Professional Documents
Culture Documents
Bridges
4. Public meetings. Public meetings will also often be held, so that any citizens with
concerns about the road construction project can voice their opinions. The local, state,
or federal governmental entities building the road will also solicit construction bids from
a variety of contractors to make sure that the road can be built as economically as
possible.
7. Embankment. All fill materials must be free from vegetable matter and the
material must be approved as suitable. The material should be of an appropriate nature
and at a moisture content that it can be compacted to form a stable layer. Generally
embankments should be constructed in 150 mm compacted layers parallel to the
finished grade of the road.
8. Subgrade. All subgrade material must be free from vegetable matter. The
subgrade must be shaped to the required profile. The subgrade should be of an
appropriate material and at a moisture content
that it can be compacted to form a stable layer,
for the full width of the embankment.
8.1. Subgrade drains. Subgrade drains
are constructed to ensure that water in the
pavement, which would weaken the road, is
allowed to drain away. Subgrade drains should
be extended to the edge of the embankment with
drains on opposite sides of the road being staggered. In case of roads with minimal
longitudinal fall it is often better to install subgrade drains longitudinally at the edge of
the road pavement.
9. Drainage and Channel Construction. The most basic way to drain off rain
and stormwater is via open channels. A more developed but also more expensive
solution is a separate sewer system. Separately collected stormwater has high potential
for increasing agricultural production in rural areas. In addition a more integrated
approach to water management in urban areas can be achieved by replenishing
freshwater resources after a natural pre-treatment of the collected stormwater (e.g. free-
surface constructed wetlands) and a recharge of surface or groundwater bodies (see
also stormwater management). In both cases the receiving water bodies may be
sea, lake, river or groundwater (also see surface disposal of liquids, surface
groundwater recharge, subsurface groundwater recharge).
11. Preparation of materials. Cement, Water, Sand, Gravel or crushed stone and
more materials should be prepared ahead of time to avoid problems.
Debris is removed and in most instances, Wolf Paving recycles the old asphalt
and concrete in our asphalt plants, turning deteriorating waste into strong, usable new
asphalt.
In fact, Wolf Paving typically recycles nearly 100% of the materials removed from
a job site, making the choice to use Wolf Paving both green and environmentally
friendly.
11. Grading and Sloping. With a clean slate, technology helps Wolf Paving
asphalt professionals prepare the surface for appropriate water drainage.
Using laser guided transits and automatic motor graders, the Wolf Paving team
grades the surface to be paved to ensure that water will run-off appropriately.
Proper water drainage is vital to your asphalt, because water is a major cause of
damage, including potholes, cracks and heaving.
12. Prepare the Sub Base. You’d never guess that the most important part of your
new asphalt surface is actually the sub base.
During the installation, base thickness, base stability and compaction are
important steps. If the sub base is not appropriately compacted, the asphalt surface on
top will not provide years of durability.
13. Proof Roll, Undercutting and Sub Base Repair. Once the sub base is
fully graded and compacted, Wolf Paving completes an extra step, called a proof roll, to
ensure the underlying surface is strong and ready to support new asphalt.
A Wolf Paving proof roll involves driving a quad-axle dump truck, loaded with
72,000 pounds, row by row over the entire surface.
If the gravel flexes more than an inch under the weight of the truck, it means that
the base is not properly supported.
14. Binder and Surface Course. Once the sub base is laid and any soft areas
are identified and repaired, it is time to add the binder.
The binder layer is large aggregate mixed with oil, making it very strong and
durable.
The binder layer can be thought of as the strength of any new asphalt surface.
15. Install New Asphalt Surface. Once the supportive structures of a new asphalt
surface are installed, the top layer of fresh asphalt is added to provide a clean, smooth
ride.
16. Butt Joints and Transitions. It is very rare to install an asphalt surface that
does not connect to existing driveways, roadways or parking lots. As such, asphalt-
paving contractors must find a way to smooth the transition from old surface to new.
Butt joints are areas were old asphalt or concrete meets new asphalt pavement.
These transitional areas require special attention to ensure that the grading and
water run-off is appropriate.
Butt joints are important to ensure drivers and pedestrians don’t notice a
difference in the surfaces.
17. Final Roll. Once the asphalt and butt joints have been laid, the entire surface is
smoothed and compacted.
Using a roller truck, the new asphalt pavement surface is compacted and
smoothed.
This process step ensures that no small bumps of aggregate or stone are left
poking through the smooth new surface.
Your asphalt paving contractor should follow these installation steps to make sure your
new asphalt surface will provide years of durability and functionally for your home,
business, city or town.
