You are on page 1of 1

SUB-STRUCTUR

QUANTITY SHEET
Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity
(ft)
(ft) (ft)
1 Site clearence
1 45.00 30.00 1350.00 Cft
1350.00 cft
2 Site layout
1 45.00 30.00 1350.00 cft
1350.00 cft
3 Excavation in
**Foundation:
1. walls for L foundation
1 92.00 2.25 1.83 379.43 cft

2. walls for T foundation


1 185.69 3.75 1.83 1276.39 cft
1655.82 cft
4 PCC in foundation
1. walls for L foundation
1 92.00 2.25 0.33 68.31 cft

2. walls for T foundation


1 185.69 3.75 0.33 229.79 cft
298.10 cft
5 Brick work in foundation
1.first step .
1. walls for L foundation
1 92.00 1.83 0.75 126.27 cft

2. walls for T foundation


1 185.69 3.08 0.75 428.94 cft
2.second step .
1. walls for L foundation
1 92.00 1.83 0.75 126.27 cft
2. walls for T foundation
1 185.69 2.25 0.75 313.35 cft
3.third step .
1. walls for L foundation
1 92.00 1.16 2.25 240.12 cft
2. walls for T foundation
1 185.69 1.58 2.25 660.13 cft
1895.08 cft
6 D.P.C in foundation
1. walls for L foundation
1 92.00 1.16 0.25 26.68 cft

2. walls for T foundation


1 185.69 1.58 0.25 73.35 cft
100.03 cft
7 Earthfilling in Plinth:
Drawing Room 1 11.50 12.00 2.25 310.50 cft
Bed Room 1 11.50 11.75 2.25 304.03 cft
Kitchen 1 8.50 8.50 2.25 162.56 cft
Bed Room 1 13.50 10.00 2.25 303.75 cft
tv lounge 1 13.75 21.00 2.25 649.69 cft
store 1 11.50 7.33 2.25 189.66 cft
bath 1 7.58 4.50 2.25 76.75 cft
bath 1 7.00 4.92 2.25 77.49 cft
open 1 2.17 4.50 2.25 21.93 cft
2096.36 cft