Professional Documents
Culture Documents
Batu Hijau Paper PDF
Batu Hijau Paper PDF
ABSTRACT
Indonesia is prone to high seismicity because of its geological location. The remote island of
Sumbawa, east of Bali and part of the vast archipelago of Indonesia, has one of the largest open
cut gold mines in the world. The open cut gold mine is up to 930 m in depth and over 2
kilometers in diameter. In full production, up to 600,000 MT of rock is excavated each day with
an estimated 3.0 million tones to be mined over the lifespan of this project.
The project involved planning, design and construction of various structures like concentrator to
source the valuable ore from the excavated material, a conveyor belts to assist in the movement of
materials and a waste rock tailing dam. Mechanically stabilized Earth structures with gabion
fascia were used successfully in the project for constructing structures up to 25m high, taking into
consideration design factors like high seismic forces and local factors like difficult site access and
shortage of skilled labor.
Keywords : Open cast mine, Mechanically Stabilized Earth, geogrid
1.0 INTRODUCTION
Batu Hijau copper-gold mine is located on the remote island of Sumbawa in the south central
portion of the Indonesian archipelago in the province of West Nusa Tenggara, 1,530km (950
miles) east of Jakarta. Topography elevation of the mine is approximately 450m above sea level.
A direct translation from Indonesia “Batu Hijau” which means “green rock” describes the scenery
of the tropical climate island with terrain generally consists of very steep hill slope. In this paper,
Mechanically Stabilized Earth for mine related project in a complex geographical condition is
described in terms of constructability and effectiveness.
1
2.0 PROJECT PURPOSE
The Batu Hijau Project involves the development of 200 million tonnes per annum copper/gold
mine in the coastal mountains of south west Sumbawa. The project will mine ore from a large
open pit centered on the mountain of Batu Hijau. Ore from the mine will be transported to the
132,000 tonnes per day concentrator via a 5.5 km overland conveyor. The concentrate will be
transported about 18 km to storage and port facilities at Benette Bay. The Benette Bay facilities
are linked to the mine and township by a 25 km access road which traverses steep mountainous
terrain. The mine waste dumps, which ultimately will contain about 3.5 billion tonnes of soil and
rock, are to be constructed in three valleys close to the mine. The waste dump management
facilities include a number of dams, water diversions and acid water treatment facilities.
Among the Mechanically Stabilized Earth Structures proposed for this project were:
• A 20m high wall and 80m long near vertical wall to support flotation cells as part of the
concentrator plant. The concentrator is built on a series of cut and fill platform on the side
of a hill.
• A 25m high vertical retaining wall was required at the primary crusher, located at the
mine end of an overland conveyor. The wall was used for construction access for the
crusher and to support the truck loads at the top.
2
• An 800m long and 20m high retaining wall was built along the alignment of the overland
conveyor between the mine and the concentrator. This wall was constructed by
mechanical filling gabion facing units and was completed in around 3 months.
3
5.0 COMPONENTS OF MECHANICALLY STABILIZED EARTH WITH GABION
FASCIA
5.1 Gabion Fascia
The main component consist of PVC coated heavily galvanized steel wire mesh box-shaped
basket with a section of the grid-type mesh extending into the soil to act as soil reinforcement into
the backfill soil. The wire mesh is mechanically pre-fabricated to become a uniform
hexagonal woven mesh wherein the joints are twisted at each pair of wires through three
half-turns (commonly known as double twist), to prevent unraveling. The basket is filled
on site with clean-hard stones. The units are supplied in standard lengths and heights that require
site erection. The units are supplied in collapsed form, folded and bundled. The bundles are
compressed and strapped together at the factory for easy shipping and handling. Each bundle is
labeled with a tag reporting the size of the units contained.
Figure 3, Cross Section of Steel Mesh Reinforcement with Gabion Fascia Unit
4
• The versatility of gabions, which allows the formation of a structure with vertical,
battered or stepped front face as required and minimization of environmental impact.
