You are on page 1of 94

CABLE-SUSPENDED PEDESTRIAN BRIDGE DESIGN

FOR RURAL CONSTRUCTION


by
AVERY LOUISE BANG
B.S. University of Iowa, 2007
B.A. University of Iowa, 2007

A project submitted to the


Faculty of the Graduate School of the
University of Colorado in partial fulfillment
of the requirement for the degree of
Master of Science
Department of Civil and Environmental Engineering
2009
Abstract

Lack of access to health care facilities, schools and markets is a great impediment.
For many communities in the developing world, alleviating rural isolation would help
break the cycle of poverty by providing access to educational opportunities, markets,
medical clinics and other basic services. The development of cable suspended
pedestrian bridges are one of the most economical and sustainable solutions to rural
isolation. This also presents a challenge for performing engineering analysis with
experimental material properties. A review of simple techniques for soil testing,
geotechnical models and designs for equivalent structures are reviewed. The affect of
soil parameters on anchor ultimate uplift capacity design are examined and
recommendations are presented for design and construction in the developing world.
A case-study in Ethiopia provides a baseline example as simplifying design
assumptions are justified, and design process outlined. Finally, lessons learned from
simplifying design for development purposes and general ethical considerations are
discussed.

2
This report entitled:

Pedestrian Bridge Design Best Practices for Rural Construction


written by Avery Louise Bang
has been approved by the Department of Civil and Environmental Engineering

____________________________________________________
Professor Bernard Amadei (committee chair)

____________________________________________________
Asst Professor John McCartney

____________________________________________________
David Jubenville, P.E., Instructor

Date

The final copy of this paper has been examined by the signatories, and we
find that both the content and the form meet the acceptable presentation standards
of scholarly work in the above mentioned discipline.

3
Table of Contents

Chapter 1: Introduction and Background .................................................................... 10

1.1 Cable-Suspended Pedestrian Bridges ............................................................... 10

1.1.1 Rural Transportation .................................................................................. 10

1.1.2 Pedestrian Bridges ..................................................................................... 10

1.1.3 Bridges to Prosperity.................................................................................. 13

1.1.4 Case Study: Sebara Dildi, Ethiopia............................................................ 15

1.2 Research Objectives .......................................................................................... 19

1.3 Expected Research Contributions ..................................................................... 20

1.4 Organization of Report ..................................................................................... 20

Chapter 2: Typical Bridge Design Scenario ............................................................... 22

2.1 Model of Typical Bridge ................................................................................... 22

2.2 Structural Failure Parameters ............................................................................ 24

2.3 Geotechnical Failure Parameters ...................................................................... 26

Chapter 3: Structural Considerations .......................................................................... 28

3.1 Structural Analysis ............................................................................................ 28

3.1.1 Horizontal Tension..................................................................................... 29

3.2 Pedestrian Bridge Loading................................................................................ 31

3.2.1 Liveloads .................................................................................................... 31

4
3.2.2 Dead Loads ................................................................................................ 33

3.2.3 Wind Loads (Overturning) ......................................................................... 33

3.2.4 Load Combinations .................................................................................... 34

3.3 Structural Design .............................................................................................. 34

3.3.1 Suspenders ................................................................................................. 34

3.3.2 Main Cables ............................................................................................... 35

3.3.3 Decking ...................................................................................................... 38

Chapter 4: Geotechnical Considerations ..................................................................... 42

4.1 Fine-Grained Soils: Clays and Silts .................................................................. 42

4.1.1 Geotechnical Analysis & Anchor Capacity ............................................... 42

4.1.2 Recommended Parameters ......................................................................... 49

4.2 Coarse-Grained Soils: Sands, Gravels and Non-Plastic Silts ........................... 49

4.2.1 Geotechnical Analysis & Anchor Capacity ............................................... 49

4.2.2 Recommended Parameters ......................................................................... 53

4.3 Geotechnical Design ......................................................................................... 53

4.3.1 Design Process ........................................................................................... 53

4.3.2 Soil Classification & Testing ..................................................................... 55

4.3.3 Design Example: Sebara Dildi Case-Study ............................................... 65

Chapter 5: Quality Control Considerations................................................................. 67


5
5.1 Material Specifications ..................................................................................... 67

5.1.1 Concrete Mixture ....................................................................................... 67

5.1.2 Steel Cable ................................................................................................. 69

5.1.3 Cable Clamps ............................................................................................. 71

5.2 Construction Quality Control............................................................................ 72

5.2.1 Cable Clamps ............................................................................................. 72

5.2.2 Backfill and Compaction ........................................................................... 74

Chapter 6: Conclusion and Discussion ....................................................................... 76

6.1 Summary ........................................................................................................... 76

6.2 Design for the Developing World ..................................................................... 77

6.2.1 Design Simplification ................................................................................ 77

6.2.2 Ethics of Accountability ............................................................................ 78

6.2.3 Transferring Best Practices to Developing Nations ................................... 80

6.3 Opportunities for Future Research .................................................................... 82

References ................................................................................................................... 84

Appendices .................................................................................................................. 88

Appendix 1: Soil Identification Table (Helvetas, 2001) ......................................... 88

Appendix 2: Computation of Simple Active & Passive Pressures ......................... 89

(DM-7 Section 7.2, Naval, 2009)............................................................................ 89


6
Appendix 3: Breaking Strength Properties of Cable............................................... 90

Appendix 4: Specific Weight of Wood Specimen (CSG) ...................................... 91

Appendix 5: Explanation of Logan’s Pull-out tests for Footings in Sands............. 92

Appendix 6: Abbreviated Unified Soil Classification System (Coduto, 2001) ...... 93

Appendix 7: Bjerrum Correction Factor for Vane Shear Test ................................ 94

7
Index of Figures

Figure 1 Suspension and Suspended Bridge Comparison .......................................... 12

Figure 2 Typical Suspended Footbridge, Las Vegas, Honduras ................................. 14

Figure 3 Map of Ethiopia & Sebara Dildi Bridge Site................................................ 16

Figure 4 Sebara Dildi Bridge Rope Crossing ............................................................. 17

Figure 5 Typical Bridge Profile .................................................................................. 22

Figure 6 Typical Abutment Profile for Cable-Suspended Footbridges ...................... 23

Figure 7 Free Body Diagram of Anchor and Tower ................................................... 23

Figure 8 Typical Decking Cross-Section .................................................................... 25

Figure 9 Schematic to Derive Moment at Mid-Span .................................................. 29

Figure 10Typical Decking Detail Plan View .............................................................. 38

Figure 11 Typical Decking Cross-Section with Dimensions ...................................... 40

Figure 12 Variation of Fc' with H'/h Ratio (Adapted from Das, 1990) ...................... 44

Figure 13 Variation of β with Embedment Ratio for ψ=0 .......................................... 45

Figure 14 Net Ultimate Holding Capacity with Variation in Cohesion using Das

(1990) .......................................................................................................................... 47

Figure 15 Net Ultimate Holding Capacity with Soil Unit Weights using Das (1990) 48

Figure 16 Minimum Embedment with Friction Angles using Meyerhof and Adam

(1968) .......................................................................................................................... 51

Figure 17 Variation of Minimum Embedment with Soil Unit Weight using Meyerhof

and Adam (1968) ........................................................................................................ 52

Figure 18 Free Body Diagram Anchor (Adapted from DM-7, 2009)......................... 54


8
Figure 19 Sieve Test (Adapted from Concrete, 2009) ................................................ 56

Figure 20 Typical Triaxial Testing Apparatus ............................................................ 58

Figure 21 Expected UU Triaxial Test Results for Cohesive Soil ............................... 59

Figure 22 Pocket Vane Shear Test .............................................................................. 62

Figure 23 Pocket Penetrometer ................................................................................... 62

Figure 24 Soil Classification and Testing Flow Chart ................................................ 64

Figure 25 Cable Uncoiling Procedure (Helvetas, 2001) ............................................. 70

Figure 26 Proper Cable Transport Technique ............................................................. 70

Figure 27 Failed Nepali bridge: Clamp Slippage ....................................................... 71

Figure 28 Proper Cable Clamp Installation ................................................................ 73

Figure 29 Reduction in Cable Cross-Section with Proper Torque ............................. 73

Figure 30 Proper Cable Clamp Installation and Torque Wrench ............................... 74

Figure 31 Hand Rammer ............................................................................................. 75

Index of Tables

Table 1 Liveload Schedule for 1.0-meter Deck Width ............................................... 32

Table 2 Assumed Dead Loading ................................................................................. 33

Table 3 LRFD Load Combination Alternatives.......................................................... 39

Table 4 Wood LRFD Resistance Factor Values ......................................................... 39

Table 5 Soil Property Assumptions Summary Table.................................................. 53

Table 6 Correlations for Coarse Grained Soils (Terzaghi, Peck & Mesri, 1996) ....... 63

Table 7 Concrete Ratios by Volume (Adapted Engineers, 2006) ............................... 69

9
Chapter 1: Introduction and Background

1.1 Cable-Suspended Pedestrian Bridges

1.1.1 Rural Transportation

It is estimated that about 900 million rural people in developing countries do not have

reliable year-round access to road networks, and 300 million are without motorized

access (Lebo, 2001). Aid dollars being invested into infrastructure improvements for

paved highways and major vehicular bridges are only serving those with a standard of

living appropriating vehicle use. The remaining 300 million rural citizens have

unreliable access to even the most basic services or opportunities.

Many governments lack the basic infrastructure capacity to link feeder roads and rural

footpaths, and the dilapidated state of the paved roads often is prioritized.

Investment in rural transportation improvements would help to reduce poverty

through improving access to markets, medical clinics and educational opportunities

not currently accessed. Accordingly, a country’s ability to maximize its economic

potential is closely linked to the efficiency of its transport system (Haynes, 2003).

1.1.2 Pedestrian Bridges

For nearly 50 percent of the world’s population living in rural isolation, the lack of

access reinforces the cycle of poverty (United Nations, 2005). Rural community

members spend a great deal of time and effort on transport activities to fulfill their

basic needs. Whether walking miles downriver to reach a river crossing en route to

10
school, or spending a full day to reach the weekend market, the worlds’ poorest

people are faced with the disadvantages of lack of direct access to the basic amenities

and adequate transport infrastructure necessary to reach them.

Rivers and streams isolate villagers of many communities, stranded from the feeder

roadways and pedestrian paths during annual floods. A development strategy that

gives priority to providing reliable, year-round access, to as much population as

possible has been proposed in several forms (Lebo, 2001: Blaikie, 1979). A main

proponent of these strategies is the need for pedestrian bridge crossings.

Affordability of an infrastructure project, pedestrian bridge or otherwise, is primarily

determined by a population's capacity to maintain its infrastructure over the long

term. In rural communities where motorized access is neither existent nor affordable,

improvements to the existing trail networks and the provision footbridges over river

crossing locations is one of the most cost-efficient investments to create the largest

impact. Many countries do not have a single pedestrian bridge in county and those

that do are most often over-sized, difficult to maintain and prohibitively expensive

structures. A simple footbridge design would provide a cost effective solution to be

built without foreign design assistance.

Pedestrian bridge technologies vary vastly in design, cost and function. Crossings

can be as simple as a fallen tree or as complex as a multi-million dollar work of art.

From a structural standpoint, pedestrian bridges have taken a number of forms, each

with the function of providing safe transport over an otherwise impassable crossing.

11
Arched bridges, simple beam bridges, truss bridges and cable-stayed bridges

constitute four main types of pedestrian bridges: a review of suspended cable-stayed

bridges follows. The difference between a cable-suspension bridge and a cable-

suspended bridge type is shown in Figure 1, where the blue cable indicates load-

bearing in both.

Figure 1 Suspension and Suspended Bridge Comparison

The development of cable-suspended pedestrian bridge construction has played an

interesting role in the history of human civilization (Gade, 1972). The first recorded

bridge with suspenders connecting handrail and walkway cables was built as early as

285 BC in the Province of Sichuan in China (Peters, 1987). Other known suspension

structures during a similar time period were documented in the Eastern Himalayas

and consisted of single woven cable, transversed by holding onto either two handrail

cables or in a movable basket. Perhaps in a parallel line of invention or speculatively

through early Chinese travelers, similar technical knowledge emerged in South

America (Peters, 1987). Ancient Incan civilization used rope bridges to span deep

gorges, connecting footpaths between villages. These bridges consisted of a pair of

12
stone anchors and massive woven grass cables and two additional woven cables for

guardrails. Consistent maintenance and annual replacement of the woven cables

made these bridges strong enough to carry the Spaniards while riding horses after

they arrived (Gade, 1972). Such primitive rope bridges led to the basic idea of

modern cable bridges.

