You are on page 1of 16

Time Study

Presented by:-
Chhavi Narayan
Khushboo singh
Abhishek sahoo
Dhondup
CONTENTS
• Introduction
• Objectives of Time study
• Advantages
• Time study by stop watch
• Diff between Time and Motion study
• Type of Elements
• Methods
• Sample calculation
• Computation of NT & ST
• Applications
• Conclusion
INTRODUCTION

WORK STUDY:-
 Motion study
 Time study:-
o A qualified, well trained operator
o Normal pace
o Doing a specific task
OBJECTIVES OF TIME STUDY

• To increase productivity

 To set labour standard for satisfactory performance.

 To determine basic times/normal times.

 To determine the number of machines an operator can

handle.

 To determine standards costs.


Advantages

 To develop suitable working conditions

 To improve utilization of resources

 To reduce human effort by proper design of

processes
Diff between time & motion study

TIME STUDY MOTION STUDY

 Notes the time involved  Study of motions on an


in carrying out each operation
element of operation.
 Aims at fixing the  To reduce wastage of
standard time for time
carrying out a job.
 Suitable for all types of
 Is not suitable for
workers where quality is
jobs.
prime consideration
Types of elements involved in a job

 Repetitive element:- Occurs in every work cycle of the job.

 Occasional element:- Occurs at intervals.

 Constant element:- Basic or normal time remains constant.

 Variable element:- Basic or normal time varies.

 Manual element:- Performed manually.

 Governing element :- Occupies a longer time than any other

element.
Methods

 1.Predetermined time standard system

 2.Stop watch reading

a) Continuous

b) Snap-back

 3.Work sampling
Sample calculation
𝒑(𝟏−𝒑)
1. E=2√ P=proportion of phoning of
𝒏
activity
𝟒𝒑(𝟏−𝒑)
2. 𝒏 = E=error
𝑬𝟐
n=sample size
Que. A preliminary study indicates that the proportion of
idle time of a machine is 30% ; rest of the time it is
working . To get a good estimate of the idle time with a
precision of ±1% , then what should be the sample size?

4(0.30)(1−0.30)
n= 2 =8400
(0.01)
Computation of NT & ST
Work a b c d*
element
Obs. rating 0.56min 0.25min 0.50min 1.10min
Performanc 100% 80% 110% 100%
e rating

PFD allowance=15% * Irregular element performed every 5


cycles

Normal
time=0.56(1.0)+0.25(0.80)+0.50(1.10)+1.10(1.0)/5=1.53min
Standard time=1.53(1+0.15)=1.76
Applications

 In decision making

 Provides accuracy

 Organisation and method