• Structural safety in case of fire near the front face
• Permeability of the front face, guaranteeing drainage of the backfill material
• The woven steel mesh is not subjected to any adverse effects of creep
• The steel wire mesh are nor subjected to long term creep and PVC coating provides
comprehensive protection against all forms of corrosion (with an expected life expectancy
of 120 years).
• The pullout resistance of the mesh panels is developed from both frictional stress transfer
and bearing of the wires against surrounding soil.
• Connection between the fascia and the reinforcement is not required because both are part
of the same piece of mesh.
• Wires used in the fabrication of the units are heavily galvanized in accordance to BS 443
which gives additional durability.
5
the material permits the passage of water and relieving the hydrostatic pressure behind the gabion
fascia.
Below are the cross section and picture of the wall after construction. To date, the completed
Mechanically Stabilized Earth Wall with Gabion Fascia is performing satisfactorily. (see figure 2,
3, 4 & 5)
6
Figure 6, Typical Cross Section of Main Wall
7
6.0 DESIGN CONCEPT
MacStar computer program was used for stability analysis the Mechanically Stabilized Earth
Structure. The Macstar program, version 2000, has been developed to check the stability of
reinforced soils in structures which provides the slope stability using reinforcing units that are
able to absorb the tensile stress. Furthermore this program allows the user to conduct the stability
checks using the Limit Equilibrium Method even considering unreinforced slopes. The following
soil parameters were used to check the stability of the structure using Macstar 2000:
8
t = c + ( s – u ) . tan ( f’ )
where:
t = maximum tangential stress
FOS > 1.2
c = cohesion
s = total normal pressure
u = interstitial pressure
f’ = friction angle
Sliding Analysis
The safety coefficient against sliding (Fss) is given by the following equation:
Fss = Fstab/Fhtot
Where Fhtot = (Sa + Fhun) = total horizontal force
Fstab = total stabilizing force acting at the base of the wall
Sa = maximum active thrust acting on the wall
Fhun = horizontal un-stabilizing force acting on the wall (due to seismic option or hydraulic
forces)
Overturning Analysis
The safety coefficient against overturning (Fov) is given by the following formula:
Fov = (Mstab – Mu)/(Ma + Mov)
Where:
Mstab = stabilizing moment due to the force acting on the wall
9
Mu = overturning moment due to the interstitial forces acting at the base of the wall
Ma = overturning moment due to the maximum active thrust acting on the wall
Mov = overturning moment due to the un-stabilizing horizontal forces acting on the wall (due
to seismic actions or hydraulic force)
10
potential sliding originates from the toe of the reinforcing structure and passing through the
reinforcement and terminates uphill. The internal stability analysis is computed as follows:
Ts = σv Ka * ΔH
11
FOS > 1.3
12
7.3 Foundation
Foundation was excavated down to level of the medium strong rock. The foundation was proof-
rolled prior to placement of fascia units and fill material.
13
7.5 Filling and Compaction
Backfilling is carried out immediately
after the laying the reinforcement mesh.
The fill material is specified to be granular
and non expansive. The fill is compacted
to 95% of the maximum dry density at of
every 300mm lift in the direction of
parallel to the face of the wall.
8.0 CONCLUSION
The construction of 25m high Mechanically Stabilized Earth Wall using gabion fascia with steel
mesh reinforcement were successfully constructed in 1997 despite the various main constrain
factor i.e. high seismic area, difficult access and hilly terrain. Not only it is proven to be the most
cost effective system, structurally is stable. The Mechanically Stabilized Earth Wall with Gabion
Fascia has been used to cater the mining process for the past 10 years and there have not been any
structural defects to the mechanically
stabilized wall recorded so far. Within 10
working years the wall should have
reached a stable state. The project shows
that a simple construction method with
simple technology can and be used to
construct a very high vertical structure and
yield a safe and stable structure.
14
REFERENCES
BS 8006:1995 Code of Practice for Strengthened/Reinforced Soils and Other Fills, British
Standards Institution.
FIGURES
15