The modern cable-suspended bridges constructed by Bridges to Prosperity do not

vary greatly from many of the historical bridges. The simple design, constructed

using manually-powered tools and only locally available materials are all the same

challenges faced by designers for rural developing world bridges today.

1.1.3 Bridges to Prosperity

Bridges to Prosperity (B2P) is a United States based non-profit organization that has

recognized the need for rural pedestrian bridges. Their work building and training a

specific cable suspended footbridge technology has connected rural communities with

access and opportunities in over a dozen countries around the world. The suspended

cable footbridge design used by B2P was first developed by the Swiss organization

Helvetas (2001). Helvetas took footbridge building practices from improvised

construction to a standardized bridge design manual while creating the world’s largest

trail bridge program in Nepal (Nepal, 2008). The suspended design relies on each

cable for load distribution and lacks the tall towers equated with suspension bridges.

An example of the Helvetas-type suspended bridge is shown in Figure 2.

13
Figure 2 Typical Suspended Footbridge, Las Vegas, Honduras

Helvetas successfully accomplished their goal of standardizing the design such that a

visual geotechnical evaluation and rudimentary topographic Abney level survey could

be used to produce entire construction drawings: only very basic geometry

calculations are required. Although the modulated design was appropriate for deep

gorge applications as found in Nepal, there is a desire to break-down the design

process to allow for easier design modifications more suitable for non-gorge

crossings. The author concluded that an example design process would allow a

designer to optimize the design to fit local capacity and material availability.
14
Many of the existing bridge design resources are specific to developed nations where

constructability and material availability may be considered a lower priority than cost

or time of construction (Bridges, 2009). Rural construction, particularly in the

developing world, creates a number of additional constraints and often present

challenges to engineers only experienced with developed-world design practices.

With the increase in humanitarian-aid engineering projects through organizations

such as Engineers Without Borders (EWB), there is an increased need for both final

modular designs as well as design process resources. B2P identified an

organizational goal to create a best-practices approach to rural footbridge design and

construction for general dissemination and internal reference (Bridges, 2009).

Bridges to Prosperity started in 2001 by using the Helvetas design manual as it was

the most comprehensive design reference available. Several design alterations and

modifications have taken B2P away from the original designs as many B2P crossings

have topographic situations not addressed in the Helvetas manual. All of these design

addendums and calculation assumptions have been posted on their internet site. This

document seeks to provide a more complete best-practice document to serve as a

resource for potential bridge-builders around the world through B2P’s online

database.

1.1.4 Case Study: Sebara Dildi, Ethiopia

On behalf of Bridges to Prosperity, the author will be constructing a 100 meter

suspended bridge in the Ethiopian state of Amhara in the summer of 2009. A site

15
visit and engineering survey were conducted in June of 2008. During the trip, the

need for a more complete design guide for soil testing and design was realized.

1.1.4.1 Background & Location

Approximately 40 kilometers from Lake Tana, a broken multi-arched bridge spans

the Blue Nile River gorge. The bridge links a major caravan route between two

trading regions: the Gonder region and the city of Debra Tabor to the north, and the

Gojjam region and the city of Debre Markos to the south. The bridge site is marked

in yellow in Figure 3 and the two aforementioned towns marked in red.

Figure 3 Map of Ethiopia & Sebara Dildi Bridge Site

"Sebara Dildi,” or broken bridge in the local Amharic dialect, was built in the mid-

1600’s of stone, sand, lime, and egg: an early version of an elastomeric adhesive

(Bridges, 2009). During World War II, the middle arch of the bridge was destroyed

by Ethiopian Patriots to impede Mussolini's Italian invasion force. During the effort

to cut away the arch, it collapsed and killed 40 men (Snailham, 1968) but succeeded

16
in slowing the Italian forces. After the Italian retreat, the bridge was never repaired.

The current method of crossing is both expensive and dangerous and requires one to

pay to be manually pulled across while holding to a knotted rope, as seen in Figure 4.

Figure 4 Sebara Dildi Bridge Rope Crossing

Approximately 450,000 people live directly on either side of the bridge and although

dangerous, traffic remains heavy at the crossing to avoid the additional 75 kilometer

trip required to use the next closest bridge (Bridges, 2009). Those who operate the

rope charge 3 Ethiopian Birr ($0.38) or approximately 20 percent of a person’s

average daily salary.

In 2002, Bridges to Prosperity attempted to fix the crossing by building a steel truss

bridge, set atop bridge remains. The bridge was swept away during the first rainy

17
season that followed, as water levels at the crossing point currently reach a higher

elevation than when the bridge was originally designed. This could be attributed to

high levels of deforestation in Ethiopia and in turn, higher levels of runoff (Nile,

2008). The failure of this bridge project led to the creation of the Bridges to

Prosperity organization, and although the first attempt to repair the bridge was

unsuccessful, Bridges to Prosperity plans to build a bridge with adequate freeboard

and clearance.

The crossing point is extremely remote. Flying from the capital city of Addis Ababa,

one must arrive by air in Bahir Dar: the closest city to the site. Approximately 3 hour

drive south is the township of Mota from which one must walk approximately 8 hours

through Ethiopian highlands into the Blue Nile Gorge at Sebara Dildi. The remote

nature of this site limits survey and testing equipment to what can be carried.

Construction materials will need to be brought in on mule thus designers must limit

the size and weight of any particular material or tool required for bridge construction.

1.1.4.2 Site Visit

The author visited the site in June 2008 with the intention to choose the best location

for a suspended bridge crossing. A site 200 meters downstream and up-trail from the

current crossing was selected based on a narrowing of the river and an avoidance of

several residuals landslides.

A rudimentary surveying approach using an Abney level and string was used to create

a topographic cross-section of the site. This process has been well documented:

18
reference the Helvetas Volume 1 Suspended Manual for further detail (Helvetas,

2001). The final span was found to be 100 meters, with a negligible height difference

between the abutments.

The suggested process for soil identification required only a visual identification by

which the surveyor classified the soil based on ability to ‘see’ more than fifty percent

of the grains (Appendix 1). Both abutments were excavated to one meter depth and a

soil sample was attained for visual classification. The soil visually classified as a

sand at both abutments. The author found it difficult to conclude on design

parameters from such a basic approach. A greater understanding of design

assumptions was required to conclude whether a more in-depth testing and

classification process was feasible or necessary.

1.2 Research Objectives

Extensive literature exists for equivalent structure behavior in the developed world,

but very limited documentation has been created that adequately addresses design for

development applications. Through a review of existing testing and modeling

approaches for comparable structures and parametric studies with pertinent

geotechnical models, a simplified design approach is desired. This includes

identifying viable geotechnical classification testing approaches, and offering

recommended soil parameter assumptions as needed. A design case-study, inclusive

of both structural and geotechnical design methods, will be included to improve

general understanding. The end result will allow future bridge designers to identify

19
the underlying assumptions in order to modify the design for sites where the Helvetas

standard does not apply.

1.3 Expected Research Contributions

Minimal research has been completed specifically on the geotechnical proprieties of

anchorages intended for rural pedestrian cable stay bridges. A review of cable

behavior and assumed failure mechanisms will be discussed. Structural design

process will be outlined, including a case-study example for a 100 meter span.

Furthermore, a literature review of models intended for similar structures commonly

used as foundation systems that require uplift or lateral resistance will be included.

By reviewing design and modeling of these well-understood structures, a design

approach for soil anchorages for small cable-stayed bridges will be proposed.

Furthermore, as testing equipment available in rural developing world applications

are often not available, conservative soil parameters will be proposed with respective

justification based on impact on geotechnical models. Existing documentation has a

greater emphasis on modulated design rather than design process. This document

will produce a design guide for soil classification and testing, structural and

geotechnical design and engineering quality control for pedestrian bridge design for

the developing world.

1.4 Organization of Report

The introduction chapter has given context for the cable-suspended bridge. The

following chapter will more precisely identify the technical challenge and parameters

20
through discussion of a typical cable-suspended bridge. Chapter 3 will detail the

structural design considerations including assumed cable behavior, cited codes and

standards, example loading calculations and a complete design process for the case-

study bridge. The main objective of the chapter is to demonstrate how to calculate

the anticipated loads being transferred from the structure into the anchorage system.

Chapter 4 discusses geotechnical design. Discussion into how to classify as soil as

either coarse or fine-grained followed by pertinent models for each. One specific

model is detailed for each soil type, from which assumptions are justified through

parametric studies. A simplified geotechnical model is proposed for design use for

cable-suspended bridges. Testing programs for both soil types are also discussed.

Chapter 5 introduces many of the quality control issues faced in footbridge

construction including both material property and construction quality assurance.

The final chapter concludes with a discussion of engineering design for the

developing world. Lessons learned from this report in design simplification are

presented and more general concepts on the topics of ethics of accountability are

discussed.

21
Chapter 2: Typical Bridge Design Scenario

2.1 Model of Typical Bridge

The primary objective of this report is to suggest an anchor design approach to resist

pull-out failure for footbridge deadman anchors, shown in Figure 5.

Figure 5 Typical Bridge Profile

Where:
L = span in meters
Lb = Backstay length
hsag = cable sag in meters
ho.b. = height overburden
Typical spans for consideration range from 40 to 120 meters, backstay lengths range

from 5 to 10 meters, cable sag range from 2 to 10 percent of the span and overburden

heights range from 1.5 to 3 meters. To limit the scope of this report, the

aforementioned characteristic dimensions will be considered the limits conditions for

each respective parameter.

The modulated Helvetas cable-suspended bridge design was developed with few

components and minimal connection points. The primary components of a cable-

22
suspended pedestrian bridge are: anchorage (1), ramped approaches (2), foundation

tiers and towers (3), handrail and walkway cables (4 & 5 respectively) and deck

walkway, as shown in Figure 6.

3 5

2
1

Figure 6 Typical Abutment Profile for Cable-Suspended Footbridges

A simplified free body diagram detailed in Figure 7 depicts the typical forces inflicted

upon the anchorage and tower. Chapter 3 will discuss the structural analysis process

needed to solve for forces in the tower and Chapter 4 will discuss geotechnical

analysis for the anchorage design based on those forces.

Figure 7 Free Body Diagram of Anchor and Tower


23
Where:
Pt = Cable tension =Force imposed on anchor
PV and PH = Respective components of the force.
Wt = Weight of Block + Weight Soil above Block = WB + WS
WB = X * Y * γ B
Ws = X * h * γs
γs = unit weight of soil
γB = unit weight of reinforced concrete
c = cohesion intercept of the soil
ϕ = Angle of Friction of the soil
ψ = Angle of anchor cable
θ = Cable deflection angle
Pp = Passive force (Appendix 2).
Therefore, the geotechnical parameters of interest are the angle of friction (ϕ), the soil

unit weight (γs) and the cohesion (c). The only structural variable that influences the

final anchor design is the loading, (Pt).

2.2 Structural Failure Parameters

For cable to fail, the strands must elongate past the elastic range into the elastic-

plastic portion of the material’s stress-strain curve. As the deck live load increases,

the load to the walkway cables is increased proportionally until the added length due

to stretch forces the suspenders to transfer the load onto the handrail cables. Only

when both the handrail and walkway cables were fully loaded would cable have the

24
potential to go beyond the elastic state required for cable failure. The aforementioned

cable connection is shown in Figure 8.

Figure 8 Typical Decking Cross-Section

Steel cable is the primary load-bearing structural component, diverting the decking

loads between the towers and anchorage systems. The cable carrying the transverse

load results in a geometrical configuration where horizontal force at mid span is

inversely proportional to the sag. It follows that cable pulled infinitely horizontal is

unable to carry any transverse load as zero sag implies an infinitely large cable force

(Pugsley, 1957). Likewise, significant increase in cable sag would result in a greater

vertical reaction at the towers. Structural design optimization requires the designer to

designate a sag ratio that properly balances these two considerations.

