.n.p.D
Ket :
D : dimensi tiang
S : jarak antar tiang
m : jumlah baris tiang arah - x
n : jumlah baris tiang arah - y
EFFISIENSI PILE GRUP
Type n-pile Lr Br Luas Kel qc fs.L Qfb Qcb Tahanan S tahanan Eff
(m) (m) (m2) (m) t/m2 t/m ( ton ) ( ton ) ijin blok ijin tiang tunggal
( ton ) ( ton )
Ket :
Qcb : Luas x qc
Qfb : Keliling x L x fs
KONTROL GESER PONS
bo = 2*390+2*250+4*300
bo = 2480 mm
bc = 250/390
bc = 0.64
Vc1 = ( 1+2/0.64)*(1/6V18.6)*2480*300
Vc1 = 2205.98 kN
Vc2 = 1/3V18.6*2480*300
Vc2 = 1069.56 kN ( menentukan )
fVc = 0.6*1069.56
fVc = 641 kN = 64.173 ton > Vu=36 ton
keterangan:
Vc1 : ( 1 + 2/bc).(1/6 V fc' ).bo.d
Vc2 : 1/3Vfc'.bo.d
ok
not
fVc > Vu
ok
KONTROL GESER PONS
( blk-d )
keterangan:
Vc1 : ( 1 + 2/bc).(1/6 V fc' ).bo.d
Vc2 : 1/3Vfc'.bo.d
adap sisi kolom ok
not
Vu fVc > Vu
kN
671.33 ok
811.97 ok
863.86 ok
PERHITUNGAN DAYA DUKUNG TIANG PANCANG
Type jumlah ukuran jarak jarak jarak jarak jarak jarak P Effisiensi P Ijin Ket
Lokasi poer tiang tiang X1 X2 Y1 Y2 terjauh terjauh P total Mx My 1 Tiang Pile Grup 1 tiang
( Axis ) pancang pancang (m) (m) (m) (m) X Y (kg) (kgm) (kgm) (kg) kg
A,4 P2 2.0 0.250 0.000 0.000 0.375 0.375 0.000 0.375 51292.4 296.0 0.0 26040.9 0.9 33750 ok
B,4 P3 3.0 0.250 0.375 0.375 0.200 0.450 0.375 0.450 81024.6 114.0 106.0 27331.1 0.85 31875 ok
I,1b P1 1.0 0.250 0.300 0.300 0.300 0.300 0.300 0.300 6359.7 172.0 67.0 6558.9 1 37500 ok
BEARING CAPACITY OF PILE PONDATION
CALCULATION
N-SPT average = 14
Pile Data :
Size : f 40 cm
Length : 24 m ( from existing ground level)
where :
Nb = N-SPT value at bottompile
Ab = area of pile tip ( m2)
N ave = N-SPT value average as long pile
As = are of pile shaft ( m2)
SF = safety factor ( this case is taken 3 )
Q all = allowable capacity of pile
Q ult = ultimate pile capacity
Ab = 0.25*3.14*0.4*0.4 = 0.1256 m2
As = 3.14*0.4*24 = 30.16 m2
Section 1 : Multipurpose,Office,Canteen,Classroom
Section 2 : Power house,Guest House,GM house
Section 3 : Apartment, Trainee Dormitory
BLKG-99
A-10 P1 1.0 0.300 0.000 0.000 0.000 0.000 0.000 0.000 15691.0 5000.0 20691.0 0.0
B-10 P2 2.0 0.300 0.000 0.000 0.450 0.000 0.000 0.450 26543.0 0.0 26543.0 23.0
H-10 P1 1.0 0.300 0.000 0.000 0.000 0.000 0.000 0.000 9674.0 5000.0 14674.0 0.0
A-10 P1 1.0 0.300 0.000 0.000 0.000 0.000 0.000 0.000 16505.0 5000.0 21505.0 0.0
B-10 P2 2.0 0.300 0.000 0.000 0.450 0.000 0.000 0.450 27000.0 0.0 27000.0 2299.0
