Assignment
1. On 1st May 20x1, Roger took a loan of Php 1,000,000 from a bank at the annual interest rate of 5%. The
purpose of this loan was to finance a construction of a production hall. The construction started on June 1
20x1. Roger temporarily invested Php 800,000 borrowed money during the months of June and July 20x1 at
the rate of 2% p.a.
2. During 20x2, Roger Co. constructed a new manufacturing facility at a cost of Php 12,000,000. The
weighted average accumulated expenditures for 20x2 were calculated to be Php 5,400,000. The company
had the following debt outstanding at December 31, 2002:
b. 12 percent, 20-year bonds issued at par on April 30, 20x1, Php 8,400,000
3. Roger had the following loans in place at the beginning and end of 20x1:
a. The bank loan at 6% p.a. was taken in July 20x1 to finance the construction of a new
production hall (construction began on 1 March 20x1)
b. The bank loan at 8% p.a. and debenture stock were taken for no specific purpose and KLM
used them to finance general spending and the construction of a new machinery.
c. Roger used Php 60,000 for the construction of the machinery on 1 February 20x1 and
Php 25,000 on 1 September 20x1.
4. On January 1, 2023, the Roger Co. began construction of a building to be used as its office headquarters.
The building was completed on June 30, 2024. Expenditures on the project, mainly payments to
subcontractors, were as follows:
January 3, 2023 600,000
March 31, 2023 300,000
September 30, 2023 600,000
Accumulated expenditures at December 31, 2023 (before interest capitalization) 1,500,000
January 31, 2024 600,000
April 30, 2024 300,000
On January 2, 2023, the company obtained Php 500,000 loan with an 8% interest rate for the building
construction. The loan was outstanding during the entire construction period. The company’s other interest-
bearing debt included two long-term notes of Php 2,000,000 and Php 4,000,000 with interest rates of 6%
and 12%, respectively. Both notes were outstanding during the entire construction period.