The minimum safe working load of steel cable can be found by dividing the

manufacturers supplied breaking strength by the safety factor. The recommended

factor of safety for load-bearing steel cable is 3.5 (Bureau Reclamation, 2009). Cable

clamps are required to reach 80 percent efficiency rating, thus an accumulative factor

25
of safety of 2.8. As the material specifications are highly regulated and guaranteed

for a high level of precision, the result is a highly unlikely case for structural cable

failure. Discussions into the behavior of the cable and construction elements identify

other potential failure mechanisms.

Prior to the wide-spread use of computer modeling and finite element techniques,

cable typically was assumed to behave as a parabolic curve (Pugsley, 1957). This

simplified parabolic model allows a basic understanding of the fundamental

interdependence between stability, stiffness, and strength. The cable analysis

described in Chapter 3 is overly-simplified but included to provide a basic

understanding of cable behavior and to provide the framework for design

understanding.

2.3 Geotechnical Failure Parameters

The geotechnical failure mode of interest is anchor pull-out. As such, the ultimate

uplift capacity (Qu) of the soil must be found. Chapter 4 will outline an empirical

approach for calculating Qu for both fine and coarse-grained soils. The soil

parameters of interest in both models are soil unit weight (γ), friction angle (ϕ) and

cohesion (c).

The primary geotechnical failure mode of consideration is anchor pull-out. To

prevent pull-out failure, the anchor must be placed at an appropriate depth and

distance from the tower with consideration for soil strength parameters. The soil

parameters of interest are the soil unit weight (γ), cohesion (c), and the friction angle

26
(ϕ) of a soil. Separate design approaches for fine and coarse-grained soils is

recommended for calculating ultimate uplift capacity of anchors (Das, 1990). Smith

and Stalcup (1966) suggested that fine-grained cohesive soils attained up to 30%

increase in holding capacity as compared to coarse-grained, but 2 to 3 times the

horizontal displacement was required to activate the passive earth pressure. This

initial research indicated that further investigation was needed before assuming a

similar design model was appropriate for both fine and coarse grained soils.

Rock masses will not be considered herewith in as the following models are not

applicable to jointed rock masses where strength is controlled by joint orientation.

Furthermore, intermediate rock masses will not be considered as the anchor design

for excavatable rock mass is not based on the soil properties but rather the rock and

anchor’s ability to attach to surrounding material as a single mass. The designation

between intermediate rock mass and a soil will be defined as the later is able to be

excavated with man-powered shovels.

27
Chapter 3: Structural Considerations

Structural design requires few site-specific parameters and thus can be implemented

off-site. The best-practice approach to design requires identifying applicable codes

and regulations. Under most conditions, structural design codes applicable in the

United States or equivalent will be at least as comprehensive and well-proven as

those in the country of consideration. A designer must address the differences in

codes during his or her work, but may use a design methodology documented herein.

The international nature of this design further encourages a designer to consult local

codes and learn from the experience of comparison.

Redundancy in the modulated Helvetas design has resulted in only one documented

failure in over 2000 bridge constructions (Helvetas, 2001). The failure of this

particular bridge was due to insufficient torque on the clamps used to tie the cable

around the anchor. As this is a relevant material and construction quality control

item, quality control will be discussed in Chapter 5.

3.1 Structural Analysis

Assuming the cable is frictionless and a perfectly flexible material, the cable hangs in

a parabolic arc (Pugsley, 1957). The primary assumption is that the intensity of the

vertical distributed load 𝜔𝑐 is constant. The perfectly flexible cable is considered to

give no resistance to bending at any point and thus the resultant tensile force is

tangent to the curve at any point in the cable. Thus, to find the maximum tension in

28
the cable, it is necessary to know the relations involving tension, span, sag and the

length of cables (Meriam, 2007).

3.1.1 Horizontal Tension

Taking the moments about point A taken at mid-span and assuming that the supports

are at equivalent heights, one can solve for the horizontal tension in the cable per the

Figure 9.

Figure 9 Schematic to Derive Moment at Mid-Span

𝑊𝑐 (𝐿2 )
𝑇ℎ =
8ℎ

Where:
Wc = distributed load
Th = horizontal tension
L = span in meters
h = cable sag, in meters
Given the horizontal tension in the cable, solve for the slope of the cable at the towers

to acquire the maximum cable tension at the height of the towers.

29
The slope of the cable, the corresponding total tension in all cables and the tension in

each cable may be calculated from the following relationships:

4ℎ
𝜃 = 𝑡𝑎𝑛−1 � �
𝐿

𝑇ℎ
𝑇′ =
𝑐𝑜𝑠 𝜃

𝑇′
𝑇𝑐 =
𝑁

Where:
θ = cable deflection angle
T’ = cable tension, in kN
N = number of cables
Tc = allowable tension per cable

One must chose the number of cables based on the availability of cable and its

respective breaking strength. Although each cable supplier must verify the breaking

strengths of the cable, Appendix 3 may be used for academic purposes. The sum of

the walkway and handrail cable design strengths must exceed the tension in the cable

after accounting for allowable stress design factors. Each cable takes a load

proportional to its’ cross sectional area and thus if cables of differing sizes are used,

each cable will take a proportional load to its cross-sectional area ratio.

In accordance with AASHTO (2003) standards, the following design approach and

assumptions were used throughout this report. To illustrate the design process, a
30
design example has been included through the text. By outlining pertinent

assumptions and processes, modifications to the standard design may be used. One

such scenario is a community’s request to widen the decking from 1.0 meter width to

1.5 meters to allow for animal-pulled carts or a decrease in deck-width for low traffic

crossings.

3.2 Pedestrian Bridge Loading

To find the tension in the cable, the load on the cable must be computed. The

following details the recommended design approach per American Association of

State Highway and Transportation Officials (AASHTO) article 3.16 and the

supplemental “Guide Specifications for Design of Pedestrian Bridges” document

(AASHTO, 1997). It is recommended that the reader reference applicable codes and

specifications in area of intended construction prior to design.

3.2.1 Liveloads

A liveload of 85 pounds per square foot is designated unless the walkway area is

greater than 400 square feet. Then the live load figure is slowly reduced between 400

square feet and 850 square feet, at which time the minimum standard of 65 pounds

per square foot is used. The 65 pounds per square foot minimum load limit is used to

provide a measure of strength consistency with the LRFD specifications, which

specify 85 pounds per square foot less a load factor indicated in the LRFD Design

specifications (AASHTO, 1997). The formula is as follows:

𝐿𝐿 = 85(0.25 + 15/√𝐴)
31
Where A is the total square feet of walkway surface area. Therefore, using a 1.0 -

meter walkway cross sectional area, the following live load schedule would apply:

Table 1 Liveload Schedule for 1.0-meter Deck Width

Span English Unit Loading Metric unit Loading

(m) (lbs/ft²) (kN/m²)

1-37 m 85 lbs/ft² 4.07 kN/m²


38-78 m proportional reduction, proportional reduction, from
from 85 to 65 lbs/ft² 4.07 - 3.11 kN/m²
79 + m 65 lbs/ft² 3.11 kN/m²

As noted in AASHTO (1997), the live load reduction for decking areas exceeding 400

square feet is consistent with ASCE 7-95, “Minimum Design Loads for Buildings and

Other Structures.” The reduction accounts for the reduced probability of the large

loading area of the structure being fully loaded at any given time. The likelihood of

the rural footbridge being fully loaded is somewhat unrealistic, but failure cases have

been reported during heavy traffic (Nepal, 2009). Furthermore, the likely case of

small motor-vehicles and animal-driven carts would require both distributed and

point-load analysis to find maximum loading case. As such, the conservative

assumption loading of 4.07 kN/m² (85 lb/ft²) is recommended.

Total LL = 4.07 kN/m, assuming 1.0 meter width

32
3.2.2 Dead Loads

Table 2 Assumed Dead Loading

Assumptions/Conversions Loading

Suspenders 8 mm diameter x 1.7 m steel rebar = 8.5e-5 m³ per rod 0.007 kN/ m
Unit weight steel = 490 lb/ft³ = 7847.3 kg/m³
0.67 kg per suspender
0.0098 kN/kg
Suspender spacing 1 meter on center per side
Cross 10 cm x 10 cm x 1.4 m 0.082 kN/m
beams Assume 600 kg/ m³ (Appendix 4)
Cross beams 1 meter on center
Decking 5 cm x 20 cm x 2 m = 0.02 m³ per 2 meter member 0.196 kN/m
Assume 400 kg/ m³ (Appendix 4)
8 kg per decking panel
5 decking panels across
Cable Assume 6x19 IWRC galvanized steel cable 0.036 kN/m
Assume 32 mm cable (1 ¼”) : 2.89 lb/ft
Assume 6 cables
1 lb/ft = 1.288 kg/m
Total DL = 0.321 kN/m, assuming 1.0 meter width

3.2.3 Wind Loads (Overturning)

A wind load applied horizontally at right angles to the longitudinal axis of the bridge

shall be applied at 35 pounds per square foot (1.676 kN/m²), assuming that the wind

can readily pass through the bridge profile, per AASHTO specifications. The

specified wind pressures are for a base wind velocity of 100 miles per hour which in

such case a site has higher wind-velocity requirements: AASHTO Article 3.15 (1997)

may be referenced. Given the projected profile of the bridge is 1.1 meters in height:

the resulting wind overturn force is 1.843 kN/m.

Total WL = 1.843 kN/m, assuming 1.1 meter railing height

33
3.2.4 Load Combinations

The following load combinations will be used, extracted from Table 3.22.1A in

AASHTO (1997):

• Group I - (Dead + Live) at 100% of Allowable Stress (i.e., Load Combination


Reduction Factor = 1.0).
• Group II - (Dead + Wind) /125% of Allowable Stress (i.e., Load Combination
Reduction Factor = 1.25).
• Group III - (Dead + Live + 0.3 Wind) /125% of Allowable Stress (i.e., Load
Combination Reduction Factor = 1.25).

kN 𝑘𝑁
Group I: 𝐷𝐿 + 𝐿𝐿 = 0.321 m2 + 4.07 𝑚2 = 4.39  directs

(𝐷𝐿+𝑊𝐿)
Group II: 1.25
= 1.73𝑘𝑁/𝑚²

(𝐷𝐿+𝐿𝐿+0.3∗𝑊𝐿)
Group III: 1.25
= 3.95 𝑘𝑁/𝑚²

Wc = 4.39 kN/m²

3.3 Structural Design

3.3.1 Suspenders

Suspenders transfer the loads from the deck to main cables, and are attached to

crossbeams at 1 meter intervals. Thus, with a 1 meter deck width, each suspender has

a tributary area of 0.5 m², and thus must be able to carry 2.03 kN of loading from the

4.07 kN/m loading. The minimum diameter of suspender can be calculated per the

following equation:

34
𝐹𝑠
𝐴𝑠 =
𝑃𝑠

Where:
Fs = applied force in kN
Ps =allowable yield strength in kN/m²

Assuming ASTM A36 Grade 300 (ASTM) with a minimum yield strength of 24.5

kN/cm² (250 MPa) and a factor of safety of 1.5, and assuming a 1.0 meter deck width,

the minimum diameter of a suspender would be 3.9 mm. Due to the high surface area

to volume ratio of the suspender and thus increased likelihood of corrosion, a

minimum suspender diameter of 8 mm is recommended.

3.3.2 Main Cables

Assuming a 100 meter crossing, the design process is as follows for selection of the

primary cable. For further details on the mathematical derivation of the following

equations, see reference (Meriam, 2007).

𝑊𝑐 = 4.39 𝑘𝑁/𝑚²

Therefore:

𝑘𝑁
𝑊𝑐 (𝐿2 ) (4.39 𝑚2 )(100 𝑚)²
𝑇ℎ = = = 1097.5 𝑘𝑁
8ℎ𝑠𝑎𝑔 8 ∗ (5 𝑚)

Where:

35
Th = horizontal tension, in kN.

L = Span in meters

hsag = cable sag, in meters

4ℎ
𝜃 = 𝑡𝑎𝑛−1 � � = 11.3°
𝐿

Where:
θ = cable deflection angle
𝑇ℎ
𝑇′ = = 1119 𝑘𝑁
𝑐𝑜𝑠 𝜃

Where:
T’ = cable tension, in kN
𝑇′
𝑇𝑐 =
𝑁

Where:
N = number of cables
Tc = Allowable tension per cable
The sum of the walkway and handrail cable design strengths must exceed the tension

in the cable. In this example, 1119 kN may be distributed either 4 cables (2 walkway

and 2 handrail) or 6 cables (4 walkway and 2 handrail) in order to support the load.