H-10 P1 1.0 0.300 0.000 0.000 0.000 0.000 0.000 0.000 7295.0 5000.0 12295.0 0.0
P* Aksial hasil output Etabs belum termasuk dinding lt bawah ( output terlampir )
BLKG-100
P
My 1 TIANG
(kgm) (kg)
0.0 20691.0
191.0 13483.7
0.0 14674.0
P
My 1 TIANG
(kgm) (kg)
0.0 21505.0
5378.0 19475.6
0.0 12295.0
Proyek : Ruko Pengampon Permai
Blok C
GAYA LATERAL TIANG
Office
Type n- pile P eff- pile Pall
kg kg
factory
Type n- pile P eff- pile Pall
kg kg
electric room
Type n- pile P eff- pile Pall
kg kg
F max = 1250 kg
D = 0.4 m
F/Cr.D = 62.5
from tabel = M/Cr.D2 = 140
e/D = 0
M= 140*Cr*D^2
M= 140*50*0.4^2
M= 1120 kgm
Mu = 1.5*1120
Mu = 1680 kgm
TABEL PERHITUNGAN REAKSI KOLOM & JUMLAH TIANG PANCA
===================================================
PRELIMINARY BERDASARKAN TRIBUTARY AREA
= =
Project : PT YASUNAGA INDONESIA, CIKANDE - SERANG
Client : KUMAGAII KADII JOINT OPERATION
No. Diameter Panjang penamp. SPT end Daya dukung SPT rata2 selimut Daya dukung Daya dukung Safety Daya Dukung
Strauss Ab Nb Pend Navg As Pskin Pultimate SF P ijin
(m) (m) (m2) ( ton ) (m2) ( ton ) ( ton )
BORE HOLE B3
No. dimensi Panjang penamp. qc Daya dukung JHP selimut Daya dukung Daya Dukung
Ab qonus As Pskin P ijin
(m) (m) (m2) ( ton ) (m2) ( ton )
berdasarkan S1
1 0.25 6 0.0491 16 2.617 300 0.785 3.925 6.542
2 0.25 7 0.0491 22 3.598 380 0.785 4.972 8.570
5 0.25 10 0.0491 40 6.542 1000 0.785 13.083 19.625
PROYEK : GEDUNG CRITICAL & MEDICAL CENTER, RSUD DOK II, JAYAPURA
GEDUNG : BLOK E
PERHITUNGAN PONDASI
Pijin = Pult / SF
dimana :
No. Diameter Panjang penamp. Daya dukung selimut Daya dukung Daya Dukung
Ab Nb end bearing Navg As Pskin P ijin
(m) (m) (m2) ( ton ) (m2) ( ton )
berdasarkan borehole 1 :
berdasarkan borehole 2 :
Ram ( cm ) 20 30 40 50 60 70 80 90
stroke (inch) 7.874 11.811 15.748 19.685 23.622 27.559 31.496 35.433
( cm) ( inch) ( ton ) ( ton ) ( ton ) ( ton ) ( ton ) ( ton ) ( ton ) ( ton )
0.1 0.039 166.9 250.4 333.8 417.3 500.7 584.2 667.6 751.1
0.2 0.079 83.5 125.2 166.9 208.6 250.4 292.1 333.8 375.6
0.3 0.118 55.6 83.5 111.3 139.1 166.9 194.7 222.5 250.4
0.4 0.157 41.7 62.6 83.5 104.3 125.2 146.0 166.9 187.8
0.5 0.197 33.4 50.1 66.8 83.5 100.1 116.8 133.5 150.2
0.6 0.236 27.8 41.7 55.6 69.5 83.5 97.4 111.3 125.2
0.7 0.276 23.8 35.8 47.7 59.6 71.5 83.5 95.4 107.3
0.8 0.315 20.9 31.3 41.7 52.2 62.6 73.0 83.5 93.9
