Professional Documents
Culture Documents
Nasa Evm Reference Card Aug 2018
Nasa Evm Reference Card Aug 2018
EVM system compliance and use is required on all acquisitions for development designated as major in accordance with PERFORMANCE MANAGEMENT REFERENCE CARD
OMB Circular A-11 and the Capital Programming Guide. At NASA, EVM is required for development or production Revised August 2018
contracts and subcontracts (including those for flight and ground systems, institutional requirements (facility, information
technology, investment, etc.) valued at or greater than $20 million. EVM is required on NASA spaceflight projects with life ETC
cycle cost of $250 million or greater. SMD Mission Risk Class-D space flight projects and contracts with a LCC of up to EAC
$150M (not including launch costs) have an approved deviation from the EVM requirements of NFS 1834.201. Class-D
missions with a LCC of up to $150M (not including launch costs) should use the processes per the SMD Class-D Total Allocated Budget (TAB)
Tailoring/Streamlining Policy. EVM reporting begins no later than 60 days post Key Decision Point-C (KDP-C). The Management Reserve (MR)
primary consideration for EVM applicability is the nature of the work, associated risks, and the value of the effort. EVM is BAC
not recommended on Firm Fixed Price contracts or contracts that are exclusively LOE. Refer to the NASA Earned Value PMB
Management website at https://evm.nasa.gov/.
EVM required on NASA spaceflight projects with a life cycle cost of $250 million or greater. EVM reporting begins no
Schedule Slip
Schedule Variance
later than 60 days post KDP-C. Projects with EVM requirements will use the NASA EVM capability. Cost Variance
Project
$ “Actuals”
ACWPCum
Development/P EIA-748 NASA EVMS Cost “Plan”
roduction EVMS Solicitation & Report BCWSCum
Contract (Total Standard Contract IPMR DRD
“Earned”
Estimated (PCD 15- Clause DRD WBS (Non- Supplier Flow
BCWPCum
Value) 05) (PCD15-05) (PIC 15-06) DRD EVM) Down (EVM)