Using example design breaking strengths in Appendix 3 (including the factor of

safety of 3.5), the load can be split between 4 cables. Assuming each cable is to be

the same, each must have a minimum design strength equivalent to Tc. Thus, the

result is the minimum cable size of 34 mm, per Appendix 3. Each cable takes a load

proportional to its’ cross sectional area. The total design load imposed on the anchor
36
is equivalent to T’ or 1119 kN in the case of a 100 meter bridge with a 1.0 meter

decking.

To calculate the amount of cable to order, one must first know the length of each

cable between towers:

8 ℎ 2
𝐿𝑐𝑎 = 𝐿[1 + � � � � ]
3 𝐿

For a 100 meter span and 5 percent sag, 𝐿𝑐𝑎 is equal to 100.67 meters per cable

between towers. To calculate the total length of cable required to purchase, one must

first decipher the length of the backstay which requires geotechnical design. For

practical purposes, a simplified equation would allow field supervisors to order cable

without an intimate understanding of the design process. As the length of the cable is

only increased by less than one percent when accounting for sag, neglecting this

added length and alternatively including a four percent contingency is practical. The

following is proposed:

𝐿𝑐𝑎 = 1.04[𝐿 + 14 + �𝑑𝐿𝑒𝑓𝑡 𝑡𝑜𝑤𝑒𝑟 𝑡𝑜 𝑎𝑛𝑐ℎ𝑜𝑟 � + �𝑑𝑅𝑖𝑔ℎ𝑡 𝑡𝑜𝑤𝑒𝑟 𝑡𝑜 𝑎𝑛𝑐ℎ𝑜𝑟 �]

The 14 meter addition allows for cable wrap-back, seven meters at either anchor,

approximate but standard on all crossings.

There are several design alterations that may be considered to reduce the length and

thus cost of cable, but while the length of the span may reduce to lessen this cost, the

tower height likely would increase thus increasing masonry costs.

37
3.3.3 Decking

There are two primary code sources used for bending stress problems in The United

States: Load and Resistance Factored Design (LRFD) and Allowable Stress Design

(ASD). LRFD will be discussed herein. A full design process is not detailed herein

as it is beyond the scope of this report, but the following provides context and

background for how the modular decking design alternatives currently in use by

Bridges to Prosperity were developed.

A typical decking plan view is shown in Figure 10. Note that the crossbeam spacing

is 1.0 meters. The deck width will be assumed 1.0 meters as well.

Figure 10Typical Decking Detail Plan View

3.3.3.1 LRFD Loadings

LRFD use slightly different nomenclature from the loading section at the beginning

of the chapter but for consistency, the following will continue to use similar

nomenclature.
38
Table 3 LRFD Load Combination Alternatives

LRFD Load combination alternatives:


1. 1.4DL
2. 1.2DL+1.6LL+.5(Lr or S or R)
3. 1.2DL+1.6(Lr or S or R)+(.5LL or .8WL)
4. 1.2DL+1.6WL+.5LL+.5(Lr or S or R)
5. 1.2DL+/- 1.0E+.5LL+.2S
6. 0.9DL +/- (1.6WL or 1.0E)

Table 3 lists the six fundamental factored load combinations from Minimum Design

Loads for Buildings and Other Structures (ANSI/ASCE 7-88) used for safety analysis

in LRFD. There will be assumed no roof (Lr), no snow (S) no rain (R), and no earth

(E) loadings. Therefore the LRFD design strength is 6.89 kN/m². from load

combination 2. As the member is being design for compression, the required nominal

strength, assuming a resistance factor of 0.9 from Table 4, would be 7.66 kN/m².

Table 4 Wood LRFD Resistance Factor Values

Mode ϕ
Compression 0.90
Flexure 0.85
Tension 0.80
Shear 0.75

Structural design includes resistance to shear failure, flexure failure and for

serviceability, a maximum displacement must not occur. The crossbeams and

decking panels must be considered independently and for two load case scenarios:

fully loaded and point loaded in cross-section.

39
3.3.3.2 Cross beams

Crossbeams are the members that are spaced perpendicular to the length of the bridge.

There are three initial design choices: crossbeam spacing, and the width of the

decking.

Figure 11 Typical Decking Cross-Section with Dimensions

Figure 11 depicts a cross-section for a typical decking cross-section with a small

spacer board that is for constructability, but will not be considered in the following

calculations. The crossbeam bending calculations will be based off a cross beam

dimensioned (X+36 cm) by Y cm by Z cm (into the page). The additional 36 cm is

included for connection spacing on either side, as recommended from practical

experience.

3.3.3.3 Decking Planks

The length of the decking planks is recommended to be 3.0 meters, although 2.0

meter decking planks are also acceptable with a slight reduction in longitudinal

rigidity, as shown in the plan view of a typical decking in Figure 10. Design for

longitudinal beams should assume a multi-support, simple beam analysis. To identify


40
the maximum shear and applied moment, both point load and distributed load

scenarios should be considered.

For both cross-beam and decking plank design, one must state the material properties

and assume an initial member size. Material properties of interest are the material

yield strength, Fy, the ultimate flexural strength, Fu and the modulus of elasticity, E.

An initial member size is selected for the following parameters: cross-sectional area,

Ag, moment of inertia, I, the radius of gyration, r, and the corresponding slenderness

ratio, kL/r, the section modulus, S, and the maximum deflection (∆ = L/360).

As detailing every potential consideration and design alternative for decking design is

beyond the scope of this project, a modulated design is recommended for use.

Bridges to Prosperity has provided modular designs for both wood and steel decking

solutions: both provided with several size alternatives on their website (Bridges,

2009).

41
Chapter 4: Geotechnical Considerations

The main geotechnical design component of the bridge is the anchor block. The

primary purpose of these anchors is to transmit a tensile load from the cables to the

anchor and soil to prevent pull-out failure. Accordingly, it must have adequate

weight and placed at an appropriate depth and distance from the abutment to provide

adequate resistance (Das, 1990). Design models used to find the ultimate uplift

capacity of the anchor are separated for fine and coarse-grained soils due to their

difference in behavior. They behave differently due to the rate of pore water pressure

dissipation during loading. The following will discuss fine-grained-specific soil

analysis and recommendations, followed by coarse-grained-specific soil models and

recommendations. A recommended design process will summarize the findings from

these two proceeding sections.

4.1 Fine-Grained Soils: Clays and Silts

4.1.1 Geotechnical Analysis & Anchor Capacity

There are relatively few studies relating the holding capacity of inclined anchors

embedded in fine-grained materials under a tensile load (Das, 1990). One of the

most comprehensive studies of inclined plate anchors was completed by Das (1983).

The results showed that the net ultimate holding capacity of an inclined rectangular

anchor is related to an empirical breakout factor Fc’ as follows:

𝑄𝑢 = 𝐴𝑆𝑢 𝐹𝑐 ′ + 𝑊𝑠 𝑐𝑜𝑠𝜑

42
Where:
Fc’ = average breakout factor

𝑊 = 𝐴𝛾𝐻′𝑐𝑜𝑠𝜓
Qu = net ultimate holding capacity
A = area of anchor plate = Bh
B = width of anchor plate
Cu = undrained cohsion of the clay soil (ϕ = 0 condition)
Ws = Weight of soil above anchor

ψ = anchor inclination with respect to horizontal

H’ = average depth of embedment


Therefore, for rectangular anchors, the breakout factor can be recalculated as follows:

𝑄𝑢 2
− 𝛾𝐻 ′𝑐𝑜𝑠 𝜑
𝐹𝑐′ = 𝐵ℎ
𝐶𝑢

The breakout factor Fc’ increases with the average embedment ratio H’/h to a

maximum value, at which point it asymptotically approaches a maximum value, as

depicted in Figure 12.

43
Figure 12 Variation of Fc' with H'/h Ratio (Adapted from Das, 1990)

The first step in solving for the ultimate holding capacity of the anchor is to calculate

the critical average embedment ratio (H’/h)cr for a rectangular anchor as follows:

𝐻 𝐻 𝐵 𝐻
= ∗ (0.73 + 0.27 � � < 1.55 ∗
ℎ 𝑐𝑟 𝑟𝑒𝑐𝑡 ℎ 𝑐𝑟 𝑠𝑞𝑢𝑎𝑟𝑒 ℎ ℎ 𝑐𝑟 𝑠𝑞𝑢𝑎𝑟𝑒

Where:

𝐻
= 0.107𝐶𝑢 + 2.5 < 7.0
ℎ 𝑐𝑟 𝑠𝑞𝑢𝑎𝑟𝑒

Cu = undrained cohesion in kN/m²

𝐻
If the design ratio H/h is greater than ℎ 𝑐𝑟 𝑟𝑒𝑐𝑡
, then it is considered a deep anchor and

the breakout factor assuming a zero degree anchor angle is as follows:


𝐹𝑐′𝜓=0 = �7.56 + 1.44 � ��
𝐵

44
𝐻
If the design ratio H/h is less than ℎ 𝑐𝑟 𝑟𝑒𝑐𝑡
, then it is considered a shallow anchor and

the breakout factor assuming a zero degree anchor angle is as follows:


𝐹𝑐′𝜓=0 = �7.56 + 1.44 � �� ∗ 𝛽
𝐵

Where β is found using Figure 13.

1
0.9
0.8
0.7
0.6
0.5
β

0.4
0.3
0.2
0.1
0
0 0.2 0.4 0.6 0.8 1
α=(H'/h)/(H'/h)cr

Figure 13 Variation of β with Embedment Ratio for ψ=0

The next step is to estimate the breakout factor for an anchor with a cable angle of 90

degrees. Although unrealistic, the process eventually correlates the actual backstay

angle to the ratio of the breakout factor at 0 degrees and 90 degrees.

𝐻
+ 0.5 𝐵
ℎ 𝑐𝑟 𝑟𝑒𝑐𝑡
= �0.9 + 0.1 � < 1.31
𝐻 ℎ
+ 0.5
ℎ 𝑐𝑟 𝑠𝑞𝑢𝑎𝑟𝑒

45
Where:

𝐻
= 0.0606𝐶𝑢 + 4.2 < 6.5
ℎ 𝑐𝑟 𝑠𝑞𝑢𝑎𝑟𝑒

𝐻
If the design ratio H/h is greater than ℎ , it is considered to be a deep anchor and
𝑐𝑟 𝑟𝑒𝑐𝑡

the breakout factor assuming a zero degree anchor angle is as follows:


𝐹𝑐 ′ 𝜓=90 = 9 ∗ �0.825 + 0.175 � ��
𝐵

𝐻
If the design ratio H/h is less than ℎ 𝑐𝑟 𝑟𝑒𝑐𝑡
, then it is considered a shallow anchor and

the breakout factor assuming a zero degree anchor angle is as follows:

𝐹𝑐 ′ 𝜓=90 𝑛′
′ =
𝐹𝑐 𝜓=90
∗ 0.41 + 0.59𝑛′

Where :

𝐻
+ 0.5
′ ℎ 𝑐𝑟 𝑟𝑒𝑐𝑡
𝑛 =
𝐻
+ 0.5
ℎ 𝑐𝑟 𝑠𝑞𝑢𝑎𝑟𝑒

Das details the process where Fc’ is determined through the following equation,

relating the variation of the average breakout factor as follows:

𝜓
𝐹𝑐 ′ 𝜓 = 𝐹𝑐 ′ 𝜓=0 + �𝐹𝑐 ′ 𝜓=90 − 𝐹𝑐 ′ 𝜓=0 � ∗ ( )²
90

46
With Das’ (1990) empirical procedure outlined above, a parametric study was

conducted with several assumed backstay cable inclinations, as shown in Figure 14.

