Professional Documents
Culture Documents
Approval Sheet
Name Title Date Signature
Revision Status
Owner
Rev Issue Date By Chk App Issue Purpose
Signature
A 04-Apr-2018 AB AB AS Issued for Review
B 06-Apr-2018 ADK RN DS Re-Issued for Review
0 09-Apr-2018 ADK RN DS Issued for Approval
1 10-Apr-2018 ADK RN DS Issued for Construction
2 17-Apr-2018 ADK RN DS Re-Issued for Construction
PT. PHE ONWJ Pipe Cutting Procedure for Dead Man Pile using Broco
SPA-R-PRC-0251~2 Page 2 of 12
Paper Copies are Uncontrolled
PT. PHE ONWJ Pipe Cutting Procedure for Dead Man Pile using Broco
SPA-R-PRC-0251~2 Page 3 of 12
Paper Copies are Uncontrolled
PT. PHE ONWJ Pipe Cutting Procedure for Dead Man Pile using Broco
Table of Contents
Review & Endorsement Records...................................................................................................... 2
Revision Log Register ...................................................................................................................... 3
Table of Contents ............................................................................................................................. 4
Table of Figures ................................................................................................................................ 4
1. Introduction ............................................................................................................................... 5
1.1 General ............................................................................................................................. 5
1.2 Objective ........................................................................................................................... 5
1.3 Definition and Abbreviations ............................................................................................. 5
1.4 References ....................................................................................................................... 6
2. GENERAL INFORMATION ...................................................................................................... 6
2.1 Project Title ....................................................................................................................... 6
2.2 Communication ................................................................................................................. 6
3. Roles and Responsibilities ........................................................................................................ 6
3.1 Offshore Construction Manager ....................................................................................... 6
3.2 Field Engineer................................................................................................................... 6
3.3 Lifting Supervisor .............................................................................................................. 6
3.4 Crane Operator ................................................................................................................. 6
3.5 Signalman ......................................................................................................................... 7
3.6 Rigger ............................................................................................................................... 7
3.7 HSSE Coordinator ............................................................................................................ 7
3.8 Surveyor ........................................................................................................................... 7
3.9 Diving Supervisor.............................................................................................................. 7
4. Tools and Equipment ................................................................................................................ 8
5. Man Power ................................................................................................................................ 8
6. Methodology ........................................................................................................................... 10
6.1 Preparation Work of Surface .......................................................................................... 10
6.2 Preparation Work of Underwater at DMP Location ........................................................ 11
6.3 Underwater Operation .................................................................................................... 11
6.4 Final Operation ............................................................................................................... 12
7. Attachments ............................................................................................................................ 12
Attachment A – Anchor Pattern AWB EP-300 ........................................................................ 12
Attachment B – L2RA ............................................................................................................. 12
Attachment C – Specification of Broco Underwater ............................................................... 12
Table of Figures
Figure 1-1 SPA Platform Location .................................................................................................... 5
SPA-R-PRC-0251~2 Page 4 of 12
Paper Copies are Uncontrolled
PT. PHE ONWJ Pipe Cutting Procedure for Dead Man Pile using Broco
1. Introduction
1.1 General
SP New Field Development Project is a gas development strategically aimed at delivering gas to
support PHE ONWJ Gas Sales and Purchase Agreement to Customer.
The SPA Platform is located at approximately 11.3 KM southwest of existing B2C Platform, 12.0
KM southwest of NGLB Platform, 7.5 KM north of KCOM Platform and 5.5 KM southeast of
existing BZZB Platform. The Normally Unmanned Installation (NUI) concept is utilized for platform
development.
The figure below shows the location of SPA Platform (Latitude: 05o 57’ 06.761” S and Longitude:
107o 39’ 06.344” E):
The new SPA Platform will only produce gas and water with initial gas production of 30 MMSCFD.
The gas and liquid production is directly sent to B2C Platform via 12” subsea pipeline.
1.2 Objective
The purpose of this document is to provide the detail method and sequence for underwater
cutting of dead man pile tubular which protrude from sea bed using broco system.