0.9 0.354 18.5 27.8 37.1 46.4 55.6 64.9 74.2 83.5
1 0.394 16.7 25.0 33.4 41.7 50.1 58.4 66.8 75.1
1.1 0.433 15.2 22.8 30.3 37.9 45.5 53.1 60.7 68.3
1.2 0.472 13.9 20.9 27.8 34.8 41.7 48.7 55.6 62.6
1.3 0.512 12.8 19.3 25.7 32.1 38.5 44.9 51.4 57.8
1.4 0.551 11.9 17.9 23.8 29.8 35.8 41.7 47.7 53.7
1.5 0.591 11.1 16.7 22.3 27.8 33.4 38.9 44.5 50.1
1.6 0.630 10.4 15.6 20.9 26.1 31.3 36.5 41.7 46.9
1.7 0.669 9.8 14.7 19.6 24.5 29.5 34.4 39.3 44.2
1.8 0.709 9.3 13.9 18.5 23.2 27.8 32.5 37.1 41.7
1.9 0.748 8.8 13.2 17.6 22.0 26.4 30.7 35.1 39.5
2 0.787 8.3 12.5 16.7 20.9 25.0 29.2 33.4 37.6
2.1 0.827 7.9 11.9 15.9 19.9 23.8 27.8 31.8 35.8
2.2 0.866 7.6 11.4 15.2 19.0 22.8 26.6 30.3 34.1
2.3 0.906 7.3 10.9 14.5 18.1 21.8 25.4 29.0 32.7
2.4 0.945 7.0 10.4 13.9 17.4 20.9 24.3 27.8 31.3
2.5 0.984 6.7 10.0 13.4 16.7 20.0 23.4 26.7 30.0
2.6 1.024 6.4 9.6 12.8 16.0 19.3 22.5 25.7 28.9
2.7 1.063 6.2 9.3 12.4 15.5 18.5 21.6 24.7 27.8
2.8 1.102 6.0 8.9 11.9 14.9 17.9 20.9 23.8 26.8
2.9 1.142 5.8 8.6 11.5 14.4 17.3 20.1 23.0 25.9
3 1.181 5.6 8.3 11.1 13.9 16.7 19.5 22.3 25.0
3.1 1.220 5.4 8.1 10.8 13.5 16.2 18.8 21.5 24.2
3.2 1.260 5.2 7.8 10.4 13.0 15.6 18.3 20.9 23.5
3.3 1.299 5.1 7.6 10.1 12.6 15.2 17.7 20.2 22.8
3.4 1.339 4.9 7.4 9.8 12.3 14.7 17.2 19.6 22.1
3.5 1.378 4.8 7.2 9.5 11.9 14.3 16.7 19.1 21.5
3.6 1.417 4.6 7.0 9.3 11.6 13.9 16.2 18.5 20.9
3.7 1.457 4.5 6.8 9.0 11.3 13.5 15.8 18.0 20.3
3.8 1.496 4.4 6.6 8.8 11.0 13.2 15.4 17.6 19.8
3.9 1.535 4.3 6.4 8.6 10.7 12.8 15.0 17.1 19.3
4 1.575 4.2 6.3 8.3 10.4 12.5 14.6 16.7 18.8
4.1 1.614 4.1 6.1 8.1 10.2 12.2 14.2 16.3 18.3
4.2 1.654 4.0 6.0 7.9 9.9 11.9 13.9 15.9 17.9
4.3 1.693 3.9 5.8 7.8 9.7 11.6 13.6 15.5 17.5
4.4 1.732 3.8 5.7 7.6 9.5 11.4 13.3 15.2 17.1
4.5 1.772 3.7 5.6 7.4 9.3 11.1 13.0 14.8 16.7
4.6 1.811 3.6 5.4 7.3 9.1 10.9 12.7 14.5 16.3
4.7 1.850 3.6 5.3 7.1 8.9 10.7 12.4 14.2 16.0
4.8 1.890 3.5 5.2 7.0 8.7 10.4 12.2 13.9 15.6
4.9 1.929 3.4 5.1 6.8 8.5 10.2 11.9 13.6 15.3
5 1.969 3.3 5.0 6.7 8.3 10.0 11.7 13.4 15.0
100 110 120 130
39.370 43.307 47.244 51.181
ULTIMATE
Vu = fVn
Vu = fVc + fVs
Vc = (1 +Nu/14.Ag).(Vfc'/6).bw.d
Vc = 0
Vc = 1/6(vfc')bw.d
Vc = 1/6*V21.300.246
Vc = 56365 N = 5636 kg
Vs = Av.fy.d/s
Vs = 2.0,25.p.8.8.240.246/100
Vs = 59353 N = 5935 kg
ok
ok
ok
GAYA GESER DASAR & GESER TINGKAT
LOCKER
S Wi = 234205 kg
S Wi x hi = 1237040 kgm
GAYA GESER DASAR = 11710.25 kg