70

60
Minimum Cohesion to resist pull-out failure (kN/m²)

50

40

30

20

10

0
0 500 1000 1500 2000
Net Ultimate Holding Capactiy (kN)

30 degrees 35 degrees
40 degrees 45 degrees
60 degrees Linear (30 degrees)
Linear (35 degrees) Linear (40 degrees)
Linear (45 degrees) Linear (60 degrees)

Figure 14 Net Ultimate Holding Capacity with Variation in Cohesion using Das (1990)

Using Das’ approach for shallow-anchor design, Figure 14 summarizes the

dependency on cohesion for a load of 1119 kN (which is representative for a 100

meter span), assuming an anchor with a 1.2 m by 3.0 meter surface. A soil unit

weight of 19 kN/m³ was assumed because the dependence on the unit weight is

insignificant for all ranges of loading types, as shown in Figure 15.

47
70

Minimum Cohesion to resist pull-out failure (kN/m²)


60

50

40

30

20

10

0
300 500 700 900 1100 1300 1500
Net Ultimate Holding Capactiy (kN)

17 kN/m3 19 kN/m3 21 kN/m3 25 kN/m3

Figure 15 Net Ultimate Holding Capacity with Soil Unit Weights using Das (1990)

As the dimensions of interest are considered ‘shallow’ by Das’ (1990) definition, the

deep anchor scenario was not modeled. The assumed parameters for this model

included a surface length perpendicular to cable (h) of 1.2 m, an average embedment

depth (H’) of 5.0 meters, and an anchor width (B) of 3.0 meters. For typical loading,

detailed in the structural analysis in Chapter 3, the minimum cohesion values required

to resist pull-out failure for an 1119 kN load are within realistic cohesion values for

fully saturated fine-grained soils.

48
4.1.2 Recommended Parameters

The conclusion is that the soil unit weight and the minimum cohesion are fairly

insignificant soil properties within the pertinent parameters of interest. As detailed in

Chapter 2, the longest typical bridge of consideration is 120 meters. Accordingly,

even though the cohesion is important for high loads, these will not be observed in

these bridges.

Figure 14 proves the relative insignificance of soil parameters at given conditions of

interest. If no testing is available, a conservative cohesion of 20 kN/m² may be

assumed. Assuming that the structure is quickly loaded and the undrained strength

parameters direct, assuming a zero friction angle is also appropriate. Figure 15 shows

that the depth of embedment is relatively insensitive to the soil unit weight (19

kN/m³). Non-plastic silts will exhibit little or no cohesion and friction therefore they

are included with coarse grained soils.

4.2 Coarse-Grained Soils: Sands, Gravels and Non-Plastic Silts

4.2.1 Geotechnical Analysis & Anchor Capacity

Meyerhof and Adams (1968) proposed a semi-empirical relationship for estimating

the ultimate uplift capacity of strip, rectangular and circular anchors in coarse-grained

materials. It is one of few methods available for estimating the capacity of

rectangular anchors. Many alternative models are presented in literature for circular

or square anchor plates, but those will not be discussed as the shape of the anchor

requires a shape factor not included in other design models (Das, 1990). The
49
introduction of further empirically derived correction factors ideally would be

accompanied by experimental validation for use with anchorages similar in size and

use as footbridges. The Meyerhof and Adam’s model includes fewer assumed

assumptions than other models and thus will be discussed.

To find the ultimate uplift capacity per unit width of anchor, the following equation

may be used:

1
𝑄𝑢′ = 𝐾 𝛾 𝐻 2 + 𝛾𝑠 ℎ𝐻𝑐𝑜𝑠 2 𝜓
2 𝑏 𝑠

Where:
Qu’ = ultimate bearing capacity per unit width
Kb = Passive Pressure Coefficient
h = height of embedment
H = depth of bottom of anchor
H’ = average embedment of anchor
ψ = Angle of cable from anchor, from horizontal
γs = unit weight of soil

Several parametric studies were completed analyzing the impact of material

assumptions on the Meyerhof procedure for inclined anchors in a cohesionless soil

(Meyerhof, 1973). A study comparing the impact of backstay angles and minimum

embedment depth for an 1119 kN load (from Chapter 3, structural loading for a 100

meter bridge) with various friction angles is summarized in Figure 16.

50
Backstay Angle (degrees from horizontal)

20 30 40 50 60 70 80
0.00

1.00

2.00
Minimum embedment (m)

3.00

4.00

5.00

6.00

7.00

Phi = 25 degree Phi = 30 degrees


Phi = 35 degrees Phi = 40 degrees

Figure 16 Minimum Embedment with Friction Angles using Meyerhof and Adam (1968)

As the backstay angle had a minimal impact on the embedment depth, a simplifying

conclusion specifying a minimum embedment of 6.0 meters may be suggested. As

this analysis is specific to a 100 meter bridge loading, these results may not be

extrapolated to all spans. The outlined analysis may be followed to produce similar

simplifying conclusions for any span of interest.

This particular study assumed a soil unit weight of 19 kN/m³, because the minimal

impact on the model for this parameter as shown in Figure 17.

51
Assumed Unit weight of soil (kN/m³)
15 17 19 21 23 25 27
0.00

Minimum Embedment depth (m) 1.00

2.00

3.00

4.00

5.00

6.00

Phi assumed 26 degrees, backstay assumed 30 degrees

Figure 17 Variation of Minimum Embedment with Soil Unit Weight using Meyerhof and Adam (1968)

Varying the backstay angle of the anchor was found to have relatively minimal

impact on required friction angles within the range of feasible anchor angles from 20

to 60 degrees from the horizontal.

The variations of Kb for shallow strip anchors can be obtained from the earth pressure

coefficients of an inclined wall, and were summarized in a chart (Das, 1990). Each

anchor angle and assumed soil friction angle will have a unique empirical value.

Given the opportunity, pull-out tests on various sandy soils may provide further

insight and negate the need for conservative friction-angle assumptions. Logan

(Logan, 1976) completed an experimental series of pull-out tests for footings in sand.

Footings were loaded to failure and the failure mechanism was documented. Future

52
work in this area could find his testing procedures and findings applicable. For

further details of Logan’s study and findings, reference Appendix 5.

4.2.2 Recommended Parameters

Figure 16 shows an increase in load when the friction angle is increased from 25 and

30 degrees. If no testing is available, it is recommended that a value of 26 degrees be

assumed for the value of friction angle. This is relatively low for quartz sands, as it is

the angle of repose. Figure 17 depicts a relative insensitivity for the assumed soil unit

weight thus 19 kN/m³ may be assumed. The most conservative strength for a coarse-

grained soil is when it is fully-drained in which case it will have a zero cohesion

intercept. Table 5 is a summary of recommended soil assumptions.

Table 5 Soil Property Assumptions Summary Table

Fine-grained soil
γsoil 19 kN/m³
ϕ 0 Degrees
c 20 kN/m²
Coarse-grained soil
γsoil 19 kN/m³
ϕ 26 Degrees
c 0

4.3 Geotechnical Design

4.3.1 Design Process

Sections 4.1 and 4.2 detailed two distinct analysis approaches for anchors in fine and

course grained soils respectively to identify design simplifications. The following is

53
modified DM-7 design approach (2009) that may be used for design of anchors in

fine or coarse-grained soils. Soil parameter assumptions justified in the

aforementioned sections may be used, or further testing approaches detailed later in

the chapter may be used to reduce material uncertainty.

Figure 18 Free Body Diagram Anchor (Adapted from DM-7, 2009)

Where:
Pt = Force (can be found from the Structural Considerations section)
PV and PH = Respective components of the force.
Wt = Weight of Block + Weight Soil above Block = WB + WS
WB = X * Y * 2300 kg/m³ (unit weight concrete)
WB = X * h * γ
γ = unit weight of Soil
c = cohesion
ϕ = Angle of Friction
Pp = Passive pressure (Appendix 2).

54
The design process is very straight forward and only requires verification that the

anchor of interest is able to resist the vertical force and the horizontal force with

independent calculations.

1) Step 1: Check resistance to vertical force:


𝑊𝑡
≥ 1.5
𝑃𝑣
2) Step 2: Check resistance to horizontal force :
𝑃𝑝
≥ 1.5
𝑃ℎ

4.3.2 Soil Classification & Testing

4.3.2.1 Soil Classification

The geotechnical component of the design for rural bridges involves an estimate of

the resistance to pull-out of an anchor. The parameters governing the mechanical

response of the soil to such loadings as well as the recommended testing approaches

are dependent on the rate of loading and the drainage characteristics of the soil. The

main parameters needed are the shear strength, usually represented by the Mohr-

Coulomb failure envelope where the strength is sensitive to the water content and

density:

𝜏 = 𝑐 + 𝜎 tan (𝜙)

For the case of short-span pedestrian footbridge design, the anchorage systems have

been proven in Sections 4.1 and 4.2 to be relatively insensitive to input soil

parameters. As such, it is recommended by the author that the soil at a minimum be

classified with the objective to choose between the two modeling alternatives. If no

55
further testing is possible, use of the conservative soil parameters are suggested for

these groups.

The Unified Soil Classification System (USCS) groups soils using their grain-size

distribution and plasticity characteristics, in order to separate them by their expected

engineering behavior (Appendix 6). The USCS assigns a group symbol to the soil,

along with standardized descriptions appropriate for that group name which is useful

for selection of design strategies. The USCS begins by separating the soil into either

coarse-grained or fine-grained, depending if greater that 50 percent of the material is

larger or smaller than a 200 sieve, with the exception of highly organic soil. Highly

organic soils often will smell have fibers and are typically dark in color. If found on

site, organic soil should be excavated and discarded due to their poor properties and

thus will not be discussed herein.

Figure 19 Sieve Test (Adapted from Concrete, 2009)

56
USCS further differentiates between the coarse-grain into ‘gravels and sands’ and

fine-grain into ‘silts and clays’. This second classification step requires further

sieving for coarse-grained soils and laboratory work including the Atterberg limit

tests for fine-grained soils.

For on-site feasibility, the use of a 0.074 mm screen, equivalent to sieve size #200

should be used. If the in-situ soil is clumped, the soil must be washed prior to using

the sieve. To collect the soil sample, the site investigator shall dig a small trench and

sieve one 5-gallon bucket of material onto a standard 75 micrometer mesh

(Wovenwire, 2009). The action of digging a test-pit also gives one a better

understanding of soil variability and an increased awareness of drainage issues to

better identify where the soil may present excavation difficulties.

A second required classification step is to administer the dilatancy test detailed in

Section 4.4.2.2. Given the results of the sieve and dilatancy test, respective field

testing approaches should be completed for soils classified with greater than 50

percent passing the 0.074 mm sieve. The test requires a sample with a soft putty

consistency. Observe the reaction during shaking, followed by squeezing the soil in

ones hand with vigorous tapping. During the test, if the soil behaves as a fine-grained

soil, the vibration would densify the soil and water would appear on the surface. In a

clay sample, no change occurs and thus may be classified as fine-grained (Field,

2009). Silt has a tendency for dilatancy so excess water would disappear from the

57
surface. In such case, this soil behaves similarly to a coarse-grained soil and should

be tested and modeled as such.

4.3.2.2 Shear Strength of Fine-Grained or Cohesive Soils

For a designer interested in optimizing the size of the anchor, soil testing would

reduce conservative assumptions.

For fine-grained soils, it is relatively straight forward to obtain an undisturbed

sample, and test it in the laboratory. In a triaxial test a cylindrical soil specimen is

confined within a flexible membrane which permits the application of isotropic

stresses while permitting the specimen to deform under axial loads. The stress-strain

curve can then be obtained for different confining pressures (Saada & Townsend,

1981).

Figure 20 Typical Triaxial Testing Apparatus

Strength values can be defined on the stress-strain curve plotted on a Mohr-Coulomb

diagram to get c and ϕ. As drainage does not occur quickly in the field, excess pore
58
water pressure does not dissipate quickly. Therefore, the shear strength corresponds

to short-term or undrained conditions. With ideal testing and laboratory accessibility,

an unconsolidated, undrained (UU) triaxial test would simulate a similar loading

(Coduto, 2001). The UU test is performed in the triaxial cell with the drain valves

closed throughout the test.

For the bridge described in Chapter 2, the structural loading condition would

correspond to a sudden, large volume of bridge traffic. Sudden bridge loadings are

common in the case of festivals, post-school departures. During the rainy season it

would not be expected to have nearly saturated soil along the banks of a river. Figure

21 shows representative data expected from UU triaxial tests in a laboratory.