18. Construction of lane stripes and reflectors . Road surface marking is any
kind of device or material that is used on a road surface in order to convey official
information; they are commonly placed with road marking machines (or road marking
equipment, pavement marking equipment). They can also be applied in other facilities
used by vehicles to mark parking spaces or designate areas for other uses.
Road surface markings are used on paved roadways to provide guidance and
information to drivers and pedestrians. Uniformity of the markings is an important factor
in minimizing confusion and uncertainty about their meaning, and efforts exist to
standardize such markings across borders.
19. Road Signs. Traffic signs or road signs are signs erected at the side of or
above roads to give instructions or provide information to road users. The earliest signs
were simple wooden or stone milestones.
20. Guard Railings. Guard rail, guardrails—or railings around properties and more
generally outside of North America in some uses overlaps the industrial term "guide
rail". They are a boundary feature and may be a means to prevent or deter access to
dangerous or off-limits areas while allowing light and visibility in a greater way than
a fence. Common shapes are flat, rounded edge, and tubular in horizontal railings,
whereas tetraform spear-headed or ball-finialled are most common in vertical railings
around homes. Park and garden railings commonly in metalworking feature swirls,
leaves, plate metal areas and/or motifs particularly on and beside gates.
3. Location Study for Bridge Construction. While having a location study and
fixing the location of the bridge, it is very essential to consider the need and the location
of cross drainage works if any. The cross-drainage work is said to have 15 to 20 % of
the overall project cost if it must be implemented. Hence before choosing the alignment
for bridge construction, it is necessary to determine all the possible CD works and its
effect.
o Hydrological data
7. The Foundations. They serve as a basis for the future structure and should not
be underestimated. The foundations have the function of distributing various loads of
the bridge (mass, weight, overload, forces …) in an efficient manner and that according
to the nature of the ground hosting the structure. Indeed, the characteristics of the
environment will guide the technical decisions and the process to be put in place.
Deep foundations: This type of foundation is more suitable when the bridge
begins to gain height. In this case it happens regularly that the soil reveals a layer more
resistant in depth. During the construction, three situations are found giving rise to three
types of foundation:
o The so-called “good” soil, when it is possible to lay the foundations directly
on a stable ground, is called flat foundation.
o The so-called “bad then good” soil requires to lay four piles in the unstable
ground until they reach the consistent ground.
o The soil is “unstable”, when the ground does not offer good soil, there is
no choice but to install many piles that will give good resistance even in case of
significant compression.
When there is no resistance at depth it is still necessary to find a solution to exert
effective support on the surface using so-called “floating” piles.
10. Pouring the Slab. The beams are equipped on factory with connectors that
allow the steel structure to be bonded to the concrete slab of the latter. Thus, once the
beams installed on their final supports, we put lost formwork on them and a
reinforcement before pouring a layer of concrete of a thickness of about 25cm which will
be the slab of the structure.
11. Finishes. To finalize the work, after several months, even years of construction,
the final step is to lay asphalt on the road. Asphalt is a very specialized type of bitumen
whose intrinsic characteristics allow it to withstand deck expansions. Thus, even with
some deformations of steel, the bitumen will not crack and remains of quality to
accommodate the road traffic.
12. Testing of Bridges. Since bridge construction is an expensive project, it is
essential that all necessary tests may be conducted prior to the actual construction.
These tests and investigations can reveal the bridge behavior under different dynamic
loads. Computer aided design and testing are powerful tools that must be used to assist
in the bridge design. Bridge design has benefited considerably due to the growth of
computer programs. Such computer programs reveal immense information concerning
the effect of different forces being applied on a bridge. Wind tunnels are being used
extensively for the analysis of aircraft designs. Now these techniques are also being
applied for bridge design examination. A wind tunnel is basically a space that is
enclosed. Air at a fast speed is moved through the bridge model. Likely design and
structural defects can be discovered by photography and study of the air movement
pattern over the model.
Design Speed
Design speed, according to AASHTO, is the speed that is selected to determine the
conceptual design of the roadway that will have a major influence on traffic operations.
AASHTO states that the design speed should be set as maximum as possible so that
drivers are satisfied with the level of services of the road throughout its life span. Low
volume traffic ranging from 0 to 50 vehicles per day with design speed for flat terrain is
45 km/hour, rolling terrain with 30 km/hour, and mountainous terrain is 30 km/hour. It
can be concluded that the design speed of vehicles is influenced by the average daily
traffic and types of terrain.
Alignment
When a design engineer designs a road system, he/she should not design the roadway
with a sudden change from flat to sharp curve. This not only causes discomfort for
drivers, but also will invite accidents. This is where road alignment comes into use.
Alignment of a road is composed of horizontal and vertical alignment.