2
1.3 Definition and Abbreviations
COMPANY PT. Pertamina Hulu Energi – Offshore North West Java (PHE ONWJ)
CONTRACTOR PT. Meindo Elang Indah (MEI)
CAR Company Authorized Person
TRA Task Risk Assessment
AHT Anchor Handling Tug
AWB Accommodation Work Barge
ROV Remotely Operated Vehicle
EP Eka Pasifik
L2RA Level 2 Risk Assessment
HSSE Health, Security, Safety and Environment
SPA-R-PRC-0251~2 Page 5 of 12
Paper Copies are Uncontrolled
PT. PHE ONWJ Pipe Cutting Procedure for Dead Man Pile using Broco
1.4 References
Company Document
PHEONWJ-R-SPE-0001 Specification for General Offshore Construction
PHEONWJ-T-PRC-0006 Vessel Approach Procedure
PHEONWJ-Z-SPE-0101 Specification for Vessel Anchoring
Project Document
SPA-R-PRC-0202 Anchor Handling Procedure
SPA-Q-PLA-0010 Emergency Response Plan at Offshore
SPA-R-PRC-0006 Offshore Lifting and Rigging Operation Procedure for EP
300
SPA-Q-PRC-0001 Control of Work Procedure
2. GENERAL INFORMATION
2.1 Project Title
The project title is “SP New Field Development Project”.
2.2 Communication
This document is presented in English Language. Any dispute or inconsistence, shall refer to
CONTRACT STC-1017 General terms & Conditions.
SPA-R-PRC-0251~2 Page 6 of 12
Paper Copies are Uncontrolled
PT. PHE ONWJ Pipe Cutting Procedure for Dead Man Pile using Broco
3.5 Signalman
Signalman is the leader who will give instructions during lifting operation. Signalman also
responsible for:
- Reviewing and understanding the lifting plan & L2RA which will be used for lifting reference.
- Discussing the lifting plan and L2RA at site before lifting execution with all lifting team
involved.
- Ensure that both the signalman and crane operator are familiar with the method of signaling
to be used.
- Reviewing and understanding the complicated and complex lifting operation to be performed.
- Use hand signals in accordance with the recommendations of British Standards BS7121.
- Use radio handy talkie for communication with specified channel.
3.6 Rigger
The rigger is responsible for:
- Riggers are appointed where it is necessary to ensure that loads are correctly attached to the
lifting equipment.
- Perform daily check and inspect the rigging gears to be used.
- Be aware of the wind speed and direction.
- Check that the lifting equipment being used is in good condition, certified for use correctly
color code, and of sufficient capacity to carry out the lift.
- Ensure taglines are always attached to loads that are likely to swing.
- Be aware of any obstructions within the crane radius and working area.
- Check around the load is clear and no personnel are below line of fire.
3.8 Surveyor
Surveyor is to assist Tug Master and Barge Master to positioning of vessel (barge) to determined
location as per project requirements.
SPA-R-PRC-0251~2 Page 7 of 12
Paper Copies are Uncontrolled
PT. PHE ONWJ Pipe Cutting Procedure for Dead Man Pile using Broco
5. Man Power
Number
No Title of
Personnel
1 Offshore Construction Manager 1
2 Field Engineer 2
3 Surveyor 4
4 HSSE 2
5 Crane Operator 2
6 Rigger 4
7 Diver 6
8 Technician 2
SPA-R-PRC-0251~2 Page 8 of 12
Paper Copies are Uncontrolled
PT. PHE ONWJ Pipe Cutting Procedure for Dead Man Pile using Broco
SPA-R-PRC-0251~2 Page 9 of 12
Paper Copies are Uncontrolled
PT. PHE ONWJ Pipe Cutting Procedure for Dead Man Pile using Broco
7. Methodology
As information the configuration of installed dead man pile is 12 m length with 10.5 meter
penetrate on under seabed. Meanwhile, the remaining 1.5 m is protrude from the seabed.
CONTRACTOR is proposing to cut off the DMP pile section as per figure at below using Broco
system.
2
SPA-R-PRC-0251~2 Page 10 of 12
Paper Copies are Uncontrolled
PT. PHE ONWJ Pipe Cutting Procedure for Dead Man Pile using Broco
- Diver is equipped with proper diving dress and life support equipment is good condition.
Rubber gloves must be worn.
- Appropriate eye protection is attached to the diver’s faceplate.