Figure 21 Expected UU Triaxial Test Results for Cohesive Soil

The UU tests on saturated fine-grained soils may be carried out either on undisturbed

or remolded samples. With the σ3 acting on the entire sample, the axial pressure is

increased until failure occurs at the deviator stress (σ1- σ3), from which the major
59
principle stress is determined. Several tests should be completed to create a similar

plot to that detailed in Figure 21. In this case, (σ1- σ3) is not sensitive to σ3 as the

increase in total stress is carried completely by the pore water. The input parameter

from the test to use in the design models is su which is related to the maximum

principal stress difference (σ1- σ3), by the following relationship.

𝜎1 − 𝜎3
𝑐=
2

The VST is often used in-situ to obtain approximations of shear strength of saturated

cohesive soils, specifically where undisturbed samples of acceptable quality are

difficult to obtain (Terzaghi, Peck & Mesri, 1996). The VST consists of a metal

vane which is inserted into the ground and torque is applied until the soil fails in

shear, when the test is completed according to ASTM D2573. It is pertinent to note

that the rate of vane rotation is intended to ensure undrained conditions at failure. As

such, it is very beneficial to sample the soil either before or after testing, to

understand the drainage conditions of the soil tested because the presence of a silt or

coarse-grained soil will not produce usable results (ASTM D2573, 2008).

Furthermore, as the soil must be saturated prior to testing, it is advised to take a

sample near the stream bed rather than in the intended area of excavation, assuming

homogeneity between the two sites.

The undrained shear strength of a fine grained soil is correlated to the torque required

for failure, the vane dimensions and the plasticity index per the following equation:

60
6𝑇𝑓
𝑠𝑢 = 𝜆
7𝜋𝑑 3

Where:
su = undrained shear strength
Tf = torque at failure
d = diameter of vane

𝜆= Bjerrum correction factor

To properly identify the Bjerrum correction factor (Appendix 7), the plasticity index,

Ip, must be found. The Plasticity Index of a soil is the numerical difference between

the liquid limit and the plastic limit, (LL-PL) (Coduto, 2001). The water content is

one of the parameters which is very difficult to ascertain in the field without access to

an oven.

The pocket vane shear tester is a more portable and inexpensive version of the VST.

The pocket VST test should be completed according to ASTM D 4648 which

designates the rotation of a 12.7-mm high x 12.7-mm diameter vane at approximately

90 degrees per minute (Geotest, 2009). The vane may be advanced to depths of

interest by first excavating a small pit, to 1.5 to 2.0 meters in depth, or to a depth

more closely correspond to the soil properties at the depth of the anchor.

61
Figure 22 Pocket Vane Shear Test

The pocket penetrometer is another method to obtain the undrained shear strength of

a saturated soil. By pushing the small probe into a fine-grained soil, the measured

unconfined compressive strength measured can be converted to shear strength by

diving by 2 (Coduto, 2006). Figure 24 shows a picture of a typical pocket

penetrometer.

Figure 23 Pocket Penetrometer

The spring operated pocket penetrometer is a small and transportable device that

measures the undrained compressive strength by pushing a 0.25” (6.4 mm) diameter

loading piston into the material of interest, to the depth of a calibration groove

machined on the piston 0.25 cm from the end. The strength in kN per square cm is

obtained by noting the position of the indicating ring on the scale, which is retained

62
until reset (Professional, 2009). Both of these testing devices are highly mobile and

inexpensive thus providing a viable testing solution for rural applications.

4.3.2.3 Strength of Coarse-Grained or Cohesionless Soils

If the soil is classified as coarse-grained, obtaining undisturbed samples is nearly

impossible, especially in rural areas. Accordingly, it is difficult to quantify strength

without field tests like the Standard Penetration Test (SPT) or the Cone Penetration

Test (CPT). However, these tests require specialized equipment unavailable in the

field. Accordingly, it is recommended to use correlations. Correlations involve an

estimate of the soil density. Efforts should be made to estimate the density in the

field and use correlations such as those presented in Table 6.

Table 6 Correlations for Coarse Grained Soils (Terzaghi, Peck & Mesri, 1996)

If advanced testing is not available, conservative soil strength parameters are given in

Figure 24. These were developed based on the findings of the analyses in Sections

4.1 and 4.2. For every soil type, the first step is to sieve with a 0.074 screen. The

second step is the dilatancy test, outlined in Section 4.3.2. If the soil shows properties

of dilatant silts, it will be modeled as a coarse-grained soil.

63
Based on the classification of the soil, either tests or correlations should be used to

identify soil strength properties. If adequate testing is devices are not available, the

analyses suggest that conservative values can be used.

Figure 24 Soil Classification and Testing Flow Chart

64
4.3.3 Design Example: Sebara Dildi Case-Study

100 meter span results in 1120 kN load onto the anchor, as detailed in the Structural

Design section. Soil classification resulted in a coarse-grained soil on either

abutment. Using the Meyerhof method detailed in Section 4.2.1, and Figure 16, an

initial embedment depth of 5.0 meters was chosen, and similar anchor geometries

were chosen: block X, Y, L = 1 meter x 1 meter x 3 meter wide at a depth of 3.0

meters.

Assumptions
γ_soil 19 kN/m³
ϕ 26 Degrees
c 0
ψ 30 Degrees
h 5 m
B 3 m
Qu(total) 1119 kN
Qu (g) 373 kN/m

Pt = 1119 kN = 373 kN/m


PV = Pt * sin(ψ) = 186.5 kN/m
PH = Pt * cos(ψ) = 323 kN/m
WB = X * Y * 25 kN/m³ (unit weight reinforced concrete) = 1 x 1 x 25 = 25 kN
Ws = X * h * γ = 1 x 5 x 19 kN/m³ = 95 kN
Wt = 25 kN + 95 kN = 120 kN
Pp = Passive pressure (Appendix 2 for Granular Soil)
ϕ 𝐻 30 5.0
𝑃𝑝 = tan(45 + ) ∗ 𝛾 ∗ = tan(45 + ) ∗ 19 ∗ = 82.27 kN
2 2 2 2

65
1) Check

𝑊𝑡
≥ 1.5
𝑃𝑣

120 𝑘𝑁
= −−≥ 1.5— 𝑁𝑜𝑡 𝑂𝑘
186 𝑘𝑁

2) Check

𝑃𝑝
≥ 1.5
𝑃ℎ

82.27 𝑘𝑁
= −−≥ 1.5— 𝑁𝑜𝑡 𝑂𝑘
323 𝑘𝑁

In conclusion, the 1 meter by 1 meter by 3 meter anchor at a depth of 5.0 meters is

not acceptable for a 100 meter span with coarse-grained soil conditions. As detailed

in Chapter 4, further design iterations could increase the depth of embedment with the

objective to reduce the size of the anchor depending on priorities for optimization to

calculate an adequate sized anchor. The conclusion from this case study is that soil

testing with a greater level of precision much be available. Alternatively, the soil

mass above the backstay of the anchor may be included in the calculations to resist

pull-out failure. The result of oversimplification of soil parameters produces

unreasonable excavation depths for rural construction applications.

66
Chapter 5: Quality Control Considerations

Although engineers and project designers intend for designs to be constructed exactly

per specification, as-built drawings even in the developed world often vary greatly

from the original designs. Design factor of safety and the in-situ factor of safety are

rarely the same. Due to inadequacies in workmanship, material quality, quality

control, etc., the capacity of the completed bridge is not actually known, thus the

design factor of safety must be liberal to account for those conditions.

Designers must include added factors of safety in design to account for the probable

occurrence of inadequate craftsmanship and material specifications. The following

will detail a few of the critical quality control issues that a field supervisor must

account for, but further research is needed to adequately address quality control

measures.

5.1 Material Specifications

5.1.1 Concrete Mixture

Concrete is one of civilization’s oldest building materials and most often is a material

already widely used in most rural communities. Teaching the local laborers the

importance of proper mixing techniques and mixture types will improve the quality of

all concrete construction and thus may be one of a project’s primary successes

(Ruskulis, 1996).

67
Concrete is produced by mixing water, Portland cement and sand and gravel. To

produce a good concrete block, care needs to be taken in the quality of the sands and

gravels used in the mixture. Construction quality control of the sand and gravel

materials often requires preparatory work as natural conditions rarely leave well-

graded deposits. The fine aggregate with a diameter less than 5 mm, more commonly

referred to as sand, is often available on rural construction sites. No silt or clay

passing a #200 sieve or about 0.074 mm may be used. Similar to the process for soil

classification, if sand is sourced locally out of a riverbed, a mesh screen must be used

to ensure proper grain-size. Sands need to be washed and sifted through a screen with

5 mm openings. Coarse aggregate or gravel is a mixture of rock with a range of 6-20

mm diameter which may be found in-situ or created by crushing larger locally

available rock. The gravels and sands should have regular grain-size grading without

one specific size dominating the size distribution: with sand, particularly too many

fines (Ruskulis, 1996).

Water content controls the workability of the mixture and chemically reacts with the

cement to bond the resulting concrete. One of the critical components of quality

control is to ensure that the proper ratio is maintained during construction for

increased portions of water will improve workability but decrease material strength

(Engineer, 2002). For hand-mixing, a water to cement ratio of about 0.55 produces a

workable and durable concrete (Davis, 2002) but for more specific cement ratios,

Table 7 may be referenced.

68
Table 7 Concrete Ratios by Volume (Adapted Engineers, 2006)

Mix Ratio by Volume Typical Use on Approximate


(Cement:Sand:Gravel:Water) Bridges Yield (m³)
1 : 3 : 6 : 1.6 Tower Foundations, 0.24
Block Anchors
1 : 2.5 : 5 : 1.6 Tower Foundations 0.21
on poor soil
1 : 2 : 4 : 1.6 Non-structural 0.17
Approach walls
1 : 2.5 : 3.5 : 1.6 Structural Column in 0.17
Tower

Mixing technique is another aspect of quality concern. Many rural laborers are

familiar with mixing concrete but local methods of mixing are often inferior as there

is a lack of quality control standards. Common is the volcano approach, in which

aggregates and cement are mixed by hand, forming a pile. A hole dug out of the top

provides a bowl-form for the water to be poured and mixed. Although common, this

approach is not appropriate as it is difficult to attain an even mixture. Alternatively,

to hand-mix concrete, one must specify that the water is to be splashed into the

mixture in lifts while being manually mixed using a shovel.

Once set, the fresh concrete must be kept wet during the curing period. Concrete will

set in three days but reaches workable strength after seven days (Hazeltine,2003).

For greater detail on appropriate methods for concrete mixtures, reference Engineers

Without Borders, Concrete Mixes Guidelines (Engineers, 2006).

5.1.2 Steel Cable

Steel cable has two types of elongation: elastic stretch that fluctuates with the applied

load and the permanent stretch that corresponds with the cable strands rearranging
69
and tightening in cross-section. The type of cable purchased dictates the amount of

hoisting sag. Cable may be purchased as either non-prestretched or prestretched, the

latter which will be considered herein. It is pertinent to not that if non- prestretched

cable is used, the design engineer must increase the anticipated sag onset from

loading which would have a greater impact on the hoisting sag set.

Cable handling is of paramount importance. It is critical not to unwind the cable

incorrectly, as this may cause kinks in the cable which result in weak points in the set

cable and thus potential failure points. Figure 26 shows the proper way to unwind the

cable.

Figure 25 Cable Uncoiling Procedure (Helvetas, 2001)

Cable transport from the drop point to the bridge site is also critical. Figure 27 shows

the proper way to transport cable.

Figure 26 Proper Cable Transport Technique


70
5.1.3 Cable Clamps

U-bolt clamps, often referred to as bull-dog clamps, are used to tie the cable around

the anchors. The singularity of the clamping method is one of the few design aspects

that does not include redundancy. As such, the material properties of the steel used to

create the clamps and the process used to attach the clamps is critical for the quality

assurance a bridge project.

The structural integrity of the clamps used to connect the steel cable is an area of

concern, as clamp failure is the source of the only known bridge failure to date

(Nepal, 2008) as shown in Figure 28.

Figure 27 Failed Nepali bridge: Clamp Slippage

Malleable steel clamps are most common but are inadequate for continuous load-

bearing design (Crosby, 2009) such as in the case of cable-suspended bridges. Drop-

71
forged are of superior quality for bridge-type loadings but are often difficult to locate

in developing countries.