0.9*GAYA GESER DASAR = 10539.225 kg
JUMLAH LANTAI = 2
PERIODE BANGUNAN = 0.91
KOEFISIEN GEMPA DASAR = 0.05
FAKTOR KEUTAMAAN = 1
TIPE STRUKTUR = 1
S Wi = 234205 kg
S Wi x hi = 1237040 kgm
GAYA GESER DASAR = 11710.25 kg
0.9*GAYA GESER DASAR = 10539.225 kg
DATA GEMPA :
WG 6, pakai SNI 1726 gambar 2, Tanah Lunak
Faktor keutamaan (I) : 1
Nilai R : untuk arah U-S, Sistem Ganda ( SG ) : 8.5
untuk arah B-T, Sistem Ganda ( SG ) : 8.5
1. BEBAN RENCANA
PERENCANAANPERENCANAANPERENCANAAN
PLAT PORTAL GEMPA
kg/m2 kg/m2 kg/m2
BEBAN MATI
A. BERAT LANTAI
LANTAI BERAT ( KG )
ATAP 165539.79
5TH 699083.19
4TH 1098799.07
3RD 1439006.60
2ND 1499221.62
1ST 1312481.43
GRD 2054554.32
TOTAL 2054554.32
JUMLAH LANTAI = 7
FAKTOR KEUTAMAAN STRUKTUR ( I ) = 1
FAKTOR TYPE STRUKTUR ( K ) = 1
BERAT TOTAL ( Wt ) = 2054554.32 kg
V = C X I X K X Wt
ARAH - X
PERIODE GETAR BANGUNAN - X = 1.930
KOEFISIEN GEMPA DASAR ( C ) = 0.030
GAYA GEMPA DASAR ( V ) = 61636.63 kg
REDUKSI 10% ( 0.9 V ) = 55472.97 kg
ARAH - Y
PERIODE GETAR BANGUNAN - Y = 1.860
KOEFISIEN GEMPA DASAR ( C ) = 0.030
GAYA GEMPA DASAR ( V ) = 61636.63 kg
REDUKSI 10% ( 0.9 V ) = 55472.97 kg
Lantai Geser Tingkat Geser Tingkat Geser Tingkat Rencana Geser Tingkat Beban Gempa ( Fi )
Analisa Dinamik dengan Faktor Koreksi 0.9 * V ( Final ) ( Final )
kg kg kg kg kg
X - dir Y - dir X - dir Y - dir X - dir Y - dir X - dir Y - dir X - dir Y - dir
ROOF 10839 10577 10839 11391 8385 8385 10839 11391 10839 11391
1ST-FL 48674 41012 48674 44169 44169 44169 48674 44169 37835 32778
Faktor Koreksi : Gaya Geser Dasar Analisa Statik = 44169 = 0.91 dipakai 1
( X - dir ) Gaya Geser Dasar Analisa Dinamik 48674
1. BEBAN RENCANA
PERENCANAANPERENCANAANPERENCANAAN
PLAT PORTAL GEMPA
kg/m2 kg/m2 kg/m2
BEBAN MATI
A. BERAT LANTAI
LANTAI BERAT ( KG )
LT-8 1632823.40
LT-7 1748198.73
LT-6 1748198.73
LT-5 1748208.54
LT-4 1716339.24
LT-3 1716339.24
LT-2 1697906.67
TOTAL 12008014.53
JUMLAH LANTAI = 7
FAKTOR KEUTAMAAN STRUKTUR ( I ) = 1
FAKTOR TYPE STRUKTUR ( K ) = 1
BERAT TOTAL ( Wt ) = 12008014.53 kg
V = C X I X K X Wt
ARAH - X
PERIODE GETAR BANGUNAN - X = 1.187
KOEFISIEN GEMPA DASAR ( C ) = 0.045
GAYA GEMPA DASAR ( V ) = 540360.65 kg
REDUKSI 10% ( 0.9 V ) = 486324.59 kg
ARAH - Y
PERIODE GETAR BANGUNAN - Y = 1.202
KOEFISIEN GEMPA DASAR ( C ) = 0.045
GAYA GEMPA DASAR ( V ) = 540360.65 kg
REDUKSI 10% ( 0.9 V ) = 486324.59 kg
