You are on page 1of 1

PT.

WIJAYA KARYA (persero) Tbk


PROYEK JALAN TOL BALIKPAPAN - SAMARINDA SEKSI 2.2
RENCANA JADWAL PENGECORAN 30 APRIL 2019
\
Tanggal TOTAL VOLUME
30 APRIL 2019 30 APRIL 2019 30 APRIL 2019 30 APRIL 2019 30 APRIL 2019 30 APRIL 2019
Keterangan RENCANA (m3)
PEKERJAAN Lean Concrete Mainroad Lean Concrete Mainroad Lean Concrete Mainroad Lean Concrete Mainroad Rigid Pavement Rigid Pavement
TIPE BETON E E E E P P
VOLUME (M3) 91 m3 91 m3 182 m3 91 m3 205 m3 360 m3
STATION
JAM
Sta 47+350 L1 - 47+450 L1
09.30
Sta 39+650 R2 - 39+750 R2
10.00
Sta 39+700 L2 - 39+900 L2
13.30
Sta 47+350 R1 - 47+450 R1
13.30
Sta 39+270 - Sta 39+390
15.00
Sta 47+595 R2 - Sta 47+795 R2
15.00
1.020 m3
PIC Fuat / 082377775744 Doni / 082177161499 Doni / 082177161499 Fuat / 082377775744 Prima / 081258244223 Ruri / 081390167948
BATCHING PLANT BP 3 BP 9 BP 9 BP 3 BP 1 BP 3

CATATAN :

Loa Janan, 29 April 2019


Diterima Oleh, Diajukan Oleh,
PT. WIKA - BETON PT. WIJAYA KARYA (Persero) Tbk.

_________________ ___________________
Wika Beton Seksi 2.2 Engineering Seksi 2.2