You are on page 1of 2

PT.

ADHI PERSADA BETON


PABRIK PRECAST KELAPA GADING
Jl. Pegangsaan 2 KM. 3 No. 66 Kelapa Gading - Jakarta Utara

MONITORING PENGIRIMAN PRODUK BOX GIRDER

Deskripsi Produk Waktu Lokasi


No Plat No. Ekspedisi Keterangan
No. Produk Span Seg. Deck Type Lebar Tanggal Berangkat On Site Kembali On Site Plant Pengiriman
1 20 P8.53-P8.54 6 L S3-4 13,10 21-Okt-18 22.02 22.27 22.41 23.12 B 9662 UEM Geo Trans P8.01
2 69 P8.53-P8.54 14 L S3-3 13,10 21-Okt-18 23.40 23.59 00.15 00.34 B 9662 UEM Geo Trans P8.01
3 73 P8.53-P8.54 15 L S3-2 13,10 22-Okt-18 01.38 01.51 02.07 02.22 B 9662 UEM Geo Trans P8.01
4 37 P8.53-P8.54 9 L S3-5 13,10 22-Okt-18 23.00 23.20 00.20 00.40 B 9662 UEM Geo Trans P8.01 Lokasi pengiriman hujan
5 26 P8.53-P8.54 9 R S3-5 13,10 23-Okt-18 22.10 22.34 22.50 23.08 B 9662 UEM Geo Trans P8.01
6 18 P8.53-P8.54 5 L S3-5 13,10 23-Okt-18 23.27 23.45 00.14 00.27 B 9662 UEM Geo Trans P8.01
7 58 P8.53-P8.54 12 L S3-4 13,10 24-Okt-18 00.40 00.59 01.55 02.10 B 9662 UEM Geo Trans P8.01
8 64 P8.53-P8.54 13 L S3-5 13,10 24-Okt-18 02.45 02.59 03.36 03.48 B 9662 UEM Geo Trans P8.01
25-Okt-18 tidak ada pengiriman dikarenakan
9 8 P8.53-P8.54 4 L S3-3 13,10 26-Okt-18 21.30 21.56 22.22 22.45 B 9662 UEM Geo Trans P8.01 spreader beam KSO tidak ada
10 3 P8.53-P8.54 3 R S3-1 13,10 26-Okt-18 22.56 23.19 23.42 23.59 B 9662 UEM Geo Trans P8.01
11 46 P8.54-P8.55 14 R S3-3 13,10 29-Okt-18 20.08 20.16 20.49 20.53 B 9662 UEM Geo Trans Pegangsaan 2
12 16 P8.53-P8.54 6 R S3-4 13,10 29-Okt-18 21.19 21.31 21.52 21.57 B 9662 UEM Geo Trans Pegangsaan 2 30-Okt-18 Tidak ada pengiriman, dikarenakan
13 4 P8.53-P8.54 3 L S3-1 13,10 31-Okt-18 14.35 17.56 15.15 15.26 B 9984 BN Geo Trans Pegangsaan 2 kesiapan plat pijakan crane KSO

14 54 P8.54-P8.55 13 L S3-5 13,10 31-Okt-18 16.11 16.22 16.38 B 9984 BN Geo Trans Pegangsaan 2 Trailer Lowbed mogok kendala di Host
15 30 P8.54-P8.55 8 L S3-4 13,10 01-Nov-18 14.39 14.46 15.03 15.15 B 9662 UEM Geo Trans Pegangsaan 2
16 17 P8.54-P8.55 6 R S3-4 13,10 01-Nov-18 16.02 16.13 16.31 16.40 B 9662 UEM Geo Trans Pegangsaan 2
17 19 P8.54-P8.55 6 L S3-4 13,10 01-Nov-18 19.48 20.11 20.32 20.44 B 9662 UEM Geo Trans Pegangsaan 2
18 11 P8.53-P8.54 4 R S3-3 13,10 01-Nov-18 20.59 21.08 21.19 21.27 B 9662 UEM Geo Trans Pegangsaan 2
19 21 P8.53-P8.54 7 R DV 13,10 02-Nov-18 15.18 15.32 16.30 17.00 B 9662 UEM Geo Trans Pegangsaan 2 Ban Trailer Kempes
20 14 P8.53-P8.54 5 R S3-5 13,10 02-Nov-18 20.26 20.37 20.52 20.59 B 9662 UEM Geo Trans Pegangsaan 2
21 10 P8.54-P8.55 4 L S3-3 13,10 02-Nov-18 21.22 21.32 21.44 21.49 B 9662 UEM Geo Trans Pegangsaan 2 03-Okt & 04-Okt Tidak ada pengiriman
22 32 P8.53-P8.54 8 L S3-4 13,10 05-Nov-18 20.24 20.31 20.54 21.05 B 9662 UEM Geo Trans Pegangsaan 2 dikarenakan supir trailer pulang

23 44 P8.53-P8.54 15 R S3-2 13,10 05-Nov-18 21.17 21.25 21.46 21.52 B 9662 UEM Geo Trans Pegangsaan 2
24 29 P8.53-P8.54 10 R S3-4 13,10 05-Nov-18 22.15 22.24 22.33 22.37 B 9662 UEM Geo Trans Pegangsaan 2
25 42 P8.53-P8.54 14 R S3-3 13,10 05-Nov-18 22.46 22.52 23.05 23.10 B 9662 UEM Geo Trans Pegangsaan 2 Adanya produk amblas sehingga tempat
26 36 P8.53-P8.54 12 R S3-4 13,10 06-Nov-18 00.32 00.35 00.51 00.55 B 9662 UEM Geo Trans Pegangsaan 2 produk ke 7 digunakan untuk produk amblas,
dan lahan lain belum siap
27 33 P8.53-P8.54 11 R DV 13,10 06-Nov-18 01.04 01.09 01.24 01.29 B 9662 UEM Geo Trans Pegangsaan 2
MONITORING PENGIRIMAN PRODUK BOX GIRDER

P8.53-P8.54 P8.54-P8.55
Segmen
R Lokasi L Lokasi R Lokasi L Lokasi
1
2
3 26-Okt-18 P8.01 31-Okt-18 Pegangsaan 2
4 01-Nov-18 Pegangsaan 2 26-Okt-18 P8.01 02-Nov-18 Pegangsaan 2
5 02-Nov-18 Pegangsaan 2 23-Okt-18 P8.01
6 29-Okt-18 Pegangsaan 2 21-Okt-18 P8.01 01-Nov-18 Pegangsaan 2 01-Nov-18 Pegangsaan 2
7 02-Nov-18 Pegangsaan 2 # - 27 Jalur 1
8 # - 22 Jalur 1 05-Nov-18 Pegangsaan 2 #2 - 24 Jalur 5 01-Nov-18 Pegangsaan 2
9 23-Okt-18 P8.01 22-Okt-18 P8.01
10 05-Nov-18 Pegangsaan 2 # - 41 Jalur 1
11 06-Nov-18 Pegangsaan 2 # - 48 Jalur 5
12 06-Nov-18 Pegangsaan 2 24-Okt-18 P8.01
13 #1 - 39 Jalur 5 24-Okt-18 P8.01 31-Okt-18 Pegangsaan 2
14 05-Nov-18 Pegangsaan 2 21-Okt-18 P8.01 29-Okt-18 Pegangsaan 2
15 05-Nov-18 Pegangsaan 2 22-Okt-18 P8.01
16
17
Jumlah 11,00 Segmen 10,00 Segmen 2,00 Segmen 4,00 Segmen

Rencana Kirim Produk Terkirim = 27,00 Segmen