C. GAYA GESER TINGKAT RENCANA
DRIFT RATIO
Lantai Drift Ratio Drift Ratio Drift Ratio Drift Control
x Faktor koreksi Ijin
X - dir Y - dir X - dir Y - dir X - dir Y - dir
DISPLACEMENT
Lantai Displacement Displacement Tinggi Lantai Displacement Displacement
x Factor koreksi m Ijin
X - dir Y - dir X - dir Y - dir X - dir Y - dir
DRIFT RATIO
Lantai Drift Ratio Drift Ratio Drift Ratio Kontrol Drift
x Faktor Koreksi Ijin
arah - X arah - Y arah - X arah - Y arah - X arah - Y
SIMPANGAN TINGKAT
Lantai Simpangan Simpangan Tinggi Lantai Simpangan Simpangan
x Faktor Koreksi m Ijin
arah - X arah - Y arah - X arah - Y arah - X arah - Y
POSISI BEBAN
es
I G
L1
L2
ebA
ebB
TITIK REFERENSI
ebA = es - 0.05b
ebB = 1.5es + 0.05b
a. ARAH - X
LANTAI b G I es ebA ebB L1 L2
(m) (m) (m) (m) (m) (m) (m) (m)
b. ARAH - Y
LANTAI b G I es ebA ebB L1 L2
(m) (m) (m) (m) (m) (m) (m) (m)
Dm = 0.7RDs
Drifts max = 0.02 x 4 = 0.08m
0
5 29.315 29.1 29.548
15 30
ton
45 60
75 90
EXIST
BRACE
S.WAL
L
STOREY
1 1.5 2 2.5 3 3.5 4 4.5 5
EXIST
BRACE
S.WAL
L
STOREY EXIST BRACE S.WALL
1 1070 1090 1120 STOREY
2 840 855 874
3 560 566 578 1 1.5 2 2.5 3 3.5 4 4.5 5
4 312 313 319
OVERTURNING MOMEN
0
5 116 115 117
EXIST
BRACE
S.WAL
L
STOREY EXIST BRACE S.WALL
1 0.0019 0.001 0.0009 STOREY
2 0.0024 0.0014 0.0012
3 0.0026 0.0013 0.0011 1 1.5 2 2.5 3 3.5 4 4.5 5
4 0.0026 0.0012 0.001
0
5 0.0023 0.001 0.0009
EXIST
BRACE
S.WAL
L
TEGANGAN PONDASI PLAT SETEMPAT
1 25553 20442.4 2 2 4
2 43054 34443.20 2 2.3 4.6
30 21632 17305.60 1.6 1.6 2.56
MPAT
Tegangan Pondasi
kg/m2
5110.60
7487.65
6760.00
BAB IX
PERHITUNGAN PONDASI
a. Lebar 0.6 m :
Mu = 1/2*2500*0.3^2*1.5
Mu = 169 kgm
b. Lebar 0.7 m :
Mu = 1/2*2500*0.35^2*1.5
Mu = 230 kgm
c. Lebar 1 m (tengah) :
Mu = 1/2*2500*0.5^2*1.5
Mu = 469 kgm
d. Lebar 1 m (tepi) :
Mu = 1/2*2500*1^2*1.5
Mu = 1875 kgm
PERHITUNGAN PONDASI PELAT LAJUR
T = 113040 N
Cs = 0N
Cc = 12750 a
a = 8.86588235 mm
Mn = 11368100 Nmm
1137 kgm > 945 kgm [ O.K ]
GAYA GULING :
Gaya Tekan ( 2 ) = 0 kg
Tinggi Guling (2 ) = 0 meter
Momen Guling (2 ) = 0 kg-m
Gaya Tekan ( 4 ) = 0 kg
Tinggi Guling ( 4 ) = 0 meter
Momen Guling ( 4 ) = 0 kg-m
Gaya Tekan ( 2 ) = 0 kg
Tinggi Guling (2 ) = 0 meter
Momen Guling (2 ) = 0 kg-m
TOTAL MOMEN GULING = 1560.94 + 0 + 2604.167 + 0+
= 6038.23 kgm
T = 424528 N
Cs = 203874 N
Cc = 15810 a
a = 13.95659 mm
Mn 67428801 Nmm
6743 kgm > 6038.23 kgm [ ok ]