The difference between the two is the process used to create the clamp. As with all

steel, the principal mechanical properties of interest to designers are strength,

ductility and hardness all of which are dependent on the process used to create the

clamp. In the casting process to create malleable clamps, the mold has the shape of

the desired component and the liquid metal flows into the desired shape. Malleable

clamps are able to attain the same efficiency ratings based on breaking strength of

wire rope, but are apt to continuously loosen with continued load and thus reduce

their ‘grip’ on the cable. With forged steel, the original shape is an ingot that is

forged into shapes by presses. The resulting product has a greater material strength

and lower ductility. As such, the torque specified to reach maximum efficiency rating

is greater than a malleable clamp of comparable diameter but once torque, the clamp

is far less likely to slip. It is the engineering field supervisor’s responsibility to

ensure that the clamps used on-site are per specification.

5.2 Construction Quality Control

5.2.1 Cable Clamps

Proper installation of cable clamps is one of the most critical components of

construction quality control. Correct installation is shown in Figure 29 and shows

both ropes are arrayed parallel and in contact with the bow clamp screws twisted on

72
from the side of the carrying rope. It is essential that the clamp saddle surrounds the

‘live end’ of the cable, as shown.

Figure 28 Proper Cable Clamp Installation

To attain maximum efficiency rating of the clamp, the manufacturer designates a

minimum torque required. It is the author’s experience that for the clamp to be fully

torqued, the cross-sectional area of the dead-end of the cable will be reduced by

approximately 25% as shown in Figure 30.

Figure 29 Reduction in Cable Cross-Section with Proper Torque

73
To attain the required torque, one must reference manufactures standards. As the

installation of cable clamps occurs within a short span (a 26 mm cable requires 7

clamps, each spaced at 15 cm on center), it is very difficult to exert excess force.

Based on the 26 mm diameter of the cable, the required torque is approximately 300

ft-lbs. Assuming a typical laborer may be able to exert 80 to 100 pounds of force, a

3-foot wrench barely achieves full torque. It is unreasonable to require a torque-

wrench to measure actual torque applied at rural construction sites, thus one clamp in

addition to manufacturer’s specifications is recommended for each cable. Figure 31

shows a completed clamp installation in with the wrench used for cable installation.

Figure 30 Proper Cable Clamp Installation and Torque Wrench

5.2.2 Backfill and Compaction

Care must be taken when backfilling the approaches. Soil should be placed in layers

no greater than 15 cm thick. In the case of clays or silt backfill, a hand-rammer

should be used to compact the soil, shown in Figure 32.

74
Figure 31 Hand Rammer

Alternatively, community members or livestock walking thoroughly atop each layer

will ensure proper compaction. With soil placed in lifts the weight of the soil above

the anchor relied on in the design can be achieved. Furthermore, compaction of the

backfill ensures excessive settlement will not damage the approach ramp concrete.

Several other quality control items are critical to ensure the safety of the pedestrian

footbridges. The inclusion of these few is intended to encourage bridge designers and

field supervisors to consult the Helvetas manual (2001) for a more complete

coverage. Further research and publication in this area would also be extremely

beneficial for those working with rural footbridge technologies.

75
Chapter 6: Conclusion and Discussion

6.1 Summary

Pedestrian bridges ensure access to education and health, commerce and opportunity.

Rural pedestrian bridges contribute towards the improvement of living conditions for

some of the world’s most economically and socially disadvantaged. The simplicity of

the technology and the availability of a design example will ensure many more

bridges are built.

A review of pertinent structural design codes and geotechnical models were reviewed.

Parameter assumptions were justified through parametric models, and a simple design

approach adapted from DM-7 (Naval, 2009) was proposed for design use for both

fine and coarse grained soil types.

The loading assumptions and structural design approach was presented in Chapter 3,

including a case-study based on a 100 meter span and 1.0 meter decking. Chapter 4

detailed pertinent academic approaches to anchor design for fine and coarse grained

soils. Separate consideration for either soil type was given and soil parameter

assumptions concluded upon. A recommended soil testing and classification flow

chart was provided to acquire soil parameters for use in the DM-7 anchor design

process. Structural loading assumptions and codes are provided in the context of a

case-study example. The final product found that the 100 meter Ethiopia bridge case

study with a sandy-soil at either abutment must resist 166 kN of loading. One anchor

design solution is detailed. Several of the key quality control measures were outlined

76
in Chapter 5, with the intention to introduce the reader to the importance of material

and construction quality control for footbridge projects.

6.2 Design for the Developing World

The spectrum of potential benefits for infrastructure projects in developing countries

ranges from improved beneficiary access, for example improved educational standard

allowed from year-round access to schools, to the introduction of construction

technology transfer. Despite the benefits of any type of international aid work,

ethical dilemmas of accountability and safe practice are pertinent. The process of

design simplification presents a number of technical and logistical challenges.

Furthermore, professional ethics must be considered when detailing the operations,

maintenance and project lifespan accountability. A general discussion of transferring

a technology from the developed to developing world is also considered from a

lessons-learned context.

6.2.1 Design Simplification

Great care must be taken not to reduce the quality of a design when simplifying.

Many technologies needed in the developing world have well-documented design

approaches for use in developed countries. To make these technologies appropriate

for rural applications, modifications for material availability, low cost and limited

tools and equipment must be accounted for. The process of simplification requires

the engineer to make many of the same design decisions as in an industrialized

context, but with a varying hierarchy of priorities. For example, in the case of

77
infrastructure projects, a designer in The United States may be willing to sacrifice an

increase in budget to reduce the construction time. In the developing world, most

often time and labor are least expensive and thus lowering the cost of a project would

be prioritized. Finding the balance between cost, and construction time is of

paramount importance.

Standardizing designs and design processes specifically for development work

provides a greater level of comfort in a design, reducing this likelihood of project

design failure. But, modulated designs require a number of assumptions: a design

code to be followed, material availability and project objectives by the beneficiaries.

Local engineering design codes and community usage requests must be taken when

simplifying a design from the original context in the developed world to that of the

developing. As such, even a simplified and modulated design must have the

flexibility to be modified. Design manuals are often created for use in the developing

world as was the case of the Helvetas manual. It is the suggestion of the author that

development projects may have the greatest impact when a modulated design also is

supplied with a detailed explanation of the design process and assumptions used.

This allows for a more general use of the work as secondary contributors are able to

modify to better suit their local community and national standards.

6.2.2 Ethics of Accountability

Accountability for humanitarian-aid projects requires one to consider the professional

ethical codes for practice in a country other than where one is licensed. In typical

78
industry work, the engineering profession has a very high level of professional

accountability but design codes and regulations allow an engineer a level of

confidence in his or her work. Abroad, the same codes and regulations are

applicable, but the designs often are impractical and thus additional individual

consideration must be given to each project. Furthermore, as developing world

construction techniques and quality control are often inferior to those considered

standard in the developed world, making standardized quality assurance and control

documents for each type of project further ensures project reliability and safety.

The inadequacy of the legal framework in many developing countries measures

reduces the liability of contractors to ensure quality control by their own measures

(Leisninger, 2009). If a developing country has no regulation or has one but does not

enforce it, it is likely that additional margin of safety should be included in the design

as well. A complete best-practice design guide includes the assumed factors of

safety, but an additional document improving the quality control would allow a

designer to fully understand the areas of concern and more assign appropriate factors

of safety considering local capacity for local accountability.

Additionally, project engineers and implementing organizations need to take the

initiative to be personally accountable for each project. A plan of how to avoid

failure as well as what happens in the case of failure is essential. Insurance

companies in the developed world play an essential role in the guarantee of an

engineered project: the developing world projects deserve a similar level of project

79
assurance. Attention in all humanitarian projects should address the issue of ethical

responsibility and how to address a failure situation.

Bridges to Prosperity takes great lengths to ensure quality control throughout each

project. A document is currently being created that would be inclusive of all critical

quality control and maintenance issues. Ultimately, it is the engineer’s responsibility

to take personal accountability for a project’s enduring success and thus operation and

maintenance instructions and training should be included as a required component of

every project. Returning to assist with maintenance also helps to reduce the risk of a

failure.

6.2.3 Transferring Best Practices to Developing Nations

Many lessons were learned in the attempt to transfer a technology fairly well-

understood under typical engineering conditions into a setting for development work.

Perhaps the greatest lesson learned was not attempt to reinvent the wheel. Many

military and emergency engineering documents exist. An academic understanding of

the design issue is necessary but the most pertinent and useful reference materials are

those which consider the lack complexity in simple design.

In the case of footbridge design, the first step was to identify the intended audience

for the report. Ideally a document would be produced that could be used as a field

manual in the developing world. This particular document targeted a more academic

audience. With the vocabulary of choice more technical, further steps were taken to

identify the specific engineering problem and pertinent parameters. When the

80
number of input parameters exceeded the feasible ability of in-situ testing, the model

was used for parametric studies to compare possible material assumptions. As the

intended audience was identified as having a working knowledge of geotechnical

engineering, a greater focus was placed on justifying assumptions. Documents with a

more general intended audience may chose to include technical assumptions and

models in an appendix.

Constructability is another critical issue. Many of the design references for soil

anchors for power-lines assumed that changing the depth of embankment would be

the easiest control variable. In the case of rural construction, each meter of added

excavation could add weeks to a project as only man-powered excavation is possible.

This additional construction time may be preferred over additional cost, but the

balance between design cost and time is vastly different from the original design

intent outlined in academic sources. A considerable amount of effort should be taken

to consider both the theoretical and practical sides of a testing program or design.

Designers interested in creating a best-practices guide to design for developing

applications are suggested to limit the amount of theoretical information gathered and

to focus on what is already being done. This report is primarily concerned with

existing academic literature applicable to a somewhat specific product. In future

research and publication, a lesser focus would be placed on academia and a greater

emphasis would be placed on constructability and cost issues, as these are of

paramount importance to application in developing world applications.

81
6.3 Opportunities for Future Research

Future experimental research is needed to verify the correlation between assumed soil

parameters and the ultimate uplift capacity of rectangular dead-man anchors.

Although research pertinent to equivalent structures were reviewed, the lack of

studies with similar loading and geometrical scenarios was disappointing. Further

research could address one of the following: comparison between increases in anchor

width versus burying the anchor to a greater depth, correlation between rudimentary

field tests and laboratory tested friction angles and changes in ultimate pull-out

capacity for various coarse-grained and fine-grained soils. From experimental data, a

more complete database and design assumption matrix may be created. Furthermore,

the need for an improved testing approach would need to be developed or a testing

device, such as those detailed in Chapter 4, would need to be correlated to the

empirical findings to calibrate the devices.

A Best Practice Guide for Construction Quality Assurance and Quality Control,

including Safety precautions also would be an excellent contribution to the field of

pedestrian bridge design. Chapter 5 briefly addressed a few of the key quality control

components, but a document properly addressing this topic was beyond the scope of

this report. Included in any effective construction document should be the design

process used and the assumed quality of each component. For example, a structural

engineer in The United States must specify A50 steel if he or she assumed 50 ksi

yield stress in their design. Without this declaration of material standard and without

the proper system of quality control, an unknowing contractor may choose to use a
82
less expensive and more readily available A36 steel with inferior yield strength. In

the developing world, this component of construction and material quality control

must be documented very clearly.

83
References

AASHTO's Standard Specifications for Highway Bridges: Guide for Design of


Pedestrian Bridges, 1997.
ASCE Bearing Capacity of Soils, Technical Engineering and Design Guides as
Adapted from the U.S. Army Corps of Engineers, No. 7.
ASCE Design of Sheet Pile Walls, Technical Engineering and Design Guides as
Adapted from the U.S. Army Corps of Engineers, 1996, pp 36-37.
ASCE Soil Sampling, Technical Engineering and Design Guides as Adapted from the
U.S. Army Corps of Engineers, No. 30.
ASTM D 2488, Standard Practice for Description and Identification of Soils (Visual-
Manual Procedure) ASTM International, West Conshohocken, PA. Accessed online
October 2008: (http://www.dem.ri.gov/pubs/sops/wmsf5.pdf).
ASTM D 5878 -08 Standard Guides for Using Rock-Mass Classification Systems for
Engineering Purposes. ASTM International, West Conshohocken, PA.
ASTM D 6032-08. Standard Test Method for Determining Rock Quality
Designation (RQD) of Rock Core. ASTM International, West Conshohocken, PA.
ASTM D1556, “Standard Test Method for Density and Unit Weight of Soil in Place
by the Sand-Cone Method.” ASTM International, West Conshohocken, PA,
www.astm.org.
Bjerrum, L. (1972). “Embankments on soft ground,” ASCE Conference on
Performance of Earth and Earth-Supported Structures, Purdue University. 2, pp. 1-54.
Blaikie, M. P., Cameron, J. and Seedon, J. D. 1979. The Struggle for Basic Needs in
Nepal. Development Center of the Organization for Economic Cooperation and
Development.

