Today

November 21 December 11 January 1 January 21 February 11


Start Piping and wiring at Building B Cab… C… C… Loop Checking E… Ope… Finish
November 6, 2019 November 6, 2019 - December 28, 2019 Janu… Ja… Ja… February 5, 20… Fe… Febr… February 21, 2020

Ordering and Installation of Transformer Testin… T…


November 27, 2019 - February 5, 2020 Februa… Fe…
Ordering and Installation of Genset and ATS
November 27, 2019 - February 5, 2020
Installation of devices and Lighting Fixtures (Building B) Cable Termination
December 2, 2019 - January 11, 2020 January 20, 2020 - February 8, 2020
Installation of Pull Box and Panels (Building B)
December 16, 2019 - January 25, 2020