KONDISI :
- BEBAN AIR TIDAK ADA
- ADA BEBAN KENDARAAN DI ENTRANCE
GAYA GULING :
TINGGI : 3 meter
kedalaman dasar pondasi : 1.5 meter
Berat Jenis Tanah : 1800 kg/m3
TINGGI : 0 meter
kedalaman dasar pondasi : 0.6 meter
Berat Jenis Air : 1000 kg/m3
Gaya Tekan ( 3 ) = 0 kg
Tinggi Guling (3 ) = 0.6 meter
Gaya Guling (3 ) = 0 kg-m
Gaya Tekan ( 4 ) = 0 kg
Tinggi Guling ( 4 ) = 0.3 meter
Momen Guling ( 4 ) = 0 kg-m
= 11472.3 kgm
COUNTER LOAD :
TINGGI : 3 meter
kedalaman dasar pondasi : 1.5 meter
lebar batu kali atas : 0.5 meter
lebar batu kali bawah : 2.5 meter
Berat Jenis Batu : 2000 kg/m3
1 40 0.17 1600 1000 400 0.22 4.5989 9 8 0 3131.17678 0 86.98 42270.9 0.0 3522.6
Penahan
L.Ret. H tanah qa=Kp.gt.H W tanah W kend. Kohesi M(a) M(b) M(c) M(d) M.penahan
(m) (m) kg/m kg kg 2cVKa kgm kgm kgm kgm M(a+b+c+d)
kg/m2 kgm
2.6 0 0.00 37440 1040 1585.4 0.00 48672 1352 50734.27 100758.27
SF Guling = M.Guling/M.Penahan
= 2.20
45793.5 14873.1
F.penahan
kg
34209.2708
PERHITUNGAN DINDING PENAHAN TANAH W1
KONDISI :
- BEBAN AIR SETINGGI 2 METER
- DIAREA TAMAN ADA BEBAN TAMBAHAN 100 kg/m2
GAYA GULING :
TINGGI : 2 meter
kedalaman dasar pondasi : 0 meter
Berat Jenis Air : 1000 kg/m3
T = 464328 N
Cs = 221677 N
Cc = 15810 a
a = 15.3479392 mm
Mn = 81339499 Nmm
8134 kgm
DIPAKAI DINDING PENAHAN TEBAL 250 mm dengan tulangan utama Dia 13-100
0 0
PENULANGAN TANGGA ( MULTI PURPOSE )
Material Properties :
fy = 400 Mpa
fc' = 21 Mpa
12.74
Proyek : Office Buliding ( Slipi Mas )
ECCENTRICITY DESIGN
LEVEL DIRN FORCE A FORCE B CORy CORx COMy COMx ecY ecX edY edX
PH X 43803.31 0 38.4 26
PH Y 0 47289.32 22.87 1.90 -10.24
PH ROT -553235.81 808647.37 12.63 17.10 26.6 17.5 13.97 0.40 12.05 -0.90 0.58
GENSET X 853884.73 0 44 35
GENSET Y 0 828669.34 6.78 11.73 19.15
GENSET ROT -22145240 14615604 25.93 17.64 22.88 24.29 3.05 6.65 0.85 4.90 25.08
446794268.xlsx
Proyek : Office Buliding ( Slipi Mas )
446794268.xlsx
PERHITUNGAN PONDASI
M = H x d
Ukuran Pondasi :
B = 1m
H = 2m
Jarak as - kolom ke tepi pondasi (1) : ### m
Jarak as - kolom ke tepi pondasi (2) : ### m
Jarak eksentrisitas (e) ### m
s1 = ### kg/m2
s2 = 234 kg/m2
M = 1/2.q.l.l
q = ### kg/m'
l = 1.45 m
M = ### kgm
Mu = ### kgm
PERHITUNGAN PEMBEBANAN :
BEBAN MATI :
P = 15525.5
M = 14080.1 + 20726.485722
34806.5
Mu = 52209.8
T 1185413 N
Cs 568679 N
Cc 4743 a
a 130.03 mm
Mn 5.5E+08 Nmm
55018 kgm > 52209.808 kgm [ ok ]