The intersection of a road must be provided with certain degree of curve which is
determined by its radius, so that when a vehicle is moving towards the corner of a road,
the driver of the vehicle will not feel any sudden changes while driving and will have a
comfortable driving experience. This curve is known as horizontal alignment and
usually provided on a horizontal profile of a road, which is simply known as the plan
view.
Vertical alignment is a curve provided by the designers during the design phase on the
vertical profile of a roadway. These curves consist of crest vertical curve and sag
vertical curve. The main objective of vertical alignment is to give a gradual change of a
road slope when a vehicle is moving uphill or downhill.
Grades
AASHTO has set maximum grades based on the types of roads and design speeds. For
low-volume local rural roads, grades may be 2% steeper. Roads with design speed of
70 miles per hour have maximum grades of about 5 % and a 30 miles per hour design
speed; AASHTO has set the maximum grades range from 7 to 12 %.
Width of Roadway
The design speed of vehicles will influence the width of the road and when the design
speed increases, the width of roadway also increases proportionally.
Sight Distance
The ability of a driver to see the road ahead is called sight distance. It is the most
important to the safety and smoothness of traffic operations of a road. The road design
engineer who is in charge of the design process must provide sufficient sight distance of
a certain length. Sufficient sight distance is crucial in road design so that drivers can
control their speed while driving and to avoid striking unexpected vehicles coming from
the opposite direction of travel. Roadways with two lanes must have sufficient sight
distance to enable drivers to overtake another vehicle safely without striking any vehicle
traveling in the opposite direction.
Superelevation
When a vehicle is navigating from a normal straight road to a curve, the elevation of the
left edge of the road will gradually get higher than the right edge of the road or vice
versa depending on the topography of the road. This is also known as superelevation or
road cambering, and its main purpose is to counter balance the centrifugal force of the
vehicle navigating on road corners.
Flexible Pavements:
Flexible pavement can be defined as the one consisting of a mixture of asphaltic or
bituminous material and aggregates placed on a bed of compacted granular material of
appropriate quality in layers over the subgrade. Water bound macadam roads and
stabilized soil roads with or without asphaltic toppings are examples of flexible
pavements.
The design of flexible pavement is based on the principle that for a load of any
magnitude, the intensity of a load diminishes as the load is transmitted downwards from
the surface by virtue of spreading over an increasingly larger area, by carrying it deep
enough into the ground through successive layers of granular material.
Types of Flexible Pavements
The following types of construction have been used in flexible pavement:
Conventional layered flexible pavement,
The major flexible pavement failures are fatigue cracking, rutting, and thermal cracking.
The fatigue cracking of flexible pavement is due to horizontal tensile strain at the bottom
of the asphaltic concrete. The failure criterion relates allowable number of load
repetitions to tensile strain and this relation can be determined in the laboratory fatigue
test on asphaltic concrete specimens. Rutting occurs only on flexible pavements as
indicated by permanent deformation or rut depth along wheel load path. Two design
methods have been used to control rutting: one to limit the vertical compressive strain
on the top of subgrade and other to limit rutting to a tolerable amount (12 mm normally).
Thermal cracking includes both low-temperature cracking and thermal fatigue cracking.
Road Cracks
Road distresses disturb and adversely affect the traffic flow and traffic safety leading to
poor performance of the road. They also cause an increase in fuel costs, result in time
delay and prove troublesome for every road user. Identification of the road cracks at an
early stage is essential as preventive road maintenance and effective remedial
measures can be applied before the problem becomes too severe and the pavement
fails. Pavement maintenance thus leads to enormous economic benefits in preventing
the pavement from failing. Also, the distresses whether of a smaller or larger scale are a
nuisance to the road users and may prove hazardous if neglected for a long period as
their condition worsens with time. Proper, timely and selective road maintenance thus
becomes an important principle which lengthens the life of the pavement and also
reduces the cost of maintenance.
Cracks formed in the direction of the traffic flow are termed as longitudinal cracks and
those that are formed perpendicular to the traffic flow are called transverse cracks.
(1st photo: Longitudinal Crack. 2nd photo: Transverse crack)
4. Corrugation and Shoving:
5. Depression:
6. Potholes:
7. Raveling:
9. Water Bleeding:
10. Stripping:
ROAD EQUIPMENT:
Earth-Moving Equipment
1. Bull Dozers is the most versatile earthmoving tool
as it accomplishes various tasks like pushing, towing,
ripping etc. Basically dozer blades consist of a
moldboard, cutting edges, end bits and blade arms
connecting the blade to the tractor. Blades vary in size
and type Straight blade, Angle blade, and Special
purpose blade are the main types. Dozers are also
equipped with rippers at the rear of the tractor.