ABOUT PROJECT
M/s. ATS Homes Pvt. Ltd. Proposed to set up a Group Housing Project at Plot No. – SC-01/01, Sector – 152,
Noida, Uttar Pradesh having Plot Area 14.287 ha. (1,42,879.51 sq. m.) and built up area 682938.39 sq. m.
As per the EIA notification, 14.09.2006 (Amended time to time), this project falls under Category ‘B’ and
Project or Activity 8 (a) [Building Construction Project].
SALIENT FEAT
FEATURES
ATURES OF THE PROJECT
Particulars
Project Name Proposed Group Housing Project
Location Plot No. – SC-01/01, Sector – 152, Noida, Uttar Pradesh
Type of project Building Construction Project
Total Project area 14.287 ha. (1,42,879.51 sq. m.)
Built up 682938.39 sq. m (F.A.R- 4,52,552.98 sq. m + Area Under Services – 60,011.98
sq. m + Basement Area- 101138.42 sq. m+ non-F.A.R. area – 69235.01 sq. m)
Ground coverage Permissible: 42,863.86 sq. m (30 % of plot area)
Proposed: 26,398.46 sq. m (18.47% of plot area)
F.A.R Permissible Permissible: 473662.36 sq. m.
F.A.R Proposed Proposed: 452552.98 sq. m. (Proposed F.A.R. for Commercial: 14650.00 sq.
m. + Proposed F.A.R. for Residential: 437902.98 sq. m.)
Maximum height Tower- 111 m.
Number of Towers 32 Tower + 1 Commercial Center
Number of floors 2 Basement + Stilt + Upper 36 Floor
Basement Area detail Particular Parking Area Service Area Total Area in sq. m
Basement 89314 sq.m. 11824.42 sq.m. 101138.42 sq.m.
Parking For Required Parking-
Parking- F.A.R/50
Commercial = 14650.00/50
= 293 Cars
Proposed Parking-
Parking-
Particular Area for Car Parking No. of Parking
Provided
Surface Parking (@ 25 m2/ECS) 2350 Sq.m. 94 Cars
Basement (@ 35 m2/ECS) 12322Sq.m. 457 Cars
Total 551 Cars
Water requirement during Construction Phase: Requirement of water during construction period will be 100
KLD (Approx.)
KLD and whole of the treated water available will be used for flushing, horticulture, HVAC/D.G. Cooling
and Road Washing etc.
WATER REQUIREMENT
REQUIREMENT CALCULATION
Base of
Type of Expected Fresh Treated Recycled Water Total Water
S. Calculation
Particulars Populatio Populatio Water (KLD) (KLD) Consumption
No. (KLD)
n n (KLD)
(KLD
Domestic Flushing Domestic Others Flushing Others
A. Water Requirement
Requirement for Commercial
Ground + First + Fixed 1111 15 30 16.66 - 33.33 - 49.99
1. Second Floor (Retail &
Common Area) Floating 2223 5 10 11.11 - 22.23 - 33.34
Ground + First + Fixed 67 15 30 1.00 - 2.01 - 3.01
2. Second Floor (Food
Court) Floating 600 21 49 12.60 - 29.40 - 42.00
WATER REQUIREMENT
TOTAL
OTAL WATER REQUIREMENT (FRESH 1050 KLD + RECYCLED1208
RECYCLED1208 KLD) 2258 KLD
TOTAL FRESH WATER REQUIREMENT 1050 KLD
FRESH DOMESTIC WATER REQUIREMENT 997 KLD
WATER REQUIRED FOR GREEN AREA DEVELOPMENT 595 KLD
TOTAL WASTE WATER GENERATION 885 KLD
TREATED WATER RECOVER FROM STP 796 KLD
RAIN WATER HARVESTING
The rainwater collected from the rooftop and other paved areas within the project area will be
conveyed into to the rainwater harvesting system consisting of de-silting-cum-filter Chamber, Oil &
Grease Separators and Boreholes for recharge into the groundwater. Rainwater harvesting plan is as
per the design approved in the manual issued by the GOI.
VOLUME OF 1 RAINWATER HARVESTING PIT WITH DIAMETER- 2.90 M & DEAPTH – 1.90 M
= πr2 h
= 3.14 X 1.45 X 1.45 X 1.90
= 12.54 SAY 13
TOTAL NO. OF RAINWATER HARVESTING PIT
= 363 /13
= 27.92 Number SAY
= 28 Number
As per calculation the total 28 no. of RWH pits required and we are providing 35 no of RWH pits.
PARKING NEEDS-
NEEDS- There will be the sufficient parking space for the vehicles. The provision of
parking space will be as per the Norms. The parking provision will be made at basements and open
surface. We are providing total 5474 ECS.
PARKING DETAIL
Required Parking for Commercial - F.A.R/50
= 14650.00/50
= 293 Cars
Required Parking for Residential - F.A.R/80
= 437902.98/80
= 5474 Cars
Basement (@ 35
12322Sq.m. 457 Cars
m2/ECS)
Total 551 Cars
Proposed Parking for Residential-
Residential-
Particular Area for Car No. of Parking
Parking Provided
Surface Parking (@ 25
13550 Sq.m. 542 Cars
m2/ECS)
Stilt Parking (@ 30
76157 Sq.m. 2482 Cars
m2/ECS)
Lower Basement (@
76992 Sq.m. 2803 Cars
35 m2/ECS)
Total 5827 Cars
As per calculation the total no. of parking required comes out to be 5474 ECS and we are providing
5827 ECS.
********