- Set the welding power source to 150 amps delivered to the torch and the oxygen regulator
delivery pressure to 90 psig over ambient pressure at depth.
- Make sure the supply valve, regulator, hose and torch are clean and free of any grease, oil
or particles. Purge the oxygen cylinder valve by opening it and then closing it. Attach the
oxygen regulator to the oxygen supply and purge the oxygen cylinder valve by opening and
closing it. Attach the oxygen supply hose to the regulator outlet. Make sure the supply
valve, regulator, hose and torch are clean and free of any grease, oil or particles. Purge the
regulator and hose with oxygen to clear any obstruction.
- Attach the torch to the oxygen supply hose.
- Set the regulator delivery pressure to 90 psig over the ambient bottom pressure or other
2
pressure which may be required due to depth or nature of operation. Regulator delivery
pressure must be increased with increased working depth.
- Purge the torch, check fittings, connections and the torch for leaks using soap.
- Attach the safety knife switch to the torch power lead. Attach the other ends of the torch
power lead to the torch cable. Attach a cable from the welding power source negative
terminal to the safety knife switch is positioned within reach of the tender. The safety knife
switch is activated only upon command from the diver.
- Wrap all cable to cable connections with rubber strips and electrical tape.
- Attach the ground cable to the welding power source positive terminal. Attach the other end
of the ground cable to the ground clamp.
- With the safety knife switch in the open position, start the welding power source and set
output for 150 amps maximum at the rod tip.
SPA-R-PRC-0251~2 Page 11 of 12
Paper Copies are Uncontrolled
PT. PHE ONWJ Pipe Cutting Procedure for Dead Man Pile using Broco
- Lift the rod from the work and release the oxygen lever to extinguish the cutting rod.
- After the tender has confirmed the current is off, loosen the collect nut ½ turn and remove
stub from the torch.
- Insert a new cutting rod and repeat the process until the cut is complete.
8. Attachments
Attachment A – Anchor Pattern AWB EP-300
Attachment B – L2RA
Attachment C – Specification of Broco Underwater
SPA-R-PRC-0251~2 Page 12 of 12
Paper Copies are Uncontrolled
PT. PHE ONWJ Pipe Cutting Procedure for Dead Man Pile
Using Broco
ATTACHMENT A
Anchor Pattern AWB EP-300
SPA-R-PRC-0251~2 ATT
Paper Copies are Uncontrolled
ANCHOR NO.P1
863.0 m Length
E = 359283.86
.9
N =9346916.56
103
MB P1A
.1
178
113.6
MB P1B
MB P1A
6
1. MB P1B ANCHOR NO.S1
17 950 m Length
0.6 E = 360514.33
12 4.3
100.0
N =9346278.21
10
.9
88 MB S1A
.8
70 52.6
100.0
MB S1B
ANCHOR NO.P3
1076 m Length
E = 358467.23 MB P3A
N =9346017.78 MIDLE BUOY LIST
NO TAG NO COORDINATES DISTANCE FROM ANCHOR
MB 2B
1 MB-P1A E. 359440.39m N. 9346594.49m 358.1 M
0
30
EP
2 MB-P1B E. 359562.57m N. 9346343.25m 637.5 M
MB S2A 3 MB-P3A E. 359134.92m N. 9345980.15m 669.3 M
MB P4B 4 MB-P4A E. 358840.92m N. 9345729.02m 327.2 M
5 MB-P4B E. 359160.80m N. 9345829.07m 662.4 M
ANCHOR NO.S2 6 MB-S3A E. 359999.35m N. 9345237.80m 353.9 M
1085 m Length 7 MB-S3B E. 359795.24m N. 9345565.49m 740.2 M
8 MB-S2A E. 360367.92m N. 9345868.89m 309.5 M
E = 360672.72
175.9
E = 358433.19
156
ATTACHMENT B
L2RA
SPA-R-PRC-0251~2 ATT
Paper Copies are Uncontrolled
PT. PHE ONWJ Pipe Cutting Procedure for Dead Man Pile
Using Broco
ATTACHMENT C
Specification of Broco Underwater
SPA-R-PRC-0251~2 ATT
Paper Copies are Uncontrolled
UNDERWATER CUTTING
& WELDING SOLUTIONS
Our experience runs deep
Broco® sets the world standard Ultimate
in underwater welding, Underwater
Ultrathermic cutting products, Cutting
and customer satisfaction.