Bowles, Joseph E., 1996. Foundation Analysis and Design, 5th Edition. McGraw-
Hill.

Bridges to Prosperity. Accessed online January 2009: www.footbridges.org.


Field Determination of Texture for Sand, Silt & Clay. British Columbia Ministry of
Environment, Lands & Parks. Accessed Online: February 2009:
http://ilmbwww.gov.bc.ca/risc/pubs/teecolo/terclass/appii.htm

84
CSG Wood Specifications. Accessed online October 2008:
http://www.csgnetwork.com/specificgravwdtable.html

Das, B.M., 1990. Earth Anchors: Developments in Geotechnical Engineering, Vol.


50. Elsevier, New York.
Das, B.M., 1983. A Procedure for Estimation of Uplift Capacity of Rough Piles.
Soils and Foundations, Japan, 23(2):122-126.
Davis, J., Lambert, R. 2002. Engineering in Emergencies: 2nd Edition. Intermediate
Technology Publications, London.
Dayaratram, P. International Conference on Suspension, Cable Supported and Cable
Stayed Bridges. Nov. 19-21 1999, Hyderabad. Indian Institute of Bridge Engineers.

FM 3-34.343 Military Nonstandard Fixed Bridge. Chapter 8: Suspension-Bridge


Design. Accessed online October 23, 2008. www.sachs.us/nsfb.pdf
Foster + Partners. London Millennium Bridge Project. Accessed online March 2009.
http://www.fosterandpartners.com/Projects/0953/Default.aspx
Gade, D. W. 1972. Bridge types in the central Andes. Annals of the Association of
American Geographers, v. 62 (1), p. 94-109.
Geotest Instrument Incorporated. E-285 Pocket Vane Shear Tester. Accessed online
February 2009: http://www.geotestinst.com/Catalog/ItemInfo.phtml?id=E-285

Haynes, R., Lovett, A., Sunnengerg, G. 2003. Potential Accessibility, Travel Time
and Consumer Choice: Geographical Variations in General Medical Practice
Registrations in Eastern England. Environment and Planning A 35: 1733-1750.

Hazeltine, B., Bull, C. 2003. Field Guide to Appropriate Technology. Academic


Press, London.

Helvetas International. 2001. Short Span Trail Guide Survey Guide, First Edition.
Volume 1.
His Majesty’s Government, Ministry of Local Development. 2005. Integrated Rural
Accessibility Planning. Kathmandu, Nepal. Second Edition.

Kulhawy, Trautman and Nicolaides. 1987. Spread Foundations in Uplift:


Experimental Study: Foundations for Transmission Towers. Geotech. Spec. Pub. 8
ASCE, 110.

Kulhawy, 1983. Transmission Line Structure Foundation for Uplift-Compression


Loading: Final Report. Research Project EL-2870.

85
Lebo, J. and Schelling, D. 2001. World Bank Technical Paper No. 496. Design and
Appraisal of Rural Transport Infrastructure: Ensuring Basic Access for Rural
Communities. The World Bank. Washington, D.C.

Leisinger, K. Ethical Challenges of Agricultural Biotechnology for Developing


Countries. Accessed online March 2009:
http://www.doylefoundation.org/icsu/CG%20Leisinger.pdf

Logan, C.E. , 1976. Footing Tests for Transmission Line Towers: A Collection of
Data. Report No. SA-9. United States Department of the Interior, Bureau of
Reclamation.

Martinette,C.V., 2007. Trench Rescue: Awareness, Operations, Technician: 2nd


Edition. Jones and Bartlett Publishers, Sudbury, MA.
Meriam, J. L. & Kraige, L. G. 2007. Engineering Mechanics: Statics, Sixth Edition,
John Wiley and Sons, Inc.
Meyerhof, G.G. , 1976. Bearing Capacity and Settlement of Pile Foundations,
Journal of Geotechnical Engineering Division, ASCE, Vol. 102, No. GT3.
Meyerhof, G.G. , 1973. The Uplift Capacity of Foundation Under Oblique Loads.
Journal of Geotechnical Engineering Division, ASCE, Vol. 10, pp. 64-70.
Meyerhof, G.G. and Adams, J.I. (1968). The Ultimate Uplift Capacity of
Foundations. Canadian Geotechnical Journal. 225-244.
Murray, E.J., & Geddes, J.D. 1987. Uplift of anchor plates in Sand. J. Geotech
Engineering, Div. ASCE 113, No. 3, 202-215.
Naval Facilities Engineering Command, Soil Mechanics Design Manual 7.01.
Accessed online October 2008:
http://www.geotechnicaldirectory.com/publications/Dm701.pdf
Naval Facilities Engineering Command, Foundations and Earth Structures Design
Manual 7.02. Accessed online October 2008:
http://www.ce.washington.edu/~geotech/courses/cee523/manuals/NAVFAC72.pdf
Nepal Trail Bridge Section. Accessed online December 2008:
http://www.nepaltrailbridges.org.
Nile Basin Initiative (NBI). Accessed online February 2008:
http://www.nilebasin.org/_borders?theNileRiver.htm
Peters, Tom. 1987. Transitions in Engineering: Guillaume Henri Dufour and the Early
19th Century Cable Suspension Bridges. Birkhauser, Geneva.

86
Professional Equipment: Pocket Penetrometer Standard. Accessed online January
2009: http://www.professionalequipment.com/pocket-penetrometer-geotest-e280/soil-
sampling/
Pugsley, A. 1957. The Theory of Suspension Bridges. London: Edward Arnold
Publishers.
Ruskulis, O. 1996. Micro-Concrete Roofing Tile Production. IT Technical Enquiry
Service in Appropriate Technology, Vol. 23, No.1.

Ryall, M. J., Parke, G. A. R. and Harding, J. E. (Editors). 2000. The Manual of Bridge
Engineering. First Edition. London: Thomas Telford.
Saada, A.S. and Townsend, F.C. 1981. Laboratory Strength Testing of Soils, ASTM
STP 740, American Society for Testing and Materials, Philadelphia.
Snailham, Richard. 1968. The Blue Nile Revealed: The Story of the Great Abbai
Expedition. Chatto & Windus, London,
Smith, J. E., Stalcup, J.V., 1966. Deadman Anchorages in Various Soil Mediums.
Naval Civil Engineering Lab Port Hueneme California.

Terzaghi, K., Peck, R., Mesri, B. 1996. Soil Mechanics in Engineering Practice, 3rd
ed., John Wiley and Sons, New York.

Unified Facilities Criteria (UFC) Geotechnical Engineering Procedures for


Foundation Design of Buildings and Structures. 2005. Accessed online January
2009: http://www.wbdg.org/ccb/DOD/UFC/ufc_3_220_01n.pdf.

United Nations. 2005. Department of Economic and Social Affairs, Population


Division, World Population.

U.S. Department of Energy, Richland Operations Office. Hanford Site Hoisting and
Rigging Manual. Accessed Online February 2009:
http://offroadrecovery.zoovy.com/category/riggingoffroad#P164_6009
U.S. Department of Interior, Bureau of Reclamation. Safety Manual: Appendix D:
Wire Rope. Accessed Online April 2009:
http://www.usbr.gov/ssle/safety/RSHS/AppD.pdf

Vesic, A.S. , 1977. Design of Pile Foundations, National Cooperative Highway


Research Program Synthesis 42, Transportation Research Board.
Woven Wire Resources. Accessed online December 2008:
http://www.wovenwire.com/reference/sievescreen.htm

87
Appendices

Appendix 1: Soil Identification Table (Helvetas, 2001)

The above table is provided for reference only but is not implicitly recommended

through inclusion. The table is used in Helvetas’ design manual (2001).

88
Appendix 2: Computation of Simple Active & Passive Pressures

(DM-7 Section 7.2, Naval, 2009)

89
Appendix 3: Breaking Strength Properties of Cable

Typical IWRC 6x19 Cable Properties: Assumed tensile


strength of 1770 MPa) Verify with Supplier
Nominal Breaking Design Breaking
Diameter Weight Breaking strength strength strength (FS = 3.5)

Inches mm lbs/ft kg/m tons kg kN kN

1/4 6.4 0.116 0.17 2.94 2667.12 26.16 7.47

5/16 7.9 0.18 0.27 4.58 4154.91 40.75 11.64

3/8 9.5 0.26 0.39 6.56 5951.13 58.36 16.67

7/16 11.1 0.35 0.52 8.89 8064.87 79.09 22.20

1/2 12.7 0.46 0.68 11.5 10432.62 102.31 29.23

9/16 14.3 0.59 0.88 14.5 13154.18 129.00 36.86

5/8 15.9 0.72 1.07 17.9 16238.61 159.25 45.50

3/4 19.1 1.04 1.55 25.6 23223.93 227.75 65.07

7/8 22.2 1.42 2.11 34.6 31388.59 307.82 87.95

1 25.4 1.85 2.75 44.9 40732.59 399.45 114.13

1 1/8 28.6 2.34 3.48 56.5 51255.94 502.65 143.61

1 1/4 31.8 2.89 4.30 69.4 62958.62 617.41 176.40

1 3/8 34.9 3.5 5.21 83.5 75749.93 742.85 212.24

1 1/2 38.1 4.16 6.19 98.9 89720.57 879.86 251.39

90
Appendix 4: Specific Weight of Wood Specimen (CSG)

Wood - dried kg/m³

Afromosia 705
Apple 660 - 830
Ash, black 540
Ash, white 670
Aspen 420
Balsa 170
Bamboo 300 - 400
Birch (British) 670
Cedar, red 380
Cypress 510
Douglas Fir 530
Ebony 960 - 1120
Elm ( English ) 600
Elm ( Wych ) 690
Elm ( Rock ) 815
Iroko 655
Larch 1280 - 590
Lignum Vitae 1370
Mahogany ( Honduras) 545
Mahogany ( African ) 495 - 850
Maple 755
Oak 590 - 930
Pine ( Oregon ) 530
Pine ( Parana ) 560
Pine ( Canadian ) 350 - 560
Pine ( Red ) 370 - 660
Redwood ( American ) 450
Redwood ( European ) 510
Spruce ( Canadian ) 450
Spruce ( Sitka ) 450
Sycamore 590
Teak 630 - 720
Willow 420

91
Appendix 5: Explanation of Logan’s Pull-out tests for Footings in Sands

Logan (1976) completed a series of pull-out tests for pad and stem footings in sand
which appear appropriate to the footbridge anchors due to similarities in geometry
and loadings. The test method described a series of instruments installed around each
tests footing to evaluate the uplift movement of the surrounding ground due to pull-
out, taken to failure.

During the tests, movement was negligible up to 30 kips (133 kN) of load with
geometries within reasonable footbridge anchor sizes. As detailed in Chapter 3, this
loading is within 15% of expected tensile loads incurred on an anchorage for a 100
meter bridge. The tests found that upward movement of the ground was confined to
the effective volume of soil included within a slope of 30 degrees from the top corner
of the anchor pad (Logan, 1976, pg 72). It should be noted that Logan’s tests were
conducted by pulling the footing at a slope 78.9 degrees which is significantly greater
than found in footbridge applications. Thus, although the experimental objective was
to model failure patterns, the study provided insight into the true behavior of anchors
in coarse-material under tensile loadings.

92
Appendix 6: Abbreviated Unified Soil Classification System (Coduto, 2001)

93
Appendix 7: Bjerrum Correction Factor for Vane Shear Test

Bjerrum’s Correction Factor for use in the Vane Shear Test is for use with saturated,

normally consolidated clays. Ip is the plasticity Index of a soil is the numerical

difference between the liquid limit and the plastic limit, LL-PL, presented in a percent

form (Coduto, 2001).

94

You might also like