1
Broco®
Underwater
Products
Broco Underwater welding electrodes set the standard for commercially available
mild and stainless steel wet welding electrodes, and more recently, nickel based
wet welding electrodes have been added to our line. SofTouch, EasyTouch,
Ni-Touch and specialty stainless electrodes assure engineers, diving companies
and clients that Broco offers the right electrodes for their job’s criteria.
Selected features of the BR-21 include an index notch on the head to help divers
find the hole which improves rod insertion even in a low-visibility environment.
The beveled seat keeps the electrode at the ideal angle and the groove eliminates
electrode wiggle. The over-sized head is easier to hold and the handle and head
are from hexagonal stock for sure gripping by a gloved hand. The BR-21 also
includes a resistance O-ring on the shoulder to ensure tension when the head is
tightened and increase head life.
4 5
Ni-Touch™ Electrodes
Broco’s Ni-Touch™ nickel wet welding electrode was developed to allow
underwater wet welding of higher carbon and high tensile steels which would
normally require the use of more expensive dry chamber welding. Ni-Touch
electrodes produce welds with less porosity, while allowing deeper welding in the
overhead position than similar electrodes. They are appropriate for all position
groove and fillet welds. Test results exceed the requirements of the American
Welding Society (AWS) Specification D3.6–99 for Class B underwater wet welds.
Yield strengths typically exceeding 70 ksi and tensile strengths exceeding 80 ksi
can be expected from the nickel weld metal in the as-welded condition. Ni-Touch
is presently qualified at a water depth of 33 feet.
With Ni-Touch™ the nickel electrode mitigates the effect of hydrogen. This results
in successful underwater wet welds involving a broad range of high carbon
equivalent steels, including HY-80 quenched, and tempered steel used in Naval
ships with carbon equivalents exceeding 0.50 percent. Ni-Touch meets the more
stringent requirements of the Navy’s Naval Ship Technical Manual NSTM 074.
SofTouch®
Broco’s proprietary flux enhancing formulation, BroCote™, makes this electrode
particularly impervious to water penetration and denigration and ensures
consistent certifiable underwater weld quality eliminating costly rework.
SofTouch electrodes are used for wet welding repairs in many applications where
steel must be joined underwater according to code specifications. SofTouch welds
consistently meet or exceed AWS D3.6-99 specifications for Class B welds in all
positions (flat, horizontal, vertical and overhead). SofTouch is designed to pass all
AWS test requirements, including radiograph, tensiles, bends and hardness.
Since 1989, SofTouch electrodes have been specified in the U.S. Navy’s Ships
Husbandry Manual Chapter 11, “Underwater Wet and Dry Chamber Welding.”
SofTouch electrodes are lot certified and available in various sizes and mild steel
and stainless alloys. Available diameters include 1/8 inch, 5/32 inch, and 3/16 inch.
Stainless electrodes are sold in 1/8 inch and 5/32 inch sizes.
Broco Underwater wet welding electrodes are sealed in a Mil-Spec foil pouch to
prevent contamination and then inserted in a rigid resealable plastic tube which
provides maximum protection. The color-coded end cap denotes mild or stainless
steel electrodes type. Operating guidelines are printed on the label.
EasyTouch®
For many repairs the resultant weld is allowed more leeway in terms of porosity,
inclusions, integrity and appearance. To fill the void between “to-code” work and
economy, Broco applied its experience and knowledge to the
design of a quality electrode specifically for the economy
market. The result is EasyTouch, a moderately priced
electrode yielding excellent results. It is easy
to start, easy to run (a controllable puddle More offshore cutting is
with rippled bead appearance) and
easy to clean. EasyTouch is a
done with Broco than all
high deposition all-position
electrode.
competitors combined.
6 7
Broco Underwater Products List Spare Parts – BR-22 PLUS
P R O D. N U M B E R DESCRIPTION
www.Broco-Rankin.com
CAUTION: This equipment is potentially dangerous to operate and must be used in strict accordance
with the instructions provided. Underwater cutting and welding should only be performed by
trained professional commercial divers and in accordance to industry accepted safe diving practices.
Copyright 2017